CN1526524A - Perforating apparatus and method for slab workpiece - Google Patents

Perforating apparatus and method for slab workpiece Download PDF

Info

Publication number
CN1526524A
CN1526524A CNA2004100055509A CN200410005550A CN1526524A CN 1526524 A CN1526524 A CN 1526524A CN A2004100055509 A CNA2004100055509 A CN A2004100055509A CN 200410005550 A CN200410005550 A CN 200410005550A CN 1526524 A CN1526524 A CN 1526524A
Authority
CN
China
Prior art keywords
perforate
plate
plate workpiece
image
mark
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2004100055509A
Other languages
Chinese (zh)
Other versions
CN1326674C (en
Inventor
东海林健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Seiko Precision Inc
Original Assignee
Seiko Precision Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Seiko Precision Inc filed Critical Seiko Precision Inc
Publication of CN1526524A publication Critical patent/CN1526524A/en
Application granted granted Critical
Publication of CN1326674C publication Critical patent/CN1326674C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B26HAND CUTTING TOOLS; CUTTING; SEVERING
    • B26DCUTTING; DETAILS COMMON TO MACHINES FOR PERFORATING, PUNCHING, CUTTING-OUT, STAMPING-OUT OR SEVERING
    • B26D7/00Details of apparatus for cutting, cutting-out, stamping-out, punching, perforating, or severing by means other than cutting
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B26HAND CUTTING TOOLS; CUTTING; SEVERING
    • B26DCUTTING; DETAILS COMMON TO MACHINES FOR PERFORATING, PUNCHING, CUTTING-OUT, STAMPING-OUT OR SEVERING
    • B26D5/00Arrangements for operating and controlling machines or devices for cutting, cutting-out, stamping-out, punching, perforating, or severing by means other than cutting
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B26HAND CUTTING TOOLS; CUTTING; SEVERING
    • B26DCUTTING; DETAILS COMMON TO MACHINES FOR PERFORATING, PUNCHING, CUTTING-OUT, STAMPING-OUT OR SEVERING
    • B26D7/00Details of apparatus for cutting, cutting-out, stamping-out, punching, perforating, or severing by means other than cutting
    • B26D7/01Means for holding or positioning work
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B26HAND CUTTING TOOLS; CUTTING; SEVERING
    • B26FPERFORATING; PUNCHING; CUTTING-OUT; STAMPING-OUT; SEVERING BY MEANS OTHER THAN CUTTING
    • B26F1/00Perforating; Punching; Cutting-out; Stamping-out; Apparatus therefor
    • B26F1/02Perforating by punching, e.g. with relatively-reciprocating punch and bed
    • B26F1/04Perforating by punching, e.g. with relatively-reciprocating punch and bed with selectively-operable punches
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B26HAND CUTTING TOOLS; CUTTING; SEVERING
    • B26FPERFORATING; PUNCHING; CUTTING-OUT; STAMPING-OUT; SEVERING BY MEANS OTHER THAN CUTTING
    • B26F1/00Perforating; Punching; Cutting-out; Stamping-out; Apparatus therefor
    • B26F1/02Perforating by punching, e.g. with relatively-reciprocating punch and bed
    • B26F1/14Punching tools; Punching dies

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Forests & Forestry (AREA)
  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Perforating, Stamping-Out Or Severing By Means Other Than Cutting (AREA)
  • Drilling And Boring (AREA)
  • Machine Tool Sensing Apparatuses (AREA)
  • Numerical Control (AREA)

Abstract

The fixture plate 362 provided with a plurality of reference holes 362f is detachably provided on a chuck 36 transferring the plate-like work 1 to a boring part while sucking and retaining it. The chuck 36 for adsorbing and retaining the plate-like work 1 also has a function of the fixture plate 362. Therefore, it is not required that the fixture plate 362 is separately manufactured and installed and outstanding cost reduction is realized. The exchange work of the fixture plate can be extremely easily and quickly carried out by detachably providing the fixture plate 362 on the chuck.

