CN1773402A - Stacking shop traveller and ground reclaimer interlocking protecting method and apparatus - Google Patents

Stacking shop traveller and ground reclaimer interlocking protecting method and apparatus Download PDF

Info

Publication number
CN1773402A
CN1773402A CN 200510200654 CN200510200654A CN1773402A CN 1773402 A CN1773402 A CN 1773402A CN 200510200654 CN200510200654 CN 200510200654 CN 200510200654 A CN200510200654 A CN 200510200654A CN 1773402 A CN1773402 A CN 1773402A
Authority
CN
China
Prior art keywords
travelling crane
overhead travelling
stacking overhead
plc system
detector switch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200510200654
Other languages
Chinese (zh)
Other versions
CN100419602C (en
Inventor
祁晓牧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CNB200510200654XA priority Critical patent/CN100419602C/en
Publication of CN1773402A publication Critical patent/CN1773402A/en
Application granted granted Critical
Publication of CN100419602C publication Critical patent/CN100419602C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Control And Safety Of Cranes (AREA)
  • Carriers, Traveling Bodies, And Overhead Traveling Cranes (AREA)

Abstract

The present invention discloses a stacking overhead crane and ground conveyer interlocking protecting method. Said method includes the following steps: using detection switch to detect stacking overhead crane position over the ground coveyer which is controlled by program controller PLC system, transferring the action signal of detection switch to the program controller PLC system of working station to which said ground conveyer is belonged, according to said signal said program controller PLC system can lock said ground conveyer to stop its operation. All the 'locking' and 'releasing' operations can be automatically implemented by PLC system.

