CN116733139A - Connection method of archaized clear water brick wall and modern structure - Google Patents

Connection method of archaized clear water brick wall and modern structure Download PDF

Info

Publication number
CN116733139A
CN116733139A CN202310723280.8A CN202310723280A CN116733139A CN 116733139 A CN116733139 A CN 116733139A CN 202310723280 A CN202310723280 A CN 202310723280A CN 116733139 A CN116733139 A CN 116733139A
Authority
CN
China
Prior art keywords
brick wall
archaized
layer
water brick
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310723280.8A
Other languages
Chinese (zh)
Inventor
朱晓璇
黄轶
谷志旺
王伟茂
孙沈鹏
刘晓
马燕
杨成斌
马思齐
何娇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 4 Group Co Ltd
Original Assignee
Shanghai Construction No 4 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 4 Group Co Ltd filed Critical Shanghai Construction No 4 Group Co Ltd
Priority to CN202310723280.8A priority Critical patent/CN116733139A/en
Publication of CN116733139A publication Critical patent/CN116733139A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/66Sealings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/74Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
    • E04B1/76Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/07Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
    • E04F13/08Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
    • E04F13/0801Separate fastening elements
    • E04F13/0803Separate fastening elements with load-supporting elongated furring elements between wall and covering elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/07Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
    • E04F13/08Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
    • E04F13/14Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements stone or stone-like materials, e.g. ceramics concrete; of glass or with an outer layer of stone or stone-like materials or glass
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/24Structural elements or technologies for improving thermal insulation
    • Y02A30/244Structural elements or technologies for improving thermal insulation using natural or recycled building materials, e.g. straw, wool, clay or used tires

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Acoustics & Sound (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Finishing Walls (AREA)

Abstract

The invention provides a connection method of an archaized water brick wall and a modern structure, which connects the water brick wall and a masonry wall into a whole through a drawknot device, reduces the height-width ratio of the water brick wall and improves the safety of the water brick wall; meanwhile, the connection structure of the archaized clear water brick wall and the modern structure can realize prefabrication of complex decoration of the outer facade of the archaized clear water brick wall, thereby improving construction efficiency while guaranteeing decoration effect.

Description

Connection method of archaized clear water brick wall and modern structure
Technical Field
The invention relates to a connection method of an archaized clear water brick wall and a modern structure.
Background
With the improvement of the traditional style protection consciousness of the historical block, the building shapes of modern buildings in the historical block need to be considered to be coordinated with the original style of the block, so that the outer facades of the buildings are mostly archaized. Wherein, the clear water brick wall is the main outer facade form of the historic block stone storehouse door building of Shanghai.
To make modern buildings have clear water brick wall facades, two main modes are currently adopted:
the method comprises the following steps: similar to the traditional building, the brick wall is used as the building enclosure structure, but the brick wall has poor waterproof and heat-insulating properties, and is difficult to meet the functional requirements of the modern building.
The second method is as follows: the construction method is characterized in that the brick wall is directly built outside the building outer wall, the brick wall is not connected with a modern building structure, the brick wall is only used as a layer of shell at the outer part of the building, the height-width ratio is overlarge, the overturning risk is caused, and the potential safety hazard is extremely high.
Meanwhile, when the two methods are adopted, the brick wall with clear water can only be realized in a construction site masonry mode at complicated facade modeling positions such as mountain flowers, door heads, arches and the like, the masonry quality is difficult to control, and a large amount of labor is consumed.
Disclosure of Invention
The invention aims to provide a connection method of an archaized clear water brick wall and a modern structure.
In order to solve the problems, the invention provides a connection method of an archaized clear water brick wall and a modern structure, which comprises the following steps: the tie bar is welded with the galvanized steel sheet to form a tie device of the brick wall and the masonry wall;
when the masonry wall is built, a tie device is arranged on the masonry wall according to a preset interval, tie bars of each tie device are arranged in mortar joints of the masonry wall, and galvanized steel plates are arranged on the inner wall surface of the masonry wall;
a ring beam is added in the masonry wall at the height position of the outer elevation mountain flower and the arch ticket between the drawknot devices, and a concrete lug is arranged outside the ring beam;
after the masonry wall is completely built, plastering a cement mortar leveling layer on the surface of the masonry wall, and then brushing waterproof paint on the surface of the cement mortar leveling layer;
after the waterproof coating is dried, arranging longitudinal and transverse light steel keels on the outer side of the waterproof coating, and filling an insulating layer between the longitudinal and transverse light steel keels;
fixing the waterproof and breathable film on the longitudinal and transverse light steel keels by using a shooting nail at the outer side of the rock wool heat preservation layer, and repairing the waterproof and breathable film by using a flexible butyl waterproof adhesive tape at the shooting nail position;
constructing a double-layer galvanized steel wire mesh cement mortar painting layer outside the waterproof breathable film;
an archaized water brick wall is built on one side of the double-layer galvanized steel wire mesh cement mortar painting layer, and the archaized water brick wall is connected with the masonry wall through tie bars to form a whole; when the clear water brick wall is built to the elevation decoration position of the flowers and the arches, the prefabricated flowers and the arches are connected to the concrete lugs through expansion bolts.
Further, in the above method, the tie device for welding the tie bar and the galvanized steel sheet to form the brick wall and the masonry wall comprises:
one end of the drawknot tendon is vertically connected with one side of the galvanized steel sheet.
Further, in the above method, the step of arranging the tie devices on the masonry wall at a predetermined interval includes:
according to the vertical spacing of 480mm and the horizontal spacing of 1800mm, a tie device which is tied with the archaized water brick wall is arranged on the masonry wall.
Further, in the method, in the process of brushing the waterproof paint on the surface of the leveling layer, the waterproof paint is JSA-101 waterproof paint.
Further, in the above method, the heat-insulating layer is a rock wool heat-insulating layer.
Further, in the method, the longitudinal and transverse light steel keels are C50 light steel keels.
Further, in the method, the specification of the steel wire mesh sheet of the double-layer galvanized steel wire mesh cement mortar powder coating layer is 6 mm in diameter and 200 mm in interval.
Further, in the above method, a double-layer galvanized steel wire mesh cement mortar painting layer is constructed outside the waterproof breathable film, comprising:
and fixing the steel wire mesh on the longitudinal and transverse light steel keels through shooting nails.
Further, in the above method, the step of building the archaized water brick wall on one side of the double-layer galvanized steel wire mesh cement mortar painting layer comprises the following steps:
the archaize clear water brick wall is pasted with the cement mortar painting layer of the double-layer galvanized steel wire gauze through the cement mortar bonding layer.
Further, in the above method, after the prefabricated flowers and the coupons are connected to the concrete lugs by the expansion bolts, the method further comprises:
the rest positions outside the double-layer galvanized steel wire mesh cement mortar painting layer with the same height as the mountain flowers and the arches are built by adopting ridge bricks with preset sizes
Compared with the prior art, the connection structure of the archaized clear water brick wall and the modern structure connects the clear water brick wall and the masonry wall into a whole through the drawknot device, so that the aspect ratio of the clear water brick wall is reduced, and the safety of the clear water brick wall is improved; meanwhile, the connection structure of the archaized clear water brick wall and the modern structure can realize prefabrication of complex decoration of the outer facade of the archaized clear water brick wall, the construction efficiency is improved while the decoration effect is ensured, and the invention realizes the following innovation:
1) The connection structure of the archaized water brick wall and the modern structure connects the archaized water brick wall and the modern structure into a whole through the drawknot device.
2) The drawknot device is formed by welding the galvanized steel plate and the drawknot ribs, the galvanized steel plate is placed on the inner side of the masonry wall, the drawknot ribs are placed in mortar joints of the masonry wall, and compared with the drawknot ribs which are generally only adopted and are anchored by mortar joints and drawknot ribs, the drawknot device adopting the mode has a more stable drawknot effect, and the situation that the brick wall is unstable due to the fact that the anchoring force of the steel bars in the mortar joints is smaller and the steel bars fall off is avoided.
3) The connection structure of the archaized clear water brick wall and the modern structure supports the adoption of prefabricated components for complex decorations such as flowers, arches and the like on the outer facade of the clear water brick wall, and the connection structure is reliably connected with the inner modern structure through the concrete lug.
4) According to the connection structure of the archaized clear water brick wall and the modern structure, the waterproof performance of the node is improved by arranging the two waterproof layers on the outer side of the masonry wall and the outer side of the rock face respectively.
The connection structure of the archaized clear water brick wall and the modern structure can enable the modern structure to have the outer elevation shape of the archaized clear water brick, simultaneously has good heat preservation and waterproof functions of the modern building enclosure structure, and can adopt a prefabricated mode aiming at clear water brick wall outer elevation floriation such as complicated mountain flowers, arch coupons and the like, thereby avoiding the problems that the construction site masonry quality of the clear water brick wall is difficult to control and the labor consumption is large, and further achieving the archaized effect of the outer elevation of the modern building in a high-efficiency and high-quality manner.
Drawings
FIG. 1 is a block diagram of a first step of construction of an embodiment of the present invention;
FIG. 2 is a block diagram of a second construction step of an embodiment of the present invention;
FIG. 3 is a block diagram of a third construction step of an embodiment of the present invention;
FIG. 4 is a block diagram of a fourth step of the construction of an embodiment of the present invention;
FIG. 5 is a block diagram of a fifth step of the construction of an embodiment of the present invention;
FIG. 6 is a block diagram of a sixth construction step according to an embodiment of the present invention;
FIG. 7 is a block diagram of a seventh construction step according to an embodiment of the present invention;
fig. 8 is a block diagram of an eighth construction step according to an embodiment of the present invention.
Detailed Description
In order that the above-recited objects, features and advantages of the present invention will become more readily apparent, a more particular description of the invention will be rendered by reference to the appended drawings and appended detailed description.
Aiming at the problems of the existing methods for adopting the outer vertical surfaces of the archaized clear water brick walls for two modern buildings, the invention provides a connection structure of the archaized clear water brick walls and a modern structure and a construction method thereof, which can connect the clear water brick walls with the structural system of the modern buildings, increase the integrity of the clear water brick walls and realize the prefabrication of complex flowers and arches. The invention can realize the connection of the archaized clear water brick wall and the modern structure, increase the integrity, reduce the height-width ratio of the clear water brick wall and improve the safety performance, and simultaneously can improve the work efficiency of the construction site at the complicated position of the facade modeling such as the mountain flower, the arch coupon and the like compared with the prefabricated mountain flower and arch coupon components, thereby ensuring the decoration effect.
The connection node structure of the archaized clear water brick wall and the modern structure is shown in fig. 8:
wherein, 1 is a 50 multiplied by 5 galvanized steel sheet, 2 is phi 6 tie bars, and 2 and 1 are welded and connected to form a tie device 21; the concrete is characterized in that the concrete is composed of a structural lug, a customized ridge brick or prefabricated mountain flower and arch coupon member, a 20mm cement mortar leveling layer, a JSA-101 waterproof coating, a light steel keel, a rock wool heat insulation layer filled between the longitudinal and transverse keels, a waterproof breathable film, a double-layer galvanized steel wire mesh cement mortar painting layer, a cement mortar bonding layer, a clear water brick wall, a masonry wall and a ring beam, wherein the cement mortar bonding layer is arranged at the bottom of the concrete, the cement mortar leveling layer is arranged at the bottom of the concrete, the concrete is arranged at the bottom of the concrete, and the concrete is composed of the concrete.
The connection structure of the archaized water brick wall and the modern structure can realize the effective connection of the water brick wall and the modern structure, improve the integrity of the water brick wall, reduce the height-width ratio of the water brick wall and improve the safety performance of the water brick wall; meanwhile, in the complicated position of facade modeling such as flowers, coupon, etc., prefabricated flowers, coupon members can be adopted to be connected with the concrete lug, so that the veneer effect is ensured and the site construction efficiency is improved.
As shown in fig. 1 to 8, the present invention provides a method for connecting an archaized clear water brick wall with a modern structure, comprising:
as shown in fig. 1, the first step is: the tie bar 2 is welded with the galvanized steel sheet 1 to form a tie device 21 of the brick wall and the masonry wall;
preferably, one end of the tie bar 2 is vertically connected to one side of the galvanized steel sheet 1;
as shown in fig. 2, the second step: when the masonry wall 13 is built, the tie devices 21 are arranged on the masonry wall 13 according to preset intervals, wherein tie bars 2 of each tie device 21 are arranged in mortar joints of the masonry wall, and galvanized steel plates 1 are arranged on the inner wall surface of the masonry wall;
preferably, the masonry wall 13 is provided with a drawknot device 21 which is drawknot with the archaized water brick wall according to the vertical interval of 480mm and the horizontal interval of 1800 mm;
as shown in fig. 3, the third step: a ring beam 14 is added in the masonry wall 13 at the height position of the outer elevation mountain flower and the arch ticket 5 between the drawknot devices 21, and a concrete lug 4 is arranged outside the ring beam 14;
as shown in fig. 4, the fourth step: after the masonry wall 13 is completely built, painting a 20mm cement mortar leveling layer 6 on the surface of the masonry wall 13, and then painting a waterproof paint 7 on the surface of the leveling layer 6;
preferably, the waterproof paint 7 is a JSA-101 waterproof paint;
as shown in fig. 5, the fifth step: after the waterproof coating 7 is dried, arranging longitudinal and transverse light steel keels 8 on the outer side of the waterproof coating 7, and filling a rock wool heat insulation layer 9 between the longitudinal and transverse light steel keels 8;
preferably, the longitudinal and transverse light steel keels 8 are C50 light steel keels;
as shown in fig. 6, the sixth step: fixing a waterproof and breathable film 10 on a longitudinal and transverse light steel keel 8 by using a shooting nail at the outer side of a rock wool heat preservation layer 9, and repairing the waterproof and breathable film by using a flexible butyl waterproof adhesive tape at the shooting nail position;
as shown in fig. 7, seventh step: a double-layer galvanized steel wire mesh cement mortar painting layer 11 is constructed outside the waterproof breathable film 10;
preferably, the specification of the steel wire meshes of the double-layer galvanized steel wire mesh cement mortar painting layer 11 is 6 mm in diameter and 200 mm in interval, and the steel wire meshes are fixed on the longitudinal and transverse light steel keels 8 through shooting nails;
as shown in fig. 8, eighth step: an archaized fresh water brick wall 15 is built on one side of a double-layer galvanized steel wire mesh cement mortar painting layer 11, the archaized fresh water brick wall 15 is connected with a masonry wall 13 through tie bars 2 into a whole,
preferably, the archaized water brick wall 15 is adhered to the double-layer galvanized steel wire mesh cement mortar plastering layer 11 through the cement mortar bonding layer 12;
when the clear water brick wall is built to the elevation decoration position of the flowers and the arches, the prefabricated flowers and the arches 5 are connected to the concrete lugs 4 through expansion bolts, and the rest positions outside the double-layer galvanized steel wire mesh cement mortar painting layer 11 with the same height as the flowers and the arches 5 are built by adopting the ridge bricks with preset sizes.
According to the connection structure of the archaized water brick wall and the modern structure, the water brick wall and the masonry wall are connected into a whole through the drawknot device, so that the height-width ratio of the water brick wall is reduced, and the safety of the water brick wall is improved; meanwhile, the connection structure of the archaized clear water brick wall and the modern structure can realize prefabrication of complex decoration of the outer facade of the archaized clear water brick wall, the construction efficiency is improved while the decoration effect is ensured, and the invention realizes the following innovation:
1) The connection structure of the archaized water brick wall and the modern structure connects the archaized water brick wall and the modern structure into a whole through the drawknot device.
2) The drawknot device is formed by welding the galvanized steel plate and the drawknot ribs, the galvanized steel plate is placed on the inner side of the masonry wall, the drawknot ribs are placed in mortar joints of the masonry wall, and compared with the drawknot ribs which are generally only adopted and are anchored by mortar joints and drawknot ribs, the drawknot device adopting the mode has a more stable drawknot effect, and the situation that the brick wall is unstable due to the fact that the anchoring force of the steel bars in the mortar joints is smaller and the steel bars fall off is avoided.
3) The connection structure of the archaized clear water brick wall and the modern structure supports the adoption of prefabricated components for complex decorations such as flowers, arches and the like on the outer facade of the clear water brick wall, and the connection structure is reliably connected with the inner modern structure through the concrete lug.
4) According to the connection structure of the archaized clear water brick wall and the modern structure, the waterproof performance of the node is improved by arranging the two waterproof layers on the outer side of the masonry wall and the outer side of the rock face respectively.
The connection structure of the archaized clear water brick wall and the modern structure can enable the modern structure to have the outer elevation shape of the archaized clear water brick, simultaneously has good heat preservation and waterproof functions of the modern building enclosure structure, and can adopt a prefabricated mode aiming at clear water brick wall outer elevation floriation such as complicated mountain flowers, arch coupons and the like, thereby avoiding the problems that the construction site masonry quality of the clear water brick wall is difficult to control and the labor consumption is large, and further achieving the archaized effect of the outer elevation of the modern building in a high-efficiency and high-quality manner.
In the present specification, each embodiment is described in a progressive manner, and each embodiment is mainly described in a different point from other embodiments, and identical and similar parts between the embodiments are all enough to refer to each other.
It will be apparent to those skilled in the art that various modifications and variations can be made to the present invention without departing from the spirit or scope of the invention. Thus, it is intended that the present invention also include such modifications and alterations insofar as they come within the scope of the appended claims or the equivalents thereof.

Claims (10)

1. The connection method of the archaized clear water brick wall and the modern structure is characterized by comprising the following steps:
the tie bar is welded with the galvanized steel sheet to form a tie device of the brick wall and the masonry wall;
when the masonry wall is built, a tie device is arranged on the masonry wall according to a preset interval, tie bars of each tie device are arranged in mortar joints of the masonry wall, and galvanized steel plates are arranged on the inner wall surface of the masonry wall;
a ring beam is added in the masonry wall at the height position of the outer elevation mountain flower and the arch ticket between the drawknot devices, and a concrete lug is arranged outside the ring beam;
after the masonry wall is completely built, plastering a cement mortar leveling layer on the surface of the masonry wall, and then brushing waterproof paint on the surface of the cement mortar leveling layer;
after the waterproof coating is dried, arranging longitudinal and transverse light steel keels on the outer side of the waterproof coating, and filling an insulating layer between the longitudinal and transverse light steel keels;
fixing the waterproof and breathable film on the longitudinal and transverse light steel keels by using a shooting nail at the outer side of the rock wool heat preservation layer, and repairing the waterproof and breathable film by using a flexible butyl waterproof adhesive tape at the shooting nail position;
constructing a double-layer galvanized steel wire mesh cement mortar painting layer outside the waterproof breathable film;
an archaized water brick wall is built on one side of the double-layer galvanized steel wire mesh cement mortar painting layer, and the archaized water brick wall is connected with the masonry wall through tie bars to form a whole; when the clear water brick wall is built to the elevation decoration position of the flowers and the arches, the prefabricated flowers and the arches are connected to the concrete lugs through expansion bolts.
2. The method of connecting an archaized water brick wall with a modern structure of claim 1, wherein the tie device for welding tie bars with galvanized steel sheets to form a water brick wall and a masonry wall comprises:
one end of the drawknot tendon is vertically connected with one side of the galvanized steel sheet.
3. The method for connecting an archaized clear water brick wall with a modern structure according to claim 1, wherein the step of arranging tie devices on the masonry wall at a preset interval comprises the steps of:
according to the vertical spacing of 480mm and the horizontal spacing of 1800mm, a tie device which is tied with the archaized water brick wall is arranged on the masonry wall.
4. The method for connecting an archaized clear water brick wall with a modern structure according to claim 1, wherein in the leveling layer surface brushing waterproof paint, the waterproof paint is JSA-101 waterproof paint.
5. The method of connecting an archaized clear water brick wall with a modern structure of claim 1, wherein the insulation layer is a rock wool insulation layer.
6. The method of connecting an archaized clear water brick wall with a modern structure of claim 1 wherein the longitudinal and transverse light steel keels are C50 light steel keels.
7. The method for connecting an archaized clear water brick wall and a modern structure according to claim 1, wherein the steel wire mesh specification of the double-layer galvanized steel wire mesh cement mortar painting layer is 6 mm in steel wire diameter and 200 mm apart.
8. The method for connecting an archaized clear water brick wall with a modern structure according to claim 7, wherein the construction of a double-layer galvanized steel wire mesh cement mortar render layer outside the waterproof breathable film comprises:
and fixing the steel wire mesh on the longitudinal and transverse light steel keels through shooting nails.
9. The method of connecting an archaized dry brick wall to a modern structure of claim 1, wherein the step of constructing an archaized dry brick wall on one side of a double-layer galvanized steel wire mesh cement mortar render layer comprises:
the archaize clear water brick wall is pasted with the cement mortar painting layer of the double-layer galvanized steel wire gauze through the cement mortar bonding layer.
10. The method of joining an archaized, clear water brick wall to a modern structure of claim 1, wherein after joining the prefabricated flowers and coupons to the concrete lugs by expansion bolts, further comprising:
the rest positions outside the double-layer galvanized steel wire mesh cement mortar painting layer with the same height as the mountain flowers and the arches are built by adopting the ridge bricks with preset sizes.
CN202310723280.8A 2023-06-19 2023-06-19 Connection method of archaized clear water brick wall and modern structure Pending CN116733139A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310723280.8A CN116733139A (en) 2023-06-19 2023-06-19 Connection method of archaized clear water brick wall and modern structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310723280.8A CN116733139A (en) 2023-06-19 2023-06-19 Connection method of archaized clear water brick wall and modern structure

Publications (1)

Publication Number Publication Date
CN116733139A true CN116733139A (en) 2023-09-12

Family

ID=87916560

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310723280.8A Pending CN116733139A (en) 2023-06-19 2023-06-19 Connection method of archaized clear water brick wall and modern structure

Country Status (1)

Country Link
CN (1) CN116733139A (en)

Similar Documents

Publication Publication Date Title
WO2021253808A1 (en) Building technique for low-carbon society in high-technology era
CN101845857B (en) Metal mesh built-in insulating outer wall and construction method thereof
CN202611016U (en) Thermal insulating wall on concrete overhanging eaves board
CN103572866A (en) Assembly type wall
CN203174810U (en) Bearing-and-leaning type installed assembly wall body
CN107201791A (en) A kind of new assembling type steel structure external wall system
CN112031210A (en) Composite heat-insulation outer wall structure of hollow wall and preparation method
WO2009012660A1 (en) A composite wall with steel bar and/or metal wire mesh and mortar on internal and external sides thereof and bonding construction method therefor to resist cracking
CN209958534U (en) Low-energy-consumption energy-saving building system
CN215802445U (en) Outsourcing fire prevention structure suitable for steel sheet shear force wall
CN101089309A (en) Construction method of cast-in-place sompound wall
CN113802760A (en) Heat preservation is decorated and is maintained integration wallboard and wall structure
CN210767302U (en) Enhanced vertical-filament rock wool board external wall insulation system
CN101089307A (en) Cast-in-place light compound wall
CN209907676U (en) Hollow internal mold metal mesh cement self-heat-insulation internal and external partition wall
CN116733139A (en) Connection method of archaized clear water brick wall and modern structure
CN207130912U (en) A kind of new assembling type steel structure external wall system
CN215948495U (en) GSY outer wall board is high low to stride movement joint department connected node structure
CN115928909A (en) Short-limb shear wall assembled light steel combined truss bearing steel wire mesh frame mortar-perlite-polyphenyl composite enclosure wall and manufacturing method thereof
CN115977278A (en) Assembled light steel combined truss supported steel wire mesh frame mortar-perlite-polyphenyl composite shear wall and manufacturing method thereof
CN108412116A (en) Cast in place reinforced bar lightweight concrete retaining wall and preparation method thereof
CN210256666U (en) Non-dismantling template light assembled plate
CN2911049Y (en) In-situ light-weight composite wall
CN109779008B (en) Anti-seismic anti-cracking steel structure house and construction method thereof
CN114233015A (en) Method for connecting steel structure and masonry filler wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination