CN115478880B - Construction method for reducing rebound rate of sprayed concrete - Google Patents

Construction method for reducing rebound rate of sprayed concrete Download PDF

Info

Publication number
CN115478880B
CN115478880B CN202211294208.XA CN202211294208A CN115478880B CN 115478880 B CN115478880 B CN 115478880B CN 202211294208 A CN202211294208 A CN 202211294208A CN 115478880 B CN115478880 B CN 115478880B
Authority
CN
China
Prior art keywords
sprayed
concrete
water
sprayed concrete
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202211294208.XA
Other languages
Chinese (zh)
Other versions
CN115478880A (en
Inventor
张玉强
张亚军
陈凤熔
李智勇
刘争刚
王国强
李华伟
郑文龙
贺瑞
张宏
陈超
陈雨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Tunnel Group Co Ltd CRTG
CRTG Road and Bridge Engineering Co Ltd
Beijing China Railway Tunnel Construction Co Ltd
Original Assignee
China Railway Tunnel Group Co Ltd CRTG
CRTG Road and Bridge Engineering Co Ltd
Beijing China Railway Tunnel Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Tunnel Group Co Ltd CRTG, CRTG Road and Bridge Engineering Co Ltd, Beijing China Railway Tunnel Construction Co Ltd filed Critical China Railway Tunnel Group Co Ltd CRTG
Priority to CN202211294208.XA priority Critical patent/CN115478880B/en
Publication of CN115478880A publication Critical patent/CN115478880A/en
Application granted granted Critical
Publication of CN115478880B publication Critical patent/CN115478880B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

A construction method for reducing rebound rate of sprayed concrete relates to the technical field of sprayed concrete support in a subsurface tunnel, and specifically comprises the following steps: testing and detecting coarse aggregate, fine aggregate, cement, accelerator, water reducing agent and mixture fusion agent on a construction site, and ensuring that the performance of the cement, the accelerator, the water reducing agent and the mixture fusion agent is qualified; the water content of aggregate is actually measured on site, the construction proportion is adjusted according to actual conditions to meet design requirements, then the material is weighed and fed through an automatic electronic weighing system, and before the construction of sprayed concrete, the sprayed surface is treated, the construction of sprayed concrete is carried out, the sprayed surface is leveled, the back cavity and leakage grouting are carried out; according to the invention, the mixture fusion agent is added into the raw materials of the original sprayed concrete, so that the early strength and the spraying performance of the sprayed concrete are greatly improved, the use cost is reduced, the adhesion between layers and the spraying compactness are improved by adopting a layered spraying mode, and meanwhile, the surface of the square spade is repaired, and the surface flatness is improved.

