CN1183503A - Side wall anchored bearing and its installation method - Google Patents

Side wall anchored bearing and its installation method Download PDF

Info

Publication number
CN1183503A
CN1183503A CN 94115365 CN94115365A CN1183503A CN 1183503 A CN1183503 A CN 1183503A CN 94115365 CN94115365 CN 94115365 CN 94115365 A CN94115365 A CN 94115365A CN 1183503 A CN1183503 A CN 1183503A
Authority
CN
China
Prior art keywords
metal plate
fastener
reinforcing bar
bearing structure
structure body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 94115365
Other languages
Chinese (zh)
Inventor
黄嘉雄
江俊华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 94115365 priority Critical patent/CN1183503A/en
Priority to US08/498,567 priority patent/US5535562A/en
Priority to FR9508269A priority patent/FR2724960B1/en
Priority to DE19534945A priority patent/DE19534945C1/en
Publication of CN1183503A publication Critical patent/CN1183503A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

A side wall type of anchor holder which can be installed to side wall or bottom of prestressed concrete structure for installing the anchorage of prestressed steel bar is composed of bearing structural member and anchorage installation body. Said bearing structural member is a rectangular metal plate block with two clamping parts at one side for clamping the anchorage installation body which has a hollow triangular cover body formed integrally with its front panel that has an opening for installing anchorage. The bottom of two clamping parts has a hollow conic body and ribbed plate on inner side of the bottom.

