CN1403686A - Hydraulic tunnel bogie for installing facing - Google Patents

Hydraulic tunnel bogie for installing facing Download PDF

Info

Publication number
CN1403686A
CN1403686A CN 02139359 CN02139359A CN1403686A CN 1403686 A CN1403686 A CN 1403686A CN 02139359 CN02139359 CN 02139359 CN 02139359 A CN02139359 A CN 02139359A CN 1403686 A CN1403686 A CN 1403686A
Authority
CN
China
Prior art keywords
turntable
oil cylinder
tunnel
piston rod
sheet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 02139359
Other languages
Chinese (zh)
Other versions
CN1215250C (en
Inventor
肖聪
齐学义
郜立焕
郭光辉
赵伟国
黎义斌
冯俊豪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GANSU POLYTECHNIC UNIV
Original Assignee
GANSU POLYTECHNIC UNIV
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GANSU POLYTECHNIC UNIV filed Critical GANSU POLYTECHNIC UNIV
Priority to CN 02139359 priority Critical patent/CN1215250C/en
Publication of CN1403686A publication Critical patent/CN1403686A/en
Application granted granted Critical
Publication of CN1215250C publication Critical patent/CN1215250C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

In the hydraulic tunnel bogie, the rotary bearing is installed inside a fixing ring; and several bearing balls are installed in the bonding site of the fixing ring, the rotary bearing and the rotating stage. On the rotating stage there are four vertical guide pillars, one vertical hydraulic elevating cylinder and one tray on the guide pillars and capable of moving up and down. The roller bracket on the tray consists of columns, worm and rollers; two circular backing supports are connected via an oil cylinder and two guiding slide blades on the upper surface of the backing supports can slide inside the slide way. Each of the two obliquely supporting oil cylinders is hinged between the lower part of the tray and the lower part of one of the backing supports. Two locking oil cylinders are installed in the lower parts of the backing supports separately.

Description

A kind of hydraulic pressure tunnel and Double sheet built is installed chassis
Technical field
The present invention is a kind of engineering mechanical device that is used for constructing tunnel.
Technical background
The all-hydraulic steel form concrete lining of available technology adopting platform building cart mechanical execution equipment, but concrete all carries by delivery pump, and cost and energy consumption are higher.
Summary of the invention
The present invention is that a kind of hydraulic pressure tunnel and Double sheet built is installed chassis, lining cutting is prefabricated in advance, wheel by the bottom can be walked on rail, its vehicle frame is installed in the rotating shaft of wheel, circular swivel bearing is installed in the retainer plate, the turntable that geomery is identical with swivel bearing be installed in the retainer plate and swivel bearing on, turntable is connected with bolt with swivel bearing, at retainer plate, the joint portion of swivel bearing and turntable along the circumferential direction is equipped with several balls, the present invention is symmetrical in the center of circle O of turntable, Plane Installation perpendicular to the turntable place has 4 or a plurality of vertical lead, the vertical lifting hydraulic jack is installed on the turntable, pallet is installed on 4 leads and can moves up and down at the effect lower edge of vertical lifting hydraulic jack lead, the roller carriage is installed on the pallet, the roller carriage is by the column that is vertically mounted on the pallet center position, the snail bar of circular arc is formed with two rollers that are installed in snail bar two ends, the mid point of snail bar is connected with column, the circular arc at snail bar place is that the pin joint O ' of two sheet builts of circular arc is the center of circle with the cross section, OO ' is perpendicular to the plane at turntable place, cross section is to be connected by an oil cylinder between two of the circular arc back of the body framves, on two back of the body frame upper inside surface, the identical guiding slide plate of a plate shape is installed respectively, the plane at guiding slide plate place is perpendicular to the inner arc surface of back of the body frame, the guiding slide plate can slide in the chute of roller, there are two diagonal brace oil cylinders to be hinged on the two ends of pallet respectively, the other end of two diagonal brace oil cylinders respectively with the C of bottom of two back of the body framves, 2 of D are hinged, C, D two point symmetries are in OO ', and C, the line that D is 2 is perpendicular to OO ', lower end at two back of the body framves is separately installed with a locked cylinder, the position of corresponding locked cylinder has a lock hole in the lining cutting, and the piston rod of locked cylinder can insert wherein.Before entering the tunnel, two sheet builts that the top is hinged together by hinge hang on back of the body frame, the diagonal brace oil cylinder stretches out piston rod, two sheet built spares are opened, regain the piston rod of vertical lifting oil cylinder simultaneously, make overall height be lower than the top, hole, when entering the hole, the turntable rotation makes two sheet builts be in the dark direction in hole in tunnel, starts running gear then and enters the tunnel, when arriving the precalculated position, tunnel, the lock line walking system is regained the piston rod of diagonal brace oil cylinder, rises the piston rod of vertical lifting oil cylinder simultaneously, the turntable half-twist, make two sheet built spare installation in position, regain the piston rod of locked cylinder, regain the diagonal brace oil cylinder simultaneously, the oil cylinder between two back of the body frame top and the piston rod of vertical lifting oil cylinder, make two back of the body framves break away from lining cutting fully, chassis withdraws from the tunnel.
Description of drawings
Fig. 1 is that application scenario-cross section of the present invention is horseshoe-shaped tunnel junction composition, and Fig. 2 is the front view of the present invention on tunnel depth direction.
Specific implementation
As shown in Figure 1, the present invention is mainly used in 6.3 meters installations with the prefabricated lining cutting of inner tunnel three hinged arch of diameter, can be used for the installation of tunnel cross section for circle, the shape of a hoof and city gate type tunnel lining.
As shown in Figure 2,4 wheels 2 at pallet bottom are bearing on the rail 1, available hydraulic running gear or machine-walking system drive, vehicle frame 3 is installed in the rotating shaft of wheel 2, circular swivel bearing 4 is installed in the retainer plate 6, geomery and swivel bearing 4 identical turntables 5 are installed in the retainer plate 6 and on the swivel bearing 4, turntable 5 is connected with swivel bearing 4 usefulness bolts, in the joint portion of retainer plate 5, swivel bearing 4 and turntable 5 several balls 7 are installed along the circumferential direction.
Be symmetrical in the center of circle O of turntable 5, Plane Installation perpendicular to turntable 5 places has 4 vertical leads 8, vertical lifting hydraulic jack 9 is installed on the turntable 5, pallet 11 is installed on 4 leads 8 and can moves up and down at the effect lower edge of vertical lifting hydraulic jack 9 lead 8, roller carriage 12 is installed on the pallet 11, roller carriage 12 is by the column 12-1 that is vertically mounted on pallet 11 center positions, the snail bar 12-3 of circular arc and be installed in snail bar 12-3 ends A, the roller 12-2 that 2 of B locate forms (claiming that 12-3 is because the similar snail of its shape angle for " snail bar "), the mid point of snail bar 12-3 is connected with column 12-1, and the circular arc AB at snail bar 12-3 place is that the pin joint O ' of two sheet builts 16 of circular arc is the center of circle with the cross section.
OO ' is perpendicular to the plane at turntable 5 places, cross section is that two of circular arc carry on the back between frame 17 tops by an oil cylinder 15 connections, on two back of the body frame 17 upper inside surface, the identical guiding slide plate 13 of a plate shape is installed respectively, the plane at guiding slide plate 13 places is perpendicular to the inner arc surface of back of the body frame 17, guiding slide plate 13 can slide in the chute of roller 12-2, there are two diagonal brace oil cylinders 10 to be hinged on the two ends of pallet 11 respectively, the other end of two diagonal brace oil cylinders 10 respectively with the C of bottom of two back of the body framves 17,2 of D are hinged, C, D two point symmetries are in OO ', and C, the line that D is 2 is perpendicular to OO '.
Lower end at two back of the body framves 17 is separately installed with a locked cylinder 18, the position of corresponding locked cylinder 18 has a lock hole in the lining cutting 16, the piston rod of locked cylinder 18 can insert wherein, can realize the locking and two functions of threading off, the piston rod of locked cylinder 18 inserts in the lock hole in the lining cutting 16 during locking, can prevent two sheet builts 16 and 17 slippages of back of the body frame, treat two sheet builts, 16 installation in position after, locked cylinder 18 is regained piston rod, is that lining cutting 16 breaks away from back of the body frame 17.
Before entering the tunnel, two sheet builts 16 that the top is hinged together by hinge 14 hang on back of the body frame 17, diagonal brace oil cylinder 10 stretches out piston rod, 16 of two sheet builts are opened, regain the piston rod of vertical lifting oil cylinder 9 simultaneously, make overall height be lower than the top, hole, when entering the hole, turntable 5 rotations make two sheet builts be in the dark direction in hole in tunnel, start running gear then and enter the tunnel, when arriving the precalculated position, tunnel, the lock line walking system is regained the piston rod of diagonal brace oil cylinder 10, rises the piston rod of vertical lifting oil cylinder 9 simultaneously, turntable 5 half-twists, make 16 installation in position of two sheet builts, regain the piston rod of locked cylinder 18, regain diagonal brace oil cylinder 10 simultaneously, the piston rod of oil cylinder 15 and vertical lifting oil cylinder 9, make two back of the body framves 17 break away from lining cutting 16 fully, chassis withdraws from the tunnel.

Claims (2)

1, a kind of hydraulic pressure tunnel and Double sheet built is installed chassis, wheel 2 by the bottom can be walked on rail 1, vehicle frame 3 is installed in the rotating shaft of wheel 2, circular swivel bearing 4 is installed in the retainer plate 6, geomery and swivel bearing 4 identical turntables 5 are installed in the retainer plate 6 and on the swivel bearing 4, turntable 5 is connected with swivel bearing 4 usefulness bolts, at retainer plate 6, swivel bearing 4 along the circumferential direction is equipped with several balls 7 with the joint portion of turntable 5, feature of the present invention is the center of circle O that is symmetrical in turntable 5, Plane Installation perpendicular to turntable 5 places has 4 vertical leads 8, vertical lifting hydraulic jack 9 is installed on the turntable 7, pallet 11 is installed on 4 leads 8 and can moves up and down at the effect lower edge of vertical lifting hydraulic jack 9 lead 8, roller carriage 12 is installed on the pallet 11, roller carriage 12 is by the column 12-1 that is vertically mounted on pallet 11 center positions, the snail bar 12-3 of circular arc and the roller 12-2 that is installed in snail bar 12-3 two ends form, the mid point of snail bar 12-3 is connected with column 12-1, the circular arc AB at snail bar 12-3 place is that the pin joint O ' of two sheet builts 16 of circular arc is the center of circle with the cross section, OO ' is perpendicular to the plane at turntable 5 places, cross section is that two of circular arc carry on the back between frame 17 tops by an oil cylinder 15 connections, on two back of the body frame 17 upper inside surface, the identical guiding slide plate 13 of a plate shape is installed respectively, the plane at guiding slide plate 13 places is perpendicular to the inner arc surface of back of the body frame 17, guiding slide plate 13 can slide in the chute of roller 12-2, there are two diagonal brace oil cylinders 10 to be hinged on the two ends of pallet 11 respectively, the other end of two diagonal brace oil cylinders 10 respectively with the C of two back of the body frame 17 bottoms, 2 of D are hinged, C, D two point symmetries are in OO ', and C, the line that D is 2 is perpendicular to OO ', lower end at two back of the body framves 17 is separately installed with a locked cylinder 18, the position of corresponding locked cylinder 18 has a lock hole in the lining cutting 16, and the piston rod of locked cylinder 18 can insert wherein.
2, hydraulic pressure tunnel and Double sheet built according to claim 1 is installed chassis, it is characterized in that before entering the tunnel, two sheet builts 16 that the top is hinged together by hinge 14 hang on back of the body frame 17, diagonal brace oil cylinder 10 stretches out piston rod, 16 of two sheet builts are opened, regain the piston rod of vertical lifting oil cylinder 9 simultaneously, make overall height be lower than the top, hole, when entering the hole, turntable 5 rotations make two sheet builts be in the dark direction in hole in tunnel, start running gear then and enter the tunnel, when arriving the precalculated position, tunnel, the lock line walking system, regain the piston rod of diagonal brace oil cylinder 10, rise the piston rod of vertical lifting oil cylinder 9 simultaneously, turntable 5 half-twists make 16 installation in position of two sheet builts, regain the piston rod of locked cylinder 18, regain diagonal brace oil cylinder 10 simultaneously, the piston rod of oil cylinder 15 and vertical lifting oil cylinder 9 makes two back of the body framves 17 break away from lining cutting 16 fully, and chassis withdraws from the tunnel.
CN 02139359 2002-07-31 2002-07-31 Hydraulic tunnel bogie for installing facing Expired - Fee Related CN1215250C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 02139359 CN1215250C (en) 2002-07-31 2002-07-31 Hydraulic tunnel bogie for installing facing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 02139359 CN1215250C (en) 2002-07-31 2002-07-31 Hydraulic tunnel bogie for installing facing

Publications (2)

Publication Number Publication Date
CN1403686A true CN1403686A (en) 2003-03-19
CN1215250C CN1215250C (en) 2005-08-17

Family

ID=4750045

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 02139359 Expired - Fee Related CN1215250C (en) 2002-07-31 2002-07-31 Hydraulic tunnel bogie for installing facing

Country Status (1)

Country Link
CN (1) CN1215250C (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101775990A (en) * 2010-03-15 2010-07-14 中国葛洲坝集团股份有限公司 Three-dimensional space curved surface steel mould trolley
CN102061927A (en) * 2010-12-10 2011-05-18 中铁隧道集团有限公司 Tunnel waterproof material laying equipment and method
CN102135001A (en) * 2011-03-25 2011-07-27 中铁三局集团有限公司 Device for paving tunnel waterproof boards
CN101260808B (en) * 2007-03-07 2012-02-29 株式会社小松制作所 Quadrant mounting device
CN102607357A (en) * 2011-06-16 2012-07-25 中铁十六局集团有限公司 Method for rapidly detecting radian of template of tunnel lining trolley and debugging trolley in position
CN103184878A (en) * 2013-03-25 2013-07-03 中交路桥建设有限公司 Method for improving second lining construction efficiency in tunnel widening section
CN103806924A (en) * 2014-03-07 2014-05-21 陕西理工学院 Steel form carrier variable camber gear for concrete lining for cave depot
CN105673045A (en) * 2015-12-30 2016-06-15 中铁十二局集团有限公司 Large reverse slop and small cross-section tunnel double chassis direct connection lining construction method
CN106638338A (en) * 2016-12-30 2017-05-10 河南工程学院 Template walking trolley

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101260808B (en) * 2007-03-07 2012-02-29 株式会社小松制作所 Quadrant mounting device
CN101775990A (en) * 2010-03-15 2010-07-14 中国葛洲坝集团股份有限公司 Three-dimensional space curved surface steel mould trolley
CN101775990B (en) * 2010-03-15 2012-04-25 中国葛洲坝集团股份有限公司 Three-dimensional space curved surface steel mould trolley
CN102061927A (en) * 2010-12-10 2011-05-18 中铁隧道集团有限公司 Tunnel waterproof material laying equipment and method
CN102061927B (en) * 2010-12-10 2012-07-18 中铁隧道集团有限公司 Tunnel waterproof material laying equipment and method
CN102135001A (en) * 2011-03-25 2011-07-27 中铁三局集团有限公司 Device for paving tunnel waterproof boards
CN102607357A (en) * 2011-06-16 2012-07-25 中铁十六局集团有限公司 Method for rapidly detecting radian of template of tunnel lining trolley and debugging trolley in position
CN102607357B (en) * 2011-06-16 2016-01-20 中铁十六局集团有限公司 A kind of quick detection tunnel lining trolley template radian and debugging chassis method in place
CN103184878A (en) * 2013-03-25 2013-07-03 中交路桥建设有限公司 Method for improving second lining construction efficiency in tunnel widening section
CN103184878B (en) * 2013-03-25 2015-02-25 中交路桥建设有限公司 Method for improving second lining construction efficiency in tunnel widening section
CN103806924A (en) * 2014-03-07 2014-05-21 陕西理工学院 Steel form carrier variable camber gear for concrete lining for cave depot
CN103806924B (en) * 2014-03-07 2016-09-14 陕西理工学院 A kind of cave depot concrete-lined telescoping steel form variable camber gear
CN105673045A (en) * 2015-12-30 2016-06-15 中铁十二局集团有限公司 Large reverse slop and small cross-section tunnel double chassis direct connection lining construction method
CN106638338A (en) * 2016-12-30 2017-05-10 河南工程学院 Template walking trolley
CN106638338B (en) * 2016-12-30 2019-08-27 河南工程学院 A kind of template moving trolley

Also Published As

Publication number Publication date
CN1215250C (en) 2005-08-17

Similar Documents

Publication Publication Date Title
CN1799983A (en) Method for kingsize gate-type crane translational transfer and its rotary device
CN1215250C (en) Hydraulic tunnel bogie for installing facing
CN101979803B (en) Method for mounting prefabricated members of roof or floor in place and mounting equipment
WO2015124068A1 (en) Dual-column stationary two-level vehicle parking apparatus
CN109295999B (en) Prefabricated assembled comprehensive pipe rack mounting machine and construction method thereof
CN1590673A (en) Parking method and equipment
CN108643941B (en) Gantry type arch installs trolley
CN115653650A (en) Temporary support mechanism for coal mine roadway and using method thereof
CN211819422U (en) Lifting walking template trolley suitable for construction of curve tunnel
CN111691456A (en) Use method of internal formwork rack for pipe gallery construction
CN205857853U (en) The elevating mechanism of two layers of parking stall column
CN105781410A (en) Novel long-spiral drilling machine
CN113997426B (en) Intelligent wheel type wire saw for reinforced concrete support dismantling operation
CN215244786U (en) Rotary direction-adjusting device for rubber-tyred vehicle
CN212358378U (en) Lifting trolley for pipe gallery construction
CN202829498U (en) Hydraulic jacking device
CN106013152A (en) Cast-in-situ bored pile steel protection pipe recycling device without damage
CN206384785U (en) A kind of modularization gate-type multifunctional rock drilling trolley job platform
JP2003239697A (en) Tunnel interior-finish working device
CN221346790U (en) Drill carriage central auxiliary support and anti-rotation mechanism
CN219174077U (en) Well lid erection equipment
CN219412047U (en) Well type underground parking garage
CN217107035U (en) Vault lining section divides lining cutting structure
CN110758208B (en) Haulage equipment for tunnel construction
CN104499745B (en) Three-dimensional self-avoiding type lifting parking facility

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee