CN1327087C - 复合地基的施工方法 - Google Patents

复合地基的施工方法 Download PDF

Info

Publication number
CN1327087C
CN1327087C CNB2004101027101A CN200410102710A CN1327087C CN 1327087 C CN1327087 C CN 1327087C CN B2004101027101 A CNB2004101027101 A CN B2004101027101A CN 200410102710 A CN200410102710 A CN 200410102710A CN 1327087 C CN1327087 C CN 1327087C
Authority
CN
China
Prior art keywords
stake
pile
composite foundation
job practices
pile body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CNB2004101027101A
Other languages
English (en)
Other versions
CN1641112A (zh
Inventor
王继忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Pocentre Geotechnical Engineering Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNB2004101027101A priority Critical patent/CN1327087C/zh
Publication of CN1641112A publication Critical patent/CN1641112A/zh
Application granted granted Critical
Publication of CN1327087C publication Critical patent/CN1327087C/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

本发明的目的在于提供一种复合地基的施工方法,通过该方法可快速简便地形成复合地基,通过增加桩顶的扩径部,使普通CFG桩的置换率大大提高,从而减少桩的数量,较大幅度的节约工程开支,实现材料的节约,施工的简化。施工方法包括下述步骤:①钻机就位,在桩位处螺旋钻孔至地基中的预定深度;②一边泵送水硬性混合填料,一边提拔钻杆至地表形成桩身;③形成位于桩顶部的用于增加与将要铺设的褥垫层的接触面积的桩顶扩径部;④在所形成的桩顶扩径部的顶面和地基表面上,铺设褥垫层。

Description

复合地基的施工方法
技术领域
本发明涉及土木工程领域,特别是涉及建筑物地基的加固处理。
背景技术
在建筑物的地基加固处理中,通常采用两种方法:桩基和复合地基。复合地基加固处理是指地基下一定深度的土性较好且土层较稳定,但强度和变形不能满足上部荷载的要求,人们为了发挥土的承载能力而采取补强的方法,如碎石桩、CFG桩、水泥土桩等施工方法。其中目前使用较多的是螺旋压浆水泥粉煤灰碎石桩,即CFG桩。
CFG桩的受力特性是桩与***同承担上部荷载,其基础承载力计算公式为:
fa=mRk/Ap+(1-m)fsk
式中:m-面积置换率
Rk-单桩承载力标准值(kN)
Ap-桩端面积(m2)
fsk-基底土地基承载力标准值(kPa)
该式中决定承载力大小的关键参数为m值,即面积置换率。置换率的大小取决于CFG桩的直径大小和布桩的间距,因此如果不提高桩土置换率,桩的承载力再高也无法提高地基处理的承载力。由于目前CFG桩桩径的有关标准为350mm~600mm的等径,且桩间距较小,如果要提高置换率进而提高地基处理的承载力,减少地基变形,只能采用增加桩的数量或者加大桩的整体直径。无疑,这两种方法都会使工程量加大,工程成本增多。
发明内容
本发明的目的在于提供一种加固地基的施工方法,通过该方法可快速简便地形成复合地基,在该复合地基中,通过增加桩长和简单的桩顶扩径,在提高桩的承载力同时大大提高置换率,比普通CFG桩减少桩的数量,从而较大幅度的节约工程开支。
为了实现上述目的,本发明的复合地基的施工方法包括下述步骤:
①钻机就位,在桩位处螺旋钻孔至地基中的预定深度,该预定深度是这样确定的,即在该深度处其土层是层位稳定的,土性较好的土体,同时桩身长度和强度能够提供足够的承载力;
②一边泵送水硬性混合填料,一边提拔钻杆至地表形成桩身;
③形成位于桩顶部的用于增加与将要铺设的褥垫层的接触面积的桩顶扩径部;
④在所形成的桩顶扩径部的顶面和地基表面上,铺设褥垫层。
最好,在上述的混凝土桩的施工方法中,上述步骤①中桩身长度和强度能够提供足够的承载力是指,桩身提供的摩擦力和桩端提供的端阻力,以及桩身的强度,能够满足桩顶扩径后分担上部荷载的承载力要求。
最好,在上述的混凝土桩的施工方法中,上述步骤②中成孔至预定深度后,先开始泵送混合料后再提升钻杆。
最好,在上述的混凝土桩的施工方法中,上述步骤②中水硬性混合料是由碎石、水泥、砂、水、粉煤灰构成的。
最好,在上述的混凝土桩的施工方法中,上述步骤③中首先将螺旋钻掏出土体清运后,再形成位于桩顶部的用于增加与褥垫层的接触面积的桩顶扩径部。
最好,在上述的混凝土桩的施工方法中,上述步骤③中位于桩顶部的用于增加与褥垫层的接触面积的桩顶扩径部是通过下述方式浇注成形的,该方式为:在桩顶部的周围开挖土体,形成与桩身相连的桩顶扩径部,对该桩顶扩径部进行浇注,使其与桩身形成一体。
最好,在上述的混凝土桩的施工方法中,上述步骤③中桩顶扩径部浇注的是与桩身同级的水硬性混合料。
最好,在上述的混凝土桩的施工方法中,上述步骤④中褥垫层是由级配砂石构成的柔性层。
通过以上方法形成的复合地基的特点和优势在于:
①显著提高桩土置换率。既不需增加CFG桩的数量,也不需扩大桩身的整体桩径,只通过简单的桩顶扩径,即在桩上部制作大直径桩顶,可显著提高桩土的置换率,相比普通CFG桩面积置换率提高3~4倍,起到了事半功倍的效果。
②提高桩的承载力。由于普通CFG桩为桩***同受力,桩本身不用分担过多的上部荷载,因此桩的长度不必太长,桩的承载力不高。而采取了桩顶扩径后,桩本身要求的承载力必须满足桩顶面积增大后的上部荷载要求,因此需在原设计桩长的基础上再将桩身延长,其承载力要求比普通CFG桩更高。
③显著降低工程造价。虽然桩身长度比普通CFG桩进行延长,但由于桩土置换率的提高,在获得与普通CFG桩相同或更大的地基承载力的同时,可大大减少桩的数量,显著降低工程造价。
④工艺简单。桩顶扩径部只需开挖后灌注混合料即可,制作简单,质量可控。
附图说明
图1作为本发明的一个实施例的扩顶CFG桩的施工方法的工序图。
具体实施方式
作为本发明的一个实施例的混凝土桩的施工方法,其包括下述步骤,首先,如图1a所示,钻机就位,在桩位处采用螺旋钻1钻孔;然后,如图1b所示,螺旋钻孔至常规桩端持力层;接着,如图1c所示,继续钻进至一定深度;之后,如图1d所示,一边向钻孔内泵送水硬性混合填料2,一边提拔螺旋钻1;然后,如图1e所示,将螺旋钻1拔出地表,压灌完毕;然后,如图1f所示,在桩顶部的周围开挖土体,形成与桩身相连的桩顶扩径部3,对该桩顶扩径部3进行浇注;最后,如图1g所示,在桩顶部铺设褥垫层4。

Claims (8)

1、一种复合地基的施工方法,包括下述步骤:
①钻机就位,在桩位处螺旋钻孔至地基中的预定深度,该预定深度是这样确定的,即在该深度处其土层是层位稳定的,土性较好的土体,同时桩身长度和强度能够提供足够的承载力;
②一边泵送水硬性混合填料,一边提拔钻杆至地表形成桩身;
③形成位于桩顶部的用于增加与将要铺设的褥垫层的接触面积的桩顶扩径部;
④在所形成的桩顶扩径部的顶面和地基表面上,铺设褥垫层。
2、根据权利要求1所述的复合地基的施工方法,其特征在于上述步骤①中,桩身长度和强度能够提供足够的承载力是指,桩身提供的摩擦力和桩端提供的端阻力,以及桩身的强度,能够满足桩顶扩径后分担上部荷载的承载力要求。
3、根据权利要求1所述的复合地基的施工方法,其特征在于上述步骤②中,成孔至预定深度后,先开始泵送混合料后再提升钻杆。
4、根据权利要求1所述的复合地基的施工方法,其特征在于上述步骤②中,水硬性混合料是由碎石、水泥、砂、水、粉煤灰构成的。
5、根据权利要求1所述的复合地基的施工方法,其特征在于上述步骤③中,首先将螺旋钻掏出土体清运后,再形成位于桩顶部的用于增加与褥垫层的接触面积的桩顶扩径部。
6、根据权利要求1所述的复合地基的施工方法,其特征在于上述步骤③中,位于桩顶部的用于增加与褥垫层的接触面积的桩顶扩径部是通过下述方式浇注成形的,该方式为:在桩顶部的周围开挖土体,形成与桩身相连的桩顶扩径部,对该桩顶扩径部进行浇注,使其与桩身形成一体。
7、根据权利要求1所述的复合地基的施工方法,其特征在于上述步骤③中,桩顶扩径部浇注的是与桩身同级的水硬性混合料。
8、根据权利要求1所述的复合地基的施工方法,其特征在于上述步骤④中,褥垫层是由级配砂石构成的柔性层。
CNB2004101027101A 2004-12-28 2004-12-28 复合地基的施工方法 Active CN1327087C (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2004101027101A CN1327087C (zh) 2004-12-28 2004-12-28 复合地基的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2004101027101A CN1327087C (zh) 2004-12-28 2004-12-28 复合地基的施工方法

Publications (2)

Publication Number Publication Date
CN1641112A CN1641112A (zh) 2005-07-20
CN1327087C true CN1327087C (zh) 2007-07-18

Family

ID=34869668

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2004101027101A Active CN1327087C (zh) 2004-12-28 2004-12-28 复合地基的施工方法

Country Status (1)

Country Link
CN (1) CN1327087C (zh)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101818493A (zh) * 2010-03-23 2010-09-01 南通宏华建筑安装有限公司 复合地基的施工方法
CN102162245A (zh) * 2011-03-17 2011-08-24 中铁二局股份有限公司 软土地区地基加固的施工方法
JP6173671B2 (ja) * 2012-10-03 2017-08-02 常郎 後藤 構造物用基礎
CN104314078A (zh) * 2014-11-05 2015-01-28 王继忠 混凝土桩的施工设备及其施工方法
CN105386433B (zh) * 2015-12-08 2017-06-16 南京林业大学 一种微生物固土cfg桩复合地基及施工方法
CN110241695A (zh) * 2019-06-19 2019-09-17 贵州正业工程技术投资有限公司 一种碎石土超高填方地基加固方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1224786A (zh) * 1998-12-17 1999-08-04 何世鸣 一种新型短桩复合地基及其施工工艺
CN2352578Y (zh) * 1997-12-18 1999-12-08 中国建筑科学研究院地基基础研究所 异形水泥、粉煤灰、碎石桩
JP2001164569A (ja) * 1999-12-13 2001-06-19 Nippon Kaikou Kk オールケーシング式場所打杭構築方法
CN1424468A (zh) * 2003-01-21 2003-06-18 王继忠 复合地基的施工方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2352578Y (zh) * 1997-12-18 1999-12-08 中国建筑科学研究院地基基础研究所 异形水泥、粉煤灰、碎石桩
CN1224786A (zh) * 1998-12-17 1999-08-04 何世鸣 一种新型短桩复合地基及其施工工艺
JP2001164569A (ja) * 1999-12-13 2001-06-19 Nippon Kaikou Kk オールケーシング式場所打杭構築方法
CN1424468A (zh) * 2003-01-21 2003-06-18 王继忠 复合地基的施工方法

Also Published As

Publication number Publication date
CN1641112A (zh) 2005-07-20

Similar Documents

Publication Publication Date Title
CN104988907A (zh) 一种混凝土桩的施工方法
CN105625294A (zh) 一种复合地基及其施工方法
CN104929109B (zh) 置换式压灌水泥土复合桩及其施工方法和施工方法中采用的长螺旋钻机
JP5243669B1 (ja) 構造物傾動及び地盤改良の工法
CN104314078A (zh) 混凝土桩的施工设备及其施工方法
CN107513994A (zh) 一种分段变径自支护旋挖桩及其施工方法
CN103015396A (zh) 软土地基施工方法
CN106676993B (zh) 一种加筋碎石框架结构路基加固体系及其加固方法
CN101200888A (zh) 复合地基的施工方法
CN104099925A (zh) 混凝土桩的施工装置及其施工方法
CN1743561A (zh) 新型柱锤强夯置换法
CN1327087C (zh) 复合地基的施工方法
CN103195060A (zh) 软土地基预应力锚杆加固结构及其用途
CN102839683B (zh) 散体桩-透水性混凝土桩二元复合地基及处理方法
CN111379253A (zh) 高速铁路膨胀水泥浆后注浆散体材料桩复合地基施工方法
JP6158398B1 (ja) 合成基礎杭
JPH0547685B2 (zh)
CN104153355B (zh) 混凝土桩的施工装置及其施工方法
RU2286424C1 (ru) Буронабивной ступенчатый фундамент и способ его возведения
RU2662841C1 (ru) Способ уплотнения оснований, сложенных слабыми минеральными грунтами
CN1424468A (zh) 复合地基的施工方法
CN110258526A (zh) 预制式地下连续墙以及施工地下室外墙和楼板的方法
CN205776209U (zh) 混凝土桩的施工设备
JP2651893B2 (ja) 基礎杭構造
KR100687496B1 (ko) 건축단지 천공 층간에 확대공간을 갖는 착정공의 파일시공방법

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C57 Notification of unclear or unknown address
DD01 Delivery of document by public notice

Addressee: Wang Jizhong

Document name: Notification to Pay the Fees

EE01 Entry into force of recordation of patent licensing contract

Assignee: Beijing Pocentre Geotechnical Engineering Co.,Ltd.

Assignor: Wang Jizhong

Contract record no.: 2011110000108

Denomination of invention: Construction method of compound ground base

Granted publication date: 20070718

License type: Exclusive License

Open date: 20050720

Record date: 20110718

ASS Succession or assignment of patent right

Owner name: BEIJING PUISSANT GEOTECHNICAL ENGINEERING CO., LTD

Free format text: FORMER OWNER: WANG JIZHONG

Effective date: 20150104

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20150104

Address after: 102218, Beijing, Changping District East small town Taiping homes, building 31

Patentee after: Beijing Pocentre Geotechnical Engineering Co.,Ltd.

Address before: 102218, Beijing, Changping District East small town Taiping homes, building 31

Patentee before: Wang Jizhong