Description

Construction method for reducing rebound rate of sprayed concrete
Technical Field
The invention relates to the technical field of shotcrete support in a subsurface tunnel, in particular to a construction method for reducing the rebound rate of shotcrete.
Background
It is known that an essential procedure in the construction process of a subsurface excavation project, namely an initial support, wherein the construction of shotcrete is an important procedure of the initial support; the ideal consumption coefficient of the sprayed concrete is 1.8-2.0 times of the net quantity of the designed linear meter, but in the implementation process, the actual consumption of the sprayed concrete can reach about 2.5 times of the net quantity of the designed linear meter due to the influence of factors such as poor geological conditions, hydrogeological conditions, ground stability, mechanical equipment, manual proficiency and the like, so that the project cost is extremely unfavorable to control, and a great amount of capital consumption is caused.
Disclosure of Invention
In order to overcome the defects in the background art, the invention discloses a construction method for reducing the rebound rate of sprayed concrete.
In order to achieve the aim of the invention, the invention adopts the following technical scheme:
The construction method for reducing the rebound rate of the sprayed concrete specifically comprises the following steps:
(1) Testing and detecting coarse aggregate, fine aggregate, cement, accelerator, water reducer and mixture fusion agent on a construction site, ensuring that the performance of the construction site is qualified, and configuring a mixing ratio meeting the design strength and injection process requirements;
(2) The water content of the aggregate is measured on site by adopting concentrated mixing before construction, the actual water content of the aggregate is measured by taking the water content in the designed mixing proportion as a standard, the weight of the water in the aggregate is calculated, and the weight of the water in the actual aggregate is subtracted from the weight of the water in the designed mixing proportion, namely the weight of the water in the actual aggregate is required to be added during the mixing period;
(3) After the water content is actually measured on site, the construction proportion is adjusted according to the actual situation to meet the design requirement, then the materials are weighed and fed through an automatic electronic weighing system, the mixing time of the mixture is not less than 120s, and the mixture is placed into a concrete transport vehicle after the mixing is finished; meanwhile, the slump of the concrete is measured by adopting a slump barrel at the position of the stirring station, the slump meets the slump of the designed mixing proportion, and the concrete can be transported after being stirred uniformly;
(4) Before the construction of sprayed concrete, the sprayed surface is treated, and the method specifically comprises the following steps:
a. Before the sprayed concrete is implemented, cleaning up pumice, rock scraps and sundries on the sprayed surface, ensuring the safety of the sprayed concrete construction process, preventing the sprayed concrete from falling off, and enabling the sprayed concrete to be well bonded with the rock surface;
b. Burying a thick pile in the sprayed surface;
c. water seepage treatment is carried out on the sprayed surface;
(5) And (3) spraying concrete for construction: the spraying process is carried out from bottom to top in a segmented, segmented and layered mode, the initial spraying thickness is controlled to be 20-50 mm, the local concave cavity of the sprayed surface is backfilled, the side wall position is controlled to be 50-150 mm each time when the spraying process is carried out, the arch part is controlled to be 50-100 mm, and the spraying process is carried out after the sprayed concrete of the previous layer is finally solidified; the injection pressure is controlled to be 0.2-0.7 Mpa, and is adjusted according to the on-site trial injection effect; the nozzle is perpendicular to the sprayed surface, and the distance from the sprayed surface is preferably 0.6-1.5 m;
(6) Leveling the spraying surface: when the sprayed concrete is constructed to the last layer, the concrete thickness control pile is paid attention to at any time, and a square spade is adopted to shoveling off the sprayed concrete at the redundant part, so that the surface of the final sprayed concrete is smooth and has no macroscopic unevenness;
(7) Back cavity and leakage grouting treatment: after the sprayed concrete reaches 10Mpa, grouting holes with the diameter of 42mm are drilled along the surface of the sprayed concrete, the circumferential X longitudinal distance of the grouting holes is 2m X2 m along the sprayed surface, when the sprayed surface is free of water, the grouting depth is 30-50 mm, when the sprayed surface is discharged with water, the grouting depth is 200-300 mm, meanwhile, grouting is encrypted within the range of 3m of a leakage part, and grouting treatment is carried out on the cavity and the leakage water behind the sprayed concrete.
According to the construction method for reducing the rebound rate of the sprayed concrete, water is not added to the concrete in the concrete truck in the conveying process, and a concrete tank of the concrete truck is in an operating state.
According to the construction method for reducing the rebound rate of the sprayed concrete, on-site mixing ratio tests are required to be carried out on sprayed concrete materials in different batches, and the following data are referred to in the primary test: glue set ratio: 1:3.5-5; aggregate sand content: 45% -60%; water-to-gel ratio: 0.4 to 0.5; and after the preparation is finished, the sprayed concrete test block is standard-cultured for 28 days, and a compressive strength test is carried out to meet the design strength.
According to the construction method for reducing the rebound rate of the sprayed concrete, the thick piles are made of short steel bars, system anchor rods or primary support section steel; when the short steel bars are adopted, the short steel bars are driven into a sprayed surface, the exposed length is the thickness of sprayed concrete, and the longitudinal and circumferential distances are arranged according to 1.5m multiplied by 1.5m so as to ensure that the designed thickness of the sprayed concrete is as standard; when the system anchor rod is adopted, a concrete thickness spraying surface is marked at the exposed part of the system anchor rod, and the sprayed concrete thickness is controlled within the allowable range of the designed thickness; when the primary support section steel is adopted, the inner side of the primary support section steel is used as a control surface, and the thickness of a section steel protective layer is ensured to be enough.
According to the construction method for reducing the rebound rate of sprayed concrete, when the sprayed surface is provided with dotted or small strand water, a plurality of permeable blind pipes are embedded in the sprayed surface and are clung to the wall surface, the permeable blind pipes are clamped on the sprayed surface in a V shape through short steel bars or fixing wires by adopting hoses with diameters of 60-100 mm, and the steel bars are welded on the outer side of the section steel;
When the sprayed surface has strand-shaped or rain-shaped water outlet, the water outlet part is treated by the steps of: 1. increasing the number of the reinforcing mesh sheets, and paving double-layer reinforcing meshes or multiple layers of reinforcing meshes at the position; 2. a plastic waterproof board is paved behind the section steel, drainage is carried out on the rainy or stranded water outlet part, so that the water outlet of the sprayed surface is collected along the plastic waterproof board, and after the concrete has supporting strength, the back cavity is treated in a later period; 3. and (3) drilling a probe hole with the aperture of 40-80 mm obliquely upwards at the rear part of the finished primary support section, and punching the probe hole into the rear position of the sprayed surface to guide and discharge water.
According to the construction method for reducing the rebound rate of sprayed concrete, after the sprayed surface is treated, the construction site is leveled, the wet spraying mechanical arm, the air pipe, the water pipe, the cable line and the like are checked, good performance is ensured, the wet spraying mechanical arm is connected for trial spraying, and the parking position of the wet spraying mechanical arm is ensured to ensure that the rotary spray head of the mechanical arm can realize omnibearing spraying.
The construction method for reducing the rebound rate of the sprayed concrete is characterized in that grouting slurry is cement slurry, superfine cement slurry or double-slurry.
Due to the adoption of the technical scheme, the invention has the following beneficial effects:
1. According to the construction method for reducing the rebound rate of the sprayed concrete, the mixture fusion agent is added into the raw materials of the original sprayed concrete, and after the mixture fusion agent liquid is added, a large amount of rod-shaped ettringite crystals are precipitated from the slurry within a few minutes, the rod-shaped ettringite crystals and cellulose in the rod-shaped ettringite crystals are mutually connected to form a micro-reinforcement network structure, and meanwhile, a large amount of water is consumed for forming the rod-shaped ettringite, the slurry thickens, and the slurry is quickly coagulated under the combined action of the rod-shaped ettringite crystals and the cellulose, so that the rebound of the concrete is effectively prevented. Mg (OH) 2 in the mixture fusion agent provides crystal nucleus for the formation of C-S-H gel, promotes the crystallization of C-S-H in a large quantity, improves the strength, improves the early strength of sprayed concrete by 2-3 MPa, reduces the cement doping amount, greatly improves the early strength and the spraying performance of the sprayed concrete, and reduces the use cost.
2. According to the construction method for reducing the rebound rate of the sprayed concrete, disclosed by the invention, the water discharged from the sprayed surface is conducted to be drained or separated in advance, and the sprayed concrete is orderly collected and guided, so that the sprayed concrete is prevented from directly contacting with the sprayed concrete in a large area, the cohesiveness of the sprayed concrete, the section steel and the sprayed surface is prevented from being influenced, and the collapse and the falling block of the sprayed concrete caused by water flow scouring or water flow pressure are reduced; by grouting the cavity behind the sprayed concrete, the construction quality of the sprayed concrete is effectively ensured, and the leakage water is treated, so that the defect of a finished product in the later period is prevented.
