CN1916289A - 菱形桁架式挂篮 - Google Patents

菱形桁架式挂篮 Download PDF

Info

Publication number
CN1916289A
CN1916289A CN 200610200824 CN200610200824A CN1916289A CN 1916289 A CN1916289 A CN 1916289A CN 200610200824 CN200610200824 CN 200610200824 CN 200610200824 A CN200610200824 A CN 200610200824A CN 1916289 A CN1916289 A CN 1916289A
Authority
CN
China
Prior art keywords
frame
upper frame
main couple
track
suspension
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 200610200824
Other languages
English (en)
Inventor
杨秋利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 200610200824 priority Critical patent/CN1916289A/zh
Publication of CN1916289A publication Critical patent/CN1916289A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

一种菱形桁架式挂篮,菱形主桁架由上框架、下框架、前框架、后框架连接成菱形,上框架向前下方倾斜,上框架前端与前框架的前端固定在前支座上,其上框架和后框架的上端固定在上支座上,其后框架和下框架的后端固定在后支座上,其下框架的前端和前框架的后端固定在下支座上;下支座与上支座之间连接门形后吊架,前支座上固定连接前吊梁;前吊梁和门形后吊架连接悬吊机构,前吊梁前面连辅助吊架,前吊梁后面与上框架之间连有拉杆,辅助吊架的前端连有吊杆,吊杆连接工作平台。本发明运行方便、质量轻、用钢量小,在≤6级风的情况下仍可以施工和移动,安全可靠,受力合理,适用于桥梁预应力钢筋混凝土施工。

