CN1800495A - Grooved steel-concrete combination beam - Google Patents

Grooved steel-concrete combination beam Download PDF

Info

Publication number
CN1800495A
CN1800495A CN 200610002139 CN200610002139A CN1800495A CN 1800495 A CN1800495 A CN 1800495A CN 200610002139 CN200610002139 CN 200610002139 CN 200610002139 A CN200610002139 A CN 200610002139A CN 1800495 A CN1800495 A CN 1800495A
Authority
CN
China
Prior art keywords
steel
concrete
steel box
box beam
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200610002139
Other languages
Chinese (zh)
Other versions
CN100395410C (en
Inventor
聂建国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tsinghua University
Original Assignee
Tsinghua University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tsinghua University filed Critical Tsinghua University
Priority to CNB2006100021395A priority Critical patent/CN100395410C/en
Publication of CN1800495A publication Critical patent/CN1800495A/en
Application granted granted Critical
Publication of CN100395410C publication Critical patent/CN100395410C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Rod-Shaped Construction Members (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to a groove steel-concrete integration beam, belonging to the bridge support element area, which can be used in track bridge; railway bridge; and road Bridge. The invention comprises a steel box beam whose top is open, concrete filled in the inner side of steel box beam and the anti-cutting connection element welded on the inner side of steel box beam. wherein, said open steel box beam is formed by a bottom plate and a middle plate, whose sections are in U or W shape; the anti-cutting connection element can integrate the steel beam and the concrete as a whole to display the anti-compression property of concrete; the steel plate can resist the pulling stress of each direction and avoid surface breakage; and the anti-cutting connection element can transfer the shearing force between steel box beam and concrete and avoid their separation. The invention has the advantages of simple operation, application of avoiding surface breakage and wider application prospect, as well as the advantages of initial stress concrete groove beam.

Description

Grooved steel-concrete combination beam
Technical field
The present invention relates to a kind of grooved steel-concrete combination beam that can be applicable to city rail bridge, railroad bridge and highway bridge.Belong to the bridge construction technical field.
Background technology
Traditional city rail elevated bridge generally adopts deck type box-type section or T type cross section, and the building integral height is big.Not only bigger to the civic landscape influence, the dough figurine group causes sense of depression over the ground, and easily near resident is produced noise jamming.Trough girder is a kind of form of structure that functions such as carrying, noise reduction and operation system are organically combined, and can reach the purpose that reduces structure height and reduce vision, noise pollution simultaneously.With respect to the deck type beam bridge, the trough girder in U type cross section can utilize bearing plate track and train, reduces track absolute altitude and integral bridge height, reduces the influence to surrounding enviroment; But girder is the double as noise barrier simultaneously, has saved sound insulating panel, helps reducing pollution from environmental noise; U type beam inboard is easy to arrange equipment such as communication, electric power, the space availability ratio height in whole cross section; The top flange can be used as access path and passenger's emergency evacuation passage or uses as the part of platform; Defencive function when having derail.Existing trough girder all adopts the prestressed reinforced concrete scheme, is subjected to the restriction of prestressed concrete own characteristic, and the particularly too complicated construction technology and the reduction of durability afterwards that is easy to ftracture and ftracture bring a lot of difficulties for the application of trough girder.
Summary of the invention
The purpose of this invention is to provide a kind of grooved steel-concrete combination beam that can significantly improve structural bearing capacity, rigidity, cracking resistance and workability.
Technical scheme of the present invention is as follows:
A kind of grooved steel-concrete combination beam is characterized in that: this compound beam is by open-topped steel case beam, is cast in the steel concrete of steel case beam inboard and the shear connector that is welding on the steel case beam inboard constitutes; Described opening steel case beam is made up of base plate and web, and its section adopts U type or W type.
Technical characterictic of the present invention also is: the upper end of described web is provided with top board, concreting on the top board.Described shear connector adopts peg.
The present invention has the following advantages with respect to prior art and the high-lighting effect: the present invention is combined by grooved girder steel and concrete two parts, and steel work is a produce in factory partly, is easy to ensure the quality of products; Concrete directly utilizes steel plate to carry out cast in situs, and non-mould construction also is easy to control quality; Steel work part weight is lighter, brings convenience to installation in position; Structure tensile region encased steel plate has been avoided concrete cracking, and is convenient to safeguard good endurance; Structure construction is simple, and the girder steel base plate all can be given full play to tensile strength horizontal and vertical, with respect to prestressed reinforced concrete construction simplified construction greatly, avoids the difficulty of reinforcing bar binding, welding and prestressing force two directions tension; Bearing and joint construction are simple, by bolt or welding, can form multi-joint structure easily, thereby can further strengthen the rigidity of structure and improve the comfortableness of driving.
Description of drawings
Fig. 1 is the schematic cross-section of U type cross section monorail grooved compound beam.
Fig. 2 is the schematic cross-section of U type cross section two-rail grooved compound beam.
Fig. 3 is the schematic cross-section of W type cross section two-rail grooved compound beam.
The specific embodiment
Below in conjunction with accompanying drawing, the specific embodiment of the present invention is further described.
The invention provides the grooved steel-concrete combination beam that can significantly improve structural bearing capacity, rigidity, cracking resistance and workability.In Fig. 1, Fig. 2 and grooved steel-concrete combination beam structural representation shown in Figure 3, melting welding shear connector 3 on prefabricated profiled upper opening steel case beam.At the medial surface concreting 2 of steel case beam, and be combined into one with steel case beam.Dispose the steel bar stress and the distributing bar of some in the concrete 2.
Working procedure of the present invention is:
Grooved steel-concrete combination beam of the present invention is made up of steel work and back pouring concrete two parts, and the two is combined into whole co-operation by the shear connector 3 of melting welding on steel plate.Steel case beam is made up of base plate 4 and web 5, and its section form is determined according to instructions for use, can be U type or W type, and steel plate thickness calculates definite according to beam span and beam width.For striding the less situation in footpath, web 5 should occupy the total height.For striding the bigger situation in footpath,, can be provided with top board 6 in web 5 upper ends for improving the bearing capacity and the rigidity of combined beam structure.Concrete 2 planted agents are provided with reinforcing bar as required, are used to improve the shear-carrying capacity of shear connector, participate in whole stressed to improve the bearing capacity of combined beam structure simultaneously.The thickness of concrete 2 is 100~300mm.Shear connector 3 generally should adopt peg, needs melting welding in base plate 4, web 5 and top board 6 a concrete side to be arranged, peg diameter 16~22mm, and height 80~220mm, spacing 100~250mm can adopt rectangular mesh shape or plum blossom shape to arrange.

Claims (3)

1. grooved steel-concrete combination beam is characterized in that: this compound beam is by open-topped steel case beam, is cast in the steel concrete (2) of steel case beam inboard and the shear connector (3) that is welding on the steel case beam inboard constitutes; Described opening steel case beam is made up of base plate (4) and web (5), and its section adopts U type or W type.
2. according to the described grooved steel-concrete combination beam of claim 1, it is characterized in that: be provided with top board (6) in the upper end of described web (5), top board (6) is gone up concreting (7).
3. according to claim 1 or 2 grooved steel-concrete combination beams, it is characterized in that: described shear connector adopts peg.
CNB2006100021395A 2006-01-19 2006-01-19 Grooved steel-concrete combination beam Expired - Fee Related CN100395410C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2006100021395A CN100395410C (en) 2006-01-19 2006-01-19 Grooved steel-concrete combination beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2006100021395A CN100395410C (en) 2006-01-19 2006-01-19 Grooved steel-concrete combination beam

Publications (2)

Publication Number Publication Date
CN1800495A true CN1800495A (en) 2006-07-12
CN100395410C CN100395410C (en) 2008-06-18

Family

ID=36810681

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2006100021395A Expired - Fee Related CN100395410C (en) 2006-01-19 2006-01-19 Grooved steel-concrete combination beam

Country Status (1)

Country Link
CN (1) CN100395410C (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102619163A (en) * 2012-04-13 2012-08-01 清华大学 Middle bearing type opened-box-section steel-concrete combination beam and construction method thereof
CN102691256A (en) * 2012-04-13 2012-09-26 清华大学 Composite channel steel-concrete beam employing novel shear connector and construction method
CN104099859A (en) * 2014-06-20 2014-10-15 中铁大桥勘测设计院集团有限公司 Road and railway double-layer steel-concrete combined beam
CN104452568A (en) * 2014-11-28 2015-03-25 林同棪国际工程咨询(中国)有限公司 Steel plate girder pedestrian overbridge
CN106758745A (en) * 2016-12-30 2017-05-31 长沙理工大学 Arch bridge and construction method thereof
CN108193600A (en) * 2018-01-04 2018-06-22 武汉理工大学 Improve the method for long-span continuous rigid-framed bridge cracking resistance and composite structure box beam
CN111910500A (en) * 2020-02-21 2020-11-10 清华大学 Anti-overturning combined bridge and construction method
CN111979896A (en) * 2020-08-26 2020-11-24 中铁二院工程集团有限责任公司 Groove-shaped combination beam of pre-buried profile steel
CN112049007A (en) * 2020-09-21 2020-12-08 湖南工学院 Channel steel-concrete composite beam and manufacturing method thereof
CN114232462A (en) * 2021-12-29 2022-03-25 哈尔滨工业大学 Urban rail transit corrugated steel-concrete U-shaped combination beam and construction method thereof

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102286915B (en) * 2011-08-30 2013-06-19 北京城建设计研究总院有限责任公司 Urban railway traffic continuous basin type beam

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1064907A (en) * 1992-04-07 1992-09-30 四川省交通厅公路规划勘察设计院 Wire-mesh cement thin-walled box-girder
JP4348601B2 (en) * 2003-01-21 2009-10-21 株式会社Ihi Synthetic floor slab girder
CN1324198C (en) * 2004-04-01 2007-07-04 蔡耀中 Shape steel-concrete combined beam
CN1320210C (en) * 2005-04-06 2007-06-06 湖南大学 Steel-concrete combination backbone beam with big cantilever corrugated steel web overhanging beam

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102619163A (en) * 2012-04-13 2012-08-01 清华大学 Middle bearing type opened-box-section steel-concrete combination beam and construction method thereof
CN102691256A (en) * 2012-04-13 2012-09-26 清华大学 Composite channel steel-concrete beam employing novel shear connector and construction method
CN104099859A (en) * 2014-06-20 2014-10-15 中铁大桥勘测设计院集团有限公司 Road and railway double-layer steel-concrete combined beam
CN104452568A (en) * 2014-11-28 2015-03-25 林同棪国际工程咨询(中国)有限公司 Steel plate girder pedestrian overbridge
CN106758745A (en) * 2016-12-30 2017-05-31 长沙理工大学 Arch bridge and construction method thereof
CN108193600A (en) * 2018-01-04 2018-06-22 武汉理工大学 Improve the method for long-span continuous rigid-framed bridge cracking resistance and composite structure box beam
CN108193600B (en) * 2018-01-04 2019-06-25 武汉理工大学 Improve the method and composite structure box beam of long-span continuous rigid-framed bridge cracking resistance
CN111910500A (en) * 2020-02-21 2020-11-10 清华大学 Anti-overturning combined bridge and construction method
CN111979896A (en) * 2020-08-26 2020-11-24 中铁二院工程集团有限责任公司 Groove-shaped combination beam of pre-buried profile steel
CN112049007A (en) * 2020-09-21 2020-12-08 湖南工学院 Channel steel-concrete composite beam and manufacturing method thereof
CN114232462A (en) * 2021-12-29 2022-03-25 哈尔滨工业大学 Urban rail transit corrugated steel-concrete U-shaped combination beam and construction method thereof
CN114232462B (en) * 2021-12-29 2024-05-03 哈尔滨工业大学 Urban rail transit corrugated steel-concrete U-shaped composite beam and construction method thereof

Also Published As

Publication number Publication date
CN100395410C (en) 2008-06-18

Similar Documents

Publication Publication Date Title
CN100395410C (en) Grooved steel-concrete combination beam
CN2839363Y (en) Stayed-cable bridge steel-concrete box shape combined bridge girder
US9222225B2 (en) Pre-stressed concrete track slab of slab-type ballast-less track
CN102286915B (en) Urban railway traffic continuous basin type beam
CN204919302U (en) Few main girder structure of wave form steel web
CN203639802U (en) Large-span railway cable-stayed bridge girder structure
CN108149532A (en) A kind of magnetic levitation track traffic two-wire simply supported beam
CN105133486A (en) Corrugated steel web few-main-beam structure
KR101256130B1 (en) ease precast girder and bridge using the same
CN101200871A (en) Bottom bearing trough girder for rail traffic station
CN206328669U (en) The narrow composite beam of steel box of new concrete
CN104612000A (en) Rubber spacer light track structure with vibration reduction and noise reduction functions
CN113652948A (en) High-speed railway cable-stayed bridge with improved rigidity
CN108677679A (en) Overhead steel reinforced concrete combination beam
CN103726440B (en) A kind of pipe web grider and preparation method thereof
CN201390928Y (en) Support rail continuous beam in double track railway
CN109930469B (en) Steel box girder thin-wall pier rigid frame cable-stayed bridge suitable for straddle type monorail
CN2575148Y (en) Balance device for obstructing passage of vehicle
CN2758310Y (en) Biblock type rail bearing
CN101200872B (en) Bottom bearing box beam for rail traffic station
CN110886191A (en) Prestressed concrete-steel composite beam and preparation method thereof
KR101042379B1 (en) A multi-storied continuous rahmen bridge with both sides connected by cross beam and construction method
CN103911948B (en) Be applied to horizontal purlin formula steel work and the construction method thereof of wide concrete rib plate-girder
CN114232462B (en) Urban rail transit corrugated steel-concrete U-shaped composite beam and construction method thereof
CN105696455A (en) Box type web simply supported U-shaped girder of double-track railway

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080618