3. According to the construction method for reducing the rebound rate of the sprayed concrete, disclosed by the invention, a layered spraying mode is adopted, so that the cohesiveness and spraying compactness between layers are improved, and meanwhile, the square spade is trimmed, and the surface flatness is improved.
Drawings
FIG. 1 is a schematic view of the lateral structure of the shotcrete thickness control and drainage of the water outlet according to the present invention.
FIG. 2 is a schematic view of a water permeable blind tube installation in a lateral direction according to the present invention.
Fig. 3 is a longitudinal schematic view of the advanced drain hole of the present invention.
In the figure: 1. a system anchor rod; 2. section steel; 3. a sprayed surface; 4. a water outlet part; 5. leading the water draining hole; 6. spraying the concrete surface; 7. reinforcing steel bar meshes; 8. a drainage waterproof board; 9. short steel bars; 10. a permeable blind pipe; 11. a reinforcing steel bar fixing frame; 12. the paragraph has been supported.
Detailed Description
The invention will be explained in more detail by the following examples, the purpose of which is to protect all technical improvements within the scope of the invention.
The construction method for reducing the rebound rate of the sprayed concrete, which is described with reference to figures 1-3, specifically comprises the following steps:
(1) Testing and detecting coarse aggregate, fine aggregate, cement, accelerator, water reducer and mixture fusion agent on a construction site, ensuring that the performance of the construction site is qualified, and configuring a mixing ratio meeting the design strength and injection process requirements;
In which, the sprayed concrete materials of different batches are subjected to on-site mixing ratio tests, and the following data are referred to in the primary test: glue set ratio: 1:3.5-5; aggregate sand content: 45% -60%; water-to-gel ratio: 0.4 to 0.5; after the preparation is finished, the sprayed concrete test block is standard-cultured for 28 days, and a compressive strength test is carried out to meet the design strength; the mixture fusion agent is a tackifier produced by Yunnan Siback new material technology Co-efficient, and the main components of the mixture fusion agent are SiO 2、Ca(OH)2、CaO、Mg(OH)2, carbon nano tubes and cellulose;
(2) The water content of the aggregate is measured on site by adopting concentrated mixing before construction, the actual water content of the aggregate is measured by taking the water content in the designed mixing proportion as a standard, the weight of the water in the aggregate is calculated, and the weight of the water in the actual aggregate is subtracted from the weight of the water in the designed mixing proportion, namely the weight of the water in the actual aggregate is required to be added during the mixing period; the design of the mixing proportion is carried out in the dry state of the aggregate, and the aggregate is influenced by factors such as rain, snow and the like and is in a non-dry state during the actual construction, so that the water content of the aggregate is tested, and the aggregate comprises coarse aggregate and fine aggregate;
(3) After the water content is actually measured on site, the construction proportion is adjusted according to actual conditions to meet the design requirement, then the materials are weighed and fed through an automatic electronic weighing system, the mixing time of the mixture is not less than 120s, the mixture is placed into a concrete transport vehicle after the mixing is finished, water is not added in the conveying process, and a concrete tank of the concrete transport vehicle is in an operating state, so that good fluidity of the concrete is ensured; meanwhile, the slump of the concrete is measured by adopting a slump barrel at the position of the stirring station, the slump meets the slump of the designed mixing proportion, and the concrete can be transported after being stirred uniformly;
(4) Before the construction of sprayed concrete, the sprayed surface 3 is treated, and the method specifically comprises the following steps:
a. before the sprayed concrete is implemented, cleaning up pumice, rock scraps and sundries on the sprayed surface 3, ensuring the safety of the sprayed concrete construction process, preventing the blocks from falling off, and enabling the sprayed concrete to be well bonded with the rock surface;
b. Burying a thick pile in the sprayed surface 3; the thick pile adopts short steel bars 9, system anchor rods 1 or primary support section steel; when the short steel bars 9 are adopted, the short steel bars are driven into the sprayed surface 3, the exposed length is the thickness of sprayed concrete, and the longitudinal and circumferential spacing is arranged according to 1.5m multiplied by 1.5m so as to ensure that the designed thickness of the sprayed concrete is as standard; when the system anchor rod 1 is adopted, a concrete thickness spraying surface is marked at the exposed part of the system anchor rod 1, and the sprayed concrete thickness is controlled within the range of the designed thickness; when the primary support section steel 2 is adopted, the inner side of the primary support section steel 2 is taken as a control surface;
c. Water seepage treatment is carried out on the sprayed surface 3; when the sprayed surface 3 has dot-shaped or small strand-shaped water outlet, a plurality of permeable blind pipes 10 are embedded in the position of the sprayed surface 3 in a manner of clinging to the wall surface, the number of the permeable blind pipes 10 is laid in combination with the water outlet condition, the sprayed surface is clinged to the wall surface, water outlet drainage is conducted, local collapse and block dropping caused during construction of sprayed concrete are effectively avoided, the construction quality of the concrete is improved, the permeable blind pipes 10 are clamped on the sprayed surface in a V shape by adopting reinforcing steel bars with the diameter of 8mm, and the reinforcing steel bars are welded on the outer side of the profile steel 2;
When the sprayed surface 3 is in a strand shape or a rain shape and water is discharged, the sprayed concrete is hardly adhered to the sprayed surface under the influence of water flow impact or water pressure, and the water outlet part 4 is required to be treated at the moment, and the water outlet part 4 is treated by the following steps: 1. the number of the reinforcing mesh sheets 7 is increased, double-layer reinforcing meshes or multiple layers of reinforcing meshes are paved at the position, and the framework support in the sprayed concrete is improved; 2. a plastic drainage waterproof board 8 is paved behind the reinforcement fixing frame 11, drainage is conducted on the rainy or strand-shaped water outlet part, water outlet of the sprayed surface 3 is collected along the drainage waterproof board 8, direct contact between the water outlet and sprayed concrete is reduced, and after the concrete has supporting strength, back cavities are treated in a later period; 3. an advanced water discharge hole 5 is drilled obliquely above the rear of the supported section 12, the aperture is 40-80 mm, the advanced water discharge hole 5 is driven into the rear position of the sprayed surface 3, the water outlet condition is further detected through the exploratory hole, meanwhile, water outlet is intercepted behind the sprayed surface 3, and the water outlet of the sprayed surface 3 is reduced; after the sprayed surface 3 is treated, the construction site is parallel, and the wet spraying mechanical arm, the air pipe, the water pipe and the cable line are inspected, so that good performance is ensured, the wet spraying mechanical arm is connected for trial spraying, and the parking position of the wet spraying mechanical arm is required to ensure that the rotary spray head of the mechanical arm can realize omnibearing spraying;
(5) And (3) spraying concrete for construction: the method comprises the steps of sectioning, slicing and layering from bottom to top during spraying, controlling the initial spraying thickness to be 20-50 mm, backfilling local concave cavities of a sprayed surface 3, controlling the repeated spraying thickness of a side wall to be 50-150 mm each time during repeated spraying, controlling the repeated spraying thickness of an arch part to be 50-100 mm, and performing repeated spraying after the sprayed concrete of the previous layer is finally solidified, so that the sprayed concrete has enough strength and effective bonding among the sprayed concrete of each layer is ensured; the spraying pressure is 0.2-0.7 Mpa, the nozzle is perpendicular to the sprayed surface, and the distance from the sprayed surface is 0.6-1.5 m;
(6) Leveling the spraying surface: when the sprayed concrete is constructed to the last layer, the concrete thickness pile is noticed at any time, and a square spade is adopted to shoveling off the sprayed concrete at the redundant part, so that the surface 6 of the final sprayed concrete is smooth and has no macroscopic unevenness;
(7) Grouting treatment of the back cavity: after the sprayed concrete reaches 10Mpa, grouting holes with the diameter of phi 42mm are drilled along the sprayed concrete surface 6, the longitudinal spacing of the grouting holes is 2 x 2m along the circumferential direction of the sprayed surface, when the sprayed surface is free of water, the grouting depth is 30-50 mm, when the sprayed surface is water-out, the grouting depth is 200-300 mm, meanwhile, grouting is encrypted within the range of 3m of a leaking part, grouting treatment is carried out on the back cavity of the sprayed concrete and the leaking water, and grouting slurry is cement slurry, superfine cement slurry or double slurry which is used for guaranteeing the construction quality of the sprayed concrete and treating the leaking water, so that later-stage finished product defects are prevented.
The invention is not described in detail in the prior art.
The embodiments selected herein for the purposes of disclosing the invention are presently considered to be suitable, but it is to be understood that the invention is intended to include all such variations and modifications as fall within the spirit and scope of the invention.

Claims (5)

1. A construction method for reducing the rebound rate of sprayed concrete is characterized by comprising the following steps: the method specifically comprises the following steps:
(1) Testing and detecting coarse aggregate, fine aggregate, cement, accelerator, water reducer and mixture fusion agent on a construction site, ensuring that the performance of the construction site is qualified, and configuring a mixing ratio meeting the design strength and injection process requirements;
(2) The water content of the aggregate is measured on site by adopting concentrated mixing before construction, the actual water content of the aggregate is measured by taking the water content in the designed mixing proportion as a standard, the weight of the water in the aggregate is calculated, and the weight of the water in the actual aggregate is subtracted from the weight of the water in the designed mixing proportion, namely the weight of the water in the actual aggregate is required to be added during the mixing period;
(3) After the water content is actually measured on site, the construction proportion is adjusted according to the actual situation to meet the design requirement, then the materials are weighed and fed through an automatic electronic weighing system, the mixing time of the mixture is not less than 120s, and the mixture is placed into a concrete transport vehicle after the mixing is finished; meanwhile, the slump of the concrete is measured by adopting a slump barrel at the position of the stirring station, the slump meets the slump of the designed mixing proportion, and the concrete can be transported after being stirred uniformly;
(4) Before the construction of sprayed concrete, the sprayed surface is treated, and the method specifically comprises the following steps:
a. Before the sprayed concrete is implemented, cleaning up pumice, rock scraps and sundries on the sprayed surface, ensuring the safety of the sprayed concrete construction process, preventing the sprayed concrete from falling off, and enabling the sprayed concrete to be well bonded with the rock surface;
b. Burying a thick pile in the sprayed surface;
The thick pile adopts short steel bars, system anchor rods or primary support section steel; when the short steel bars are adopted, the short steel bars are driven into a sprayed surface, the exposed length is the thickness of sprayed concrete, and the longitudinal and circumferential distances are arranged according to 1.5m multiplied by 1.5m so as to ensure that the designed thickness of the sprayed concrete is as standard; when the system anchor rod is adopted, a concrete thickness spraying surface is marked at the exposed part of the system anchor rod, and the sprayed concrete thickness is controlled within the allowable range of the designed thickness; when the primary support section steel is adopted, the inner side of the primary support section steel is taken as a control surface, and the thickness of a section steel protective layer is ensured to be enough;
c. water seepage treatment is carried out on the sprayed surface;
When the sprayed surface is provided with dotted or small strand water, a plurality of permeable blind pipes are embedded in the sprayed surface and cling to the wall surface, the permeable blind pipes are clamped on the sprayed surface in a V shape through short steel bars or fixing wires by adopting hoses with diameters of 60-100 mm, and the steel bars are welded on the outer side of the section steel;
When the sprayed surface has strand-shaped or rain-shaped water outlet, the water outlet part is treated by the steps of: 1. increasing the number of the reinforcing mesh sheets, and paving double-layer reinforcing meshes or multiple layers of reinforcing meshes at the position; 2. a plastic waterproof board is paved behind the section steel, drainage is carried out on the rainy or stranded water outlet part, so that the water outlet of the sprayed surface is collected along the plastic waterproof board, and after the concrete has supporting strength, the back cavity is treated in a later period; 3. drilling a exploratory hole with the aperture of 40-80 mm at the rear inclined upper side of the finished primary support section, and punching the exploratory hole into the rear position of the sprayed surface to guide and discharge water;
(5) And (3) spraying concrete for construction: the spraying process is carried out from bottom to top in a segmented, segmented and layered mode, the initial spraying thickness is controlled to be 20-50 mm, the local concave cavity of the sprayed surface is backfilled, the side wall position is controlled to be 50-150 mm each time when the spraying process is carried out, the arch part is controlled to be 50-100 mm, and the spraying process is carried out after the sprayed concrete of the previous layer is finally solidified; the injection pressure is controlled to be 0.2-0.7 Mpa, and is adjusted according to the on-site trial injection effect; the nozzle is perpendicular to the sprayed surface, and the distance from the sprayed surface is preferably 0.6-1.5 m;
(6) Leveling the spraying surface: when the sprayed concrete is constructed to the last layer, the concrete thickness control pile is paid attention to at any time, and a square spade is adopted to shoveling off the sprayed concrete at the redundant part, so that the surface of the final sprayed concrete is smooth and has no macroscopic unevenness;
(7) Back cavity and leakage grouting treatment: after the sprayed concrete reaches 10Mpa, grouting holes with the diameter of 42mm are drilled along the surface of the sprayed concrete, the circumferential X longitudinal distance of the grouting holes is 2m X2 m along the sprayed surface, when the sprayed surface is free of water, the grouting depth is 30-50 mm, when the sprayed surface is discharged with water, the grouting depth is 200-300 mm, meanwhile, grouting is encrypted within the range of 3m of a leakage part, and grouting treatment is carried out on the cavity and the leakage water behind the sprayed concrete.
2. The construction method for reducing the rebound rate of sprayed concrete according to claim 1, wherein the construction method comprises the following steps: the mixing ratio test in the step (1) is as follows: in-situ mix tests are required for different batches of sprayed concrete materials, and the following data are referred to in the initial test: glue set ratio: 1 (3.5-5); aggregate sand content: 45% -60%; water-to-gel ratio: 0.4 to 0.5; and after the preparation is finished, the sprayed concrete test block is standard-cultured for 28 days, and a compressive strength test is carried out to meet the design strength.
3. The construction method for reducing the rebound rate of sprayed concrete according to claim 1, wherein the construction method comprises the following steps: and (3) adding water into the concrete in the concrete truck in the step (3) in the conveying process, wherein a concrete tank of the concrete truck is in an operating state.
4. The construction method for reducing the rebound rate of sprayed concrete according to claim 1, wherein the construction method comprises the following steps: after the sprayed surface is treated, the construction site is leveled, the wet spraying mechanical arm, the air pipe, the water pipe and the cable line are checked, the good performance is ensured, the wet spraying mechanical arm is connected for trial spraying, and the parking position of the wet spraying mechanical arm is required to ensure that the rotary spray head of the mechanical arm can realize omnibearing spraying.
5. The construction method for reducing the rebound rate of sprayed concrete according to claim 1, wherein the construction method comprises the following steps: the grouting slurry is cement slurry, superfine cement slurry or double slurry.
CN202211294208.XA 2022-10-21 2022-10-21 Construction method for reducing rebound rate of sprayed concrete Active CN115478880B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211294208.XA CN115478880B (en) 2022-10-21 2022-10-21 Construction method for reducing rebound rate of sprayed concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211294208.XA CN115478880B (en) 2022-10-21 2022-10-21 Construction method for reducing rebound rate of sprayed concrete

Publications (2)

Publication Number Publication Date
CN115478880A CN115478880A (en) 2022-12-16
CN115478880B true CN115478880B (en) 2024-05-31

Family

ID=84396504

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211294208.XA Active CN115478880B (en) 2022-10-21 2022-10-21 Construction method for reducing rebound rate of sprayed concrete

Country Status (1)

Country Link
CN (1) CN115478880B (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2013062243A1 (en) * 2011-10-28 2013-05-02 강원대학교산학협력단 High-performance wet-type shotcrete composition, and method for constructing a scenic structure using same
WO2013062244A1 (en) * 2011-10-28 2013-05-02 강원대학교산학협력단 Method for constructing a bobsleigh course using a high-performance wet-type shotcrete composition
CN103244128A (en) * 2013-05-22 2013-08-14 汇通路桥建设集团有限公司 Method for constructing large-section karst tunnels through double sidewall pilot tunnel and reservation core soil methods
WO2016095630A1 (en) * 2014-12-15 2016-06-23 中铁第四勘察设计院集团有限公司 Method for constructing extra-large variable cross section tunnel
CN106747080A (en) * 2016-12-08 2017-05-31 贵州省公路工程集团有限公司 The C20 concrete and pressing mold shotcrete technology of tunnel bracing members preliminary bracing
CN106988769A (en) * 2017-06-02 2017-07-28 安徽理工大学 A kind of deep High-geotemperature tunnel heat-insulation liner structure and its construction method
JP6402270B1 (en) * 2018-05-16 2018-10-10 株式会社水戸グリーンサービス Concrete spraying method
CN109162732A (en) * 2018-08-21 2019-01-08 华东建工集团有限公司 A kind of shotcrete construction method
CN112031821A (en) * 2020-08-04 2020-12-04 北京鸿锐嘉科技发展有限公司 Reinforcing protection treatment method for tunnel lining defects
WO2021248822A1 (en) * 2020-06-09 2021-12-16 江苏景源万河环境科技有限公司 Construction method for expanded-head prestressed concrete anchor rod

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2013062243A1 (en) * 2011-10-28 2013-05-02 강원대학교산학협력단 High-performance wet-type shotcrete composition, and method for constructing a scenic structure using same
WO2013062244A1 (en) * 2011-10-28 2013-05-02 강원대학교산학협력단 Method for constructing a bobsleigh course using a high-performance wet-type shotcrete composition
CN103244128A (en) * 2013-05-22 2013-08-14 汇通路桥建设集团有限公司 Method for constructing large-section karst tunnels through double sidewall pilot tunnel and reservation core soil methods
WO2016095630A1 (en) * 2014-12-15 2016-06-23 中铁第四勘察设计院集团有限公司 Method for constructing extra-large variable cross section tunnel
CN106747080A (en) * 2016-12-08 2017-05-31 贵州省公路工程集团有限公司 The C20 concrete and pressing mold shotcrete technology of tunnel bracing members preliminary bracing
CN106988769A (en) * 2017-06-02 2017-07-28 安徽理工大学 A kind of deep High-geotemperature tunnel heat-insulation liner structure and its construction method
JP6402270B1 (en) * 2018-05-16 2018-10-10 株式会社水戸グリーンサービス Concrete spraying method
CN109162732A (en) * 2018-08-21 2019-01-08 华东建工集团有限公司 A kind of shotcrete construction method
WO2021248822A1 (en) * 2020-06-09 2021-12-16 江苏景源万河环境科技有限公司 Construction method for expanded-head prestressed concrete anchor rod
CN112031821A (en) * 2020-08-04 2020-12-04 北京鸿锐嘉科技发展有限公司 Reinforcing protection treatment method for tunnel lining defects

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
水工隧洞钢纤维喷射混凝土永久衬砌施工技术研究及应用;江文龙;;黑龙江科技信息;20161105(31);全文 *
湿喷碳素纤维混凝土在大断面黄土隧道中的应用;姜正凯;孙士成;;中国港湾建设;20091225(06);全文 *

Also Published As

Publication number Publication date
CN115478880A (en) 2022-12-16

Similar Documents

Publication Publication Date Title
CN106759126B (en) Construction method of side slope support drainage channel
CN109881694A (en) A kind of constructing structure blocked for foundation pit substrate Sand and method
CN102776897B (en) Wash apron anti-settling anti-cracking construction method and structure
CN109488313B (en) V-level surrounding rock micro-step excavation construction process
CN104846810A (en) Self-circulating posterior grouting bored pile construction method
CN109736346A (en) Steel anchor tube reinforces weathered rock formation reinforcement balance weight retaining wall structure and construction method
CN104452591B (en) A kind of construction of cast-in-situ box-beam technique that is applied to science of bridge building
CN112412496A (en) Full-section advanced curtain grouting construction method for water-rich broken geological zone tunnel
CN111560941A (en) Karst landform cavity treatment method
CN110984171A (en) Steel pipe pile grouting combined waist beam anchor rod supporting method
CN110984221A (en) Construction method for reinforcing end socket at initial end of air shaft and guide wall structure
CN111119195A (en) Foundation pit soil nail shotcrete support construction method
CN110714447A (en) Construction method for filling and rolling in dam subareas
CN115478880B (en) Construction method for reducing rebound rate of sprayed concrete
CN211898541U (en) Guide wall structure for reinforced structure of air shaft initial end head
CN204385724U (en) A kind of polyurethane gravel pile
CN102927364A (en) Reinforced concrete pipe installation method and clamp special for reinforced concrete pipe
CN112176954A (en) Construction method for newly excavated channel
CN110242328A (en) A kind of Tunnel Second Lining Construction method
CN115030731A (en) Pilot tunnel construction method in cross tunnel engineering
CN112176953A (en) Construction method for newly-built channel
CN110847351A (en) Construction method of rock-fill concrete
CN110172978A (en) A kind of subway open-cut station waterproof basal plane construction method
CN111455970B (en) Reinforcing treatment method for backfilled weak miscellaneous soil area containing fertilizer groove
CN113175350B (en) Construction method of water-rich sand layer wastewater pump house

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant