CN1740518A - Deviation correcting pressure weight method for side rolling in double circle shield tunnel construction - Google Patents

Deviation correcting pressure weight method for side rolling in double circle shield tunnel construction Download PDF

Info

Publication number
CN1740518A
CN1740518A CN 200510029898 CN200510029898A CN1740518A CN 1740518 A CN1740518 A CN 1740518A CN 200510029898 CN200510029898 CN 200510029898 CN 200510029898 A CN200510029898 A CN 200510029898A CN 1740518 A CN1740518 A CN 1740518A
Authority
CN
China
Prior art keywords
ballast
lead
double
deflection angle
shield
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200510029898
Other languages
Chinese (zh)
Other versions
CN100516462C (en
Inventor
沈水龙
蔡丰锡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Jiaotong University
Original Assignee
Shanghai Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Jiaotong University filed Critical Shanghai Jiaotong University
Priority to CNB2005100298986A priority Critical patent/CN100516462C/en
Publication of CN1740518A publication Critical patent/CN1740518A/en
Application granted granted Critical
Publication of CN100516462C publication Critical patent/CN100516462C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The deviation correcting pressure weight method for side rolling in double circle shield tunnel construction used in tunnel construction engineering technology includes the following steps: 1. calculating the pressure weight lead block size in finite element method based on the construction of tunnel shield machine, soil condition and the deviation angle; 2. designing the shape of the lead blocks as cuboids with weight of 200 kg and 1.38x0.13x0.1 m3 size; 3. selecting the lead block setting positions; and 4. eliminating rest deviation angle in available technology in the case of relatively great deviation angle. The method of the present invention is simple and practical, can greatly reduce the negative effect on the peripheral environment, and is suitable for different kinds of double circle shield tunnel construction.

