CN201420396Y - Pre-embedded box die of concrete wall - Google Patents

Pre-embedded box die of concrete wall Download PDF

Info

Publication number
CN201420396Y
CN201420396Y CN2009203048098U CN200920304809U CN201420396Y CN 201420396 Y CN201420396 Y CN 201420396Y CN 2009203048098 U CN2009203048098 U CN 2009203048098U CN 200920304809 U CN200920304809 U CN 200920304809U CN 201420396 Y CN201420396 Y CN 201420396Y
Authority
CN
China
Prior art keywords
concrete wall
mould
die
utility
buried
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009203048098U
Other languages
Chinese (zh)
Inventor
王松山
张行良
刘全明
孙华明
李建秋
王新成
刘伟
张新炜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Glory Construction Co.,Ltd.
Ronghua Construction Group Co Ltd
Original Assignee
GENERAL CONSTRUCTION Co OF LAIXI
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GENERAL CONSTRUCTION Co OF LAIXI filed Critical GENERAL CONSTRUCTION Co OF LAIXI
Priority to CN2009203048098U priority Critical patent/CN201420396Y/en
Application granted granted Critical
Publication of CN201420396Y publication Critical patent/CN201420396Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Ladders (AREA)

Abstract

The utility model discloses a pre-embedded box die of a concrete wall, which can solve the problems existing in the prior art that existing dies have low rigidity, are easy to deform, can not be circularly used, and have higher manufacturing cost. The utility model adopts the technical solution that the pre-embedded box die of concrete wall is a four-edge table shaped box body made of steel plates, which comprises lateral plates and a bottom board, wherein a supporting shoe is arranged on the external side of the bottom board, and a plastic sleeve is packed outside the supporting shoe. After the die is applied, the rigidity is improved, the finishing cost of concrete is reduced, through the circular use of the die, the manufacturing cost is low, materials, such as bamboo plywood, wooden blocks and the like are saved, and the die has very high popularizing and application values.

