CN200971610Y - Guide lifting platform device for chimney - Google Patents

Guide lifting platform device for chimney Download PDF

Info

Publication number
CN200971610Y
CN200971610Y CN 200620136199 CN200620136199U CN200971610Y CN 200971610 Y CN200971610 Y CN 200971610Y CN 200620136199 CN200620136199 CN 200620136199 CN 200620136199 U CN200620136199 U CN 200620136199U CN 200971610 Y CN200971610 Y CN 200971610Y
Authority
CN
China
Prior art keywords
frame
chimney
hoisting
hoisting frame
handling frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 200620136199
Other languages
Chinese (zh)
Inventor
冯佳昱
郭孝良
徐俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CEEC ENERGY CHINA NWPC NO.4 ENGINEERING CO., LTD.
Original Assignee
Xibei Power Construction No4 Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xibei Power Construction No4 Engineering Co filed Critical Xibei Power Construction No4 Engineering Co
Priority to CN 200620136199 priority Critical patent/CN200971610Y/en
Application granted granted Critical
Publication of CN200971610Y publication Critical patent/CN200971610Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to a chimney lifting platform device in the concrete casting construction of the chimney building, which is composed of a derrick lifting along with the platform and a guide track lifting mechanism. The derrick lifting along with the platform is arranged on top of the guide track lifting mechanism; the guide track lifting mechanism that is attached on the concrete supporting wall of the chimney is composed of a bearing track plate as well as a handling frame and a hoisting frame that are driven by a power device, wherein the bearing track plate is composed of channel steel and is arranged on the supporting wall through two pairs of pull bolts; and the hoisting frame is sheathed in the handling frame whose two sides are provided with a channel steel guide track, while a trolley can roll and climb in the channel steel guide track is arranged on the two lateral walls of the hoisting frame; a plurality of handling frame pothooks and hoisting frame trolley pins that are fixedly connected with the baring track plate are respectively arranged on the handling frame and the hoisting frame. In work, the power device makes handling frame and hoisting frame alternately ascending and finally completes the casting construction of the whole chimney building.

Description

The guide tracked lifting platform device of chimney
Technical field
The utility model belongs to the architectural furniture technical field, relates to a kind of chimney lifting platform device that is used for chimney structure concrete casting construction.
Background technology
At present, hydraulic sliding mould construction technology and device in the building operations of reinforced concrete chimney, have been adopted more at large.Though this technology and device have characteristics such as construction period weak point, but exist some insoluble problems also, it mainly shows: owing to adopt hydraulic jack to come supporting template to rise in the construction, and the lifting of template often is to carry out under less than the situation of 1MPa at the last pouring sections of chimney wall concrete strength, so not only to expend steel in a large number, it is coarse also to be prone to concrete surface, chimney wall is easily by the drift of drawing crack and working platform generation center or phenomenon such as reverse, thereby causes being difficult to guarantee such as construction quality, construction safety lacks the generation of problems such as guarantee and execution control complexity.
The utility model content
The purpose of this utility model is the problem that prior art exists is solved, so provide a kind of simple in structure, save steel, the guide tracked lifting platform device of construction period chimney short, easy to operate, that can guarantee chimney construction quality and working security.
The technical solution that adopts is so for achieving the above object: the guide tracked lifting platform device of the chimney that is provided is by forming with a peaceful derrick and a cover guide rail hoisting mechanism.Be erected at guide rail hoisting mechanism top with peaceful derrick, being fitted with on it shakes the head hang material gin pole, radiation beam, central dram circle, in hang platform and Lifting basket etc.On the concrete tube wall of guide rail hoisting mechanism attached to chimney, it is formed by load track plate and by handling frame and hoisting frame that power set (hydraulic means or electronic deceleration device) drive, wherein load track plate is made of channel-section steel, it is installed on the barrel by two secondary split bolts, hoisting frame is set in the handling frame, the both sides of handling frame are provided with the channel-section steel guide rail, the roller that can roll and climb in the channel-section steel guide rail is being housed on the two side of hoisting frame, on handling frame and hoisting frame, also is being respectively equipped with a plurality of being used for and fixing handling frame hook and the hoisting frame roller pin that connects dress of load track plate.In the work, power set are located on the hoisting frame, and handling frame is being born the load with peaceful derrick.
The process that this device is committed to chimney construction is such: get load track plate it is adhered on the installation steel concrete barrel under construction by the mode of being arranged above and below successively by split bolt spare separately, hydraulic pressure or electric type power device are installed on the hoisting frame of guide rail hoisting mechanism, and hoisting frame is fixed on down in the pin-and-hole default on the load track plate by the hoisting frame roller pin; The forward device that turns on the power makes the power set that are fixed on the hoisting frame drive handling frame and rises along the hoisting frame roller, reach predetermined altitude after, in load track plate preformed hole, insert force-bearing pin, and make the hook of handling frame both sides hang the jail on force-bearing pin; Afterwards the fixed solution between hoisting frame and load track plate is removed, the device that oppositely turns on the power makes hoisting frame two side wheels up along handling frame channel-section steel guide rail, and then hoisting frame is that fulcrum rises along the load track with the handling frame; After putting in place, still fixed hoisting frame by the mode that the hoisting frame roller pin is fixed in the track plate pin-and-hole; On handling frame that has promoted and suspension bracket, install then, adjust, fixing inner and outer template, to radius, placing of concrete is laid bricks; Again from the disengaging of having constructed the concrete tube wall of handling frame bottom remove a joint load track plate, connect on original load-carrying member plate above, use after the leveling drawing female screw bolt to be fixed on the concrete tube wall; Hook on the unclamp operation frame, the forward device that turns on the power rises handling frame, and the handling frame fixing back in place and then the device that oppositely turns on the power again rise hoisting frame; Cycling is so again and again alternately risen load track plate, handling frame and hoisting frame, finally finishes the work progress of whole chimney structure.
The utility model is when being used for the construction of chimney structure; whole device is all attached on the steel concrete barrel; handling frame and hoisting frame promote mutually by the rotating of power; itself also rises device along with the rising of structure, can realize the synchronous construction of steel concrete barrel (urceolus), haydite concrete barrel (inner core), liner, cat ladder, signal platform etc. thus.The connection up and down of load track plate is simple and reliable in the guide rail hoisting mechanism, they both can be as the part of template in work progress, be again the hard point of all objects such as derrick, platform, hanging basket, controlled the radius of load track plate on barrel, also just controlled the radius of chimney.In addition, owing to adopted the multi pack mode that guarantees safety work, the guide rail hoisting mechanism is that the strong point promotes with load track plate, and all the load of construction equipment self is born by the barrel concrete structure that has certain intensity, steel had so both been saved, shortened the construction period, overcome again in the hydraulic slip-form technology that the concrete surface that occurs easily is coarse, chimney wall is easily by drawing crack and the drift of working platform generation center or phenomenon such as reverse, make quality of concrete that technologic assurance arranged, the physical dimension that chimney is constructed also is easy to control.Simple and reasonable, convenient and reliable operation of the present utility model, applied range and compliance are strong, and is all applicable to large-scale and small-sized chimney structure constructions such as monotubulars, sleeve, many.With regard to sliding form apparatus, can not construct winter, and device described in the utility model can be constructed in whole winter.
Description of drawings
Fig. 1 is the principle schematic of a specific embodiment structure of the present utility model.
Fig. 2 is the principle schematic of another specific embodiment structure of the present utility model.
Fig. 3 is the principle schematic (signal of A line of vision) of electric form-lifting mechanism in the device.
Fig. 4 is the connected mode schematic diagram (I enlarged drawing) of device hoisting frame and load track plate.
Fig. 5 is company's assembling structure schematic diagram of load track plate and concrete tube wall.
The specific embodiment
The utility model a kind of example structure as shown in Figure 1 by be fitted with on it shake the head hang material gin pole 2, radiation beam 8, central dram circle 9, in hang forming of platform 12 and Lifting basket 15 with peaceful derrick and the guide rail hoisting mechanism that is attached to chimney reinforced concrete barrel 16, its middle guide hoisting mechanism by branch be located at concrete tube wall 16 inboards and the outside inside and outside load track plate 6 ' and 6, internal and external dynamic device (reductor) 4 ' and 4, inside and outside handling frame 3 ' and 3 and inside and outside hoisting frame 5 ' and 5 form.Inside and outside hoisting frame 5 ', 5 is set in respectively in the inside and outside handling frame 3 ', 3, be provided with the channel-section steel guide rail 31 that constitutes by channel-section steel in the both sides of handling frame 3, at then corresponding dress on the two side of hoisting frame 5 by the roller 51 (seeing Fig. 3 for details) that can in handling frame channel-section steel guide rail, do to roll and climb.The front portion of handling frame 3 is provided with a plurality of being used for and the hook 32 of the fixing company of extension of load track plate 6, then is provided with a plurality of can roll also available block 53 and square steel pins 54 etc. in hoisting frame 5 front portions and is fixed on hoisting frame roller pin 52 (Fig. 4) on the track plate 6 in load track plate 6.Be used to make track plate 6 and chimney outer tube wall 16 connect dress split bolt 7 structure as shown in Figure 5, it comprises the high-strength bolt 73 and symmetrical two stressed collars 71 and two butterfly nuts 72 that are divided into bolt 73 outsides that are inserted in the concrete tube wall preformed hole, during installation, pass in the preformed hole that high-strength bolt 73 is left on chimney outer tube wall 16, be inserted in load track plate 6 ', 6 from bolt 73 two again, load onto stressed collar 71 successively and be screwed into butterfly spiral shell 72 in track plate 6 ', 6 outer ends then.After treating that load track plate 6 ', 6 installs, will operate (lifting) frame again and be fixed in the pin-and-hole of being opened in advance on the track plate by the fixedly multi pack spare on it.Label 10 is a bottle gouard moved by hands in the accompanying drawing; 11 is interior tube template; 13 are haydite concrete smoke evacuation barrel (inner core); 14 is refractory brick; 17 is interior compensation template; 18 is big diagonal brace; 33 is the handling frame roller.
The guide tracked lifting platform device of chimney described in the utility model also has a kind of one-sided form of implementation of establishing the guide rail hoisting mechanism as shown in Figure 2, promptly installs the form of structure that the middle guide hoisting mechanism is made up of the load-carrying member plate 6 that is located at concrete tube wall 16 outsides, reductor 4, handling frame 3 and hoisting frame 5.Relative Fig. 1 device, this structure has been cancelled a ring manipulation (liftings) frame of chimney inboard, and directly radiation beam 8 is placed on the handling frame 3 of the outside, and is inboard then with a common interior compensation steel form 17 replacement load track plates.This lifting platform device is mainly used in the building operations aspect of the less small-sized chimney of chimney breast radius.