Description

Stacking overhead travelling crane and ground reclaimer interlocking protecting method and device
Technical field:
The present invention relates to a kind of stacking overhead travelling crane and ground reclaimer interlocking protecting method and device; particularly a kind of when preventing that stacking overhead travelling crane from taking, putting the charcoal piece on floor conveyor; because of the floor conveyor error starting causes the bad stacking overhead travelling crane of hanging equipment clashing and breaking and ground reclaimer interlocking protecting method and device, belong to stacking overhead travelling crane and ground reclaimer interlocking protecting technical field.
Background technology:
At present, in the Aluminum Electrolysis Production industry, all be provided with charcoal piece transfer station between the workshop sections such as the roasting of its anode charcoal ink factory, moulding and assembling, to store and to transport the anode carbon block of each workshop section's production use or output.Each workshop section all has the charcoal piece conveyor of operation on the ground to enter charcoal piece transfer station, the carrying of charcoal piece in charcoal piece transfer station then mainly relies on the stacking overhead travelling crane that moves above the floor conveyor and carries out, and entering the conveyor of charcoal piece transfer station, each workshop section carries out interlocked control by the programming controller PLC control system of each workshop section, after certain conveyor was carried that the work of one group of charcoal piece is finished and be out of service, corresponding system promptly sent sound and light signal notice stacking overhead travelling crane and comes to take, put the charcoal piece.Stacking overhead travelling crane is come this conveyor top and is stretched out anchor clamps and takes, puts in the charcoal piece operation process, and floor conveyor is answered the No starting operation, otherwise conveyor will cause device damage with stacking overhead travelling crane anchor clamps generation hook.Therefore, when stacking overhead travelling crane on certain conveyor during idle job, stacking overhead travelling crane should send " locking " signal to the PLC system of this conveyor of control, this conveyor No starting of interlocking, after stacking overhead travelling crane was finished this subjob and left, interlocking signal was removed, and this conveyor could start operation.
At present, stacking overhead travelling crane in the prior art generally adopts " the signal trolley transmits locking signal ", " overhead traveling crane and ground control system install wireless remote controller additional and transmit locking signal " and " utilizing higher-order of oscillation switch to send and the reception locking signal " three kinds of modes to the interlocking of floor conveyor, and the shortcoming of the principle of work of these three kinds of modes and existence is as described below in the prior art:
The signal trolley transmits " locking " signal:
Set up the special signal trolley along stacking overhead travelling crane walking track, when needs locking floor conveyor, on the stacking overhead travelling crane control stand, press " locking floor conveyor " button or switch by the stacking overhead travelling crane driver, electric signal is sent to the PLC system of corresponding workshop section through the signal trolley.There is following shortcoming and defect in this mode:
In same charcoal piece transfer station, the many treads conveyor that connects each workshop section is often arranged, stacking overhead travelling crane locking is wherein during a conveyor, can not influence other conveyor work, therefore every conveyor all must be equipped with the signal trolley separately, add the power trolley of stacking overhead travelling crane, then the One's name is legion of trolley causes construction investment increase, maintenance workload to strengthen.With one 100 meters long charcoal piece transfer stations (general charcoal piece transfer station length is all more than 100 meters) is example, signal trolley of every increase, and palpus increase equipment and erected cost are 40,000 yuan approximately, and " locking " signal of both every tread conveyor must spend 40,000 yuan.
When stacking overhead travelling crane fulfil assignment leave certain conveyor after, the stacking overhead travelling crane driver needs to remove " locking floor conveyor " button or switch, floor conveyor could startup work.When being busy with one's work, the stacking overhead travelling crane driver often forgets ring off signal, and floor conveyor always can not be started, and has a strong impact on production efficiency.
Must on the stacking overhead travelling crane control stand, install " locking floor conveyor " button or switch, make the stacking overhead travelling crane operation circuit complicated.
Overhead traveling crane and ground control system install wireless remote controller additional and transmit " locking " signal:
The wireless remote control emitter is installed on stacking overhead travelling crane, wireless remote control receiving device is installed on the ground.When needs locking floor conveyor, on the stacking overhead travelling crane control stand, press " locking floor conveyor " button or switch by the stacking overhead travelling crane driver, electric signal is passed through the receiving trap that the wireless remote control emitter is sent to ground, deliver to the PLC system of corresponding workshop section again by receiving trap.There is following shortcoming and defect in this mode:
Every stacking overhead travelling crane of wireless remote controller must be provided with a cover, and every cover expense 2~30,000 yuan causes construction investment increase, maintenance workload to strengthen.