Description

菱形桁架式挂篮
(一)技术领域
本发明涉及一种桥梁建筑施工装置,特别是一种桥梁施工模板吊挂装置。
(二)背景技术
桥梁施工挂篮是用于大跨径预应力混凝土悬臂桥梁及斜拉桥的施工装置。现有的桥梁施工用挂篮具体形式有:三角形挂篮、斜拉式挂篮、平行桁架式挂篮、悬臂式挂篮、平弦形、弓形挂篮等。现有桥梁挂篮存在的问题有:结构复杂,受力不尽合理,桁架中受到的最大拉力小于或等于最大压力,使所使用材料的截面不统一,受压杆的受力不合理,悬吊机构分配梁的长度过长;吊杆采用钢带,挂篮后端采用平衡配重,自身重量较大,用钢量较大,且行走移动不便。
(三)发明内容
本发明的目的是提供一种菱形桁架式挂篮,解决桥梁施工中挂篮结构复杂、受力欠合理、使所使用材料的截面不统一、受压杆的受力不合理、悬吊机构分配梁长度过长的问题;解决挂篮自身重量过大、耗钢量过大、行走移动不便的问题。
本发明的技术方案:
这种菱形桁架式挂篮,包括菱形主桁架、主桁架底部的行走机构、主桁架后端的锚固装置、经悬吊机构与主桁架连接的模板***;其特征在于:
菱形主桁架由上框架、下框架、前框架、后框架连接成菱形,上框架向前下方倾斜,上框架前端与前框架的前端固定在前支座上,其上框架和后框架的上端固定在上支座上,其后框架和下框架的后端固定在后支座上,其下框架的前端和前框架的后端固定在下支座上;下支座与上支座之间连接门形后吊架,行走机构安装在下支座底部,并支撑于轨道上;前支座上固定连接与门形后吊架平行的前吊梁;前吊梁和门形后吊架与悬吊机构连接,悬吊机构包括:吊杆、分配梁和滑梁;前吊梁前面连接辅助吊架,前吊梁后面的上边与上框架之间连有拉杆,辅助吊架与吊杆连接,吊杆下端连接工作平台。
上述上框架向下的倾斜角度可为16-20度。
上述锚固装置为连接在主桁架和轨道之间的丝杠。
上述主桁架在下支座与轨道之间连接主油缸,在下框架与轨道之间连接推进油缸,在后支座与轨道之间连接张拉油缸。
上述吊杆是螺纹钢杆。
本发明与现有传统技术相比具有的有益效果:本发明结构简单,结构和受力更加合理,桁架中受到的最大拉力略大于最大压力,便于统一材料的截面,同时受压杆的受力更加合理,且使与之相连的分配梁长度缩短。吊杆采用精轧螺纹钢,拉力增加,重量减少。挂篮后端采用锚固丝杠代替平衡配重,节约了用钢量,进一步减轻了挂篮自身重量。主桁架采用国内生产的高强度低合金轻质钢材,采用主油缸、推进油缸和张拉油缸调节主桁架的移动和行走方式,本发明在≤6级风的情况下均可以施工和移动,安全可靠,运行方便,收、支模板及挂篮移动均实现自动化及半自动化。适用于大桥、特大桥梁预应力钢筋混凝土连续梁灌注。
(四)附图说明
图1是本发明的结构示意图。
图2中轴线右侧为图1的A-A剖面图。
图2中轴线左侧为图1的B-B剖面图。
图中:1-主桁架;2行走机构;3-辅助吊架;4-吊杆;5-推进油缸;6-锚固装置;7-张拉油缸;8-轨道;9-模板***;10-工作平台;11-分配梁;12-主油缸;13滑梁;14-底模支架;15-拉杆;16-桥梁。
101-上框架;102-后框架;103-门形后吊架;104-前框架;105-下框架;106-上支座;107-下支座;108-前支座;109-后支座;110-前吊梁。
(五)具体实施方式
实施例参见图1、2,这种菱形桁架式挂篮,主要包括菱形主桁架1、主桁架底部的行走机构22、主桁架后端的锚固装置6、经悬吊机构与主桁架连接的模板***9。上述锚固装置为连接主桁架和轨道的丝杠。
参见图1,菱形主桁架1由上框架101、下框架105、前框架104、后框架102连接成菱形,上框架101向前下方倾斜18度,上框架101前端与前框架104的前端固定在前支座108上,其上框架101和后框架102的上端固定在上支座106上,其后框架102和下框架105的后端固定在后支座109上,其下框架105的前端和前框架104的后端固定在下支座107上;下支座107与上支座106之间连接门形后吊架103,行走机构安装在下支座107底部,并支撑于轨道8上;前支座108上固定连接与门形后吊架103平行的前吊梁110;前吊梁110和门形后吊架103的两边向下方连接悬吊机构,门形后吊架103由横梁、竖杆和弦杆固定连接而成。
前吊梁110前面连接辅助吊架3,前吊梁后面的上边与上框架之间连有拉杆15,辅助吊架与吊杆4连接,吊杆下端连接工作平台10。
悬吊机构包括:吊杆4、分配梁11和滑梁13。上述吊杆4采用φ32和φ25精轧螺纹钢杆。
上述主桁架在下支座107与轨道8之间连接主油缸12,在下框架105与轨道8之间连接推进油缸5,在后支座109与轨道8之间连接张拉油缸7。施工时,主油缸12为自锁式高压油缸,工作压力为43Mpa;推进油缸5和张拉油缸7的工作压力为16Mpa。
在挂篮上可以完成模板***9的悬吊、安装、钢筋绑扎、管道安装、混凝土浇筑、预应力张拉、压浆等工作,混凝土浇筑完毕后,挂篮由前吊梁和门形后吊架吊着向下移动一段距离,使桥体整体脱模;然后,挂篮解除后锚固装置,沿轨道8移向新的挂篮施工位置。
上述菱形主桁架采用高强度低合金轻质钢材制作,模板***可以采用钢木结合的形式,整套挂篮配有液压千斤顶和泵站及电控部分,以保证施工的机械化和自动化。

Claims (5)

1.一种菱形桁架式挂篮,包括菱形主桁架、主桁架底部的行走机构、主桁架后端的锚固装置、经悬吊机构与主桁架连接的模板***;其特征在于:
菱形主桁架由上框架、下框架、前框架、后框架连接成菱形,上框架向前下方倾斜,上框架前端与前框架的前端固定在前支座上,其上框架和后框架的上端固定在上支座上,其后框架和下框架的后端固定在后支座上,其下框架的前端和前框架的后端固定在下支座上;下支座与上支座之间连接门形后吊架,行走机构安装在下支座底部,并支撑于轨道上;前支座上固定连接与门形后吊架平行的前吊梁;前吊梁和门形后吊架与悬吊机构连接,悬吊机构包括:吊杆、分配梁和滑梁;前吊梁前面连接辅助吊架,前吊梁后面的上边与上框架之间连有拉杆,辅助吊架与吊杆连接,吊杆下端连接工作平台。
2.根据权利要求1所述的菱形桁架式挂篮,其特征在于:上述上框架向下的倾斜角度为16-20度。
3.根据权利要求1所述的菱形桁架式挂篮,其特征在于:上述锚固装置为连接在主桁架和轨道之间的丝杠。
4.根据权利要求1所述的菱形桁架式挂篮,其特征在于:上述主桁架在下支座与轨道之间连接主油缸,在下框架与轨道之间连接推进油缸,在后支座与轨道之间连接张拉油缸。
5.根据权利要求1所述的菱形桁架式挂篮,其特征在于:上述吊杆是螺纹钢杆。
CN 200610200824 2006-08-28 2006-08-28 菱形桁架式挂篮 Pending CN1916289A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200610200824 CN1916289A (zh) 2006-08-28 2006-08-28 菱形桁架式挂篮

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200610200824 CN1916289A (zh) 2006-08-28 2006-08-28 菱形桁架式挂篮

Publications (1)

Publication Number Publication Date
CN1916289A true CN1916289A (zh) 2007-02-21

Family

ID=37737345

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200610200824 Pending CN1916289A (zh) 2006-08-28 2006-08-28 菱形桁架式挂篮

Country Status (1)

Country Link
CN (1) CN1916289A (zh)

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101219755B (zh) * 2007-12-14 2010-06-02 中铁大桥局股份有限公司 重型架梁起重机
CN101250856B (zh) * 2007-08-30 2010-08-04 中铁大桥局集团第一工程有限公司 梯形挂篮及其施工方法
CN101476288B (zh) * 2008-12-08 2010-12-29 中铁十五局集团有限公司 一种t型桥梁翼缘板现浇移动模架
CN101555680B (zh) * 2009-04-14 2011-01-26 中铁一局集团有限公司 斜拉桥无索区大跨度π型悬臂梁施工工艺
CN102041779A (zh) * 2010-12-29 2011-05-04 中铁大桥局集团第二工程有限公司 一种桥面吊机及其施工方法
CN101508403B (zh) * 2009-03-06 2011-05-25 武桥重工集团股份有限公司 利用三吊点超静定起重***的架梁起重机
CN102102342A (zh) * 2010-12-30 2011-06-22 广东省航盛建设集团有限公司 菱形挂篮整体结构式后上横梁
CN102134834A (zh) * 2011-04-29 2011-07-27 湖南中铁五新钢模有限责任公司 一种小墩顶施工菱形挂篮
CN102174796A (zh) * 2011-04-06 2011-09-07 湖南中铁五新钢模有限责任公司 一种主桁下置式悬浇施工挂篮
CN102220740A (zh) * 2011-04-13 2011-10-19 湖南中铁五新钢模有限责任公司 一种高速铁路四线宽幅连续梁悬灌施工挂篮
CN102330414A (zh) * 2011-08-09 2012-01-25 中铁十二局集团第二工程有限公司 大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法
CN102345273A (zh) * 2010-08-02 2012-02-08 广东省长大公路工程有限公司 连续刚构桥施工挂篮的同步移篮装置
CN102359074A (zh) * 2011-08-09 2012-02-22 贵州路桥集团有限公司 上置斜爬式挂篮
CN102758404A (zh) * 2012-07-19 2012-10-31 中铁十六局集团第一工程有限公司 空间倒八字索斜拉桥前支点挂篮行走装置
CN104452590A (zh) * 2013-09-16 2015-03-25 同济大学 一种桥面吊机结构
CN107893377A (zh) * 2017-11-27 2018-04-10 中交路桥华南工程有限公司 斜拉桥桥面吊机底篮***的现场拼装方法
CN108360395A (zh) * 2018-04-27 2018-08-03 中交武汉港湾工程设计研究院有限公司 一种桥梁长大节段箱梁施工挂篮、挂篮的混凝土箱梁施工结构、挂篮的钢箱梁施工结构
CN109667228A (zh) * 2019-01-24 2019-04-23 中铁十六局集团第五工程有限公司 一种直梁式挂篮及连续梁悬臂浇筑施工方法
CN113944115A (zh) * 2021-11-15 2022-01-18 上海市基础工程集团有限公司 用于大跨径斜拉桥砼主梁拆除的全自动一体化拆桥机