Claims (3)

1, the guide tracked lifting platform device of a kind of chimney, by forming with peaceful derrick (1) with attached to the guide rail hoisting mechanism on the chimney concrete tube wall (16), being fitted with on peaceful derrick (1) shakes the head hangs material gin pole (2), radiation beam (8), central dram circle (9), in hang platform (12) and Lifting basket (15), it is characterized in that: the guide rail hoisting mechanism is formed by load track plate (6) and by handling frame (3) and hoisting frame (5) that power set drive, wherein load track plate (6) is made of channel-section steel, it is installed on the barrel (16) by two secondary split bolts (7), hoisting frame (5) is set in the handling frame (3), the both sides of handling frame (3) are provided with channel-section steel guide rail (31), the roller (51) that can roll and climb in channel-section steel guide rail (31) is being housed on the two side of hoisting frame (5), on handling frame (3) and hoisting frame (5), also is being respectively equipped with a plurality of being used for and fixing handling frame hook (32) and the hoisting frame roller pin (52) that connects dress of load track plate (6).
2, the guide tracked lifting platform device of chimney according to claim 1 is characterized in that: the guide rail hoisting mechanism is located at the inside and outside load track plate (6 ', 6) in concrete tube wall (16) inboard and the outside by branch and is made up of inside and outside handling frame (3 ', 3) and inside and outside hoisting frame (5 ', 5) that power set drive.
3, the guide tracked lifting platform device of chimney according to claim 1 is characterized in that: the guide rail hoisting mechanism is made up of the load-carrying member plate (6), handling frame (3) and the hoisting frame (5) that are located at concrete tube wall (16) outside.
CN 200620136199 2006-11-23 2006-11-23 Guide lifting platform device for chimney Expired - Lifetime CN200971610Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200620136199 CN200971610Y (en) 2006-11-23 2006-11-23 Guide lifting platform device for chimney

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200620136199 CN200971610Y (en) 2006-11-23 2006-11-23 Guide lifting platform device for chimney

Publications (1)

Publication Number Publication Date
CN200971610Y true CN200971610Y (en) 2007-11-07

Family

ID=38882868

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200620136199 Expired - Lifetime CN200971610Y (en) 2006-11-23 2006-11-23 Guide lifting platform device for chimney

Country Status (1)

Country Link
CN (1) CN200971610Y (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101566005B (en) * 2009-05-21 2011-04-06 山东丰汇设备技术有限公司 Chimney hydraulic mould lifting device
CN102535843A (en) * 2011-12-16 2012-07-04 马鞍山钢铁建设集团有限公司 Construction method of circular reinforced concrete chimney cylinder wall and hydraulic sliding mould device
CN102704664A (en) * 2012-05-30 2012-10-03 深圳市特辰科技股份有限公司 Self-lifting quick transferring platform
CN104030154A (en) * 2014-06-20 2014-09-10 山东电力建设第一工程公司 Multiple-lifting-point lifting and mounting device for chimneys
CN114541740A (en) * 2022-01-06 2022-05-27 上海建工一建集团有限公司 Integral steel platform formwork equipment for inclined wall construction and construction method thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101566005B (en) * 2009-05-21 2011-04-06 山东丰汇设备技术有限公司 Chimney hydraulic mould lifting device
CN102535843A (en) * 2011-12-16 2012-07-04 马鞍山钢铁建设集团有限公司 Construction method of circular reinforced concrete chimney cylinder wall and hydraulic sliding mould device
CN102535843B (en) * 2011-12-16 2014-03-12 马鞍山钢铁建设集团有限公司 Construction method of circular reinforced concrete chimney cylinder wall and hydraulic sliding mould device
CN102704664A (en) * 2012-05-30 2012-10-03 深圳市特辰科技股份有限公司 Self-lifting quick transferring platform
CN104030154A (en) * 2014-06-20 2014-09-10 山东电力建设第一工程公司 Multiple-lifting-point lifting and mounting device for chimneys
CN114541740A (en) * 2022-01-06 2022-05-27 上海建工一建集团有限公司 Integral steel platform formwork equipment for inclined wall construction and construction method thereof

Similar Documents

Publication Publication Date Title
CN201411900Y (en) Hydraulic die lifter for chimneys
CN102877637B (en) Method for implementing operating platform in bottom wall construction of cantilever beam
CN200971610Y (en) Guide lifting platform device for chimney
CN101566005B (en) Chimney hydraulic mould lifting device
CN102134832B (en) Movable support and movable support assisted method for erecting steel box beams through non-variable amplitude frame beam crane
CN213268983U (en) Self-climbing discharging platform
CN201647834U (en) Device for mounting tower equipment in narrow spaces
CN111648585A (en) Construction method and device of suspended support type steel truss platform
CN107724669A (en) A kind of aluminum alloy frame formwork structure of fast assembling-disassembling
CN201635390U (en) Automatic formwork supporting machine for high-rise building elevator shaft construction
CN2253370Y (en) Electric form-lifting construction equipment for chimney
CN2424259Y (en) Electric guide rail mould lifting construction appts. for chimney
CN214885625U (en) Multi-point prefabricated part mounting platform
CN2253371Y (en) Electric form-lifting equipment for chimney
CN201770429U (en) Portal type framework used for hoisting and slipping
CN200968057Y (en) Electric mould lifting construction arrangement for chimney
CN103084817B (en) The installation method of industry cylindrical furnace radiating furnace tube
CN206800201U (en) The compound Hanging basket on front support of single cable plane
CN2703077Y (en) Novel electric mould lifting construction device
CN205346600U (en) Big plate -girder hoist and mount specialized tool
CN219826079U (en) Attached scaffold for building construction
CN205976431U (en) Tube -shape structures hydraulic pressure slipform promotes construction platform
CN2491552Y (en) Electric mould lifting construction device
CN2424258Y (en) Electric mould lifting construction appts. for chimney
CN205444731U (en) Assembled prefabricated staircase subassembly

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: NORTHWEST ELECTRIC POWER CONSTRUCTION NO. 4 COMPAN

Free format text: FORMER NAME: XIBEI POWER CONSTRUCTION NO.4 ENGINEERING CO.

CP03 Change of name, title or address

Address after: 710038 No. 1198 spinning Road, Eastern Textile Town, Xi'an City, Shaanxi Province

Patentee after: CEEC ENERGY CHINA NWPC NO.4 ENGINEERING CO., LTD.

Address before: 710038 No. 108 spinning Road, Textile City, Shaanxi, Xi'an

Patentee before: Xibei Power Construction No.4 Engineering Co.

CX01 Expiry of patent term

Granted publication date: 20071107

EXPY Termination of patent right or utility model