Description

The pre-buried chamber mould of concrete wall
Technical field
The utility model belongs to the mould of using in the building operations, specifically, relates to the pre-buried chamber mould of a kind of concrete wall.
Background technology
Along with continuing to bring out of highrise building, required same specification, more and more in the concrete wall of same seat building with the hole to be provided of shape, construction finishes and is used for big switch chamber, fire plug etc. are installed, and these hole to be provideds utilize the chamber mould to reserve out when concreting.Existing pre-buried chamber mould mainly adopts bamboo offset plate and flitch nail system to form, its rigidity is low, be difficult for fixing, displacement and distortion and not quick detachable easily take place when concreting, there is deviation at the concrete wall hole of moulding often irregularity or position, also needs the finishing of plastering again after the form removal, has not only expended man-hour but also waste material, and pre-buried chamber mould need make each hole to be provided, can't have enough to meet the need.
How to solve the problems of the technologies described above, make a kind of rigidity big, can reusable pre-buried chamber mould then be the problem that the utility model faced.
Summary of the invention
The utility model provides a kind of concrete wall pre-buried chamber mould, can solve the rigidity that prior art exists low, yielding, can not recycle and cause the cost problem of higher.
For solving the problems of the technologies described above, the utility model is achieved by the following technical solutions:
The pre-buried chamber mould of a kind of concrete wall, described mould are the truncated rectangular pyramids shape box body that steel plate is made, and comprise side plate and base plate.The employing steel plate is made, and has guaranteed the rigidity of mould, and is not yielding, and the box body shape of truncated rectangular pyramids shape is convenient to mould and is removed.
In technique scheme of the present utility model, also have following technical characterictic: the described box plate outside is provided with supporting leg.Because pre-buried hole is a single face, by the supporting leg supporting mould.
Further, the outside of described supporting leg is surrounded by plastic bushing.Supporting leg is provided with 4, is easy to fix after putting plastic bushing, is convenient to dismounting.
Further, described box plate inboard is provided with handle, is convenient to installation and removal.
Further, the base angle of described terrace with edge is 110~120 °, is convenient to the concrete mould of building and dismantle.
Further, described mould is used for the pre-buried hole that the length of side is 50~150cm.Usually the thickness of the concrete wall of using is 15~50cm.
The size of terrace with edge base plate is identical with dimension of opening, installs chamber after the form removal, tamps with dry mortar all around.
Compared with prior art, advantage of the present utility model and good effect are:
After using concrete embedded chamber mould, rigidity improves, and the openings position of reservation is accurate, size is unified regular, need not repair, and reduced concrete trimming cost usefulness, and the moulding hole is attractive in appearance solid.Turnover by mould is used, and has reduced cost, has saved materials such as bamboo offset plate and flitch, has highly application value.
Description of drawings
Fig. 1 is that the pre-buried chamber mould of the utility model concrete wall is installed in the structural representation on the concrete wall;
Fig. 2 is the A-A sectional view of Fig. 1;
The symbol of figure and explanation:
1, concrete wall; 2, pre-buried chamber mould; 2-1, side plate; 2-2, base plate; 2-3, handle; 2-4, supporting leg; 2-5, sleeve pipe;
α represents the base angle of truncated rectangular pyramids.
The specific embodiment
Below in conjunction with the drawings and specific embodiments the utility model is described in further detail.
As depicted in figs. 1 and 2, the pre-buried chamber mould 2 that a kind of concrete wall that are used for building operations 1 use is truncated rectangular pyramids shape box body, comprises four side plate 2-1 and base plate 2-2, and the base angle of terrace with edge is 115 °, is convenient to concrete dismounting of building with mould.Box body is made by the thick steel plate of 2~3mm;
Common pre-buried hole is a single face, is obstructed hole, and the box plate 2-2 outside is provided with 4 supporting leg 2-4 supporting moulds, and the outside of each supporting leg 2-4 is surrounded by plastic bushing 2-5, is convenient to remove mould, and after removing mould 2, sleeve pipe is stayed in the concrete wall 1.
For the ease of the installation and removal mould, so that recycling, box plate 2-2 inboard is provided with two handle 2-3.
The pre-buried chamber mould of the utility model is used for the pre-buried hole that the length of side is 50~150cm.Usually be applied on the concrete wall that thickness is 15~50cm.The size of terrace with edge base plate 2-2 is identical with dimension of opening, installs chamber after the form removal, tamps with dry mortar all around.
After highrise building has covered one deck, after pulling down mould, can reuse in following one deck of same structure, though single mould bamboo offset plate and flitch nail before made the die cost height that forms, but after the dismounting of mould before, can not re-use, and the utility model can use repeatedly the promptly corresponding cost that reduced.The common number of plies height of present highrise building, it is also more fixing that the chamber of typical floor is reserved the hole, makes the steel shaper by dimension of opening, and the rigidity height is not yielding, and easily installation and removal can be had enough to meet the need to use and be reduced cost.
Certainly; above-mentioned explanation is not to be to restriction of the present utility model; the utility model also is not limited in above-mentioned giving an example, and variation, remodeling, interpolation or replacement that those skilled in the art are made in essential scope of the present utility model also should belong to protection domain of the present utility model.

Claims (6)

1. pre-buried chamber mould of concrete wall, it is characterized in that: described mould is the truncated rectangular pyramids shape box body that steel plate is made, and comprises side plate and base plate.
2. the pre-buried chamber mould of concrete wall according to claim 1 is characterized in that: the described box plate outside is provided with supporting leg.
3. the pre-buried chamber mould of concrete wall according to claim 2, it is characterized in that: the outside of described supporting leg is surrounded by plastic bushing.
4. the pre-buried chamber mould of concrete wall according to claim 1 is characterized in that: described box plate inboard is provided with handle.
5. the pre-buried chamber mould of concrete wall according to claim 1 is characterized in that: the base angle of described terrace with edge is 110~120 °.
6. the pre-buried chamber mould of concrete wall according to claim 1 is characterized in that: described mould is used for the pre-buried hole that the length of side is 50~150cm.
CN2009203048098U 2009-06-22 2009-06-22 Pre-embedded box die of concrete wall Expired - Fee Related CN201420396Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009203048098U CN201420396Y (en) 2009-06-22 2009-06-22 Pre-embedded box die of concrete wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009203048098U CN201420396Y (en) 2009-06-22 2009-06-22 Pre-embedded box die of concrete wall

Publications (1)

Publication Number Publication Date
CN201420396Y true CN201420396Y (en) 2010-03-10

Family

ID=41807048

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009203048098U Expired - Fee Related CN201420396Y (en) 2009-06-22 2009-06-22 Pre-embedded box die of concrete wall

Country Status (1)

Country Link
CN (1) CN201420396Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102182301A (en) * 2011-01-12 2011-09-14 王军艇 Formwork for buildings, formwork component, cast-in-situ floor empty space and construction method thereof
CN108331346A (en) * 2017-12-22 2018-07-27 广州市时代控股集团有限公司 The method for executing indoor pipeline integrated morphology

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102182301A (en) * 2011-01-12 2011-09-14 王军艇 Formwork for buildings, formwork component, cast-in-situ floor empty space and construction method thereof
CN102182301B (en) * 2011-01-12 2013-06-05 王军艇 Formwork for buildings, formwork component, cast-in-situ floor empty space and construction method thereof
CN108331346A (en) * 2017-12-22 2018-07-27 广州市时代控股集团有限公司 The method for executing indoor pipeline integrated morphology

Similar Documents

Publication Publication Date Title
CN207392738U (en) Caisson of toilet template system
CN203334663U (en) Aluminum formwork for stairway structure
CN204590634U (en) For pouring into a mould the feed arrangement of constructional column
CN201420396Y (en) Pre-embedded box die of concrete wall
CN204235676U (en) L-shaped door buttress prefabricated section sizing punching block
CN204098420U (en) A kind of dry-hung plate wall surface decoration system
CN204691228U (en) One-shot forming hollow construction formwork
CN203097290U (en) Assembled type split bolt
CN201172962Y (en) Combined template for concrete casting
CN201190368Y (en) Detaching-free template for concrete
CN204691224U (en) A kind of composite material plane construction template
CN207892233U (en) Structure and decoration integrated cast-in-place concrete elastic decorative mould system
CN203977852U (en) Easily demoulding waterproof building template
CN202787964U (en) Concrete structure drop plate angle steel tool type combined template
CN104131697A (en) Tool type formwork system for kitchen and bath concrete waterproof guide wall and construction method of tool type formwork system
CN203669175U (en) Reinforced concrete hollow floorslab
KR100747686B1 (en) A device combining wooden form panels
CN201872231U (en) Adjustable composite steel mold
CN211114821U (en) Concrete wall pouring auxiliary device
CN210857534U (en) Vertical shaft bridge concrete body embedded part
KR101483910B1 (en) Wedge form spacer for truss girder integrated deck without permanent form and the deck
CN202850490U (en) Shear wall reserved hole shaping mould
CN209799358U (en) building pouring plastic formwork
CN210636524U (en) Detachable sewer component
CN211691471U (en) A preformed hole model for building plumbing pipe

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 266000 Shandong Province, Qingdao city Heilongjiang District Road No. 2 B Vanke center 15 Floor

Patentee after: RONGHUA CONSTRUCTION GROUP Co.,Ltd.

Address before: 266000 Shandong Province, Qingdao city Heilongjiang District Road No. 2 B Vanke center 15 Floor

Patentee before: Glory Construction Co.,Ltd.

CP03 Change of name, title or address

Address after: 266000 Shandong Province, Qingdao city Heilongjiang District Road No. 2 B Vanke center 15 Floor

Patentee after: Glory Construction Co.,Ltd.

Address before: Shandong city of Qingdao province Fuzhou City 266071 North Road No. 50-56

Patentee before: Lacey City Construction Corp.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100310

Termination date: 20180622