Cited By (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101250856B (zh) * 2007-08-30 2010-08-04 中铁大桥局集团第一工程有限公司 梯形挂篮及其施工方法
CN101219755B (zh) * 2007-12-14 2010-06-02 中铁大桥局股份有限公司 重型架梁起重机
CN101476288B (zh) * 2008-12-08 2010-12-29 中铁十五局集团有限公司 一种t型桥梁翼缘板现浇移动模架
CN101508403B (zh) * 2009-03-06 2011-05-25 武桥重工集团股份有限公司 利用三吊点超静定起重***的架梁起重机
CN101555680B (zh) * 2009-04-14 2011-01-26 中铁一局集团有限公司 斜拉桥无索区大跨度π型悬臂梁施工工艺
CN102345273B (zh) * 2010-08-02 2015-04-15 广东省长大公路工程有限公司 连续刚构桥施工挂篮的同步移篮装置
CN102345273A (zh) * 2010-08-02 2012-02-08 广东省长大公路工程有限公司 连续刚构桥施工挂篮的同步移篮装置
CN102041779A (zh) * 2010-12-29 2011-05-04 中铁大桥局集团第二工程有限公司 一种桥面吊机及其施工方法
CN102102342A (zh) * 2010-12-30 2011-06-22 广东省航盛建设集团有限公司 菱形挂篮整体结构式后上横梁
CN102174796A (zh) * 2011-04-06 2011-09-07 湖南中铁五新钢模有限责任公司 一种主桁下置式悬浇施工挂篮
CN102174796B (zh) * 2011-04-06 2012-07-25 湖南中铁五新钢模有限责任公司 一种主桁下置式悬浇施工挂篮
CN102220740A (zh) * 2011-04-13 2011-10-19 湖南中铁五新钢模有限责任公司 一种高速铁路四线宽幅连续梁悬灌施工挂篮
CN102220740B (zh) * 2011-04-13 2012-09-26 湖南中铁五新钢模有限责任公司 一种高速铁路四线宽幅连续梁悬灌施工挂篮
CN102134834A (zh) * 2011-04-29 2011-07-27 湖南中铁五新钢模有限责任公司 一种小墩顶施工菱形挂篮
CN102330414A (zh) * 2011-08-09 2012-01-25 中铁十二局集团第二工程有限公司 大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法
CN102359074A (zh) * 2011-08-09 2012-02-22 贵州路桥集团有限公司 上置斜爬式挂篮
CN102330414B (zh) * 2011-08-09 2013-04-03 中铁十二局集团第二工程有限公司 大跨连续刚构梁边跨现浇梁段的挂篮悬浇施工方法
CN102359074B (zh) * 2011-08-09 2013-07-03 贵州路桥集团有限公司 上置斜爬式挂篮
CN102758404B (zh) * 2012-07-19 2014-01-08 中铁十六局集团第一工程有限公司 空间倒八字索斜拉桥前支点挂篮行走装置
CN102758404A (zh) * 2012-07-19 2012-10-31 中铁十六局集团第一工程有限公司 空间倒八字索斜拉桥前支点挂篮行走装置
CN104452590A (zh) * 2013-09-16 2015-03-25 同济大学 一种桥面吊机结构
CN107893377A (zh) * 2017-11-27 2018-04-10 中交路桥华南工程有限公司 斜拉桥桥面吊机底篮***的现场拼装方法
CN107893377B (zh) * 2017-11-27 2019-06-21 中交路桥华南工程有限公司 斜拉桥桥面吊机底篮***的现场拼装方法
CN108360395A (zh) * 2018-04-27 2018-08-03 中交武汉港湾工程设计研究院有限公司 一种桥梁长大节段箱梁施工挂篮、挂篮的混凝土箱梁施工结构、挂篮的钢箱梁施工结构
CN109667228A (zh) * 2019-01-24 2019-04-23 中铁十六局集团第五工程有限公司 一种直梁式挂篮及连续梁悬臂浇筑施工方法
CN109667228B (zh) * 2019-01-24 2024-02-02 中铁十六局集团第五工程有限公司 一种直梁式挂篮及连续梁悬臂浇筑施工方法
CN113944115A (zh) * 2021-11-15 2022-01-18 上海市基础工程集团有限公司 用于大跨径斜拉桥砼主梁拆除的全自动一体化拆桥机
CN113944115B (zh) * 2021-11-15 2023-03-31 上海市基础工程集团有限公司 用于大跨径斜拉桥砼主梁拆除的全自动一体化拆桥机

Similar Documents

Publication Publication Date Title
CN1916289A (zh) 菱形桁架式挂篮
CN201826525U (zh) 建筑爬升模板体系装置
CN102261039B (zh) 网状系杆拱桥的整体顶推施工法
CN103074854B (zh) 后支点三角托架挂篮及应用该挂篮的桥梁施工方法
CN108004927B (zh) 双肢三角挂篮及大跨度连续刚构桥悬臂梁段施工方法
CN101029472A (zh) 索面斜拉桥的塔柱及其施工方法
CN101806038A (zh) 曲线箱梁滑移模架及施工方法
CN200967931Y (zh) 悬浇拱桥的侧桁式挂篮
CN101210419A (zh) 小半径曲线混凝土箱梁施工用内外梁***造桥机及其施工方法
CN101220580A (zh) 钢桁梁纵向多点连续拖拉施工方法
CN2597531Y (zh) 单索面牵索挂篮
CN102797227A (zh) 倒挂式三角斜爬挂篮的施工方法
CN105839549A (zh) 一种桁架式悬臂施工挂篮
WO2023016573A1 (zh) 一种斜拉桥钢混主梁的施工方法
CN1123861A (zh) 预应力混凝土斜拉桥短平台复合型牵索挂篮施工工艺
CN209456892U (zh) 斜拉桥钢悬挑人行道结构
CN101403246B (zh) 大吨位吊车单层厂房组合柱及单层厂房组合柱结构的制作方法
CN211815595U (zh) 用于索塔的下塔柱拉压结构
CN2732820Y (zh) 挂篮主桁后锚转换装置
CN202936737U (zh) 波形钢腹板连续梁挂篮吊装结构
CN201665942U (zh) 整体钢筋混凝土预应力空心板张拉机
CN214573768U (zh) 一种门槽二期混凝土浇筑自爬升滑模浇筑***
CN2263134Y (zh) 短平台复合型牵索式挂篮
CN1058311C (zh) 用应急抢修钢梁拼组的造桥机
CN202830730U (zh) 桥梁小角度斜跨构造

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication