CN201161820Y - First-in first-out dynamic storing apparatus for gross rubber - Google Patents

First-in first-out dynamic storing apparatus for gross rubber Download PDF

Info

Publication number
CN201161820Y
CN201161820Y CNU2007201597566U CN200720159756U CN201161820Y CN 201161820 Y CN201161820 Y CN 201161820Y CN U2007201597566 U CNU2007201597566 U CN U2007201597566U CN 200720159756 U CN200720159756 U CN 200720159756U CN 201161820 Y CN201161820 Y CN 201161820Y
Authority
CN
China
Prior art keywords
roller
way
parallel
parking
free
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2007201597566U
Other languages
Chinese (zh)
Inventor
杜云峰
王健
付元黎
徐大杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Triangle Tyre Co Ltd
Original Assignee
Triangle Tyre Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Triangle Tyre Co Ltd filed Critical Triangle Tyre Co Ltd
Priority to CNU2007201597566U priority Critical patent/CN201161820Y/en
Application granted granted Critical
Publication of CN201161820Y publication Critical patent/CN201161820Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Tires In General (AREA)

Abstract

The utility model relates to a rubber compound first-in first-out dynamic placing device belonging to the field of a rubber processing machine, which is provided with a placing roll table and is characterized in that the placing roll table is a section which is composed of a plurality of long rollers which are axially arranged in parallel, the placing roll table is a slope shape roll table with 1-2 degree, a feeding roll table is arranged on the front end of the placing roll table and is composed of two sections of free roll tables which are arranged in parallel, and the free roll tables are slope shape roll tables with 1-2 degree, each section of the free roll table is composed of a plurality of short rollers which are parallel in the axial direction, the short rollers and long rollers which compose the placing roll table are parallel in the axial direction, a taking-out roll table is arranged on the rear end of the placing roll table and is composed of two sections of free roll tables which are parallel in the axial direction, the short rollers and long rollers which compose the placing roll table are parallel in the axial direction.

