CN1328414C - Welding method for major repairing cathode of large aluminium electrolytic bath - Google Patents

Welding method for major repairing cathode of large aluminium electrolytic bath Download PDF

Info

Publication number
CN1328414C
CN1328414C CNB2004101009688A CN200410100968A CN1328414C CN 1328414 C CN1328414 C CN 1328414C CN B2004101009688 A CNB2004101009688 A CN B2004101009688A CN 200410100968 A CN200410100968 A CN 200410100968A CN 1328414 C CN1328414 C CN 1328414C
Authority
CN
China
Prior art keywords
cathode
welding
electrolytic tank
aluminium
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CNB2004101009688A
Other languages
Chinese (zh)
Other versions
CN1651610A (en
Inventor
王玉
干益人
齐海青
刘淼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Aluminum Zhengzhou Research Institute Of Nonferrous Metals Co Ltd
Original Assignee
Aluminum Corp of China Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Aluminum Corp of China Ltd filed Critical Aluminum Corp of China Ltd
Priority to CNB2004101009688A priority Critical patent/CN1328414C/en
Publication of CN1651610A publication Critical patent/CN1651610A/en
Application granted granted Critical
Publication of CN1328414C publication Critical patent/CN1328414C/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Arc Welding In General (AREA)

Abstract

The present invention discloses a welding method for a major repairing cathode of a large aluminum electrolytic bath, which relates to a major repairing method for a cathode of a prebaked anode aluminum electrolytic tank for aluminum electrolysis. The present invention is characterized in that during the maintenance, firstly, a cathode steel rod is cut off outside a position between the inner wall of the electrolytic tank and a cathode block, and an incision is respectively repaired, flattened and deburred. Next, a conduction connecting plate which is connected with a section of steel rod is entirely moved in the inner cavity of the electrolytic tank. Then, conventional build-up welding operation for connecting the steel plate is carried out; after being welded, the steel plate is moved outside the electrolytic tank, and two cross sections of cathode steel are coincidently abutted and are firmly welded to complete the maintenance work. On the premise of assurance of regular production of an entire series of the large prebaked anode aluminum electrolytic tank for aluminum electrolysis, the welded cathode steel rod for electrolytic tank major repairing is moved from the outside of the electrolytic tank to the inside of the electrolytic tank for welding by the principle that a steel structure tank casing of the electrolytic tank has shielding effect to a magnetic field under the circumstance of effectively solving the power failure and the load down of the production series to the major repair of the electrolytic tank.

Description

The welding process of major repairing cathode of large aluminium electrolytic bath
Technical field
The welding process of major repairing cathode of large aluminium electrolytic bath relates to a kind of overhaul method that is used for the large-sized prebaked cell for aluminum-reduction negative electrode of Aluminium Electrolysis.
Background technology
At present, in the Aluminum Electrolysis Production process, adopt the maintenance large-sized prebaked cell for aluminum-reduction that has a power failure usually.When stopping groove cleaning negative electrode, connection piece is cut off from cathode steel bar and aluminium one steel blast welding block on the cathode carbon pieces, if aluminium one steel blast welding block damages, also it to be cut off from soft being with of negative electrode aluminium that links to each other with negative busbar, under situation about having a power failure, weld the new aluminium one steel blast welding block of lastblock, and then couple together with the method for welding with connection piece cathode steel bar and aluminium one steel blast welding block.Being connected with in the termination of cathode steel bar of its cathode steel bar forms and adopts two kinds of methods of negative electrode square steel crimping with the connection steel plate is piecemeal with the built-up welding of aluminium one steel blast welding block.In electrolytic cell overhaul in the past, because electrolytic strength of current is not high, the magneticstrength in the factory building is little, and the method that the connection of its cathode steel bar is all taked to weld is carried out.Because Aluminium Electrolysis is to developing in type electrolyzer direction, along with the progressively operation of 280kA, 300KA and 350KA large-sized prebaked cell for aluminum-reduction, the ratio of the production capacity of large-scale groove in aluminium production significantly improves.But along with the continuous increase of electrolytic cell currents intensity, the difficulty of bringing for the electrolytic cell overhaul of electrolysis aluminum production enterprises is also increasing.Along with improving constantly of electrolytic cell currents magnitude, magneticstrength in the cell room constantly increases, adopt electric-arc welding commonly used to be connected to a fatal weakness, be exactly under certain magneticstrength, to be difficult for welding, even burn-on reluctantly, also may be rosin joint, can not guarantee that welding quality can not guarantee welding strength again.Therefore, the large-sized prebaked cell for aluminum-reduction of current electrolysis aluminium manufacturing enterprise is when carrying out electrolytic cell overhaul, the welding of anticathode rod iron is not to take whole electrolysis production series to be carried out repeatedly load down or power failure is welded in when welding, takes negative electrode square steel compression bonding method exactly.A kind of method was both brought the certain economic loss to electrolysis aluminum production enterprises before adopting, and brought many hidden danger for again the steady running and the safety and production of electrolyzer; And when adopting a kind of method in back, because of crimping resistance will be higher than welding resistance, As time goes on, crimping resistance may constantly increase, thereby causes power consumption to increase.
Summary of the invention
Purpose of the present invention is exactly the deficiency that exists for above-mentioned prior art, providing a kind of can make under the whole serial ordinary production situation of large-sized prebaked cell for aluminum-reduction, arbitrary electrolyzer in the series carried out large repairs, produce that series does not have a power failure or the situation of few load down under, the overhaul method of large-sized prebaked cell for aluminum-reduction.
The objective of the invention is to be achieved through the following technical solutions.
The welding process of major repairing cathode of large aluminium electrolytic bath, it is characterized in that after stopping groove cleaning negative electrode, cathode steel bar is cut off at the position of cathode steel bar between electrolyzer inwall and cathode block, respectively to the fracture place under repair, leveling, deburring, to be connected with the whole electrolyzer inner chamber that moves into of conductive connection plates of one section rod iron again, carry out conventional connection steel plate built-up welding operation, cut off aluminium-steel blast welding block, and the soft band of negative electrode aluminium is cut off from negative busbar, burn-on again new aluminium-steel blast welding block and the soft band of negative electrode aluminium, with web plate cathode steel bar and aluminium-steel blast welding block are coupled together with the method for welding at last, again it is moved on to electrolyzer after the welding and reset outward, the identical butt joint of two fracture faces of cathode steel bar is welded finish maintenance service.
Method of the present invention is characterized in that when the negative electrode casting mold, and cathode steel bar reserves and cuts off by the required length of rod iron fracture loss.
Method of the present invention, owing to adopt the method that cathode steel is blocked, the maintenance that connects steel plate is moved in the electrolyzer, because box hat has shielding effect to magnetic field, utilize the steel construction pot shell of electrolyzer that there is this principle of shielding effect in magnetic field, the welding of cathode steel bar moves to electrolyzer inside by the electrolyzer outside and welds during electrolytic cell overhaul, and the welding of cathode steel bar is moved in the electrolyzer that can weld after the shielding by unweldable high-intensity magnetic field and carries out during just electrolytic cell overhaul.When large-sized prebaked cell for aluminum-reduction stops groove cleaning negative electrode, in electrolyzer, cathode steel bar is cut off, and repair incision position neat by certain shape.When the negative electrode casting mold, reserve cathode steel bar by required length, to repair incision position neatly by certain shape equally, under situation about not having a power failure, cathode steel bar is coupled together then with connecting the built-up welding of steel plate a slice a slice.
Method of the present invention has been avoided the maintenance because an electrolytic cell overhaul has a power failure, and influences a series of electrolyzer productions, causes series to have a power failure, and can guarantee the electrolyzer smooth running, enhances productivity.
Description of drawings
Fig. 1 is the cathode steel bar welding position synoptic diagram of the welding process of major repairing cathode of large aluminium electrolytic bath of the present invention.
Specific implementation
Further describe as follows below in conjunction with accompanying drawing to method of the present invention.
The welding process of major repairing cathode of large aluminium electrolytic bath, in the maintenance process, after stopping groove cleaning negative electrode, at first will outside the position of cathode steel bar between electrolyzer inwall and cathode block cathode steel bar be cut off, respectively to the fracture place under repair, leveling, deburring, to be connected with the whole electrolyzer inner chamber that moves into of conductive connection plates of one section rod iron again, carry out conventional connection steel plate built-up welding operation again, cut off aluminium-steel blast welding block, and the soft band of negative electrode aluminium is cut off from negative busbar, burn-on again new aluminium-steel blast welding block and the soft band of negative electrode aluminium, use web plate cathode steel bar and aluminium-steel blast welding block to couple together at last with the method for welding, after the welding it is moved on to outside the electrolyzer, the identical butt joint of two sections of cathode steel is welded finish maintenance service.1 is cathode carbon pieces among Fig. 1,2. electrolyzer pot shell, 3. web plate, 4. cathode steel bar, 5. aluminium-steel blast welding block, 6. negative busbar, 7. soft band of negative electrode aluminium.
Adopt large-sized prebaked cell for aluminum-reduction overhaul of the present invention when stopping groove cleaning negative electrode, cut off at electrolyzer pot shell 2 inner cathode rod irons 4.During welding, utilize the shielding in 2 pairs of magnetic fields of steel tank shell, under situation about not having a power failure, cathode steel bar 4 is coupled together and reach the overhaul purpose with connection piece 3.Adopt method of the present invention, during the overhaul electrolyzer, under the situation that need not have a power failure, the rosin joint phenomenon do not occur, the weld volts lost meets the production standard requirement.

Claims (2)

1. the welding process of major repairing cathode of large aluminium electrolytic bath, it is characterized in that after stopping groove cleaning negative electrode, cathode steel bar is cut off at the position of cathode steel bar between electrolyzer inwall and cathode block, respectively to the fracture place under repair, leveling, deburring, to be connected with the whole electrolyzer inner chamber that moves into of conductive connection plates of one section rod iron again, carry out conventional connection steel plate built-up welding operation, cut off aluminium-steel blast welding block, and the soft band of negative electrode aluminium is cut off from negative busbar, burn-on again new aluminium-steel blast welding block and the soft band of negative electrode aluminium, with web plate cathode steel bar and aluminium-steel blast welding block are coupled together with the method for welding at last, again it is moved on to electrolyzer after the welding and reset outward, the identical butt joint of two fracture faces of cathode steel bar is welded finish maintenance service.
2. the welding process of major repairing cathode of large aluminium electrolytic bath according to claim 1 is characterized in that when the negative electrode casting mold, and cathode steel bar reserves and cuts off by the required length of rod iron fracture loss.
CNB2004101009688A 2004-12-28 2004-12-28 Welding method for major repairing cathode of large aluminium electrolytic bath Active CN1328414C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2004101009688A CN1328414C (en) 2004-12-28 2004-12-28 Welding method for major repairing cathode of large aluminium electrolytic bath

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2004101009688A CN1328414C (en) 2004-12-28 2004-12-28 Welding method for major repairing cathode of large aluminium electrolytic bath

Publications (2)

Publication Number Publication Date
CN1651610A CN1651610A (en) 2005-08-10
CN1328414C true CN1328414C (en) 2007-07-25

Family

ID=34869602

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2004101009688A Active CN1328414C (en) 2004-12-28 2004-12-28 Welding method for major repairing cathode of large aluminium electrolytic bath

Country Status (1)

Country Link
CN (1) CN1328414C (en)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100404727C (en) * 2005-08-30 2008-07-23 河南中孚实业股份有限公司 Method for randomly large scale repair and welding electrolytic bath under no cut-off condition of aluminium electrolytic series
CN100523308C (en) * 2005-11-02 2009-08-05 中国铝业股份有限公司 Method for thermite welding aluminium electrolytic cell cathode steel bar
CN100432298C (en) * 2005-11-02 2008-11-12 中国铝业股份有限公司 Method for reducing voltage drop of aluminum cell stop
CN100560806C (en) * 2006-06-20 2009-11-18 沈阳铝镁设计研究院 Potroom is connected the track insulation partition method with heavy repair department
CN101397679B (en) * 2007-09-28 2010-08-18 中国铝业股份有限公司 Minor maintenance judgment method for electrolyzer
CN102409362B (en) * 2011-12-26 2015-11-18 贵阳铝镁设计研究院有限公司 Aluminium cell is through-flow body do not have a power failure welding control system
CN103510111A (en) * 2012-06-21 2014-01-15 贵阳铝镁设计研究院有限公司 Electrolytic bath cathode steel bar connecting plate structure
CN103506744A (en) * 2012-06-21 2014-01-15 贵阳铝镁设计研究院有限公司 Magnetic shielding method for electric arc welding in high-intensity magnetic field of aluminum reduction cell
CN102806425B (en) * 2012-08-22 2014-07-16 黄河鑫业有限公司 Method for welding cathode flexible bus of aluminum electrolysis cell without series power failure
CN103320816B (en) * 2013-05-30 2016-05-25 青铜峡铝业股份有限公司 Method of attachment between a kind of aluminum cell cathode steel bar and connector presser
CN104972220B (en) * 2015-07-29 2017-03-15 武汉大学 The original position of a kind of soft master tape of aluminium electrolytic cell cathode and aluminium busbar does not have a power failure welding method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2112082C1 (en) * 1996-09-24 1998-05-27 Акционерное общество открытого типа "Всероссийский алюминиево-магниевый институт" Cathode shell of aluminum electrolyzer
RU2155824C1 (en) * 1999-03-15 2000-09-10 Оао "Суал" Cathode enclosure of aluminum electrolizer
CN2615148Y (en) * 2003-04-18 2004-05-12 杜荣华 Aluminium electrolytic cell crimp connector between cathode steel bar and cathode soft strip
CN2615149Y (en) * 2003-03-24 2004-05-12 杜荣华 Cathode steel bar and bus connector of aluminium cell

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2112082C1 (en) * 1996-09-24 1998-05-27 Акционерное общество открытого типа "Всероссийский алюминиево-магниевый институт" Cathode shell of aluminum electrolyzer
RU2155824C1 (en) * 1999-03-15 2000-09-10 Оао "Суал" Cathode enclosure of aluminum electrolizer
CN2615149Y (en) * 2003-03-24 2004-05-12 杜荣华 Cathode steel bar and bus connector of aluminium cell
CN2615148Y (en) * 2003-04-18 2004-05-12 杜荣华 Aluminium electrolytic cell crimp connector between cathode steel bar and cathode soft strip

Also Published As

Publication number Publication date
CN1651610A (en) 2005-08-10

Similar Documents

Publication Publication Date Title
CN1328414C (en) Welding method for major repairing cathode of large aluminium electrolytic bath
CN102059428B (en) Electrification welding method and device of aluminium cell under serial full current
CN102009255B (en) Downward and butt welding process for high strength steel for ship structure
CN100571958C (en) The charged welding method of aluminum cell cathode steel bar
CN102009252A (en) Vertical position welding process method of steel for high-strength hull structure
CN104827172A (en) Anti-magnetic shielding apparatus for repairing welding of electrolytic tank horizontal bus in strong magnetic field environment
CN102806425A (en) Method for welding cathode flexible bus of aluminum electrolysis cell without series power failure
CN105414708A (en) Welding repair method for gray cast iron
CN105458469A (en) Welded aluminum alloy box and welding method
CN103317249A (en) Method for repairing anode steel stud
CN102009253A (en) Transverse welding technical method for high-strength steel for ship structure
CN101357429B (en) Welding repair method of iron casting
CN113620159A (en) Welding structure hanger for steam turbine generator base and manufacturing method
CN201423498Y (en) Welding mould for original-position self-propagation welding repairing method of aluminum parent metal
CN206232825U (en) Anode steel claw is recycled after one kind corrosion
CN105195873A (en) Vertical-angle-joint welding method for hull structural steel
CN105624732A (en) Production method for low-resistance anode steel claw
CN201799783U (en) Run-on plate and run-off plate for welding of fire-resisting non-metal material body
CN213916738U (en) Welding groove structure for high-temperature alloy plate of turbine stationary blade of gas turbine
CN203356867U (en) Welding die for conducting self-propagating welding repair on cathode soft band and bus of aluminum reduction cell
CN206706219U (en) A kind of anode rod component
CN106493454B (en) The arc manipulation method of operation is welded in magnetic field environment
CN218657563U (en) Be used for prosthetic polar plate anchor clamps of positive pole steel claw
CN212384810U (en) Friction welding guide rod set
CN220376802U (en) Prebaked anode structure of aluminum electrolysis cell

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160115

Address after: 450041 No. 82, Jiyuan Road, Zhengzhou District, Henan

Patentee after: ZHENGZHOU NON-FERROUS METALS RESEARCH INSTITUTE CO., LTD. OF CHALCO

Address before: 100814, Haidian District, Fuxing Road, Beijing No. 12, China Aluminum Limited by Share Ltd

Patentee before: Aluminum Corporation of China Limited

CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 450041 No. 82, Jiyuan Road, Zhengzhou District, Henan

Patentee after: China Aluminum Zhengzhou Research Institute of Nonferrous Metals Co., Ltd.

Address before: 450041 No. 82, Jiyuan Road, Zhengzhou District, Henan

Patentee before: ZHENGZHOU NON-FERROUS METALS RESEARCH INSTITUTE CO., LTD. OF CHALCO