Description

Side wall anchored bearing and mounting method thereof
The present invention is about being provided with the anchoring part and the mounting method thereof of the anchor head (anchor) of prestressed steel tendon (wire rope) on sidewall paneling (web) that is arranged on the prestressed concrete structure or the base plate.
Prestressed concrete engineering since rose in 1940 be practical since, be applied to many large-scale prestressed reinforced concrete construction things.For example, the construction panels inside of the works of bridge, oil storage tank, cement storage bin, granary and so on sets the technology of prestress steel tendon, uses and utilizes this prestress steel tendon to bear deadweight and other loading of prestressed reinforced concrete construction thing when work progress.And after this prestressed reinforced concrete construction thing was finished, it added active forces such as load-carrying, live load and variations in temperature, and also major part is born by these prestress steel tendons.
Generally speaking, when setting the prestress steel tendon, the force side anchoring part of this prestressing force steel key is mounted in the both ends of works, yet under many special statuss, the force side anchoring part must be installed on the sidewall paneling (web) or base plate of works, just must on the sidewall paneling of works or base plate, construct again in addition this moment several from the outstanding concrete anchor ingot bar of sidewall paneling face or base plate face for installation force side anchoring part, for example: oil storage tank, the cement storage bin, the works of the drum of granary and so on needs annular prestressed and when desiring to set the prestress steel tendon in sidewall paneling inside, the concrete anchorage piece that must construct several concrete anchor ingot bars that are the pyrometric cone shape or cuboid shape on its sidewall paneling face comes for the force side anchoring part is installed.In addition, shown in the 1st figure, on the bridge that utilizes cantilevered frock method to construct, be to set various prestress steel tendons at position up and down to bear various mechanical loads, for example: the steel tendon that is disposed in box beam (Cell) top board is called top board steel tendon H (or claiming main steel tendon), when construction operation in bridge pier or the abutment Shi Zhushi that stretches out, promptly rely on this top board steel tendon burden cantilever position down the deadweight of beam body and construct in other loadings.In addition, be disposed at the end span outside and in the sidewall paneling (web) of span beam center bottom or acting as when be continuous state after the bridge closure of the base plate steel tendon L on the base plate (or claiming additional steel tendon), in order to the deadweight of beam body, loading, the variations in temperature alive of bearing part and add load-carrying etc.At this moment, the force side anchoring part of top board steel tendon H is mounted on the outside end face of box beam (Cell), and is therefore fairly simple in the construction that the force side anchoring part is installed, and do not constitute problem.But the force side anchoring part of base plate steel tendon L then is mounted on the sidewall paneling face of box beam, therefore must construct several concrete anchor ingot bars that are the pyrometric cone shape and come for the force side anchoring part is installed on this sidewall paneling face.
Construct in the engineering of bridge in the annular prestressed engineering of cylinder type thing and with cantilevered worker method, the force side anchoring part is installed on the sidewall paneling face is to take a lot of work very much and time-consuming job.Supply to install the force side anchoring part because must on the sidewall paneling face, construct the concrete anchor ingot bar that is the pyrometric cone shape in addition.Be commonly used to construct out the method for the concrete anchor ingot bar that is the pyrometric cone shape, be as shown in Figure 2, on the plate face of sidewall paneling W, the upright triangle taper reinforcing cage T who gives prominence to gradually towards the plate face outside along the long axis direction of this sidewall paneling W of elder generation's colligation group, inside in this triangle taper reinforcing cage T is embedded into: steel tendon sleeve pipe P, and be connected in this steel tendon anchoring part EA with the tail end of sleeve pipe P, and the coiled type spring EP (for the usefulness that relaxes tensile stress) that is sleeved on the outside of this anchoring part EA afterwards, again in the upright pyramidal template of triangle (not shown) that forms of this triangle taper reinforcing cage T outside group, then, carry out concrete perfusion and arrive template inside to form the concrete anchor ingot bar B of pyrometric cone shape.By the time after the concrete anchor ingot bar B of this pyrometric cone shape hardens fully, be fixed on the anchoring part EA just at the steel tendon inner dragline prestress steel tendon (not shown) of sleeve pipe P, and with the end of prestress steel tendon.
According in the past experience as can be known, when constructing bridge engineering with cantilevered worker method, need form box beam (Cell) the joint piece of the concrete anchor ingot bar B of pyrometric cone shape at sidewall paneling, need increase 1-2 working day in the engineering time aspect,, need form through the colligation groups are upright during outstanding gradually triangle taper reinforcing cage T towards the plate face outside along upright one of the long axis direction colligation group of the sidewall paneling W of this box beam (Cell) joint piece because desire by many reinforcing bar Tt and several not isometric vertical bar shape reinforcing bar Tx that are bent into the  font.Yet, each is bent into the reinforcing bar Tt of  font and the vertical bar shape reinforcing bar Tx difference because of the position that it disposed, the position of its length and bending is also inequality, so when tailoring these reinforcing bar materials, can't make in large quantities with same specification, to carry out all will tailoring reinforcing bar again and bending operation when the colligation group is found reinforcing cage, in the extreme trouble at every turn.Yet, the suitable masterful technique of need of work of the reinforcing cage of the upright pyrometric cone shape of colligation group on sidewall paneling not only, consuming time especially the taking a lot of work of work of founding out the pyramidal template of triangle organized in the reinforcing cage outside at the pyrometric cone shape again, and the cutting losing quantity of template is also big simultaneously.In addition, in order to form the concrete anchor ingot bar B of pyrometric cone shape, expend the concrete material of 1-2 stere again extraly, each side such as very uneconomical is all the problem that traditional technology is deposited.
Because the problem that the aforementioned conventional technology is deposited, purpose of the present invention is to be to solve aforesaid problem, and provide a kind of colligation group at the scene to found reinforcing cage, can be in advance prior to the sidewall paneling (web) that directly is installed to the prestressed concrete structure after completing in the workshop or side wall anchored bearing and the mounting method thereof on the base plate.
For reaching aforesaid purpose, side wall anchored bearing of the present invention be by:
An one bearing structure body and an anchor head fixing body make up and constitute, wherein:
The main body of this bearing structure body is a rectangular metal plate, form twice in this forward distolateral side of the exposed face of this metal plate and roughly be parallel first fastener and second fastener along the long axis direction of this metal plate, part between this first fastener and this second fastener forms cavity, and the hollow pointed cone cylinder of cutting sth. askew in conjunction with a process integratedly at the back side of this metal plate is to constitute the bottom of the cavity between this first fastener and this second fastener, and slightly be first floor of oblique integratedly in conjunction with a back side along the back side of the front-end edge of this metal plate with this metal plate, the roughly centre position at the back side of the bottom that the hollow pointed cone cylinder after this process is cut sth. askew is constituted slightly is second floor of oblique integratedly in conjunction with the back side with this bottom, and at this place, bottom inside end, slightly be the trislab of oblique to constitute the base plate of this bottom in conjunction with a back side integratedly with this metal plate, and be equipped with first peristome that passes through for the prestress steel tendon in the centre of trislab, insert sleeve part in conjunction with a sleeve that is the hollow cylinder shape integratedly in the foreign side of first peristome of this side of the rear end side of the close metal plate of trislab in conjunction with usefulness for the prestress steel tendon, and on the two sides of the long axis direction of this metal plate is first reinforcing bar that is combined with a plurality of U fonts, these first reinforcing bars are to be configured to extend out obliquely towards this outside, metal plate back side with the state that constitutes the oblique predetermined angular with the exposed face of this metal plate, in addition, in the presumptive area at the back side of the rear end side of this metal plate is second reinforcing bar that is combined with a plurality of U fonts with this metal plate integratedly, and these second reinforcing bars are that the state that is configured to roughly to be with the back side with this metal plate orthogonal extends out towards this outside, metal plate back side;
This anchor head fixing body is by the top panel of two first and second side plates roughly triangular in shape and a rectangle, and triangle lid shape that roughly is foursquare front panel through the hollow of combination formation integratedly, the lower edge of this first and second side plate forms the 3rd and the 4th fastener that can engage mutually with the 1st and second fastener of aforesaid bearing structure body respectively, the lower edge of this front panel is then extended the front-end edge that can prop up aforesaid bearing structure body than the more past below of the 3rd and the 4th fastener of the lower edge of this first and second side plate, and is equipped with second peristome that is provided with installing anchor head in the centre of this front panel.
Purpose of the present invention can also following mode reach: described side wall anchored bearing is characterized in that: first, second, third, fourth aforesaid fastener forms step shape or zigzag fashion.
Described side wall anchored bearing is characterized in that: the metal plate of aforementioned bearing structure body; And aforesaid first, second, third floor; Reaching aforesaid bottom and aforesaid sleeve part is to form in the metal casting mode, and aforesaid first reinforcing bar and second reinforcing bar are the metal plates that is incorporated into this bearing structure body with welding manner.
Described side wall anchored bearing is characterized in that: aforesaid anchor head fixing body is to form in the metal casting mode.
Described side wall anchored bearing is characterized in that: the predetermined angular that the exposed face of aforesaid first reinforcing bar and aforesaid metal plate constitutes oblique is the 40-50 degree.
In addition, the mounting method of side wall anchored bearing of the present invention, be for:
The reinforcing bar group of the sidewall paneling of prestressed concrete structure or base plate is upright finish after, the part reinforcing bar at place of will conflicting with the position that the bearing structure body is installed is earlier removed to vacate suitable space, again the bearing structure body is utilized the mode of iron wire colligation or welding to be fixed on the reinforcing bar of sidewall paneling or base plate, and then installation reinforcement reinforcing bar, secondly, behind sealing transverse slat on the reinforcing bar of sidewall paneling or base plate, placing of concrete, after the template of removing sidewall paneling or base plate, with the prestress steel tendon from the bearing structure body pass first peristome and sleeve part and insert be embedded in sidewall paneling or base plate interior in advance the steel tendon with in the sleeve, and then with the anchor head fixing body of triangle lid shape be placed in the bearing structure body above, make the 3rd and the 4th fastener of anchor head fixing body engage mutually with first and second fastener of bearing structure body, the lower edge of the front panel of anchor head fixing body props up the leading edge of bearing structure body simultaneously, last second peristome that again anchor head is installed in the front panel of anchor head fixing body can apply prestressed operation.
Effect of the present invention is:
Anchoring part of the present invention is by a bearing structure body, and one the anchor head fixing body combine, this bearing structure body not only can promptly be installed to the interior one that forms of reinforcing cage of the sidewall paneling (or base plate) of prestressed concrete structure, and be provided with a plurality of floors and a plurality of the 1st reinforcing bar and second reinforcing bar below this bearing structure, behind placing of concrete, these a plurality of floors and a plurality of first reinforcing bar and second reinforcing bar can be brought into play outside the effect of anti-skidding stop, a plurality of first reinforcing bars and second reinforcing bar have the effect of the reinforcing cage of the sidewall paneling (or base plate) as concrete construction again, reinforcement can be provided and prevent that concrete construction from producing the action effect in crack.Again, the anchor head fixing body is can utilize first and second fastener on its 3rd and the 4th fastener and the bearing structure body to engage mutually and can be easy to and promptly be installed to and be combined into a complete anchoring part above the bearing structure body.
Again, after all can be in the workshop a large amount of making of the bearing structure body of anchoring part of the present invention and anchor head fixing body, directly install and use at the scene of taking, needn't found out the pyramidal template of triangle as the reinforcing cage and the group of the upright pyrometric cone shape body of traditional approach colligation group, therefore need not just can significantly improve the operating efficiency that goes up the installation anchoring part at the sidewall paneling (or base plate) of prestressed concrete structure by masterful technique, shorten man-hours requirement.And because the tensile strength and the incompressible intensity of iron and steel all is much better than concrete, so of the present invention with metal material for example: iron and steel material quality waits the intensity of the anchoring part of making also to be much better than the intensity of the anchor ingot bar that forms with concrete spouting.
The simple declaration of drawing:
Fig. 1 is the allocation plan that shows the prestress steel tendon when utilizing cantilevered worker method structure bridge.
Fig. 2 is the skiagraph that shows in the past at the concrete anchor ingot bar of the constructed pyrometric cone shape of sidewall paneling.
Fig. 3 is the three-dimensional exploded view that shows anchoring part of the present invention.
Fig. 4 is the stereogram that shows after anchoring part of the present invention is assembled.
Fig. 5 is the skiagraph that shows after anchoring part of the present invention is assembled.
Fig. 6 is the profile that shows along the VI-VI section line of Fig. 5.
Fig. 7 is the profile that shows along the VII-VII section line of Fig. 5.
Fig. 8 is the profile that shows along the VIII-VIII section line of Fig. 5.
Fig. 9 is the profile that shows along the IX-IX section line of Fig. 5.
Zi Zuo is as follows with a kind of embodiment that drawing describes anchoring part of the present invention in detail.
As shown in Figure 3 and Figure 4, side wall anchored bearing 1 of the present invention is to be made of two main members: promptly in order to the bearing structure body 10 in the reinforcing cage of the sidewall paneling (or base plate) that is installed in the prestressed concrete structure and be used for being covered in these anchor head fixing bodies 30 above bearing structure body 10 and combined.Fig. 3 shows two main composition member bearing structure bodies 10 and anchor head fixing body 30 separated position before the combination as yet, and Fig. 4 shows both integralities after making up.
The main body of bearing structure body 10 by metal material for example is: the metal plate 11 that is long rectangle of iron and steel material quality made forms step-like first fastener 13 and second fastener 14 of twice along the long axis direction almost parallel of this metal plate 11 at the exposed face 12 of this metal plate 11 (being exposed at the face in the outside after the installation) near this side of front end (the F side among the figure).Part between this first fastener and this second fastener is cut the formation cavity, utilize at the back side of this metal plate 11 then welding manner in conjunction with a hollow pointed cone cylinder of cutting sth. askew equally (its shape just like pointed cone cylinder through the formed angle shape in back of cutting sth. askew) with the process of iron and steel material quality made to constitute the bottom 15 of the cavity between this first fastener 13 and this second fastener 14.This bottom 15 is as shown in Figure 5, from the front (right side Fig. 5) of this metal plate 11 toward rear end side (left side among Fig. 5) little by little toward the inboard hollow pointed cone cylindric recessed (please refer to Fig. 8) that forms.
In addition, the back side along the front (the F side among Fig. 3) of this metal plate 11 utilizes welding manner same with the first rectangular floor 16 of iron and steel material quality made in conjunction with one.As shown in Figure 5, this first floor 16 slightly is the oblique state with the back side of this metal plate 11.
Again, the roughly centre position at the back side of the bottom 15 that the hollow pointed cone cylinder after being cut sth. askew by this process is constituted utilizes welding manner in conjunction with same second floor 17 with the iron and steel material quality made.This second floor 17 slightly is the oblique state with the back side of this metal plate 11 also as shown in Figure 5.
Again, the medial end of the bottom 15 that the hollow pointed cone cylinder after being cut sth. askew by this process is constituted also is to utilize welding manner same with the rectangular trislab 18 of iron and steel material quality made in conjunction with one.This trislab 18 also constitutes the base plate of the medial end of this bottom 15 simultaneously.In addition, be equipped with first peristome 19 of a circle again in the centre position of trislab 18.First peristome 19 is the usefulness that supplies prestress steel tendon Y to pass through as shown in Figure 5.This trislab 18 also is slightly to be the oblique state with the back side of this metal plate 11.And first floor 16, second floor 17 and trislab 18 roughly constitute parastate.These slightly are first-Di trislab the 16,17, the 18th of parastate, can bring into play the effect that prevents that this bearing structure body 10 from sliding.
In addition, as shown in Figure 5, in this side of the rear end side (the R side among Fig. 3) of the close metal plate 11 of trislab 18, in the outside of first peristome 19 be utilize welding manner in conjunction with one equally with the sleeve part that is the hollow cylinder shape 21 of iron and steel material quality made.This sleeve part 21 be for the steel tendon in the sidewall paneling SW that is embedded in concrete construction in advance with the end insertion combination of sleeve pipe 22 with (please refer to Fig. 7).
Again, as shown in Figure 3-Figure 5, on the two sides of the long axis direction of this metal plate 11 is to utilize welding manner to be combined with a plurality of first reinforcing bars 23 that roughly are the U font, and these first reinforcing bars 23 are that the preceding extreme direction of state towards this outside, metal plate 11 back sides toward this metal plate 11 that is configured to constitute with the exposed face 12 with this metal plate 11 the oblique predetermined angulars extends out obliquely.And should predetermined angle of inclination be the thickness size that can cooperate the sidewall paneling SW of concrete construction, and be suitably to select in the scope of 40-50 degree.The effect of these first reinforcing bars 23 is to be installed in reinforcing cage in the sidewall paneling in order to reinforcement, and using provides reinforcement and prevent that sidewall paneling from producing the crack.Therefore, the configuration number of first reinforcing bar 23 and configuration space be cooperate concrete construction sidewall paneling SW the thickness size and suitably select.
In addition, presumptive area on the back side of the rear end side (left side among Fig. 5) of this metal plate 11, also promptly in the zone between rearward end to the trislab 18, also be to utilize welding manner to be combined with second reinforcing bar 24 of a plurality of U of being fonts, these second reinforcing bars 24 are that the state that is configured to roughly to be with the back side with this metal plate 11 orthogonal extends out towards these metal plate 11 back side rear sides.The effect of these second reinforcing bars 24 also is to be installed in reinforcing cage in the sidewall paneling in order to reinforcement, and using provides reinforcement and prevent that sidewall paneling from producing the crack.Therefore, the configuration number of second reinforcing bar 24 and configuration space also be cooperate concrete construction sidewall paneling SW the thickness size and suitably select.
As shown in Figure 3, anchor head fixing body 30 is by two first and second side plates 31,32 roughly triangular in shape of iron and steel material quality made; And the top panel 33 of a rectangle; And one roughly be foursquare front panel 34 and utilize welding manner in conjunction with the triangle lid shape that forms a hollow.The lower edge of first and second side plate 31,32 forms the 3rd and the 4th fastener 35,36 of the step shapes that can engage mutually with first and second fastener 13,14 of aforesaid bearing structure body 10 respectively.The lower edge 34a of this front panel 34 then extends than the 3rd and the 4th fastener 35, the 36 more past belows (left among Fig. 3) of the lower edge of this first and second side plate 31,32, can be as shown in Figure 5, and in order to prop up the front-end edge F of aforesaid bearing structure body 10.And the centre of plate 34 is equipped with second peristome 37 that is provided with installing anchor head 50 in front.
Again, though first, second fastener 13,14 of aforementioned bearing structure body 10 and the 3rd, the 4th fastener 35,36 of anchor head fixing body 30 are to form to distinguish the step shape of engaging mutually, but be not limited to this shape, for example: form the effect that other shape such as zigzag fashion also can reach mutual engaging.
Moreover, though metal plate 11, bottom 15, first floor 16, second floor 17, trislab 18 and the sleeve part 21 made with iron and steel material quality in the aforementioned bearing structure body 10 are to utilize welding manner to combine, but also can utilize casting method to make, if utilizing casting method makes, can be fit to a large amount of productions, and reduce cost.Similarly, aforesaid anchor head fixing body 30 also can utilize casting method to make.
Below assistant illustrates the mounting method of anchoring part 1 of the present invention with Fig. 5 to Fig. 9.Fig. 5 is the skiagraph that shows after anchoring part 1 of the present invention is assembled.Its mounting method is as follows:
After 40 groups of upright finishing of reinforcing cage of the sidewall paneling SW of prestressed concrete structure, the part reinforcing bar at place of will conflicting with the position that desire is installed bearing structure body 10 is earlier removed to vacate suitable space, again the bearing structure body 10 in the anchoring part 1 of the present invention is utilized the mode of iron wire colligation or welding to be fixed on the reinforcing cage 40 of sidewall paneling SW, and then in the sleeve part 21 of the rear side of bearing structure body 10, first floor 16, second floor 17, the reinforcement reinforcing bar 41 of vertical bar is installed on the next door of trislab 18, and extra on the reinforcing cage 40 of rear end side (left side among Fig. 5) foreign side of bearing structure body 10 the reinforcement reinforcing bars 42 that many groups are the U font is installed.Each group reinforcement reinforcing bar 42 is as shown in Figure 6, the shape that two reinforcement reinforcing bars 42 that are the U font up and down is nested together in its opening mode in opposite directions and is " square shape " utilizes the mode of iron wire colligation or welding to be fixed on the reinforcing cage 40 of sidewall paneling SW, is that the effect that has as spring can be in order to relax the tensile stress of sidewall paneling SW.Secondly, after the outside sealing template (not shown) of the reinforcing cage 40 of sidewall paneling SW, placing of concrete again, after the template of removing sidewall paneling SW, with prestressing force with steel tendon Y from bearing structure body 10 pass first peristome 19 and sleeve part 21 and insert be embedded in sidewall paneling SW inside in advance the steel tendon with in the sleeve pipe 22, and then with the anchor head fixing body 30 of triangle lid shape be placed in bearing structure body 10 above, make the 3rd and the 4th fastener 35 of anchor head fixing body 30,36 with first and second fastener 13 of bearing structure body 10,14 engagings mutually, the lower edge 34a of the front panel 34 of anchor head fixing body 30 props up the leading edge (please refer to Fig. 9) of bearing structure body 10 simultaneously, last second peristome 37 that again anchor head 50 is installed in the front panel 34 of a wrong fixing body 30 gets final product pull steel tendon Y to apply prestressed operation.

Claims (6)

1, a kind of side wall anchored bearing (1) be by: a bearing structure body (10) and an anchor head fixing body (30) are made up and are constituted, and it is characterized in that:
The main body of this bearing structure body (10) is a rectangular metal plate (11), the forward distolateral formation twice that are the exposed face (12) of this metal plate (11) are parallel first fastener (13) and second fastener (14) along the long axis direction of this metal plate (11), be positioned between this first fastener (13) and this second fastener (14) and form cavity, and the hollow pointed cone cylinder of cutting sth. askew in conjunction with a process integratedly at the back side of this metal plate (11) is to constitute the bottom (15) of the cavity between this first fastener (13) and this second fastener (14), and slightly be first floor (16) of oblique integratedly in conjunction with a back side along the back side of the front-end edge of this metal plate (11) with this metal plate (11), the centre position at the back side of the bottom (15) that the hollow pointed cone cylinder after this process is cut sth. askew is constituted is second floor (17) of oblique integratedly in conjunction with the back side with this bottom (15), and at the medial end place of this bottom (15), be the trislab (18) of oblique to constitute the base plate of this bottom (15) in conjunction with a back side integratedly with this metal plate (11), and be equipped with first peristome (19) that passes through for prestress steel tendon (Y) in the centre of trislab (18), insert sleeve part (21) in conjunction with a sleeve (22) that is the hollow cylinder shape at trislab (18) integratedly near the foreign side of first peristome (19) of the rear end side of metal plate (11) in conjunction with usefulness for prestress steel tendon (Y), and on the two sides of the long axis direction of this metal plate (11) is first reinforcing bar (23) that is combined with a plurality of U fonts, this first reinforcing bar (23) is to be configured to extend out obliquely towards this outside, metal plate (11) back side with the state that constitutes the oblique predetermined angular with the exposed face (12) of this metal plate (11), in addition, at the back side of the rear end side of this metal plate (11) and second reinforcing bar (24) that this metal plate (11) is combined with a plurality of U fonts integratedly, this second reinforcing bar (24) is to be configured to be the orthogonal state with the back side with this metal plate (24) extend out towards this outside, metal plate (11) back side;
This anchor head fixing body (30) comprises two first and second side plates (31 roughly triangular in shape, 32) and the top panel of a rectangle (33), and triangle lid shape that is foursquare front panel (34) through the hollow of combination formation integratedly, this first and second side plate (31,32) lower edge forms first and second fastener (13 with aforesaid bearing structure body (10) respectively, 14) the 3rd and the 4th fastener (35 that engages mutually, 36), the lower edge (34a) of this front panel (34) is then than this first and second side plate (31, the the 3rd and the 4th fastener (35 of lower edge 32), 36) front-end edge that props up aforesaid bearing structure body (10) is extended in more past below, and is equipped with second peristome (37) that is provided with installing anchor head (50) in the centre of this front panel (34).
2, side wall anchored bearing as claimed in claim 1 is characterized in that: first, second, third, fourth aforesaid fastener (13,14,35,36) forms step shape or zigzag fashion.
3, side wall anchored bearing as claimed in claim 1 or 2 is characterized in that: the metal plate (11) of aforementioned bearing structure body; And aforesaid first, second, third floor (16,17,18); Reaching aforesaid bottom (15) and aforesaid sleeve part (21) is to form in the metal casting mode, and aforesaid first reinforcing bar (23) and second reinforcing bar (24) are the metal plates (11) that is incorporated into this bearing structure body (10) with welding manner.
4, side wall anchored bearing as claimed in claim 1 or 2 is characterized in that: aforesaid anchor head fixing body 30 is to form in the metal casting mode.
5, side wall anchored bearing as claimed in claim 1 or 2 is characterized in that: aforesaid first reinforcing bar (23) is the 40-50 degree with the predetermined angular of exposed face (12) the formation oblique of aforesaid metal plate (11).
6, a kind of mounting method of side wall anchored bearing, it is characterized in that: after the reinforcing bar group of the sidewall paneling of prestressed concrete structure or base plate is stood and finished, the part reinforcing bar at place of will conflicting with the position that desire is installed the bearing structure body is earlier removed to vacate suitable space, to utilize the mode of iron wire colligation or welding to be fixed on the reinforcing bar of sidewall paneling or base plate as the bearing structure body among the described side wall anchored bearing of claim 1 to 5 again, and then installation reinforcement reinforcing bar, secondly, after the reinforcing bar outside sealing template of sidewall paneling or base plate, placing of concrete, after the template of removing sidewall paneling or base plate, with prestressing force with the steel tendon from the bearing structure body pass first peristome and sleeve part and insert be embedded in sidewall paneling or base plate interior in advance the steel tendon with in the sleeve pipe, and then with the anchor head fixing body of triangle lid shape be placed in the bearing structure body above, make the 3rd and the 4th fastener of anchor head fixing body engage mutually with first and second fastener of bearing structure body, the lower edge of the front panel of anchor head fixing body props up the leading edge of bearing structure body simultaneously, last second peristome that again anchor head is installed in the front panel of anchor head fixing body can apply prestressed operation.
CN 94115365 1994-09-23 1994-09-23 Side wall anchored bearing and its installation method Pending CN1183503A (en)

Priority Applications (4)

Application Number Priority Date Filing Date Title
CN 94115365 CN1183503A (en) 1994-09-23 1994-09-23 Side wall anchored bearing and its installation method
US08/498,567 US5535562A (en) 1994-09-23 1995-07-06 Saddle anchorage and mounting method thereof
FR9508269A FR2724960B1 (en) 1994-09-23 1995-07-07 SUPPORT SADDLE ANCHOR AND MOUNTING METHOD THEREOF.
DE19534945A DE19534945C1 (en) 1994-09-23 1995-09-20 Saddle anchorage and method of attaching the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 94115365 CN1183503A (en) 1994-09-23 1994-09-23 Side wall anchored bearing and its installation method

Publications (1)

Publication Number Publication Date
CN1183503A true CN1183503A (en) 1998-06-03

Family

ID=5037465

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 94115365 Pending CN1183503A (en) 1994-09-23 1994-09-23 Side wall anchored bearing and its installation method

Country Status (1)

Country Link
CN (1) CN1183503A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107268889A (en) * 2017-06-26 2017-10-20 北京交通大学 Prestressed aluminum mixes flitch-trussed beam and its construction method
CN112840082A (en) * 2018-10-09 2021-05-25 株式会社托太兹 Residual frame for forming concrete structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107268889A (en) * 2017-06-26 2017-10-20 北京交通大学 Prestressed aluminum mixes flitch-trussed beam and its construction method
CN112840082A (en) * 2018-10-09 2021-05-25 株式会社托太兹 Residual frame for forming concrete structure

Similar Documents

Publication Publication Date Title
KR100423757B1 (en) Prestressed composite truss girder and construction method of the same
AU749295B2 (en) Improved wedge-receiving cavity for an anchor body of a post-tension anchor system
US6017165A (en) Wedge-receiving cavity for an anchor body of a post-tension anchor system
US6006483A (en) Deck panel for reinforced concrete slabs
WO2007094809A2 (en) Unitized post tension block system for masonry structures
CA2023198C (en) Composite girder construction and method of making same
CN111139961A (en) Prefabricated composite floor part of assembled
CN100547169C (en) Bridge is with compound beam and the method for using this compound beam bridging
CN212295086U (en) Connecting structure behind precast concrete beam slab
CN1183503A (en) Side wall anchored bearing and its installation method
CN211572189U (en) Prefabricated composite floor part of assembled
CN1076776C (en) Structure cosisting of prefabricated components
CN1062933C (en) Construction of structure of prestressed combined beam
KR100634344B1 (en) Composite slab and the joint structure
KR100593664B1 (en) Construction Method for prestressed composite slab
JP2003138523A (en) Construction method for tension string girder bridge
CN213015377U (en) Pressure dismounting-free template for embedded part
US5535562A (en) Saddle anchorage and mounting method thereof
AU700414B1 (en) Deck panel for reinforced concrete slabs
JP3009582B2 (en) Construction method of continuous composite girder bridge between concrete slab and steel girder
KR100588350B1 (en) Bridge slab construction method for the median strip side end of the slab and upper part bracket applied therein
CN217150787U (en) External embedded frame of partition wall and novel assembled power consumption partition wall component
CN215252979U (en) Prefabricated reinforced concrete finished product forming die for basement ground beam
JPH0649676Y2 (en) Tunnel lining structure
KR100593663B1 (en) Connection method for composite slab

Legal Events

Date Code Title Description
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C06 Publication
PB01 Publication
C01 Deemed withdrawal of patent application (patent law 1993)
WD01 Invention patent application deemed withdrawn after publication