Description

The dynamic parking device of elastomeric compound first in first out
Technical field
The utility model belongs to the rubber processing machinery field, the dynamic parking device of especially a kind of tire plant elastomeric compound first in first out.
Background technology
The elastomeric compound of tire plant is the primary raw material that tire constitutes, and machines the back in the banburying workshop and is placed on the special-purpose sizing material pallet (seeing accompanying drawing) with the laminar buttress, and heavily about 1 ton of every buttress material docks to after the process stipulation time by operation down again and takes.
Aspect the mode of parking, generally be that material buttress is placed directly on the ground traditionally, and put neatly that because banburying workshop site area is limited, the material buttress is put generally very compact, a row is a row then, and access is by forklift operator, operation from outside to inside.
The above operating mode of parking exists three drawbacks that can't overcome:
One, parks confusion: because specification is many, the place is tight, often cause parking of the artificial formula of seizing every opportunity, many specifications are assorted puts by door leaf son identification, but needs by the N/R retaining inside interim the removing the outside of having to often, the result has here taken out, stifled again over there having gone up, the people parks confusion for causing, and frequently buys and sells;
Two, it is few to park quantity: because often will scratch material usefulness from the centre, so many batch turnings place will be reserved in the scene and fork truck has enough to meet the need the place, this has just influenced effective use in place, and it is on the low side to park quantity;
Three, can't guarantee first in first out: the technological requirement sizing material will be taken by the production time order, makes the storage period of every buttress sizing material roughly the same, could guarantee the production stability of back operation like this, and directly has influence on the stable of product design.But traditional park operating mode and can't guarantee this point, because park confusion, manually often can only go for material by impression, want strict and accomplish to get in chronological order to expect it is very difficult, add the relation of frequently buying and selling work capacity, often cause the phenomenon that last in, first out that follows the line of least resistance, this is unavoidable from management.
Four, labor content is big: owing to frequently buy and sell, cause the field activity amount big.
Along with production-scale continuous expansion, more than four drawbacks more and more obvious to the influence of on-the-spot logistics management and product design, seriously perplexing the rubber processing industry, especially large-scale rubber enterprise such as tire production, become the important step that restriction management and quality promote, only take new park operating mode and could fundamentally solve, what the utility model solved is exactly this problem.
Summary of the invention
In order to satisfy extensive rubber processing, especially in the tire production elastomeric compound is parked the demand of operation, the utility model provides a kind of dynamic parking device of first in first out, solve tradition and park the confusion of mode, poor efficiency, unordered, problem that operation is heavy, accomplish to classify clear, storage content big, first in first out, purpose easy and simple to handle.
The technical scheme that its technical matters that solves the utility model adopts is: be provided with and park roller-way, it is characterized in that, parking roller-way is that one section long roller by a plurality of axially parallels is formed, parking roller-way is 1~2 degree domatic roller-way, the front end of parking roller-way is a charging roller, charging roller is made up of two sections free roller-ways that be arranged in parallel, free roller-way is 1~2 degree domatic roller-way, every section free roller-way is made up of the short roller of a plurality of axially parallels, short roller is parked the long roll shaft of roller-way to parallel with composition, the rear end of parking roller-way is for getting the material roller road, getting the material roller road is made up of two sections free roller-ways that be arranged in parallel, free roller-way is 1~2 degree domatic roller-way, and every section free roller-way is made up of the short roller of a plurality of axially parallels, and short roller is parked the long roll shaft of roller-way to parallel with composition.
Get termination, material roller road and be provided with the steel stopper, its upper end is a little more than getting plane on the material roller road.
The beneficial effects of the utility model are, the use of this device, dynamically park by roller-way, three significant problems that the tradition mode of parking exists have fundamentally been solved: park chaotic problem, park the few problem of quantity, can't realize the problem of first in first out, tedious problem, with the traditional approach ratio, realized parking mechanization, accomplished in order, easy, efficient, field management and quality have been improved the good effect of playing.
Description of drawings
Below in conjunction with drawings and Examples the utility model is further specified.
Fig. 1, structural representation of the present utility model.
Fig. 2 is running condition figure of the present utility model.
1. get the material fork truck among the figure, 2. get the material roller road, 3. park roller-way, 4. charging roller, 5. material loading fork truck, 6. film buttress, 7. sizing material pallet, 8. stopper.
The specific embodiment
At Fig. 1, among Fig. 2, be provided with and park roller-way 3, parking roller-way 3 is that one section long roller by a plurality of axially parallels is formed, parking roller-way 3 is 1~2 degree domatic roller-way, the front end of parking roller-way 3 is a charging roller 4, charging roller 4 is made up of two sections free roller-ways that be arranged in parallel, free roller-way is 1~2 degree domatic roller-way, every section free roller-way is made up of the short roller of a plurality of axially parallels, short roller is parked the long roll shaft of roller-way 3 to parallel with composition, the rear end of parking roller-way 3 is for getting material roller road 2, getting material roller road 2 is made up of two sections free roller-ways that be arranged in parallel, free roller-way is 1~2 degree domatic roller-way, and every section free roller-way is made up of the short roller of a plurality of axially parallels, and short roller is parked the long roll shaft of roller-way to parallel with composition.
The dynamic parking device of elastomeric compound first in first out of the present utility model is that a kind of brand new elastomeric compound is parked mode.System architecture as shown in drawings, each several part equipment is briefly described below:
One, charging roller 4: be about 1.5 meters long two free roller-way that two sections short rollers are formed, the gradient that has 1~2 degree, purpose with the two roller-ways of short roller is to be convenient to 5 operations of material loading fork truck, after sizing material pallet 7 is put on the roller-way, material loading fork truck 5 extraction that can descend rapidly is also for selecting for use the formula light fork truck of stretching one's legs that condition is provided;
Two, park roller-way 3: this is one section 1~2 degree domatic roller-way of being made up of long roller, this is a key role of parking film buttress 6, film buttress 6 is a crowded ground queuing on roller-way, the gradient of 1~2 degree can guarantee that substantially film buttress 6 can glide, it is out of control to be unlikely to impulse force again, it is changeable that the length of this section roller-way is looked conditions of demand, but had better not surpass the length of 10 material buttress;
Three, get material roller road 2: the one section two free domatic roller-way identical with charging roller 4, be convenient to get material fork truck 1 and get material;
Four, stopper 8: get the material roller road for preventing that sizing material from going out, establish the steel stopper in the roller-way termination, a little more than getting plane on the material roller road.
The roller of above roller-way selects for use the pachydermia steel pipe of 89 millimeters of diameters to manufacture, and the material loading section expects that section adopts a solid axle barrel structure alive, the structure of the whole roll bearing seat of the section of parking employing with getting.
The utility model groundwork mainly contains 3 points:
One, the slope roller-way is dynamically parked: this is the core of device, utilizing one section gradient is that the film buttress is deposited in 1~2 free steel rider road of spending, utilize the effect of self gravitation, the film buttress can slide to low side along roller-way after high-end putting into, and film buttress nature is neatly lined up, after taking one away from low spot, catching up with automatically of back so just forms a state of dynamically parking, strict realization first in first out;
Two, branch specification multiple roll road is parked: according to the specification difference, many roller-ways are installed side by side on the ground, are deposited the specification of appointment on every roller-way, avoided mixing of specification;
Fixing high-end material stock and low side are got material: for cooperating forklift operator, short roller formula roller-way is established at two ends, and low side handicapping lug-latch prevents that the film buttress from sweeping away.This layout makes the scene only need to reserve the fork truck passage at two ends, roller-way district and gets final product, and has improved the utilization of area rate, parks quantity thereby increased, and has reduced work capacity owing to no longer needing frequently to buy and sell simultaneously.
The device working process is: the glue stuff compounding buttress is put on the charging roller by fork truck, material is piled up neatly at self gravitation effect lower edge charging roller, is parked the roller-way downslide, get on the material roller road until sliding into, continuous material loading makes material buttress form a line parking on the roller-way, when needing with fork truck from getting on the material roller road material buttress of picking, then follow-up material buttress moves ahead automatically and fills a vacancy, and fork truck can be got material from getting the material roller road continuously.
Many covering devices are installed side by side, can realize parking of the big quantity elastomeric compound of many specifications, elastomeric compound is parked realized flowing in order of mechanization and first in first out, reduced labour intensity, guaranteed the stable of sizing material quality, fundamental role is played in the raising of tire product quality and the raising of field management level, is the inevitable choice in banburying workshop from now on.
Park roller-way and can change length and angle as required.Roller can adopt solid axle barrel structure alive, also can adopt the structure of whole roll bearing seat.

Claims (2)

1, the dynamic parking device of a kind of elastomeric compound first in first out, be provided with and park roller-way, it is characterized in that: parking roller-way is that one section long roller by a plurality of axially parallels is formed, parking roller-way is 1~2 degree domatic roller-way, the front end of parking roller-way is a charging roller, charging roller is made up of two sections free roller-ways that be arranged in parallel, free roller-way is 1~2 degree domatic roller-way, every section free roller-way is made up of the short roller of a plurality of axially parallels, short roller is parked the long roll shaft of roller-way to parallel with composition, the rear end of parking roller-way is for getting the material roller road, getting the material roller road is made up of two sections free roller-ways that be arranged in parallel, free roller-way is 1~2 degree domatic roller-way, and every section free roller-way is made up of the short roller of a plurality of axially parallels, and short roller is parked the long roll shaft of roller-way to parallel with composition.
2, according to the dynamic parking device of the described elastomeric compound first in first out of claim 1, it is characterized in that the said termination, material roller road of getting is provided with the steel stopper, its upper end is a little more than getting plane on the material roller road.
CNU2007201597566U 2007-12-29 2007-12-29 First-in first-out dynamic storing apparatus for gross rubber Expired - Lifetime CN201161820Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007201597566U CN201161820Y (en) 2007-12-29 2007-12-29 First-in first-out dynamic storing apparatus for gross rubber

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007201597566U CN201161820Y (en) 2007-12-29 2007-12-29 First-in first-out dynamic storing apparatus for gross rubber

Publications (1)

Publication Number Publication Date
CN201161820Y true CN201161820Y (en) 2008-12-10

Family

ID=40182761

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007201597566U Expired - Lifetime CN201161820Y (en) 2007-12-29 2007-12-29 First-in first-out dynamic storing apparatus for gross rubber

Country Status (1)

Country Link
CN (1) CN201161820Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103010730A (en) * 2012-12-13 2013-04-03 无锡市宝禾机械设备有限公司 Automatic feeding and discharging roller conveyor
CN114074816A (en) * 2020-08-20 2022-02-22 长沙戴卡科技有限公司 Intelligence wheel hub storage warehouse

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103010730A (en) * 2012-12-13 2013-04-03 无锡市宝禾机械设备有限公司 Automatic feeding and discharging roller conveyor
CN103010730B (en) * 2012-12-13 2015-12-16 无锡市宝禾机械设备有限公司 A kind of automatic feed/discharge roller conveyor
CN114074816A (en) * 2020-08-20 2022-02-22 长沙戴卡科技有限公司 Intelligence wheel hub storage warehouse
CN114074816B (en) * 2020-08-20 2024-04-09 长沙戴卡科技有限公司 Intelligent hub storage warehouse

Similar Documents

Publication Publication Date Title
CN201161820Y (en) First-in first-out dynamic storing apparatus for gross rubber
CN202622781U (en) Multilayer drawer type material frame
CN105383850A (en) Optimal configuration method for areas of steel reel storehouse
CN201987101U (en) Stereoscopic rolling rack
CN207631902U (en) A kind of automatic stereo storage quickly sorted
CN204262219U (en) Bottom Automatic Charging Device
CN106542463A (en) A piler, 3-D storing goods shelf and solid storing warehouse are stretched multistation more
CN207360653U (en) A kind of Steel tube packaging mechanism
CN204236520U (en) A kind of PCB web-like bonding sheet storing cart
CN206108078U (en) Garbage bin that can adapt to various sizes disposal bag
CN201472818U (en) Barreled bucket transport and storage device
CN206568135U (en) A kind of electric mine locomotive pantograph pan rack
CN109436557B (en) Hanging and placing rack for plastic pipes
CN205380647U (en) A frock for installation of car wiring harness annex material
CN205819597U (en) A kind of high efficiency automatic discharge apparatus
CN205166906U (en) Easy riser package material group frame
CN203006258U (en) Step-type rain-proof heavy-duty cantilever storage rack
CN112429450A (en) Intelligent warehouse logistics platform
CN207888305U (en) A kind of automatic loading and unloading mechanism of elongate rod
CN216002670U (en) Accomodate convenient commodity wholesale and use carrier
CN205819255U (en) A kind of textile cart
CN201472436U (en) Steel pipe transporting and stacking vehicle
CN206068399U (en) A kind of automatic stereo storehouse steel tray
CN204473671U (en) A kind of rack-layer structure for gravitational goods shelves
CN209240951U (en) A kind of shared bicycle boxcar of bulk transport

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20081210