Description

The ballast method for correcting error of side rolling in the double-O-tube shield tunnel construction
Technical field
The present invention relates to a kind of job practices of construction of tunnel technical field, specifically is the ballast method for correcting error of side rolling in a kind of double-O-tube shield tunnel construction.
Background technology
Double-O-tube shield (DOT) method tunnel becomes one of job practices in subway construction and the municipal engineering tunnel construction owing to descending space resources frugally, reducing influence, reduction construction costs to the ground structure.But shield machine can produce side rolling deflection (hereinafter to be referred as sidewindering) phenomenon inevitably in construction, and promptly the section of shield machine is to a lateral deviation gyration α.Double-O-tube shield tunnel has two axis, lateral dimensions to enlarge markedly, lining segment generation rolling deflection phenomenon will directly influence pipe sheet assembling, influence normal function of use thereby make middle standing pillar produce subsidiary stress, also can influence the control of ground settlement and the use of Suporting structure simultaneously.Therefore, rolling deflection control also just becomes technology emphasis and the difficult point in the double-O-tube shield work progress.Usually, the driving of double-O-tube shield machine by about the big mutual counter-rotating of cutterhead, the moment of torsion counter-force is cancelled out each other, and sidewinders so be difficult for generation; But Just because of this,, more be difficult to correct in case sidewinder generation.Sidewinder phenomenon for what the double-O-tube shield machine produced in propelling, use the action of rectifying a deviation of shield structure jack and imitation-shaped knife in the prior art.In the correction of rolling, except that with two big cutterheads simultaneously round about rotation produce the moment of torsion of cancelling out each other and rectify a deviation the measure of action with imitation-shaped knife, also having equipped the correction jack that rolls especially and having made shield structure master jack produce eccentric force to act on the moment opposite and correct rolling deflection with rotating direction.But engineering practice proves, because 1) jack of rectifying a deviation sometimes is difficult to the deflection that produces corrected rapidly and comes; But also can produce the problem of correction transition; 2) backbreaking of imitation-shaped knife can make the stratum too much distortion of generation and influence surrounding environment.Therefore, the correcting device that need dispose on utilizing existing double-O-tube shield machine, proposition can protect environment can correct the practicable technology measure of deflection again.
Find through literature search prior art, Chinese patent application numbers 200410067139.4, denomination of invention: the method for double-O-tube shield corner control, publication number: 1614197, this patent readme is: " double-O-tube shield two waists respectively are provided with 6~8 and revise the corner jack, and it is along ± 1 ° of shield structure housing circumferencial direction rotation; in the shield driving process; in case rotation appears in the shield structure, will revise the jack reverse rotation, revises deflection; Open left shield structure bottom and right shield structure top jack, utilize independent top or bottom jack, make shield structure home position produce moment of torsion, the shield structure is turned right; Utilize imitation-shaped knife to the backbreaking of corresponding site, change shield structure yawing moment; Utilize the unearthed amount of left and right screw machine, control shield structure corner; Adopt antisymmetric grouting behind shaft or drift lining, revise the section of jurisdiction corner, further revise shield structure corner; When the shield structure deflects,, realize the rotation of shield structure to shield structure single-side pressurization weight.The present invention is applicable to the engineering that all adopt the construction of double-O-tube shield technology ..." though this patent also proposed to adopt the method for one-sided ballast to correct the double-O-tube shield corner, do not point out material, the collocation method of concrete ballast, also do not provide the relation how many drift angles how many loads can correct that adds.Thereby before the practice of construction operation, do not have predicting means, make operation be in blindly state.
Summary of the invention
The objective of the invention is to remedy defective and deficiency in the existing side rolling deviation correcting technology of double-O-tube shield machine, the ballast method for correcting error of side rolling in a kind of double-O-tube shield tunnel construction is provided, make it provide more detailed simple and effective correction scheme, required only is the transportation of lead and deposits, can alleviate the harmful effect that surrounding environment is produced greatly.
The present invention is achieved by the following technical solutions, and concrete steps are as follows:
(1) use the weight size that Finite Element calculates ballast at structure, soil nature condition and the deflection angle of shield machine, the weight of ballast adopts lead.
The calculating of Finite Element, step is as follows:
1) the finite element numerical analysis method of employing plane strain mode.
2) the modeling scope of finite element is horizontal direction 100m, and vertical direction 25m, double-O-tube shield tunnel place the centre of model, and the border, both sides is far from the actual buried depth in center, tunnel 45m surface distance consideration tunnel, and the bottom surface is 12.5m far from the center, tunnel.
3) fringe conditions is set as follows in the calculating: the inboard free boundary that adopts of shield structure housing, and the bound level displacement of model both sides, the model bottom retrains vertically and horizontal movement simultaneously.But just adopt the draining border around the model.
4) constitutive relation of soft soil layer adopts modified cambridge model, and the shield structure is taken as elastic body.