Description

The boring device of plate workpiece and boring method
Technical field
The present invention relates to a kind of boring device and boring method of plate workpiece, particularly relate to a kind of boring device and boring method of printed circuit board (PCB).
Background technology
In electronic instrument etc., be extensive use of the fixing multilayer board of a plurality of substrate laminations that will form circuit pattern.Yet, during this substrate of lamination, when stagger in the mutual position of circuit pattern, can not bring into play fully as the function and the performance of the regulation of printed circuit board (PCB).For this reason, on the assigned position of each substrate, be provided with 2 pilot holes at least, the axis of guide of anchor clamps be inserted in this pilot hole, to realize the location of each substrate.Because be positional precision according to pilot hole, the mutual positional precision when determining each substrate of lamination, therefore, must on substrate, have pilot hole accurately.
The perforate operation of this pilot hole be by in advance in the position of opening printing of the pilot hole of printed circuit board (PCB) identification use mark, detect the center of this identification usefulness mark, realize to have pilot hole in this detection position.; multilayer board is the composite that is made of Copper Foil, glass fibre and resin etc.; because the influence of the dislocation of the exposure position the when pressure distribution of the Temperature Distribution of the hot press during lamination or heat time heating time, forcing press, the thermal deformation of material or circuit pattern form etc.; identification can be staggered with the position in the design with the center of mark, exists the situation that can not realize the pilot hole function.
For this reason, applicant of the present invention has proposed a kind of perforate mechanism (for example with reference to patent documentation 1) of following pilot hole.In this mechanism, at first, printing a pair of identification mark on the printed circuit board (PCB), simultaneously, prepare a jig plate that is provided with a pair of datum hole of the correct perforate of size interval in the design.Then, a pair of datum hole of instrumentation and a pair of identification is with the relative position relation of mark, with the center of a pair of datum hole of having revised both relative position deviations as the reference position.Then, the center of a pair of datum hole of promptly having revised the deviation of relative position with this reference position is a benchmark, according to the center of this a pair of datum hole, obtains the position of the pilot hole in the design of distinguishing in advance, to leave pilot hole when this position.By using mechanism like this, can not be subjected to the influence of printed circuit board (PCB) distortion etc., can on the position of regulation, leave pilot hole accurately.Figure 12 illustrates the installation constitution of jig plate in the past.According to this structure, operation post 111 is arranged on the pedestal 112 and can moves freely along the XY direction, but jig plate 114 by hinge 119 free switch be installed on this operation post 111.And, gripping printed circuit board (PCB) P (plate workpiece) between jig plate 114 and the operation post 111.
Patent documentation 1: Japanese kokai publication hei 10-43917 communique (1-5 page or leaf, 1-6 figure)
But, in above-mentioned boring device in the past, owing to be that jig plate 114 is installed on the structure on the operation post 111 of base side, changing under the situation of jig plate 114 according to the kind of printed circuit board (PCB) P etc., be used to detect identification and can hinder the dress of jig plate 14 to take off operation, exist the problem that the replacing of jig plate 114 is wasted time and energy with the video camera of mark or the ancillary equipment that is used for the drift etc. of perforate on printed circuit board (PCB) P.
Summary of the invention
For this reason, the object of the present invention is to provide and a kind ofly can easily change jig plate, and can improve the boring device and the boring method of the plate workpiece of perforate operation according to the kind of the plate workpiece of printed circuit board (PCB) etc.
In order to solve above-mentioned technical problem, being characterized as of the boring device of plate workpiece of the present invention can be adorned the jig plate that is provided with a plurality of datum holes with taking off be arranged on the injection mechanism.Promptly, boring device of the present invention, have and be provided with the perforate mechanism of a plurality of identifications with perforate on the plate workpiece of mark, keeping described plate workpiece that it is transplanted on the injection mechanism of described perforate mechanism, image mechanism, the travel mechanism that described perforate mechanism is relatively moved to described plate workpiece, handle the image processor structure of the image pickup result of described image mechanism, calculation mechanism with the result of calculating described image processor structure, wherein, the jig plate that is provided with a plurality of datum holes can be adorned and be arranged in the described injection mechanism with taking off; The mutual relative position of described datum hole is distinguished in advance; Described image mechanism is made a video recording with mark and described each datum hole to described each identification; Described image processor structure is obtained described each identification each center with mark and described each datum hole according to the image pickup result of described image mechanism, described calculation mechanism is obtained the relative position relation of described jig plate and described plate workpiece with the center of the center of mark and described each datum hole according to described each identification, simultaneously, the boring device of calculating described plate workpiece based on the center and the described relative position relation of this each datum hole; Described travel mechanism moves to described position of opening with described perforate mechanism.
In addition, the boring method of plate workpiece of the present invention is characterised in that, have and be provided with the perforate mechanism of a plurality of identifications with perforate on the plate workpiece of mark, keeping described plate workpiece described plate workpiece to be transplanted on the injection mechanism of described perforate mechanism, image mechanism, the travel mechanism that described perforate mechanism is relatively moved to described plate workpiece, handle the image processor structure of the image pickup result of described image mechanism, calculate the calculation mechanism of the result of described image processor structure, be provided with a plurality of datum holes and can adorn the jig plate that is arranged on the described injection mechanism with taking off;
After described jig plate installed to described injection mechanism, keep described plate workpiece that described plate workpiece is transplanted on described perforate mechanism by described injection mechanism;
Afterwards, by described image mechanism, described each identification is made a video recording with mark and described each datum hole, according to this image pickup result, obtain described each identification each center by described image processor structure with mark and described each datum hole, use the center of mark and the center of this each datum hole based on this each identification, obtain the relative position relation of described jig plate and described plate workpiece by described calculation mechanism, and the position of opening of calculating described plate workpiece according to the center and the described relative position relation of described each datum hole, by described travel mechanism described perforate mechanism is moved to this position of opening, and at this position of opening by described perforate mechanism to described plate workpiece perforate.
Boring device and boring method according to plate workpiece of the present invention, be used for jig plate and can adorn the injection mechanism that is arranged on the maintenance plate workpiece with taking off and is transplanted on perforate mechanism, can on the position of dropping into plate workpiece, change jig plate, other ancillary equipment can not influence the replacing operation of jig plate, can be very easy to and carry out apace the replacing operation of jig plate.
The 2nd of the boring device of plate workpiece of the present invention is characterised in that, the described perforate of above-mentioned feature 1 mechanism is provided with a plurality of, these perforate mechanisms can move independently of each other by described travel mechanism respectively, and described image mechanism is arranged to one with described each perforate mechanism respectively.