When stacking overhead travelling crane fulfil assignment leave certain conveyor after, the stacking overhead travelling crane driver needs to remove " locking floor conveyor " button or switch, floor conveyor could startup work.When being busy with one's work, the stacking overhead travelling crane driver often forgets ring off signal, and floor conveyor always can not be started, and has a strong impact on production efficiency.
When wireless remote controller is installed, must on the stacking overhead travelling crane control stand, install " locking floor conveyor " button or switch, make the stacking overhead travelling crane operation circuit complicated.
In same charcoal piece transfer station, dispose many stacking overhead travelling cranes and floor conveyor, then many cover wireless remote controllers are worked simultaneously, easily produce mutually and disturb, and make " locking " signal malfunction or motionless, easily cause equipment and personal injury.
Utilize higher-order of oscillation switch to send and reception " locking " signal:
A higher-order of oscillation emission switch is installed on stacking overhead travelling crane, is connected " locking floor conveyor " button or switch on the control stand.By every tread conveyor, higher-order of oscillation receiving key is installed in the position of the higher-order of oscillation emission switch on the corresponding overhead traveling crane, is connected to the PLC system of corresponding workshop section.When needs locking floor conveyor, also contraposition is accurate by the stacking overhead travelling crane driver overhead traveling crane to be parked in this conveyor top, press " locking floor conveyor " button or switch on the control stand then, " locking " signal is sent to the PLC system of the corresponding workshop section in ground through higher-order of oscillation switch.There is following shortcoming and defect in this mode:
When stacking overhead travelling crane fulfil assignment leave certain conveyor after, the emitting head of higher-order of oscillation switch and receive no longer alignment of head, the disconnection of " locking " signal.But if the stacking overhead travelling crane driver forgets releasing " locking floor conveyor " button or switch, then stacking overhead travelling crane is every all can make it be " locked " through a tread conveyor to stop once.Gently then have a strong impact on production efficiency, heavy then equipment and personal injury easily take place.
This mode requires the stacking overhead travelling crane contraposition very accurate, and the head that transmits and receives of higher-order of oscillation switch is alignd.If contraposition has deviation slightly, gently then " locking " signal can't transmit, and will be heavy then slightly go here and there and cause signal interruption owing to the stacking overhead travelling crane position in the stacking overhead travelling crane operation process, and equipment and personal injury very easily take place.
Higher-order of oscillation switch emitting head is installed on the overhead traveling crane, is given a shock with the overhead traveling crane walking, and failure rate is very high.
Must on the stacking overhead travelling crane control stand, install " locking floor conveyor " button or switch, make the stacking overhead travelling crane operation circuit complicated.
Because existing stacking overhead travelling crane and ground reclaimer interlocking protecting technology exist above-mentioned shortcoming, so its result of use still is not ideal enough.
Summary of the invention:
The objective of the invention is: provide a kind of and make and operating cost is cheap, simple in structure, functional reliability is high, safe and convenient to use stacking overhead travelling crane and ground reclaimer interlocking protecting method and device, to overcome the deficiencies in the prior art.
The present invention is achieved in that stacking overhead travelling crane of the present invention with ground reclaimer interlocking protecting method is: it adopts the detector switch that is installed on the correct position that can respond to or contact stacking overhead travelling crane to detect by the stacking overhead travelling crane position above the floor conveyor of programming controller PLC system control, promptly when stacking overhead travelling crane arrives the floor conveyor top, detector switch detects stacking overhead travelling crane and moves, the actuating signal of detector switch directly is sent to the programming controller PLC system of the affiliated workshop section of this floor conveyor, and this programming controller PLC system can forbid its operation according to this signal lock fatal position face conveyor; Built on stilts conveyor top after stacking overhead travelling crane is finished the work, its detector switch is not because of detecting stacking overhead travelling crane and action returns to virgin state, after the actuating signal that detector switch returns to virgin state is sent to the programming controller PLC system of this floor conveyor, the programming controller PLC system of workshop section promptly removes the locking to conveyor under this floor conveyor, and starts the operation floor conveyor according to the system works needs.
During the programming controller PLC system of workshop section, this programming controller PLC system just forbids its operation according to this signal lock fatal position face conveyor after the actuating signal of detector switch is done delay process under the actuating signal of detector switch is sent to floor conveyor
When delay process is done by programming controller PLC system to the actuating signal of detector switch delay time moves greater than stacking overhead travelling crane with the time of jogging speed by detector switch.
Stacking overhead travelling crane of the present invention and ground reclaimer interlocking protecting device are: it comprises the programming controller PLC system (2) of control floor conveyor (1) operation; in programming controller PLC system (2), be connected with detector switch (3), and this detector switch (3) is arranged on the steel end carriage side of the stacking overhead travelling crane (4) that can respond to or touch the operation of floor conveyor (1) top or is arranged on the suitable position that can respond to or touch stacking overhead travelling crane.
Detector switch (3) is preferably disposed on the other track girder of the steel end carriage of the stacking overhead travelling crane (4) that can respond to or touch floor conveyor (1) top operation or on the wall.
More reliable in order to work, when being connected, make the signal of its detector switch (3) do the signal input end that is transferred to programming controller PLC system (2) after signal lag is handled again through programming controller PLC system (2) detector switch (3) and programming controller PLC system (2).
Used detector switch (3) is that induction type is near switch, mechanical stroke switch or optoelectronic switch.
Owing to adopted technique scheme, the present invention compared with prior art, the present invention has the following advantages:
Stacking overhead travelling crane needn't increase any device and wiring that is used for locking floor conveyor, thereby has simplified the stacking overhead travelling crane electrical system, strengthens the versatility of stacking overhead travelling crane;
All " locking " and " releasing " operations are finished automatically by the PLC system, do not need manual intervention, equipment and the personal injury of avoiding operation lack of standardization to cause;
Detector switch (can adopt the optoelectronic switch of induction type) cheap near switch or mechanical stroke switch and various ways, the detector switch that can send every conveyor of " locking " signal controlling only needs 100~200 yuan and can buy, and reduces the construction investment amount greatly;
Because the steel end carriage length of stacking overhead travelling crane generally all reaches several meters,, greatly facilitate operation to stacking overhead travelling crane so the contraposition of stacking overhead travelling crane is not required too accurate;
Because detector switch fixed installation, installation, wiring, maintenance are very convenient, and significantly reduce the Device element that causes because of vibrations and damage;
6. because the detector switch of each floor conveyor top directly connects PLC system separately, its wiring is very simple, and has avoided the phase mutual interference between each system.
Description of drawings:
Accompanying drawing 1 is a structure schematic top plan view of the present invention;
Accompanying drawing 2 is looked synoptic diagram for the left side of accompanying drawing 1.
Embodiment:
Embodiments of the invention: in the charcoal piece transfer station of existing workshop, all use signal transmssion line (5) to connect a last detector switch (3) on the signal input end of the programming controller PLC system (2) of the control floor conveyor (1) of each workshop section operation, detector switch (3) can adopt the induction type of selling on the market near switch, the optoelectronic switch of mechanical stroke switch or various ways, this programming controller PLC system (2) is being received after detector switch (3) detects the signal of object, send a locking signal to its floor conveyor of controlling (1), forbid this floor conveyor (1) operation; And when stacking overhead travelling crane (4) is finished the work back built on stilts conveyor (1) top, make detector switch (3) because of not detecting stacking overhead travelling crane and action returns to virgin state, after its actuating signal that returns to virgin state is sent to the programming controller PLC system (2) of this floor conveyor, the programming controller PLC system (2) of workshop section can remove the locking to this floor conveyor (1) under this floor conveyor (1), and starts operation floor conveyor (1) according to the system works needs; When fabrication and installation, this detector switch (3) is arranged on the other position of steel end carriage that can respond to or touch at the stacking overhead travelling crane (4) of this floor conveyor (1) top operation, preferably detector switch (3) is installed on the other track girder of the steel end carriage of the stacking overhead travelling crane (4) that can respond to or touch the operation of this floor conveyor (1) top or on the wall; In order to control more reliable and when preventing stacking overhead travelling crane (4) just through this floor conveyor (1) top, its programming controller PLC system's (2) misoperation and send locking signal, when making, with detector switch (3) with after programming controller PLC system (2) is connected, make the signal of its detector switch (3) do the signal input end that is transferred to programming controller PLC system (2) after signal lag is handled again through programming controller PLC system (2), like this, when stacking overhead travelling crane (4) is the top of this floor conveyor of process (1), though this detector switch (3) detect stacking overhead travelling crane (4) the steel end carriage signal and move, but, because doing, programming controller PLC system (2) just can lock floor conveyor after signal lag is handled, and in this section delay time, stacking overhead travelling crane (4) has run to the detected position of energy away from detector switch (3) institute, thereby can not influence the former duty of programming controller PLC system (2), thereby prevented because stacking overhead travelling crane (4) locks the misoperation of floor conveyor (1) during through floor conveyor (1) to floor conveyor (1).When the delay time of signal lag processing is done by adjustment programming controller PLC system (2), this delay time should be adjusted to when moving with the time of jogging speed, can guarantee so again floor conveyor (1) to be exported reliable control signal after delay process is done to the actuating signal of detector switch (3) by programming controller PLC system (2) by detector switch (3) greater than stacking overhead travelling crane (4).

Claims (7)

1. stacking overhead travelling crane and ground reclaimer interlocking protecting method, it is characterized in that: it adopts the detector switch that is installed on the correct position that can respond to or contact stacking overhead travelling crane to detect by the stacking overhead travelling crane position above the floor conveyor of programming controller PLC system control, promptly when stacking overhead travelling crane arrives the floor conveyor top, detector switch detects stacking overhead travelling crane and moves, the actuating signal of detector switch directly is sent to the programming controller PLC system of the affiliated workshop section of this floor conveyor, and this programming controller PLC system can forbid its operation according to this signal lock fatal position face conveyor; Built on stilts conveyor top after stacking overhead travelling crane is finished the work, its detector switch is not because of detecting stacking overhead travelling crane and action returns to virgin state, after the actuating signal that detector switch returns to virgin state is sent to the programming controller PLC system of this floor conveyor, the programming controller PLC system of workshop section promptly removes the locking to conveyor under this floor conveyor, and starts the operation floor conveyor according to the system works needs.
2. stacking overhead travelling crane according to claim 1 and ground reclaimer interlocking protecting method; it is characterized in that: during the programming controller PLC system of workshop section, this programming controller PLC system just forbids its operation according to this signal lock fatal position face conveyor after the actuating signal of detector switch is done delay process under the actuating signal of detector switch is sent to floor conveyor.
3. stacking overhead travelling crane according to claim 2 and ground reclaimer interlocking protecting method is characterized in that: when delay process is done by programming controller PLC system to the actuating signal of detector switch delay time moves greater than stacking overhead travelling crane with the time of jogging speed by detector switch.
4. stacking overhead travelling crane and ground reclaimer interlocking protecting device; it comprises the programming controller PLC system (2) of control floor conveyor (1) operation; it is characterized in that: in programming controller PLC system (2), be connected with detector switch (3), and this detector switch (3) is arranged on the steel end carriage side of the stacking overhead travelling crane (4) that can respond to or touch the operation of floor conveyor (1) top or is arranged on the suitable position that can respond to or touch stacking overhead travelling crane.
5. stacking overhead travelling crane according to claim 4 and ground reclaimer interlocking protecting device is characterized in that: detector switch (3) is arranged on the other track girder of the steel end carriage of the stacking overhead travelling crane (4) that can respond to or touch floor conveyor (1) top operation or on the wall.
6. stacking overhead travelling crane according to claim 4 and ground reclaimer interlocking protecting device; it is characterized in that: detector switch (3) is connected with programming controller PLC system (2), and the signal of its detector switch (3) is done the signal input end that is transferred to programming controller PLC system (2) after signal lag is handled again through programming controller PLC system (2).
7. according to claim 4,5 or 6 described stacking overhead travelling cranes and ground reclaimer interlocking protecting device, it is characterized in that: detector switch (3) is that induction type is near switch, mechanical stroke switch or optoelectronic switch.
CNB200510200654XA 2005-10-28 2005-10-28 Stacking shop traveller and ground reclaimer interlocking protecting method and apparatus Expired - Fee Related CN100419602C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB200510200654XA CN100419602C (en) 2005-10-28 2005-10-28 Stacking shop traveller and ground reclaimer interlocking protecting method and apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB200510200654XA CN100419602C (en) 2005-10-28 2005-10-28 Stacking shop traveller and ground reclaimer interlocking protecting method and apparatus

Publications (2)

Publication Number Publication Date
CN1773402A true CN1773402A (en) 2006-05-17
CN100419602C CN100419602C (en) 2008-09-17

Family

ID=36760413

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB200510200654XA Expired - Fee Related CN100419602C (en) 2005-10-28 2005-10-28 Stacking shop traveller and ground reclaimer interlocking protecting method and apparatus

Country Status (1)

Country Link
CN (1) CN100419602C (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101177207B (en) * 2007-03-28 2011-05-11 福建海源自动化机械股份有限公司 Stacker with mechanical hand protecting means
CN102211743A (en) * 2010-04-01 2011-10-12 沈阳铝镁设计研究院有限公司 System and method for controlling lifting unit
CN103010703A (en) * 2012-12-28 2013-04-03 上海凯思尔电子有限公司 Automatic identification and locking system of full-automatic board receiving machine
CN104834262A (en) * 2014-12-31 2015-08-12 浙江吉利汽车有限公司 Automobile stamping production line and scrap line interconnected control protection device and method
CN104075650B (en) * 2013-03-29 2017-10-27 浙江天煌科技实业有限公司 A kind of location of workpiece detection means

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101177207B (en) * 2007-03-28 2011-05-11 福建海源自动化机械股份有限公司 Stacker with mechanical hand protecting means
CN102211743A (en) * 2010-04-01 2011-10-12 沈阳铝镁设计研究院有限公司 System and method for controlling lifting unit
CN103010703A (en) * 2012-12-28 2013-04-03 上海凯思尔电子有限公司 Automatic identification and locking system of full-automatic board receiving machine
CN103010703B (en) * 2012-12-28 2015-06-03 上海凯思尔电子有限公司 Automatic identification and locking system of full-automatic board receiving machine
CN104075650B (en) * 2013-03-29 2017-10-27 浙江天煌科技实业有限公司 A kind of location of workpiece detection means
CN104834262A (en) * 2014-12-31 2015-08-12 浙江吉利汽车有限公司 Automobile stamping production line and scrap line interconnected control protection device and method

Also Published As

Publication number Publication date
CN100419602C (en) 2008-09-17

Similar Documents

Publication Publication Date Title
CN108132641B (en) Control method and system of stacker crane and electric vehicle battery replacement control method and system
CN1773402A (en) Stacking shop traveller and ground reclaimer interlocking protecting method and apparatus
WO2008145022A1 (en) A control system for overhead traeling crane to stack carbon blocks and a control method for the same
CN206126690U (en) Bulk cargo grab bucket overhead traveling crane automatic control device
CN110948206A (en) Bogie assembling and forming process and bolster and side frame assembling machine
CN203372773U (en) Control system of horizontal material conveying trolley
CN106555024A (en) It is a kind of to move certainly pricker machine to what tap hole of blast furnace assembly changed drilling rod
CN108706503B (en) Hanging weight installation method
CN2852217Y (en) Stacking crane and earth surface conveyer interlocking protection device
CN109761012A (en) A kind of battery modules transportation system and method
WO2013131415A1 (en) Sarong transportation apparatus
CN105752850A (en) Telescopic sleeve group and waste retrieval crane adopting same
CN111332951A (en) Intelligent fuel loading and unloading control system and control method
CN102079343B (en) Automatic control system of vehicle door pallet transshipping mechanism
CN110294276B (en) Automatic positioning device and positioning method for comprehensive transport vehicle
CN111865209A (en) Novel photovoltaic clean robot system of refuting
CN216004437U (en) Brick storage system with automatic transfer function
CN206368175U (en) It is a kind of to move pricker machine certainly to what tap hole of blast furnace assembly changed drilling rod
CN205090940U (en) Intelligent positional detection sensor can encode
CN204286353U (en) For the guide rail bracket joint pick-up unit of lifter
CN210272288U (en) Wafer conveying device and fault rescue system
CN205837859U (en) A kind of automatic feeding device for aluminum fusing stove
CN207326368U (en) A kind of double electric screwdriver auto lock filatures
JP2017057024A (en) Elevator control device
CN205167169U (en) Automatic maintenance system of full -automatic cement brick

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: GUIYANG ALUMINUM AND MAGNESIUM DESIGN INSTITUTE CO

Free format text: FORMER OWNER: GUIYANG ALUMINIUM AND MAGNESIUM DESIGN INST.

Effective date: 20110719

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 550004 NO. 208, BEIJING ROAD, GUIYANG CITY, GUIZHOU PROVINCE TO: 550081 NO. 2, JINZHU ROAD, JINYANG NEW DISTRICT, GUIYANG CITY, GUIZHOU PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20110719

Address after: 550081 Guiyang Province, Jinyang New District, Zhu Zhu Road, No. 2

Patentee after: Guiyang Aluminum & Magnesium Design Institute Co., Ltd.

Address before: 550004 No. 208, Beijing Road, Guiyang, Guizhou

Patentee before: Guiyang Aluminium and Magnesium Design Inst.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080917

Termination date: 20151028

EXPY Termination of patent right or utility model