5) set double-O-tube shield in the model and be in deflection state, set initial deflection angle θ degree, in the last shield structure of lifting side, add the ballast load then, calculate the relation of loading and angle of revolution.Obtain being returned to the required ballast load of 0 degree, obtain the relation of deflection angle and ballast load from deflection θ degree.
In the construction of reality,, can calculate the size of corresponding ballast load rapidly by above-mentioned algorithm owing to show the deflection angle that produces on the operation instrument in real time.
(2) design of lead shape: consider the carrying convenience of lead, generally setting every heavily is 200 kilograms (2kN).Because the jack top journey of double-O-tube shield is 1380mm.Therefore, the shaped design of lead is 1.38 * 0.13 * 0.1m 3Cuboid.And, for the ease of transportation, on every lead, be provided with and give a hand.The lead ballast is 200kN to the maximum.
(3) selection of lead deposit position: because the space in the shield machine is less, the ballast lead is deposited in the space between the shield structure jack of lifting side.Also can hang by the pipe sheet assembling drop hanger.Lead is not arbitrarily to stack.Required in order to the wide-angle correction in order to deposit lead as much as possible in limited space, lead has notch overlap joint tenon each other, and lead can be deposited in together in interlock.
(4) when deflection angle bigger, when ballast correction is not enough to correct whole deflection angles, should adopt part ballast straightening method; Promptly correct the part deflection angle with ballast, part in addition in conjunction with the correction of the correction jack in the method for prior art double-O-tube shield corner control, imitation-shaped knife backbreak, methods such as antisymmetric grouting behind shaft or drift lining solve.
The inventive method is a side that the lead ballast is placed double-O-tube shield, under the effect of ballast gravity double-O-tube shield is produced an opposite moment with yawing moment.Make the double-O-tube shield machine in the twisting action backspin reply deflection of moment angle.The size of torque reaction is relevant with the stacking weight of heavy, and weight is big more, and torque reaction is big more, and it is effective more to rectify a deviation.
Method for correcting error of the present invention is simple and practical, unites use with existing method and can alleviate the harmful effect that surrounding environment is produced greatly, and required only is the transportation of lead and deposits.And the weight in the scheme working-out stage of constructing with regard to the pairing ballast of measurable deviation adjustment angle is to formulate the reasonable construction scheme service.The present invention is applicable to the engineering that all adopt the construction of double-O-tube shield technology.
Description of drawings
Fig. 1 is a lead allocation plan of the present invention
Ballast correction conditional curve figure when Fig. 2 spends deflection angle for the present invention 0.25,0.5
The specific embodiment
Provide following examples in conjunction with technical scheme of the present invention:
Lead be shaped as cuboid, the lead size is 1.38 * 0.13 * 0.1m 3, being provided with on the every lead and giving a hand, lead has notch overlap joint tenon each other, and be advisable in the gap of filling between the shield machine master jack, as shown in Figure 1.
Embodiment 1: the ballast correction of (0.25 degree) under the condition of little drift angle
Embodiment is an example with the double-O-tube shield tunnel construction of No. 6 line ten bid sections of Shanghai Underground.Use Finite Element according to the structure of double-O-tube shield machine and soil nature condition and calculate double-O-tube shield machine required load when given deflection angle is returned to zero degree, the correlation of corresponding deflection angle correction load (kN) is as follows:
0.1 the degree deflection angle needs the correction load of 92kN; 0.2 the degree deflection angle needs the correction load of 168kN; 0.3 the degree deflection angle needs the correction load of 230kN; 0.4 the degree deflection angle needs the correction load of 290kN; 0.5 the degree deflection angle needs the correction load of 345kN; 0.6 the degree deflection angle needs the correction load of 395kN; 0.7 the degree deflection angle needs the correction load of 435kN; 0.8 the degree deflection angle needs the correction load of 477kN; 0.9 the degree deflection angle needs the correction load of 518kN; 1 degree deflection angle needs the correction load of 560kN.0.25 degree sidewinders load and the angle relation that deflection angle is returned to level, shown in figure-2.
Hence one can see that, is deflected to 0.25 degree and then needs ballast 199kN, needs 199/2=100 piece lead so altogether, with stereotyped lead, places respectively between the jack, as shown in Figure 1, looks corner variation the increase and decrease gradually lead.The result only just can make the deflection of shield machine be returned to level by the pressurization lead.
Embodiment 2: the ballast correction of (0.5 degree) under the condition of big drift angle
In the construction of No. 6 line ten bid sections of Shanghai Underground,, as be 0.5 when spending when deflection angle is bigger.Formation condition according to Shanghai is 345kN by the ballast correction load that Finite Element calculates.At this moment need lead 345/2=173 piece.But in fact the clearance spaces of shield machine is limited, can only place the lead about 100.Can only adopt the method for part ballast correction, at this moment the ballast amount is 200kN, the ballast correction conditional curve during 0.5 ° of deflection angle that Fig. 2 calculates for the method for using finite element numerical analysis.Hence one can see that, and the ballast of 200kN can make double-O-tube shield revolution 0.25 degree.0.25 degree deflection angle in addition solves according to the method for the double-O-tube shield corner control of prior art.The ballast straightening method comparatively economical and effective that should begin to rectify a deviation is adopted in The above results explanation under the condition of less deflection angle (0.25 degree).