According to structure like this, the 1st, owing to be provided with a plurality of perforate mechanisms that move independently of each other, can on plate workpiece, have guide hole etc. simultaneously, can promptly carry out the perforate operation.The 2nd, be arranged to one with each perforate mechanism respectively by making image mechanism, need not the travel mechanism of the special use of dollying mechanism, and, because of moving of the relative position that needn't consider each perforate mechanism and image mechanism, but simplified structure, and the while can be improved the perforate precision.
Description of drawings
Fig. 1 is the unitary side view of the boring device of suitable plate workpiece of the present invention.
Fig. 2 is the whole front view of boring device of the plate workpiece of Fig. 1.
Fig. 3 is the whole vertical view of boring device of the plate workpiece of Fig. 1.
Fig. 4 is the front view of the amplification of perforate mechanism.
Fig. 5 is the side view of the amplification of perforate mechanism.
Fig. 6 is the concept map of jig plate.
Fig. 7 is the view that the flat shape of jig plate and adsorption plate is shown.
Fig. 8 is the concept map of printed circuit board (PCB).
Fig. 9 is the concept map of the printed circuit board (PCB) of another embodiment.
Figure 10 is a block diagram.
Figure 11 is the action chart that the drift action is shown.
Figure 12 is the side view that the installation constitution of existing jig plate is shown.
The specific embodiment
Below, with reference to Fig. 1~Figure 11, the structure of the boring device that is suitable for plate workpiece of the present invention is described.Earlier overall structure is generally illustrated.In this boring device, 6 perforate mechanisms 2 with perforate on plate workpiece 1, keeping this plate workpiece described plate workpiece to be transported to the injection mechanism 3 of this perforate mechanism, be arranged to the image mechanism 4 of one respectively with this perforate mechanism, and the travel mechanism 5 that each perforate mechanism is moved independently of each other.And, boring device has the image processor structure 6 of the image pickup result of processing image mechanism 4 as shown in figure 10, in the time of the driving of calculating the calculation mechanism 7 of result of this image processor structure and control image mechanism 4 and injection mechanism 3, according to the controlling organization 8 of the driving of the result of calculation control perforate mechanism 2 of calculation mechanism 7 and travel mechanism 5.Below, respectively each mechanism is described in detail.
For convenience of explanation, begin explanation from injection mechanism 3.As shown in Figure 1, the horizontal rail 31 that injection mechanism 3 has on the pedestal 100 that is fixed on the supporting boring device, extend towards the left and right directions of Fig. 1 (below be called " Y direction "), guiding the arm 32 that can move in the Y direction perpendicular to this horizontal rail (below be called " Z direction ") and by this horizontal rail, and shift-out mechanism 33.Arm 32 moves along the Y direction by attaching parts 34 with shift-out mechanism 33 with linking into an integrated entity integratedly.In addition, arm 32 and shift-out mechanism 33 move towards the Y direction by servomotor 35 and feed screw (not shown).
The chuck 36 that absorption type keeps plate workpiece 1 is installed in the lower end of arm 32.Chuck 36 has connecting plate 361, coincides with respectively and is fixed to jig plate 362 and adsorption plate 363 below this connecting plate by Screw.Connecting plate 361 descends, rises towards the Z direction by spring 365 under the effect that is arranged at the cylinder 364 on the arm 32.Connecting plate 361 moves by hollow cylinder parts 366 guidings that are arranged at arm 32 lower ends the Z direction.
According to Fig. 6 and Fig. 7, the detailed construction of jig plate 362 and adsorption plate 363 is described.Fig. 6 is the concept map of the structure of jig plate 362.That is, the following a of jig plate 362 is flat rectangular shape, and central authorities in its lower section form rectangular channel b, form elongated attraction groove d1, d2, d3 respectively in the position, the left and right sides of this rectangular channel.And, attract groove d1 and rectangular channel b to be communicated with by gas leakage groove e1, attract groove d1 and attract groove d2 to be communicated with by gas leakage groove e2, attract groove d2 to be communicated with by gas leakage groove e3 with attracting groove d3.The bottom land of rectangular channel b about 2 places be provided with the open pore c that is communicated with not shown vavuum pump.
In addition, connect to form the yielding hole g of the drift of a plurality of datum hole f and perforate described later mechanism 2 on the jig plate 362.The mode that adsorption plate 363 is posted by the following a of jig plate 362 is installed with, and is provided with the through hole 326a (with reference to Fig. 7) of a plurality of absorption plate workpieces 1 at rectangular channel b and attraction groove d1~d3 opposite position with jig plate on this adsorption plate.
At this, the effect of jig plate 362 is described according to Fig. 6.The mode that jig plate 362 can clamping adsorption plate 363 is adsorbed the 3 kinds of plate workpieces 11,12,13 that vary in size of flat shape respectively selectively.And the plate workpiece 13 of flat shape maximum becomes the shape that covers all attraction groove d1~d3, attracts groove being kept by adsorption plate 363 absorption by all these.In addition, flat shape becomes the shape that can not cover attraction groove d3 less than the plate workpiece 12 of plate workpiece 13, and plate workpiece 12 is under the state that is kept by adsorption plate 363 absorption, by attracting the gas leakage groove e3 between groove d2 and attraction groove d3, suction extraneous air.And, flat shape becomes to cover less than the plate workpiece 11 of plate workpiece 12 and attracts groove d2, the shape of d3, and plate workpiece 11 is under the state that is kept by adsorption plate 363 absorption, by attracting the gas leakage groove e1 between groove d1 and the rectangular channel b, suck air outside.
That is, plate workpiece 12 is being adsorbed under the state that keeps by adsorption plate 363, the end face crosscut of plate workpiece 12 gas leakage groove e3, and e3 sucks air outside by the gas leakage groove.In addition, plate workpiece 11 is under the state that is kept by adsorption plate 363 absorption, and the end face crosscut gas leakage groove e1 of plate workpiece 11 by gas leakage groove e1, sucks air outside.If these gas leakage grooves e1, the channel section of e3 is long-pending less, is restricted because of the gas leakage groove dwindles from outside amount of air drawn.Therefore, in order to increase the attraction area of plate workpiece 1, even when strengthening the area that attracts groove d1~d3, if because of gas leakage groove e1, e3 has dwindled the inflow path of air, but the soakage of limit air can suppress the reduction of the attraction of plate workpiece 1.
But preferably, gas leakage groove e1~e3 groove width is separately set for identical and channel section separately amasss identical, perhaps the groove width of the gas leakage groove of inboard is set for groove width greater than the gas leakage groove in its outside, and the channel section of inboard gas leakage groove long-pending set for greater than the channel section of the gas leakage groove in its outside long-pending.
That is, plate workpiece 12 is by rectangular channel b and attract groove d1, and d2 attracts, and 11 of plate workpieces pass through rectangular channel b and attract.And the attraction area of plate workpiece 11 is compared with the attraction area of plate workpiece 12, just attracts groove d1, and the degree of d2 diminishes.In addition, the attraction area of plate workpiece 11 is less than the attraction area of plate workpiece 12, but the size of tabular workpiece 11 is only slightly little than the size of plate workpiece 12, because of plate workpiece 11 is lighter, can be adsorbed reliably by adsorption plate 363 and keep plate workpiece 11.In addition, if the channel section of inboard gas leakage groove is long-pending set for long-pending identical or bigger slightly with the channel section of the gas leakage groove in its outside than it, then when plate workpiece 12 is kept by adsorption plate 363 absorption, can not be subjected to the gas leakage groove e2 of its inboard, the restriction of e1 by gas leakage groove e3 amount of air drawn.In addition, if the channel section of inboard gas leakage groove is long-pending set for long-pending identical with the channel section of the gas leakage groove in its outside, then when keeping plate workpiece 12 by adsorption plate 363 absorption, by gas leakage groove e3 amount of air drawn can be when keeping plate workpieces 11 by adsorption plate 363 absorption, groove e1 amount of air drawn is identical by leaking gas, the absorption hold mode of plate workpiece 11,12 can be detected simply by single pressure sensor.
Gas leakage groove e1, e2, e3 are not limited to one separately, and as shown in Figure 7, every kind all can be provided with a plurality of.So under the situation, set for long-pending identically or bigger, then can obtain the effect identical with above-mentioned situation than it with the accumulation channel section of the gas leakage groove in the outside if the accumulation channel section of inboard gas leakage groove is long-pending.
