CN201459732U - Simple support guide device for pile casing sinking - Google Patents

Simple support guide device for pile casing sinking Download PDF

Info

Publication number
CN201459732U
CN201459732U CN2009200852468U CN200920085246U CN201459732U CN 201459732 U CN201459732 U CN 201459732U CN 2009200852468 U CN2009200852468 U CN 2009200852468U CN 200920085246 U CN200920085246 U CN 200920085246U CN 201459732 U CN201459732 U CN 201459732U
Authority
CN
China
Prior art keywords
casing
leading truck
guide
guide beam
roller
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009200852468U
Other languages
Chinese (zh)
Inventor
李维洲
孙立军
胡学成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
CCCC Road and Bridge Special Engineering Co Ltd
Original Assignee
CCCC Second Harbor Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co filed Critical CCCC Second Harbor Engineering Co
Priority to CN2009200852468U priority Critical patent/CN201459732U/en
Application granted granted Critical
Publication of CN201459732U publication Critical patent/CN201459732U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The utility model discloses a simple support guide device for pile casing sinking, which comprises pile casing guide rollers and a guide beam, wherein at least one group of guide frames are arranged in the guide beam; and the pile casing guide rollers are arranged on the guide frames. The simple support guide beam has the characteristics of safety, high efficiency, material conservation and the like.

Description

Casing sinking freely-supported guiding device
Technical field
The utility model belongs to the casing sinking and assists a ruler in governing a country device, is specifically related to a kind of casing sinking freely-supported guiding device.
Background technology
The guiding device that the sinking of the casing during bridge pile foundation construction at present adopts adopts cantilever leading truck structure.This construction weight is big, needs a large amount of weld jobs during the location; This guiding device once can only be located a casing when the casing sinking is constructed simultaneously, and efficiency of construction is slow; Interact between the traditional direction frame casing, may cause problems such as skew, unstability executing the casing that shakes, and during the cantilever operation, the difficult control of the casing off normal precision of sinking, safety is relatively poor.
Summary of the invention
The purpose of this utility model is to provide a kind of freely-supported guiding device, to overcome the defective of above-mentioned arm guiding device when the casing sinking is constructed.
The technical solution of the utility model is: casing sinking freely-supported guiding device, and it comprises the casing guide roller, and it also comprises guide beam, and at least one group leading truck is set in the guide beam, and the casing guide roller is located on the leading truck.
The quadrangle that described leading truck is connected by four frameworks.
Described casing guide roller is connected on the slide block, and slide block is connected with thrustor, and slide block is located on the bearing, and bearing is connected with leading truck.
The freely-supported guide beam possess safety, efficient, save characteristics such as material.1, in light weight: about more than 80 tons of traditional cantilever leading truck weight, and the freely-supported guide beam adopts trussed construction, about 60 tons of weight.2, the location fast: guide beam can be finished the location with its roller that carries and Chain block, suitably welds block and can fix.3, concentrate efficiently: disposable 3 casings are all transferred puts in place during construction, treats to execute to shake with vibrating hammer one by one again after casing is stablized by deadweight to put in place, effectively improves sinking efficient.4, safety, stable: freely-supported guide beam good rigidity, mid-span deflection only is 1cm during the 32m span.Separate between each casing, interference-free, safe, belong to the platform operation, more improve safety behind the top laying gauze wire cloth etc., and do not had the danger of toppling.
Description of drawings
Fig. 1 casing sinking freely-supported guiding device schematic top plan view.
Fig. 2 guide beam end face elevational schematic view.
The leading truck framework schematic diagram that Fig. 3 is vertical with guide beam.
Fig. 4 leading truck schematic top plan view.
Fig. 5 tube guide roller syndeton schematic diagram.
Fig. 6 tube guide roller structural representation.
Fig. 7 guide beam and leading truck combination schematic diagram.
The specific embodiment
As shown in Figure 1, casing sinking freely-supported guiding device is arranged on the operation platform 1. comprise guide beam 2, guide beam 2 is trussed constructions of a frustum shape, laterally on operation platform 1. the end face facade of guide beam 2 is as shown in Figure 2, it comprises vertical support bar 2.1, vertically support bar connects respectively between 2.1 about and goes up connecting rod 2.2 and 2.3, two vertical support bars 2.1 of lower link, goes up connecting rod 2.2 and lower link 2.3 formation end face frame; Two upward connect 2.4, two of transverse bars and go up connecting rod 2.2 and two top frameworks of transverse bars 2.4 formations between the connecting rod 2.2; It also has identical following framework; Two end faces at guide beam 2 are divided into by roller bracing frame 3, are connected with oblique rod member 2.5 between roller bracing frame 3 and the top framework and constitute the inclined-plane framework.
Roller bracing frame 3 is divided into roller set 4.Roller set 4 is supported on the operation platform 1, can realize guide beam moving on operation platform 1.
Shown in Fig. 1,3, be provided with leading truck 5 in the guide beam 2 of trussed construction.Be provided with three leading trucks in the present embodiment between the guide beam, can realize guiding three casings while sinkings.The quadrangle form that leading truck 5 is connected with 5.4 by four frameworks 5.1,5.2,5.3, as shown in Figure 4.For the leading truck framework vertical with guide beam, it is identical with 5.3 structure to be leading truck framework 5.1, as shown in Figure 3, is a trussed construction in fact, framework is stretched out at rod member two ends, leading truck framework upper end, is used to be hung on the top framework (as shown in Figure 7) on the guide beam.The casing guide roller is located at above four frameworks 5.1,5.2,5.3 and 5.4 (as shown in Figure 4).
Tube guide roller syndeton as shown in Figure 5, casing guide roller 6 is connected on the slide block 7, slide block 7 is connected with thrustor 8, slide block 7 is located on the bearing 9, bearing 9 is connected with leading truck.Thrustor 8 comprises pushing tow support 8.1, and pushing tow support 8.1 is connected on the leading truck, connects jack 8.2 on the pushing tow support 8.1.Jack 8.2 is connected with slide block 7.
As shown in Figure 6, casing tube guide roller 6 comprises the back shaft 6.1 that is connected with slide block 7, connects way roller 6.2 on the back shaft 6.1.
Construction sequence is:
1, sets steel pipe pile, set up freely-supported guide beam operation platform.
2, guide beam location, leading truck is installed.
3, many casings are hung in the leading truck, it is stable to sink by deadweight.
4, the vibrating hammer of slinging is concentrated casing 11 is carried out vibration-sunk.
5, the reach guide beam repeats above-mentioned steps.

Claims (5)

1. casing sinking freely-supported guiding device, it comprises the casing guide roller, it is characterized in that it also comprises guide beam, and at least one group leading truck is set in the guide beam, the casing guide roller is located on the leading truck.
2. casing sinking freely-supported guiding device according to claim 1 is characterized in that the quadrangle that described leading truck is connected by four frameworks.
3. as casing sinking freely-supported guiding device as described in the claim 2, it is characterized in that being equipped with on the tetragonal leading truck casing guide roller.
4. as casing sinking freely-supported guiding device as described in the claim 3, it is characterized in that the casing guide roller is connected on the slide block, slide block is connected with thrustor, and slide block is located on the bearing, and bearing is connected with leading truck.
5. casing sinking freely-supported guiding device according to claim 1 is characterized in that the guide beam two ends establish the roller bracing frame, and the roller bracing frame is divided into roller.
CN2009200852468U 2009-04-24 2009-04-24 Simple support guide device for pile casing sinking Expired - Fee Related CN201459732U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009200852468U CN201459732U (en) 2009-04-24 2009-04-24 Simple support guide device for pile casing sinking

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009200852468U CN201459732U (en) 2009-04-24 2009-04-24 Simple support guide device for pile casing sinking

Publications (1)

Publication Number Publication Date
CN201459732U true CN201459732U (en) 2010-05-12

Family

ID=42387085

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009200852468U Expired - Fee Related CN201459732U (en) 2009-04-24 2009-04-24 Simple support guide device for pile casing sinking

Country Status (1)

Country Link
CN (1) CN201459732U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102433880A (en) * 2011-12-30 2012-05-02 广东省长大公路工程有限公司 Simply-support guide frame of sinking steel protecting barrel and construction method for sinking steel protecting barrel
CN102587379A (en) * 2012-02-10 2012-07-18 高天宝 Construction method and device for regularly distributing grouped tubular piles at land
CN102660951A (en) * 2012-06-05 2012-09-12 上海信德建设工程有限公司 Piling locating guide frame for integrally finishing construction of H-sections and steel sheet piles
CN105649081A (en) * 2016-01-14 2016-06-08 中铁大桥局集团有限公司 Multistage guiding support for oblique inserting piling of super long and large diameter pile
CN107460877A (en) * 2017-08-17 2017-12-12 中交二航局第三工程有限公司 Steel pile casting device for positioning and supporting
CN109056540A (en) * 2018-08-28 2018-12-21 中交上海航道局有限公司 A kind of construction method of small-sized Reinforced Concrete Simple bridge
WO2022121554A1 (en) * 2021-07-05 2022-06-16 中铁上海工程局集团有限公司 Protective casing guide frame structure

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102433880A (en) * 2011-12-30 2012-05-02 广东省长大公路工程有限公司 Simply-support guide frame of sinking steel protecting barrel and construction method for sinking steel protecting barrel
CN102587379A (en) * 2012-02-10 2012-07-18 高天宝 Construction method and device for regularly distributing grouped tubular piles at land
CN102660951A (en) * 2012-06-05 2012-09-12 上海信德建设工程有限公司 Piling locating guide frame for integrally finishing construction of H-sections and steel sheet piles
CN102660951B (en) * 2012-06-05 2014-09-03 上海信德建设工程有限公司 Piling locating guide frame for integrally finishing construction of H-sections and steel sheet piles
CN105649081A (en) * 2016-01-14 2016-06-08 中铁大桥局集团有限公司 Multistage guiding support for oblique inserting piling of super long and large diameter pile
CN105649081B (en) * 2016-01-14 2018-07-17 中铁大桥局集团有限公司 A kind of oblique inserting piling multistage guiding trestle of super long-large diameter pile
CN107460877A (en) * 2017-08-17 2017-12-12 中交二航局第三工程有限公司 Steel pile casting device for positioning and supporting
CN109056540A (en) * 2018-08-28 2018-12-21 中交上海航道局有限公司 A kind of construction method of small-sized Reinforced Concrete Simple bridge
WO2022121554A1 (en) * 2021-07-05 2022-06-16 中铁上海工程局集团有限公司 Protective casing guide frame structure

Similar Documents

Publication Publication Date Title
CN201459732U (en) Simple support guide device for pile casing sinking
CN103643637B (en) Original position construction method for lifting whole after the first vertical transfer of Long-Span Concrete Filled Steel Tubular Arch Bridges
CN201106155Y (en) Inclined guy cable auxiliary full cantaliver crane trussed steel beam device
CN202544854U (en) Lining trolley for subway station
CN201506952U (en) Temporary cable matched hanging basket building concrete cable stayed bridge without supporting frame
CN204112242U (en) A kind of Concrete Filled Steel-tube Truss Arch Bridge suspender replacement special tool boom system
CN202577150U (en) Pier top lifting frame
CN201746779U (en) Prestressed tension jack moving frame
CN103628416A (en) Stiffening girder counter-straining near-pier bracket of suspension bridge
CN102777050B (en) Assembly type jig frame for longspan pipe truss roof girder
CN202000265U (en) Concrete construction formwork for high pier of bridge
CN201746781U (en) Diagonal draw type bracket for cast-in-place of continuous beam
CN104164882B (en) Side slope builds construction method and the structure on supporting and protection structure beam basis
CN203755173U (en) Formwork device used for hydraulic climbing of bridge high pier
CN203361642U (en) Assembled-structure cast-in-place stair steel molding plate
CN203568689U (en) Steel structure for wall-sleeving cantilever crane
CN203699828U (en) Simple tool-type lifting frame for mounting of steel reinforcement cages
CN203160139U (en) Wide multiple-main-truss basket travelling unit
CN201952736U (en) Auxiliary pier movable bracket for assisting invariable-amplitude beam erecting crane in erecting steel box girder
CN202388183U (en) Lifting equipment for H-shaped steel numerical control cutting machine
CN203961239U (en) High-altitude overhanging awning construction operation platform
CN204919363U (en) High mound pin -connected panel strength nature skeleton of anti high wind
CN203271122U (en) Attached template lifting frame
CN205012336U (en) Area is pile driver of feed bin down
CN204715216U (en) A kind of Arch Bridge Construction platform structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: CCCC SHEC Fourth Engineering Co., Ltd.

Assignor: China Communications 2nd Navigational Bureau

Contract record no.: 2010420000184

Denomination of utility model: Simple support guide device for pile casing sinking

Granted publication date: 20100512

License type: Exclusive License

Record date: 20101115

ASS Succession or assignment of patent right

Owner name: WUHAN CCCC ROAD + BRIDGE SPECIAL ENGINEERING CO.,

Effective date: 20120612

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 430014 WUHAN, HUBEI PROVINCE TO: 430032 WUHAN, HUBEI PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20120612

Address after: 430032. 11 Golden Lake Road, Dongxihu lake, Wuhan, Hubei

Co-patentee after: CCCC Road & Bridge Special Engineering Co., Ltd.

Patentee after: China Communications 2nd Navigational Bureau

Address before: 430014 No. 16, Nanjing Road, Jianghan District, Hubei, Wuhan

Patentee before: China Communications 2nd Navigational Bureau

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100512