Claims (6)

1, the ballast method for correcting error of side rolling in a kind of double-O-tube shield tunnel construction is characterized in that concrete steps are as follows:
(1) use the weight size that Finite Element calculates ballast at structure, soil nature condition and the deflection angle of shield machine, the weight of ballast adopts lead;
(2) design of lead shape: set every lead and heavily be 200 kilograms, shaped design is 1.38 * 0.13 * 0.1m 3Cuboid;
(3) selection of lead deposit position: the ballast lead is deposited in the space between the shield structure jack that picks up side, and lead has notch overlap joint tenon each other, and lead can be deposited in together in interlock;
(4) when deflection angle bigger, when the ballast lead can only be corrected the part deflection angle, adopt part ballast straightening method, promptly correct the part deflection angle with ballast, part deflection angle in addition solves in conjunction with the method for double-O-tube shield corner control.
2, the ballast method for correcting error of side rolling in the double-O-tube shield tunnel construction according to claim 1 is characterized in that described Finite Element is calculated, and step is as follows:
1) the finite element numerical analysis method of employing plane strain mode;
2) the modeling scope of finite element is horizontal direction 100m, and vertical direction 25m, double-O-tube shield tunnel place the centre of model, and the border, both sides is far from center, tunnel 45m; Surface distance is considered the actual buried depth in tunnel, and the bottom surface is 12.5m far from the center, tunnel;
3) fringe conditions is set as follows in the calculating: the inboard free boundary that adopts of shield structure housing, and the bound level displacement of model both sides, the model bottom retrains vertically and horizontal movement simultaneously, but adopts the draining border around the model;
4) constitutive relation of soft soil layer adopts modified cambridge model, and the shield structure is taken as elastic body;
5) set double-O-tube shield in the model and be in deflection state, set initial deflection angle θ degree, in the last shield structure that picks up side, add the ballast load then, calculate the relation of loading and angle of revolution, obtain being returned to the required ballast load of 0 degree, obtain the relation of deflection angle and ballast load from deflection θ degree.
3, the ballast method for correcting error of side rolling in the double-O-tube shield tunnel construction according to claim 2, it is characterized in that, in the construction of reality,, calculate the size of corresponding ballast load rapidly by above-mentioned Finite Element according to showing the deflection angle that produces on the operation instrument in real time.
4, the ballast method for correcting error of side rolling in the double-O-tube shield tunnel construction according to claim 1 is characterized in that, for the ease of transportation, is provided with on every lead and gives a hand.
5, according to the ballast method for correcting error of side rolling in claim 1 or the 4 described double-O-tube shield tunnel constructions, it is characterized in that the total ballast of lead is 200kN to the maximum.
6, according to the ballast method for correcting error of side rolling in claim 1 or the construction of 4 described double-O-tube shield tunnels, it is characterized in that, in the step (3), lead or hang by the pipe sheet assembling drop hanger.
CNB2005100298986A 2005-09-22 2005-09-22 Deviation correcting pressure weight method for side rolling in double circle shield tunnel construction Expired - Fee Related CN100516462C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2005100298986A CN100516462C (en) 2005-09-22 2005-09-22 Deviation correcting pressure weight method for side rolling in double circle shield tunnel construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2005100298986A CN100516462C (en) 2005-09-22 2005-09-22 Deviation correcting pressure weight method for side rolling in double circle shield tunnel construction

Publications (2)

Publication Number Publication Date
CN1740518A true CN1740518A (en) 2006-03-01
CN100516462C CN100516462C (en) 2009-07-22

Family

ID=36093029

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2005100298986A Expired - Fee Related CN100516462C (en) 2005-09-22 2005-09-22 Deviation correcting pressure weight method for side rolling in double circle shield tunnel construction

Country Status (1)

Country Link
CN (1) CN100516462C (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103244134A (en) * 2013-04-26 2013-08-14 上海交通大学 Anti-floating ballasting method for shield tunnel under negative earthing condition
CN103270246A (en) * 2010-12-07 2013-08-28 韩国建设技术硏究院 Drain system of shield tunnel lining and method for constructing shield tunnel using same
CN103670432A (en) * 2013-12-19 2014-03-26 上海市基础工程集团有限公司 Soft foundation double circle shield machine head chip cutting device
CN105203070A (en) * 2015-09-21 2015-12-30 重庆大学 Calculation method for soil deformation caused by double-circle shield tunnel construction deflection
CN105863657A (en) * 2016-05-27 2016-08-17 中铁二十局集团轨道交通工程有限公司 Start-side rolling collection device and start-side rolling collection method for earth pressure balance shield machine
CN112228094A (en) * 2019-07-15 2021-01-15 代春茹 Anti-side rolling type full-face tunnel boring machine

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US695724A (en) * 1901-09-28 1902-03-18 Reinhold Herman Electric lock.
JP2711300B2 (en) * 1989-07-26 1998-02-10 清水建設株式会社 Deflection method of double-section shield machine
CN1063826C (en) * 1994-03-07 2001-03-28 藤田株式会社 Suporting structure
CN1321258C (en) * 2003-03-04 2007-06-13 上海市隧道工程轨道交通设计研究院 Two-circle shield method tunnel lining structure
CN1614197A (en) * 2004-10-14 2005-05-11 上海隧道工程股份有限公司 Direction turning cotnrol of double circular shielding