Fig. 7 illustrates an example of the jig plate 362 and the adsorption plate 363 of actual use.In addition, part same as shown in Figure 6 is marked by identical symbol.On jig plate 362, be provided with datum hole f, the yielding hole of the drift of double as perforate described later mechanism 2 and to the identification of mark on the plate workpiece 1 described later perforation slotted hole g with mark through hole for shooting, and with the identification of mark on the plate workpiece 1 perforation slotted hole h with mark special use for shooting.On adsorption plate 363, with the datum hole f of jig plate 362, connect slotted hole g, the corresponding position of h forms than datum hole f, connects slotted hole g, h wants big yielding hole, simultaneously, with the corresponding position of each groove (being shown in dotted line) that is positioned on the jig plate 362 on be provided with a plurality of through hole 362a.
Jig plate 362 and adsorption plate 363 can be adorned by Screw 367 with taking off and be installed on the connecting plate 361.Therefore, can change easily and connect slotted hole g, different jig plate 362 or the adsorption plates 363 such as position of h or datum hole f according to the shape or the kind of plate workpiece 1.In addition, jig plate 362 and adsorption plate 363 can be adorned by Screw 367 outer various mechanisms with taking off and be installed on the connecting plate 361.For example, be provided with by driving mechanisms such as cylinders and the air spider that engages with jig plate 362 and adsorption plate 363 as connecting plate 361, and by this air spider, become jig plate 362 and adsorption plate 363 can adorn the structure that engages with taking off with connecting plate 361, then can easily adorn and take off jig plate 362 and adsorption plate 363, the dress that has improved jig plate 362 and adsorption plate 363 takes off operation.
For jig plate like this 362 owing to have also that a forms rectangular channel b and attracts groove d1 below it, d2, d3 and as the function of together adsorbing the anchor clamps 36 that keeping plate workpiece with adsorption plate 363, just needn't be provided with the plate that together adsorbs the special use that is keeping plate workpiece 1 with adsorption plate 363, reduce part count, reduced cost.In addition, jig plate 362 is not limited to the function that double as and adsorption plate 363 together adsorb the anchor clamps 36 that keeping plate workpiece, can be used as special-purpose member and is arranged on the anchor clamps 36.
Below, shift-out mechanism 33 is described.
Shift-out mechanism 33 is the structure of adsorbable maintenance plate workpiece 11,12,13, and its basic structure is identical with injection mechanism 3, omits its explanation at this.
In addition, shift-out mechanism 33 so long as the structure of adsorbable maintenance plate workpiece 11,12,13 just can, can use and omit perforation slotted hole g, the sheet material of the absorption special use of h or datum hole f replaces jig plate 362.
Next, with reference to Fig. 1~Fig. 5, to 6 perforate mechanisms 2 of perforate on plate workpiece 1, be arranged to the image mechanism 4 of one with this perforate mechanism respectively, the travel mechanism 5 that each perforate mechanism is moved independently of each other describes.Perforate mechanism 2 is respectively equipped with 3 in the both sides of the operation post 101 that is fixed in pedestal 100 tops, adds up to 6.Each perforate mechanism 2 just as shown in Figures 2 and 3, have in that be arranged to by bearing 51 on the pedestal 100 can be at Y-axis movable plate 52 that Y direction moves freely and be arranged to the X-axis movable plate 54 that can move freely the left and right directions of Fig. 2 (below, be called " X-direction ") on this Y-axis movable plate by bearing (not shown).
Y-axis movable plate 52 and X-axis movable plate 54 move in Y direction and directions X respectively under the effect of the feed screw 56,57 that is driven by servomotor 53,55 revolutions.That is, servomotor 55 is fixed on the Y-axis movable plate 52, under this servomotor effect, drives feed screw 56 by the shaft coupling revolution.And fixing nut 57 with feed screw 56 threaded engagement on the X-axis movable plate 54, by the revolution of feed screw 56, move towards directions X.In addition, fixing servomotor 53 on the pedestal 100, under the effect of this servomotor, by not shown shaft coupling, revolution drives feed screw 57.And, on Y-axis movable plate 52, fixing the not shown nut with this feed screw 57 threaded engagement, move in the Y direction by the revolution of feed screw 57.
Perforate mechanism 2 is installed on the X-axis movable plate 54.With reference to Fig. 4 and Fig. 5, perforate mechanism 2 is described.Perforate mechanism 2 have the punch die 21 that is installed on replaceably on the pedestal 24 and with these punch die 21 opposed drifts 22.(Z direction) moves about this drift, with perforate on the plate workpiece 1 between insertion itself and this punch die.Drift 22 moves up and down by driving mechanism 23.Feed screw 232 that driving mechanism 23 has the servomotor 231 that is fixed on the pedestal 24, drive by shaft coupling 3 revolutions under this servomotor effect and the nut 234 that moves up and down with this feed screw threaded engagement and the revolution by feed screw.
Fixing guiding part 235 on nut 234, this guiding part is by being arranged on the sliding guiding and moving up and down of guide rod 242 on the pedestal 24.And, being arranged on the slotted hole groove on guiding part 235 left ends, by fulcrum pin 236a, can be connected freely to rotate with an end of jack back 236.Jack back 236 is that the center is shaken with gyroaxis 237, and the other end of this jack back can be connected with drift holding components 238 freely to rotate by fulcrum pin 236b.In addition, drift holding components 238 moves up and down the drift of installing at its front end changeable type 22 by vertical projections portion 241 guidings that are arranged on the pedestal 24.
In addition, the position that is connected with drift holding components 238 is approached in the position of gyroaxis 237 of supporting jack back 236.Therefore,, strengthened the power of the guiding part 235 that moves up and down by servomotor 238, drift holding components 238 is moved up and down by the principle of lever.In addition, owing to can reduce the distance that the drift holding components 238 of guiding part 235 due to moving up and down moves up and down, control the position that moves up and down of this drift holding components easily more imperceptibly.
Below, the structure that all-in-one-piece image mechanism 4 is set with perforate mechanism 2 is described.Image mechanism 4 shown in Figure 4 is installed on the pedestal 24 with drift holding components 238 with paralleling.Image mechanism 4 is so-called 2 dimension ccd video cameras, the plate workpiece 1 that is had the hole by perforate mechanism 2 is taken, and sent its shooting results to image processor structure 6 (shown in Figure 10).And image mechanism 4 is correctly measured in advance with the relative position of drift 22, even perforate mechanism 2 moves towards the XY direction under the effect of travel mechanism 5, position that also can this image mechanism is a benchmark, can normally correctly calculate the position of this drift.
Below, the effect of this perforate mechanism is described.As an example, use printed circuit board (PCB) 11 shown in Figure 8 with plate workpiece 1, situation about having the guide hole 11b that determined with the relative position that is formed at the circuit design 11a on this printed circuit board (PCB) describes.In addition, print the identification marking 11c of 2 circles of the position of opening that is used for definite guide hole 11b described later on the printed circuit board (PCB) 11.At first, when the perforate operation, as shown in Figure 6 and Figure 7, select corresponding jig plate 362 of position of opening and adsorption plate 363 with printed circuit board (PCB) 11, and these members are installed on the connecting plate 361.At this moment, by servomotor 35, injection mechanism 3 is moved to the input position of left end, as in this position, jig plate 362 and adsorption plate 363 are installed on the connecting plate 361, then other ancillary equipment for example perforate mechanism 2 or image mechanism 4 can not hinder the dress of jig plate 362 and adsorption plate 363 to take off, can easily adorn and take off jig plate 362 and adsorption plate 363.
Then, as shown in Figure 1,, injection mechanism 3 is moved to the input position of left end, and printed circuit board (PCB) 11 is being kept by anchor clamps 36 absorption in this position by servomotor 35.At this moment, by injection mechanism 3, when putting into printed circuit board (PCB) 11 with perforate described later mechanism 2 opposed positions, 2 identification marking 11c of this printed circuit board (PCB) are in order to enter in the camera watch region that is arranged on 2 image mechanisms 4 in this perforate mechanism 2, under the state of the relative position of determining anchor clamps 36 and this printed circuit board (PCB), keeping printed circuit board (PCB) 11 by anchor clamps 36 absorption.
That is, the position of opening of opening guide hole 11b on the printed circuit board (PCB) 11 is calculated with the relative position that is arranged on the center of 2 datum hole f on the jig plate 362 according to the center of 2 identification marking 11c that taken by image mechanism 4 described later.Therefore, when putting into printed circuit board (PCB) with perforate mechanism 2 opposed positions, 2 identification marking 1c must be can not exceed the extraneous mode of the camera watch region of the image mechanism 4 of standby on the position of regulation, and the relative position ground absorption that pre-determines this printed circuit board (PCB) and anchor clamps 36 is keeping.
As determining that the example of this printed circuit board (PCB) 11 with the mechanism of the relative position of anchor clamps 36 will illustrate below.That is, as shown in Figure 1, below anchor clamps 36, be provided with printed circuit board (PCB) 11 is set platform 102 is set, this be provided with platform above, be provided with 2 ccd video cameras (not shown).Ccd video camera is taken 2 identification marking 11c of printed circuit board (PCB) 11 respectively by the through hole g and the h of jig plate 362, and its center for example makes cross symbol, and shows in monitor picture.In this monitor picture, corresponding with each kind of printed circuit board (PCB) 11, by computer, the camera watch region of determining 2 image mechanisms 4 of position of readiness is made circle represented.Therefore, when watching monitor picture, in the camera watch region of representing with circle for the center that enters cross symbol,, just can determine both relative positions by being provided with on the platform 102 with hand mobile printing circuit board 11.
When the printed circuit board (PCB) 11 on platform 102 will be set was arranged at above-mentioned relative position, anchor clamps 36 descended by cylinder 364, and absorption is keeping this printed circuit board (PCB) 11, and these anchor clamps rise by this cylinder once more.Then, arm 35 moves to the 2 opposed positions with perforate mechanism always.When moving to perforate mechanism 2 opposed positions, anchor clamps 36 descend by cylinder 364 always, and the printed circuit board (PCB) 11 that absorption is keeping is arranged on the operation post 101 that is positioned at pedestal 100 tops.In addition, because of anchor clamps 36 pass through spring 365, printed circuit board (PCB) 11 is pressed on the operation post 101, thereby can avoids taking place excessive pushing force and vibrations.
Then, the localization method to the perforate mechanism 2 that has guide hole 11b on printed circuit board (PCB) 11 describes.This position of opening is determined based on 2 following basic consideration points.The 1st is, the guide hole 11b of printed circuit board (PCB) 11 is the benchmark perforate with the center that correctly is formed at 2 datum hole f among the datum hole f on the jig plate 362.The 2nd is, the circuit design 11a that is printed on the printed circuit board (PCB) 11 is identical with the relative position that designs as far as possible with the relative position of guide hole 11b.
Be benchmark so, offer the reasons are as follows of guide hole 11b with 2 datum hole f that are arranged among the datum hole f on the jig plate 362.Promptly, printing circuit design 11a on the printed circuit board (PCB) 11 although be, with identification marking 11c in the printing of the relative position in the design of relative this circuit design, and consideration has the scheme of guide hole 11b in the center of this identification marking 11c, but in this scheme, under the situation that the temperature Change of the relative position of identification marking 11c during at printing process or because of perforate staggers, guide hole 11b is offered in the position that can not determine in design.
As other means, considered on printed circuit board (PCB) 11, be provided with 2 identification mark 11c, determine with this identification with the perforate coordinate in the design that is labeled as benchmark, on this coordinate, to open the method for guide hole 11b., in the method, also because of above-mentioned temperature Change etc., under the situation that 2 identification is staggered with the interval of mark 11c, 2 identifications are also staggered as the perforate coordinate in the design of benchmark with mark.Therefore, at first, 2 identifications correctly must be modified to numerical value in the design with the interval of mark 11c.For this reason, on jig plate 362, be provided with as 2 identifications of datum hole f with corresponding 2 the datum hole f in interval in the design of mark 11c, and set perforate reference position with this correct at interval identical guide hole 11b.Then, under the situation that printed circuit board (PCB) 11 is kept by anchor clamps 36 absorption, because of this printed circuit board (PCB) and anchor clamps can misplace at the relative position of XY direction and gyratory directions, the dislocation of relative position that must correction perforate reference position.
At this,, open the operation of guide hole 11b on the printed circuit board (PCB) 11 and carry out as follows based on above-mentioned consideration.Be pressed to position on the operation post 101 at above-mentioned printed circuit board (PCB) 11,2 identifications, enter in the camera watch region of 2 image mechanisms 4 respectively by the through hole g and the h of jig plate 362 with mark 11c.Therefore, 4 pairs of 2 identifications of camera head are made a video recording with mark 11c, and send its image pickup result to image processor structure 5.Then, the travel mechanism 5 of camera head 4 distinguishes the relative position with perforate mechanism 2 in advance.Camera head 4 is moved into place on the position of 2 datum hole f on the jig plate 362,2 datum holes are made a video recording, and send its shooting results to image processor structure 5.In addition, for 2 identifications are entered in the shooting area of camera head 4 simultaneously with mark 11c and opposed with it datum hole f,, once take with regard to it is enough printing this identification on the printed circuit board (PCB) 11 with under the situation of mark.
Next, image processor structure 5 is obtained the XY coordinate of 2 identifications with the center of mark 11c and 2 datum hole f according to photographic images, and its result is sent in the calculation mechanism 7.Then, the straight line that calculation mechanism 7 will connect the XY coordinate of center separately compares, and calculates the intersecting angle that both intersect.That is, the degree that staggers of printed circuit board (PCB) 11 and the relative position revolution that is arranged on the datum hole f on the jig plate 362 can only be this intersecting angle.For this reason, then, calculation mechanism 7 is obtained the XY coordinate of the centre coordinate (center of gravity) of the straight line that connects each center respectively, calculates the relative position relation of the two centre coordinate (center of gravity).
According to above-mentioned, can obtain the reference position that is used on printed circuit board (PCB) 11, offering guide hole 11b.That is, this reference position is centre coordinate with 2 datum hole f of jig plate 362 amount of relative position relation of the two centre coordinate (center of gravity) that staggers respectively, and then turns round the coordinate that the amount of above-mentioned intersecting angle forms.In other words, this coordinate is 2 identifications being arranged on the printed circuit board (PCB) 11 to be overlapped and then the center of the datum hole when only turning round intersecting angle with the position of centre of gravity of 2 datum hole f that are provided with on the position of centre of gravity of mark 11c and the jig plate 362.
; obtaining the method that is used for opening the reference position of guide hole 11d on printed circuit board (PCB) 11 according to 2 above-mentioned identifications with mark 11c and 2 datum hole f, the identification of this reference position is only obtained with a direction (directions X or Y direction) with the relative position relation of mark relevantly relatively.Therefore, when further obtaining both relative position relations accurately, preferably to revise and the dislocation of 2 identifications with the relative position of the perpendicular direction of mark.Below this method is described.
Printed circuit board (PCB) 11 is provided with the identification in 4 places mark 11c on every side that is in shown in Figure 9.And, on the jig plate 362, with 4 identifications with on the suitable position of the allocation position in the design of mark 11c, also be provided with 4 datum hole f.In addition, 4 identification with mark 11c be printed on the relative position relation that the circuit design on the printed circuit board (PCB) 11 has regulation.And, image mechanism 4 is taken with mark 11c and datum hole f 4 identifications respectively by the perforation slotted hole g or the h of jig plate 362, and image processor structure 6 is according to its shooting results, obtain center separately, and calculation mechanism 7 is obtained both position of centre of gravitys according to its center.
Then, calculation mechanism 7 moves to the position of centre of gravity of 4 identifications with mark 11c with the position of centre of gravity of 4 datum hole f, so that both position of centre of gravitys are consistent.Then, calculation mechanism 7 obtain 4 limits that constitute by 4 datum hole f and by 4 identifications with 4 limits that mark 11c constitutes, calculate the intersecting angle on corresponding separately 4 limits, obtain its mean value.By last, distinguish X-direction and the relative position relation these 2 directions dislocation of Y direction, 4 identifications usefulness mark 11c of having considered relative 4 datum hole f.
Promptly, 4 identifications that are arranged on the printed circuit board (PCB) 11 are not become by promptly 4 original positions of temperature deformation etc. with the position in the design of mark 11c, make the position of centre of gravity of 4 datum hole f and 4 identification coincide, be the mean value centers when center of gravity is turned round, these 4 datum holes of the intersecting angle on above-mentioned 4 limits with the position of centre of gravity of mark 11c.Therefore, as selecting arbitrarily 2 datum holes from 4 datum hole f, then the centre coordinate of these 2 datum holes becomes open 2 reference positions that guide hole 11b uses on printed circuit board (PCB) 11.
By last, distinguish behind the center of 2 datum hole f that have 2 promptly mobile XY coordinates in reference position that guide hole 11a uses on the printed circuit board (PCB) 11, calculation mechanism 7 is a benchmark with the center of these 2 datum hole f, calculates according to the center of this datum hole to be in position of opening relative position, guide hole 11a that design is upward determined.Then, travel mechanism 5 moves to the drift 22 of perforate mechanism 2 on this XY coordinate of calculating.
Below, split holes mechanism 2 operation of perforate on the printed circuit board (PCB) 11 and describe.The drift 22 of perforate mechanism 2 is kept by anchor clamps 36 absorption and is arranged on the operation post 101 up to printed circuit board (PCB) 11, all is positioned at the primary position (with reference to Figure 11) of not interfering these anchor clamps to move.Then, 21 of printed circuit board (PCB) 11 insertion drifts 22 and punch dies, absorption is keeping the anchor clamps 36 of printed circuit board (PCB) 11 to be pressed on the operation post 101.
Then, the servomotor 231 of perforate mechanism 2 makes feed screw 232 revolutions, by jack back 236, drift holding components 241 etc., drift 22 is descended, and this drift is moved to (with reference to Figure 11) on the position of readiness from primary position.This position of readiness is set for, when perforate mechanism 2 moves to the position that has guide hole 11a, drift 22 not with the height and position of interfering above of the jig plate 362 that is in the anchor clamps 36 on the operation post 101.Therefore, drift 22 can move freely along the XY direction on jig plate 362, simultaneously, can make perforate stroke (drift 22 moves to the distance (with reference to Figure 11) of the position of perforate on printed circuit board (PCB) 11 from position of readiness) minimum, can promptly carry out the perforate operation.
And 6 perforate mechanisms 2 move to respectively when printed circuit board (PCB) 11 is opened the XY coordinate position of guide hole 11a by travel mechanism 5, and servomotor 231 revolutions are to leave guide hole on this printed circuit board (PCB).In addition, on the guiding part 235 that the revolution by servomotor 231 moves up and down, be provided with Fig. 4 and shown in Figure 5, detect the sensor 25 of this guiding part in Z direction position, even thereby this guiding part 235 rises excessively, can not use excessive power to drift 22 yet.
In Fig. 7, as aforementioned, on jig plate 362 and adsorption plate 363, be provided with the yielding hole g of drift 22, the position of opening of the guide hole 11a of printed circuit board (PCB) 11 is arranged to be in this yielding hole site.In addition, the speed of gyration of the servomotor 231 that drift 22 moves up and down can suitably be changed according to the material of printed circuit board (PCB) 11 or the size of guide hole 11a etc.For example, Rou Ruan printed circuit board (PCB) 11 relatively, the ground states such as collapse limit or burr that can not produce are accelerated punching speed, and relatively more crisp printed circuit board (PCB) or be pasted with the printed circuit board (PCB) of Copper Foil etc. can not produce the slow down punching speed of from the position of readiness to the position of opening (with reference to Figure 11) of the state that breaks or peel off etc.In addition, speed of gyration by control servomotor 231, no matter drift 22 punching speed of (with reference to Figure 11) from the primary position to the position of opening, all can high-speed driving from the primary position to the position of readiness and from the position of opening to the primary position with drift 22, thus, shorten the perforate time, improved operation (with reference to Figure 11).In addition, by the driving of control servomotor 231, the position of readiness of drift 22 is also variable, according to the speed of this drift or the thickness of printed circuit board (PCB) 11 etc., the position of readiness of drift 22 can be set on the only position.In addition, owing to be under servomotor 231 effect, drive drift 22, can adjust the position of readiness of drift 22 micro-ly, be best suited for the perforate of sheet-like workpieces such as printed circuit board (PCB) by feed screw mechanism.
When the perforate of guide hole 11a finished, drift 22 rose by servomotor 231 and is driven into not primary position (with reference to Figure 11) with the mobile interference of drift 36.And drift 22 stops the attraction of printed circuit board (PCB) 11, and this printed circuit board (PCB) is retained on the operation post 101, drives by cylinder 364 and rises, and absorption is keeping next printed circuit board (PCB), and reverts to original position.When anchor clamps 36 moved to original position, the shift-out mechanism 33 of arm 35 interlocks that are connected with these anchor clamps moved to and stays the printed circuit board (PCB) 11 opposed positions on the operation post 101 together, and by the mechanism same with these anchor clamps, absorption is keeping this printed circuit board (PCB).And when anchor clamps 36 moved to next printed circuit board (PCB) 11 with perforate mechanism 2 opposed positions once more, shift-out mechanism 33 shifted out the printed circuit board (PCB) of perforate process finishing.
In addition, the action of each movable link of above-mentioned boring device is promptly moved beginning or the position of release or time etc. by the controlling organization 8 (with reference to Figure 10) in calculation mechanism 7 going along with, is controlled according to the kind of the printed circuit board (PCB) 11 that writes down in advance.In addition, be provided with the installation site of each member by adjusting fine-tuning as required whole mechanism such as screw rod.Image mechanism 4 is not limited to perforate mechanism 2 the all-in-one-piece occasion is set, and can be provided with independently.So under the occasion, can additionally be provided with image mechanism 4 towards travel mechanism that the XY direction moves.In addition, the moving up and down of drift 22 is not limited to the occasion that driven by servomotor 231, feed screw 232, jack back 236 etc., can be by drivings such as gear mechanism or rack-and-pinion mechanisms.
In addition, when being arranged on identification on the printed circuit board (PCB) 11 and being hidden in jig plate 362 following with mark 11c, image mechanism 4 uses X line video cameras, can obtain its position by perspective.In addition, above-mentioned boring device also can be used as the decision mechanism of the precision confirmation of the position that has had guide hole 11a etc. on printed circuit board (PCB) 11.
According to the boring device and the boring method of above-mentioned plate workpiece of the present invention,, can be very easy to and promptly carry out the replacing operation of jig plate owing to keeping plate workpiece to be transplanted on to adorn in the injection mechanism of perforate mechanism being provided with jig plate with taking off.
In addition, as be provided with a plurality of movably perforate mechanisms that can be separate, simultaneously, image mechanism and each perforate mechanism are provided with respectively with being integral, then can a plurality of guide holes etc. be arranged perforate simultaneously on plate workpiece, can become perforate operation fast, and, need not the travel mechanism of the special use of dollying mechanism, and needn't consider the moving of relative position of each perforate mechanism and image mechanism, in simplified structure, can improve the perforate precision.

Claims (3)

1. the boring device of a plate workpiece, have and be provided with the perforate mechanism of a plurality of identifications with perforate on the plate workpiece of mark, keeping described plate workpiece described plate workpiece to be transplanted on the injection mechanism of described perforate mechanism, image mechanism, the travel mechanism that described perforate mechanism is relatively moved to described plate workpiece, handle described image mechanism image pickup result the image processor structure and calculate the calculation mechanism of the result of described image processor structure, it is characterized in that:
The jig plate that is provided with a plurality of datum holes can be adorned and be arranged in the described injection mechanism with taking off; The mutual relative position of described datum hole is distinguished in advance; Described image mechanism is made a video recording with mark and described each datum hole to described each identification; Described image processor structure is obtained described each identification each center with mark and described each datum hole according to the image pickup result of described image mechanism; Described calculation mechanism is obtained the relative position relation of described jig plate and described plate workpiece with the center of the center of mark and described each datum hole according to described each identification, simultaneously, the boring device of calculating described plate workpiece based on the center and the described relative position relation of this each datum hole; Described travel mechanism moves to described position of opening with described perforate mechanism.
2. according to the described boring device of claim 1, it is characterized in that described perforate mechanism is provided with a plurality of, these perforate mechanisms can move independently of each other by described travel mechanism respectively, and described image mechanism is arranged to one with described each perforate mechanism respectively.
3. the boring method of a plate workpiece, it is characterized in that, have and be provided with the perforate mechanism of a plurality of identifications with perforate on the plate workpiece of mark, keeping described plate workpiece described plate workpiece to be transplanted on the injection mechanism of described perforate mechanism, image mechanism, the travel mechanism that described perforate mechanism is relatively moved to described plate workpiece, handle the image processor structure of the image pickup result of described image mechanism, calculate the calculation mechanism of the result of described image processor structure, be provided with a plurality of datum holes and can adorn the jig plate that is arranged on the described injection mechanism with taking off;
After described jig plate installed to described injection mechanism, keep described plate workpiece that described plate workpiece is transplanted on described perforate mechanism by described injection mechanism;
Afterwards, by described image mechanism, described each identification is made a video recording with mark and described each datum hole, according to this image pickup result, obtain described each identification each center by described image processor structure with mark and described each datum hole, use the center of mark and the center of this each datum hole based on this each identification, obtain the relative position relation of described jig plate and described plate workpiece by described calculation mechanism, and the position of opening of calculating described plate workpiece according to the center and the described relative position relation of described each datum hole, by described travel mechanism described perforate mechanism is moved to this position of opening, and at this position of opening by described perforate mechanism to described plate workpiece perforate.
CNB2004100055509A 2003-03-03 2004-02-18 Perforating apparatus and method for slab workpiece Expired - Fee Related CN1326674C (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP055238/2003 2003-03-03
JP2003055238A JP2004261924A (en) 2003-03-03 2003-03-03 Boring device for plate-like work and boring method

Publications (2)

Publication Number Publication Date
CN1526524A true CN1526524A (en) 2004-09-08
CN1326674C CN1326674C (en) 2007-07-18

Family

ID=33119305

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2004100055509A Expired - Fee Related CN1326674C (en) 2003-03-03 2004-02-18 Perforating apparatus and method for slab workpiece

Country Status (4)

Country Link
JP (1) JP2004261924A (en)
KR (1) KR100545817B1 (en)
CN (1) CN1326674C (en)
TW (1) TWI221438B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102822989A (en) * 2010-04-08 2012-12-12 罗伯特·博世有限公司 Method for producing a photovoltaic module comprising semiconductor cells contact-connected on the rear side
CN102834924A (en) * 2010-04-14 2012-12-19 罗伯特·博世有限公司 Method for producing a photovoltaic module comprising semiconductor cells contact-connected on the rear side, and photovoltaic module
CN101733439B (en) * 2008-11-05 2013-12-25 日立比亚机械股份有限公司 Machining device and machining method
CN104708109A (en) * 2013-12-16 2015-06-17 罗伯特·博世有限公司 Handheld tool substrate device
CN109983852A (en) * 2016-11-17 2019-07-05 住友电工印刷电路株式会社 The manufacturing method of flexible printing patch panel and the manufacturing device of flexible printing patch panel
CN110842581A (en) * 2019-11-22 2020-02-28 杭州巧狮信息科技有限公司 Building engineering makes up side fascia pressure equipment device
CN111229919A (en) * 2020-02-15 2020-06-05 厦门利德宝电子科技股份有限公司 Automatic aluminum substrate punching device and method
CN111375790A (en) * 2020-04-27 2020-07-07 福州台江茅头英科技有限公司 Machining equipment capable of automatically detecting drilling position

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5683170B2 (en) * 2009-10-15 2015-03-11 株式会社 ハリーズ Grinding apparatus, grinding method, and manufacturing method of thin plate member
CN101733438B (en) * 2009-11-10 2011-09-28 重庆理工大学 Robot for punching positioning holes on circuit board
CN103963101A (en) * 2014-04-18 2014-08-06 昆山力盟机械工业有限公司 Punching jig
CN106583786B (en) * 2016-12-07 2018-05-08 石家庄飞机工业有限责任公司 A kind of production method of carrying space angle location hole type frame and the type frame by its making
CN108788211A (en) * 2018-07-03 2018-11-13 芜湖德加智能科技有限公司 A kind of robot device of Workpiece boring
TWI752732B (en) * 2020-11-18 2022-01-11 中華精測科技股份有限公司 Via hole alignment assembly and via hole alignment method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2181347Y (en) * 1992-10-19 1994-11-02 武汉市光学科学技术研究所 Automatic sheet feeder for microcomputerized NC puncher
FR2750912B1 (en) * 1996-07-15 1998-11-06 Automa Tech Sa PRINTED CIRCUIT PLATE PUNCHING MACHINE
FR2800312B1 (en) * 1999-10-29 2002-01-25 Automa Tech Sa PUNCHING MACHINE FOR PANELS
JP3621629B2 (en) * 2000-05-31 2005-02-16 Uht株式会社 Drilling device

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101733439B (en) * 2008-11-05 2013-12-25 日立比亚机械股份有限公司 Machining device and machining method
CN102822989A (en) * 2010-04-08 2012-12-12 罗伯特·博世有限公司 Method for producing a photovoltaic module comprising semiconductor cells contact-connected on the rear side
CN102822989B (en) * 2010-04-08 2016-03-23 太阳世界工业图林根有限责任公司 For the manufacture of the method for photovoltaic module with backside contact semi-conductor cell
CN102834924A (en) * 2010-04-14 2012-12-19 罗伯特·博世有限公司 Method for producing a photovoltaic module comprising semiconductor cells contact-connected on the rear side, and photovoltaic module
US20130104957A1 (en) * 2010-04-14 2013-05-02 Metin Koyuncu Method for producing a photovoltaic module having backside-contacted semiconductor cells, and photovoltaic module
CN104708109A (en) * 2013-12-16 2015-06-17 罗伯特·博世有限公司 Handheld tool substrate device
CN109983852A (en) * 2016-11-17 2019-07-05 住友电工印刷电路株式会社 The manufacturing method of flexible printing patch panel and the manufacturing device of flexible printing patch panel
CN109983852B (en) * 2016-11-17 2022-02-01 住友电工印刷电路株式会社 Method for manufacturing flexible printed wiring board and apparatus for manufacturing flexible printed wiring board
CN110842581A (en) * 2019-11-22 2020-02-28 杭州巧狮信息科技有限公司 Building engineering makes up side fascia pressure equipment device
CN111229919A (en) * 2020-02-15 2020-06-05 厦门利德宝电子科技股份有限公司 Automatic aluminum substrate punching device and method
CN111375790A (en) * 2020-04-27 2020-07-07 福州台江茅头英科技有限公司 Machining equipment capable of automatically detecting drilling position

Also Published As

Publication number Publication date
KR20040078049A (en) 2004-09-08
JP2004261924A (en) 2004-09-24
TW200417449A (en) 2004-09-16
KR100545817B1 (en) 2006-01-24
TWI221438B (en) 2004-10-01
CN1326674C (en) 2007-07-18

Similar Documents

Publication Publication Date Title
CN1526524A (en) Perforating apparatus and method for slab workpiece
JP2930870B2 (en) Electronic component surface mounting equipment
CN1240500C (en) Perforating apparatus and workpiece processing method
KR101463090B1 (en) Drilling machine for multilayer printed circuit board
US20120287253A1 (en) Automatic vision aligned scriber
CN1501770A (en) Correcting method and apparatus for electronic components mounting apparatus
CN101362394A (en) Automatic contraposition method and system for screen process press
CN1767762A (en) Component delivery device,surface mounting machine and component experiment device
EP1179974A1 (en) Printed-wiring-board-relating-operation performing system
CN1526523A (en) Perforating device
CN210426544U (en) CCD vision counterpoint mechanism
CN1246130C (en) Boring device
CN210911622U (en) Linear screen printer
CN1257439C (en) Punching device for printing original
CN1138631C (en) Screen printing apparatus
CN1619256A (en) Omnidirectional automatic regulating device of drilling needle detecting instrument for circuit board hold drilling and its feeding device
CN1596569A (en) System and method for rapid alignment and accurate placement of electronic components on a printed circuit board
KR100689261B1 (en) Punching apparatus of pcb guide holl
CN112911922A (en) Patch system and patch method
CN202573242U (en) Single-lens double-light-path visual system for printed circuit board printing (PCB) press
JPH07314224A (en) Multi spindle drilling device for platelike work
CN215618549U (en) Automatic target shooting machine manipulator
CN216386822U (en) In-board mark detection device
JPH11291446A (en) Screen printing apparatus
JP2015103796A (en) Component supply device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20070718

Termination date: 20180218