CN201041926Y - Power line laying air upward three-wheel pulley - Google Patents

Power line laying air upward three-wheel pulley Download PDF

Info

Publication number
CN201041926Y
CN201041926Y CNU2007201045876U CN200720104587U CN201041926Y CN 201041926 Y CN201041926 Y CN 201041926Y CN U2007201045876 U CNU2007201045876 U CN U2007201045876U CN 200720104587 U CN200720104587 U CN 200720104587U CN 201041926 Y CN201041926 Y CN 201041926Y
Authority
CN
China
Prior art keywords
pulley
utility
pulleys
coaster
model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CNU2007201045876U
Other languages
Chinese (zh)
Inventor
赵新波
沈光陞
李海涛
徐鹏
李春
丁晓雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YUNNAN POWER TANSMISSION-SUBSTATION ENGINEERING CORP
Original Assignee
YUNNAN POWER TANSMISSION-SUBSTATION ENGINEERING CORP
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YUNNAN POWER TANSMISSION-SUBSTATION ENGINEERING CORP filed Critical YUNNAN POWER TANSMISSION-SUBSTATION ENGINEERING CORP
Priority to CNU2007201045876U priority Critical patent/CN201041926Y/en
Application granted granted Critical
Publication of CN201041926Y publication Critical patent/CN201041926Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Table Equipment (AREA)

Abstract

The utility model relates to an upturned three-wheeled pulley used for electric paying out. The upturned pulley is a pulley (2) coaxially arranged in an integrated way by three blocks. The utility model can put three ropes pulled by one hauling rope in an electric paying out construction into the three pulleys accurately without any human assistance and no artificial over climbing or rope distribution is needed when the rope head passes through the pulley, therefore, the operational procedure for operators is simplified effectively, the security risk is lowered and the efficient operation of construction is guaranteed.

Description

The electric power unwrapping wire is towards the sky three-fold block
Technical field
The utility model belongs to electric power releasing pulley technical field of structures.
Background technology
Utilize the remote control airship unwrapping wire to enter the construction that routinizes of electric power stringing at present, carry an elementary messenger, run through each basic iron tower of crossing over section, realize crossing in the air by dirigible.Yet, after dirigible is put logical elementary messenger, realize that every basic iron tower has five or eight pull rope, " one leads three " (three ropes of a rope band) construction that will utilize the elementary messenger of this root to carry out twice or three times realizes.Prior art be adopt three independent respectively each of installing only with a pulley towards the sky coaster, the fag end of three ropes will coming by the traction of fag end connecting plate straddles respectively on three pulleys, to carry out follow-up unwrapping wire.But when the fag end connecting plate strides across coaster, because three coasters are installed separately, the installation site is unfixing, distance between each coaster is unfixing yet, distance between adjacent two of three ropes holding with the fag end connecting plate often can not and adjacent two of three coasters between distance coincide, three ropes are difficult to be installed on exactly in the outer rim groove of three independent pulleys, and what needs were artificial crossed coaster to fag end, and manually three ropes was placed in respectively in each pulley.This mode need stop traction and carry out separated time, and not only holding time simultaneously, carries out separated time under the stressed bigger situation of rope, also has bigger potential safety hazard.In addition, when coaster was installed in lower position, stressed rope raised up and usually can rub with the members such as support that coaster is installed, and makes the rope fracture, causes construction to interrupt.
Summary of the invention
The purpose of this utility model provides a kind of artificial auxiliary three ropes of " leads three " can being placed to exactly in three pulleys of coaster that do not need in order to solve the deficiency that above-mentioned prior art exists just, save time, efficiently, safe electric power unwrapping wire is towards the sky three-fold block.
The purpose of this utility model is achieved by the following technical solution.
The electric power unwrapping wire is towards the sky three-fold block, and it is three coaxial pulleys that are installed as one towards the sky coaster.
The utility model correspondence above three pulleys is equipped with one or three fabric wheels; On the top of support the triangle link plate is installed.
Because three pulley coaxles towards the sky coaster are installed as one, the fixed-site of three pulleys, it is also fixing that the pulley outer rim is used to accept the groove location of rope, when carrying out " one leads three " construction, as long as adopt the suitable fag end connecting plate of size, make distance between adjacent two of three ropes of its pulling equal distance between the outer rim groove of adjacent two pulleys of coaster, just can in striding across the process of coaster, the fag end connecting plate exactly three ropes be installed in the groove of three pulleys, fag end no longer needs artificial crossing and separated time during by coaster, effectively simplified operating personnel's operation sequence, reduce security risk, ensure the efficient operation of construction.
The fabric wheel that is positioned at three pulley tops that the utility model is set, can be according to the size of the moment that raises up, selectivity is installed one or three fabric wheels, and the rope that passes pulley is pushed down, prevent that it from excessively raising up, avoid with coaster support or other member contact friction and rubbed.In cantilever tip the triangle link plate is installed, can be made the utility model that multiple use is arranged, as being used as lead or corner block.
Further set forth content of the present utility model below in conjunction with Figure of description.
Description of drawings
Fig. 1 is a front view of the present utility model;
Fig. 2 is a left view of the present utility model;
Fig. 3 is the schematic diagram that utilizes three lines of the utility model traction;
Fig. 4 is the line ball schematic diagram.
Embodiment
As shown in Figure 1 and Figure 2, the utility model comprises support 3, and frame bottom is equipped with the fixed head 4 of a band draw-in groove 9, and during use, the draw-in groove 9 by fixed head 4 bottoms and fastening bolt 5 are installed in the utility model on the electric power tower.One transverse axis 8 is installed on support, is coaxially installed on the transverse axis 8 towards three pulleys 2 of sky coaster and constitutes one.Triangle link plate 1 is installed on top at support 3.Before carrying out " one leads three " construction, fabric wheel 6 is not installed earlier.As shown in Figure 3, when carrying out " one leads three " construction, elementary messenger 10 is fastened top at triangle fag end connecting plate 11, three ropes 12 that are pulled are equidistantly fastened the bottom at fag end connecting plate 11, distance between adjacent two ropes 12 with equate towards the distance between adjacent two pulleys, the 2 outer rim grooves of sky coaster, elementary messenger 10 hauls fag end connecting plate 11 and strides across coaster, and three ropes 12 that fag end connecting plate 11 is leading promptly straddle respectively on three pulleys 2.After three rope straddle mountings were good, corresponding installation one or three fabric wheels 6 above three pulleys 2 were pushed down three ropes respectively again.Three fabric wheels 6 can be coaxially installed on the support 3 with axle 7.The utility model is as long as be equipped with the fag end connecting plate of the suitable special use of size, and the fag end connecting plate directly by coaster, just can successfully be installed on trailed three ropes in three pulleys, no longer need artificial separated time, not only save time, aspect personal security, higher guarantee has been arranged also.

Claims (3)

1. the electric power unwrapping wire is towards the sky three-fold block, comprise support (3) and be installed on the support towards the sky coaster, it is characterized in that described is three coaxial pulleys (2) that are installed as one towards the sky coaster.
2. electric power unwrapping wire according to claim 1 is characterized in that towards the sky three-fold block correspondence is equipped with one or three fabric wheels (10) in three pulleys (2) top.
3. electric power unwrapping wire according to claim 1 is characterized in that towards the sky three-fold block, on the top of support (3) triangle link plate (1) is installed.
CNU2007201045876U 2007-04-29 2007-04-29 Power line laying air upward three-wheel pulley Expired - Lifetime CN201041926Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007201045876U CN201041926Y (en) 2007-04-29 2007-04-29 Power line laying air upward three-wheel pulley

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007201045876U CN201041926Y (en) 2007-04-29 2007-04-29 Power line laying air upward three-wheel pulley

Publications (1)

Publication Number Publication Date
CN201041926Y true CN201041926Y (en) 2008-03-26

Family

ID=39253638

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007201045876U Expired - Lifetime CN201041926Y (en) 2007-04-29 2007-04-29 Power line laying air upward three-wheel pulley

Country Status (1)

Country Link
CN (1) CN201041926Y (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101510677B (en) * 2009-01-15 2011-01-05 国网直流工程建设有限公司 Method and system for unfolding conductor
CN101651306B (en) * 2009-08-21 2011-11-30 中国电力科学研究院 Asymmetric traction plate and matching stringing pulley for one-pull-three tension stringing
CN102611058A (en) * 2012-03-20 2012-07-25 河北省送变电公司 Traction device for primary stage of erecting transmission line
CN102142662B (en) * 2010-02-03 2012-10-10 北京送变电公司 Paying-off mechanism for rope expansion and guide of helicopter and auxiliary line-guiding paving mechanism
CN101877460B (en) * 2009-04-29 2013-04-10 国网交流工程建设有限公司 Extreme high voltage combined paying off pulley
CN103560433A (en) * 2013-11-07 2014-02-05 国家电网公司 Three-phase wire interphase imbalance tool
CN105305315A (en) * 2015-12-10 2016-02-03 四川电力送变电建设公司 Light pressing line tackle
CN107404088A (en) * 2016-10-10 2017-11-28 苏州高精特专信息科技有限公司 Antiwear device and power circuit laying method in a kind of unfolding for power circuit
AT520260A1 (en) * 2017-08-01 2019-02-15 Eqos Energie Oesterreich Gmbh Roll garlands battery
CN113642173A (en) * 2021-08-13 2021-11-12 广东电网有限责任公司广州供电局 High-simulation traction field construction simulation method based on laser cloud

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101510677B (en) * 2009-01-15 2011-01-05 国网直流工程建设有限公司 Method and system for unfolding conductor
CN101877460B (en) * 2009-04-29 2013-04-10 国网交流工程建设有限公司 Extreme high voltage combined paying off pulley
CN101651306B (en) * 2009-08-21 2011-11-30 中国电力科学研究院 Asymmetric traction plate and matching stringing pulley for one-pull-three tension stringing
CN102142662B (en) * 2010-02-03 2012-10-10 北京送变电公司 Paying-off mechanism for rope expansion and guide of helicopter and auxiliary line-guiding paving mechanism
CN102611058B (en) * 2012-03-20 2015-01-28 国家电网公司 Traction device for primary stage of erecting transmission line
CN102611058A (en) * 2012-03-20 2012-07-25 河北省送变电公司 Traction device for primary stage of erecting transmission line
CN103560433A (en) * 2013-11-07 2014-02-05 国家电网公司 Three-phase wire interphase imbalance tool
CN105305315A (en) * 2015-12-10 2016-02-03 四川电力送变电建设公司 Light pressing line tackle
CN107404088A (en) * 2016-10-10 2017-11-28 苏州高精特专信息科技有限公司 Antiwear device and power circuit laying method in a kind of unfolding for power circuit
CN107404088B (en) * 2016-10-10 2018-12-18 天津市浩源电力工程有限公司 A kind of antiwear device and power circuit laying method in power circuit unfolding
AT520260A1 (en) * 2017-08-01 2019-02-15 Eqos Energie Oesterreich Gmbh Roll garlands battery
AT520260B1 (en) * 2017-08-01 2019-09-15 Eqos Energie Oesterreich Gmbh Roll garlands battery
CN113642173A (en) * 2021-08-13 2021-11-12 广东电网有限责任公司广州供电局 High-simulation traction field construction simulation method based on laser cloud

Similar Documents

Publication Publication Date Title
CN201041926Y (en) Power line laying air upward three-wheel pulley
CN103401185B (en) A kind of Double-bundled-conductor racing vehicle
CN109610922B (en) Typical topography iron tower assemblage construction equipment
CN209554495U (en) A kind of power ampere puts line apparatus
CN106938824A (en) A kind of boom hoisting of electric equipment maintenance
CN202121256U (en) High voltage horizontal double-splitting line checking pulley
CN201033858Y (en) Tower height-adjustable double-rope freight ropeway
CN202121255U (en) Traction device for unreeling leading rope
CN102142662B (en) Paying-off mechanism for rope expansion and guide of helicopter and auxiliary line-guiding paving mechanism
CN103048759B (en) Paying-off robot and application thereof on erecting optical cables on 110kV circuit
CN207175188U (en) A kind of tractor-mounted helical elevator
CN201985472U (en) Pay-off mechanism and lead laying auxiliary mechanism for guide rope release of helicopter
CN204702975U (en) One is dried in the air cloth bar
CN204508488U (en) Device for preventing elevator from falling
CN208088954U (en) A kind of construction protective fence
CN203398633U (en) Manual transmission line double-wheel aerodyne
CN202131996U (en) Steel wire rope traction device of rotary drilling machine
CN205985971U (en) Special link plate structure of unwrapping wire coaster
CN208701560U (en) A kind of high speed highway guardrail upright post extracting apparatus
CN206188249U (en) Novel swift mounting structure of pull rod
CN208964427U (en) A kind of winch hoister rope broken protector
CN105633856B (en) Power circuit driving and the method that circuit deviation stockbridge damper is fetched using it
CN207633737U (en) A kind of safety suspension structure for building high-altitude construction for room
CN201268378Y (en) Power-down brake device of electric vehicle
CN202373941U (en) Hand winch with tail rope buffering and braking function for distribution line construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20080326