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103270246A (en) * 2010-12-07 2013-08-28 韩国建设技术硏究院 Drain system of shield tunnel lining and method for constructing shield tunnel using same
CN103270246B (en) * 2010-12-07 2015-06-24 韩国建设技术硏究院 Drain system of shield tunnel lining and method for constructing shield tunnel using same
CN103244134A (en) * 2013-04-26 2013-08-14 上海交通大学 Anti-floating ballasting method for shield tunnel under negative earthing condition
CN103244134B (en) * 2013-04-26 2015-04-29 上海交通大学 Anti-floating ballasting method for shield tunnel under negative earthing condition
CN103670432A (en) * 2013-12-19 2014-03-26 上海市基础工程集团有限公司 Soft foundation double circle shield machine head chip cutting device
CN105203070A (en) * 2015-09-21 2015-12-30 重庆大学 Calculation method for soil deformation caused by double-circle shield tunnel construction deflection
CN105203070B (en) * 2015-09-21 2017-11-14 重庆大学 A kind of double-O-tube shield tunnel construction deflection causes the computational methods of soil deformation
CN105863657A (en) * 2016-05-27 2016-08-17 中铁二十局集团轨道交通工程有限公司 Start-side rolling collection device and start-side rolling collection method for earth pressure balance shield machine
CN105863657B (en) * 2016-05-27 2018-02-23 中铁二十一局集团轨道交通工程有限公司 Balancing earth-pressure shielding machine, which originates, sidewinders correcting device and method
CN112228094A (en) * 2019-07-15 2021-01-15 代春茹 Anti-side rolling type full-face tunnel boring machine

Also Published As

Publication number Publication date
CN100516462C (en) 2009-07-22

Similar Documents

Publication Publication Date Title
CN100516462C (en) Deviation correcting pressure weight method for side rolling in double circle shield tunnel construction
Sugimoto et al. Theoretical model of shield behavior during excavation. I: Theory
US8768580B2 (en) Operation machine
CN102306225B (en) Method for simulating construction course and tunnel deformation influence value of multiline overlapping tunnel
CN106068354A (en) The control method of the control device of Work machine, Work machine and Work machine
CN104102767A (en) Numerical simulation analysis method for influence of adjacent underpinning pile foundation by shield construction
CN105825027A (en) Multi-body system dynamic value simulation method of jacking pipe jacking process
CN109706940B (en) Method for setting foundation pit servo support system
CN101215838A (en) Construction technique for foundation ditch on top of underground railway tunnel in soft soil area
CN109811769B (en) Foundation pit excavation construction method
CN111753363A (en) Foundation pit side shield tunnel confining pressure change calculation method considering foundation pit support structure deformation and space effect
CN102134853A (en) CT sealed steel pipe pile foundation pit water stop supporting device and construction method thereof
CN110555276B (en) Wharf portal crane moving load and multi-layer frame type wharf most dangerous combined load calculation method and system
CN106570221B (en) Method for calculating horizontal lateral stiffness of pile top crown beam of cylindrical foundation pit supporting pile
CN1288308C (en) Method for constructing deep-large foundation pit over operating tunnel an ddeformation-preventing strucutre
CN108763833B (en) Method for calculating deflection of foundation pit supporting pile in consideration of soil resistance sudden change
CN114741763A (en) Method for calculating active soil pressure of limited soil body of cantilever type supporting structure of foundation pit
CN110750923A (en) Method for calculating single-pile ultimate bearing capacity of coastal sludge soft soil foundation through dynamic compaction replacement treatment
CN113935098A (en) Foundation pit support active soil pressure calculation method based on slip surface shape correction
Zhou et al. Engineering characteristics and reinforcement program of inclined pre-stressed concrete pipe piles
CN102021915B (en) Method for constructing large plate type foundation of line
CN113987645B (en) Simplified internal force calculation method for mountain slope straight-inclined combined pile foundation
CN1814988A (en) Lining structure determining method of rolling deviation-rectifying based on two-targe structral tunnel side direction
CN114960695B (en) Spreading arm type drainage slide-resistant pile
CN106503383A (en) The stress of a kind of interim inverted arch or stull and deformation analysis method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090722

Termination date: 20120922