CN115330266A - Urban underground pipeline asset management method and system - Google Patents

Urban underground pipeline asset management method and system Download PDF

Info

Publication number
CN115330266A
CN115330266A CN202211237323.3A CN202211237323A CN115330266A CN 115330266 A CN115330266 A CN 115330266A CN 202211237323 A CN202211237323 A CN 202211237323A CN 115330266 A CN115330266 A CN 115330266A
Authority
CN
China
Prior art keywords
dimensional information
information model
underground
civil engineering
industry
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202211237323.3A
Other languages
Chinese (zh)
Other versions
CN115330266B (en
Inventor
詹登峰
苗东菁
叶绍泽
扈仕娥
胡亚江
闫臻
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Zhilian Xuntang Technology Co ltd
Original Assignee
Beijing Boya Smart Information Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Boya Smart Information Technology Co ltd filed Critical Beijing Boya Smart Information Technology Co ltd
Priority to CN202211237323.3A priority Critical patent/CN115330266B/en
Publication of CN115330266A publication Critical patent/CN115330266A/en
Application granted granted Critical
Publication of CN115330266B publication Critical patent/CN115330266B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/10Services
    • G06Q50/26Government or public services
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Economics (AREA)
  • Human Resources & Organizations (AREA)
  • Theoretical Computer Science (AREA)
  • Strategic Management (AREA)
  • General Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Educational Administration (AREA)
  • Marketing (AREA)
  • Development Economics (AREA)
  • General Business, Economics & Management (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Computer Graphics (AREA)
  • Geometry (AREA)
  • Software Systems (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to a method and a system for managing urban underground pipeline assets, wherein the method comprises the steps of constructing an underground civil engineering space three-dimensional model and storing the model in a public cloud; an industry use unit acquires an underground civil engineering space three-dimensional model from a public cloud according to a preset requirement, constructs an industry pipeline asset three-dimensional model based on the underground civil engineering space three-dimensional model and stores the industry pipeline asset three-dimensional model in a private cloud; when the underground pipeline data need to be accessed, an industry user sends an access request to a public cloud through a private cloud, and after the authority verification is passed, the industry pipeline asset three-dimensional model and the underground civil engineering space three-dimensional model are displayed and applied in a combined mode. The underground civil engineering space three-dimensional model and the pipeline asset three-dimensional model of the industry use unit are separately stored and managed, so that the desensitization and sharing application of the underground pipeline data can be realized by the industry use units on the premise of not exposing the sensitive pipeline data of the industry, and a solution is provided for long-term updating and maintenance of the urban underground pipeline data.

Description

Urban underground pipeline asset management method and system
Technical Field
The invention belongs to the technical field of surveying and mapping geographic information, and particularly relates to an urban underground pipeline asset management method and system.
Background
The urban underground pipeline is a life line of a city, and the safety of the urban underground pipeline is very important to the stable operation of the city. Secrecy and sharing of underground pipeline data has long been an inherent contradiction. Data encryption can limit data sharing application to a great extent, and limit data value exertion, so that efficient collaborative operation between industries/departments cannot be realized, urban underground municipal infrastructure construction efficiency is low, and potential safety hazards exist.
How to effectively desensitize the confidential data is the key to the ability to exploit the value of the data. The industry has been lacking in clear specifications for desensitization and sharing of underground pipeline data. The geospatial information comprises spatio-temporal information, right information, land feature information and the like, and has a more complex data space level compared with the traditional industry data type. In order to solve the problems of desensitization and sharing of geographic spatial information, the former protects and encrypts sensitive information in the forms of geographic information data attribute information decryption, spatial coordinate decryption, geographic information vector data precision reduction, multi-element separation and the like, so that a certain effect is achieved. However, the traditional desensitization method needs to have a complete desensitization rule and transform and search mass data, which easily causes the problems of incomplete desensitization or low data sharing efficiency.
With the requirement of national strategic deployment, the traditional underground pipeline geographic information elements, data forms and precision are difficult to meet, the establishment of a high-precision underground space three-dimensional information model becomes an important future development direction, the characteristic attributes of data are increased, and the magnitude of data is increased, so that the traditional data desensitization technology is difficult to ensure desensitization integrity and high efficiency, the data sharing is limited to a great extent, the underground pipeline data desensitization is incomplete and low in efficiency, and an underground pipeline data sharing mechanism is not perfect.
Disclosure of Invention
In view of the above, the present invention provides a method and a system for managing an urban underground pipeline asset, so as to solve the problem that desensitization integrity, high efficiency and data sharing difficulty of underground pipeline data cannot be simultaneously ensured in the prior art.
In order to achieve the purpose, the invention adopts the following technical scheme: a method for managing urban underground pipeline assets comprises the following steps:
constructing an underground civil construction space three-dimensional information model based on the measured data, and storing the model in a public cloud server;
the method comprises the steps that an industry using unit acquires an underground civil engineering space three-dimensional information model of an urban underground pipeline on line according to a preset requirement, constructs an industry pipeline asset three-dimensional information model in the underground civil engineering space three-dimensional information model according to position, form and topological resource attribute information data of an industry pipeline asset in the underground civil engineering space, which are recorded and presented by measured data, and stores the industry pipeline asset three-dimensional information model in a private cloud server of each industry using unit; the underground civil engineering space three-dimensional information model comprises an underground working well three-dimensional information model and an inter-well channel three-dimensional information model, wherein the underground working well three-dimensional information model comprises the structure and the direction of a working well, and the inter-well channel three-dimensional information model is formed by communicating three-dimensional section components corresponding to adjacent working wells as start and stop sections; the industry pipeline asset three-dimensional information model comprises a civil engineering space three-dimensional information model and a three-dimensional information model, wherein the three-dimensional information model comprises a spatial topological connection relation between industry pipeline asset components inside the civil engineering space three-dimensional information model;
when the three-dimensional information model data of the urban underground civil engineering space needs to be accessed, an industry using unit requests an access authority to the public cloud server, acquires the access authority of the three-dimensional information model of the underground civil engineering space after the request is passed, and performs combined display and application on the three-dimensional information model of the underground civil engineering space and the three-dimensional information model of the industry pipeline asset on the private cloud server.
Furthermore, a corresponding spatial data structure buffer area is estimated in an extension area of a certain range outside the boundary of the underground civil engineering space three-dimensional information model, and the range represented by the data structure of the buffer area extends outwards in the direction of the surface normal of the civil engineering space three-dimensional information model by a certain distance; the real space range corresponding to the buffer area is set according to the corresponding regulations of the underground civil engineering space ownership unit, and the extending distances of the buffer area are different in different normal directions.
Further, the obtaining the access right of the underground civil engineering space three-dimensional information model after the request access right passes includes:
after the access permission of the request is determined to pass, accessing, editing and updating the underground civil engineering space three-dimensional information model and the buffer area according to the access permission of the user;
the method comprises the steps that an access right of an underground civil engineering space three-dimensional information model with a buffer area is opened to an industry using unit, the industry using unit can carry out visual combined display on the underground civil engineering space three-dimensional information model and an industry pipeline asset three-dimensional information model, when the underground civil engineering space three-dimensional information model needs to be updated, an authorized user uploads the updated underground civil engineering space three-dimensional information model to a public cloud server, updated data are confirmed by a worker authorized by the public cloud server and then stored in the public cloud server, when the pipeline asset three-dimensional information model needs to be updated, a changed part of the pipeline asset three-dimensional model is updated by a private cloud server based on the underground civil engineering space three-dimensional model obtained from the public cloud server on line, and then the updated part is stored in the private cloud server.
Further, the access right comprises user identity information and a data range which is expected to be accessed;
the public cloud server is internally provided with a user identity verification strategy and an access authority strategy which are specified by a legally authorized worker to the public cloud server, and the user identity verification strategy and the access authority strategy are used for carrying out user identity authentication and determining access authority when the public cloud server is communicated with the private cloud server;
wherein the access permission policy includes an access permission classification, the access permission classification including: accessing a buffer zone, accessing a three-dimensional information model of an underground civil engineering space, editing the three-dimensional information model of the underground civil engineering space, editing a three-dimensional information model of a pipeline asset and performing combined setting on the authority according to the ownership relation between the user identity and the underground civil engineering space.
Further, when the public cloud server fails to authenticate the user identity of the private cloud server, access is denied;
and when the public cloud server successfully authenticates the user identity of the private cloud server, verifying the access authority of the industry use unit, if the verification fails, refusing the access, if the verification succeeds, establishing a safety protocol, and opening the access authority of the underground civil engineering space three-dimensional information model data to the industry use unit.
Further, the constructing of the underground civil engineering space three-dimensional information model based on the measured data includes:
acquiring point cloud data scanned by three-dimensional laser, and generating a panoramic image by taking the center of a scanner as a viewpoint and the gray level of the scanned point cloud as a pixel;
and constructing an underground civil engineering space three-dimensional information model and a pipeline asset three-dimensional information model based on the space coordinates and the panoramic image of the laser point cloud.
Furthermore, each industry use unit obtains the access authority of the underground civil engineering space three-dimensional information model of the industry use unit right, different industry use units are limited by the corresponding buffer area range, only the limited model is displayed, non-industry use units access industry asset part model information, and the public cloud service set buffer area conversion and the industry use unit set buffer area range shielding are carried out.
The embodiment of the application provides a city underground pipeline asset management system, the city underground pipeline asset management system comprises a public cloud server and a private cloud server which are provided by any one of the embodiments, wherein the public cloud server provides a cloud server computing and storing platform for government service operation, and the private cloud server provides a server for computing and storing data for each industry use unit.
By adopting the technical scheme, the invention can achieve the following beneficial effects:
the invention provides a city underground pipeline asset management method and a system, wherein an underground civil engineering space three-dimensional information model is constructed by actual measurement data and stored in a public cloud server, the model can display the three-dimensional structure of an underground civil engineering space and can be shared to underground pipeline industry users after being set by a buffer area, then an industry pipeline asset three-dimensional information model, such as an industry pipeline asset three-dimensional part and the space topology connection relation of the asset part, and other data are stored in a private cloud server of an industry using unit, if a non-local industry ownership unit needs to simultaneously access the underground civil engineering space three-dimensional information model and the industry pipeline asset three-dimensional information model, the access authority of combined data is obtained after buffer area setting is carried out on the respectively managed model by the underground civil engineering space three-dimensional information model and the ownership unit of the industry pipeline asset three-dimensional information model, so that the separation storage of the whole underground civil engineering space and the pipeline data of the respective industry unit is realized, and the data can be combined and called according to the authority range, thereby realizing the accurate and efficient sharing of the underground pipeline data.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the embodiments or the prior art descriptions will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and other drawings can be obtained by those skilled in the art without creative efforts.
FIG. 1 is a schematic diagram of the steps of the urban underground pipeline asset management method of the present invention.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the technical solutions of the present invention will be described in detail below. It should be apparent that the described embodiments are only some embodiments of the present invention, and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the examples given herein without any inventive step, are within the scope of the present invention.
In the related technology, the existing underground pipeline data desensitization is incomplete and low in efficiency because the traditional underground pipeline geographic information desensitization method is based on the existing database, rule matching retrieval is carried out, the purpose of data desensitization is achieved, sensitive data rules are difficult to exhaust, along with gradual improvement of dimensionality and precision of data, updating of desensitization rules is increasingly difficult, and completeness and efficiency are difficult to guarantee
The reason that the underground pipeline data sharing mechanism is not sound is that underground space information data contains national and local strategic deployment information, and after desensitization is carried out by a traditional method, the safety of the data is still difficult to guarantee. The method has the advantages that the responsibility is excessively concentrated on data management departments, so that data is difficult to share to related departments and personnel in time, the urban underground space management and data updating are greatly influenced, and the data acquired at a high cost cannot be effectively applied.
The following describes a specific method and system for managing urban underground pipeline assets provided in the embodiments of the present application with reference to the accompanying drawings.
As shown in fig. 1, the method for managing urban underground pipeline assets provided in the embodiment of the present application is applied to an urban underground pipeline asset management system, where the urban underground pipeline asset management system includes a public cloud server and a private cloud server, where the public cloud server provides a cloud server computing and storage platform for supporting government service operations, and the private cloud server provides a server for computing and storing data for each industry use unit; the method comprises the following steps:
s101, constructing an underground civil engineering space three-dimensional information model based on the measured data, and storing the model in a public cloud server;
s102, an industry using unit acquires an underground civil engineering space three-dimensional information model of the urban underground pipeline on line according to a preset requirement, constructs an industry pipeline asset three-dimensional information model in the underground civil engineering space three-dimensional information model according to resource attribute information data such as position, form, topology and the like of an industry pipeline asset in the underground civil engineering space, which are recorded and presented by measured data, and stores the industry pipeline asset three-dimensional information model in a private cloud server of each industry using unit; the underground civil engineering space three-dimensional information model comprises an underground working well three-dimensional information model and an inter-well channel three-dimensional information model, wherein the underground working well three-dimensional information model comprises the structure and the direction of a working well, and the inter-well channel three-dimensional information model is formed by communicating three-dimensional section parts corresponding to adjacent working wells as starting and stopping sections; the industry pipeline asset three-dimensional information model comprises a civil engineering space three-dimensional information model and a three-dimensional information model, wherein the industry pipeline asset part and the three-dimensional information model are in a space topological connection relation;
s103, when the three-dimensional information model data of the urban underground civil engineering space need to be accessed, an industry using unit requests the public cloud server for access permission, acquires the access permission of the three-dimensional information model of the underground civil engineering space after the request is passed, and performs combined display and application on the three-dimensional information model of the underground civil engineering space and the three-dimensional information model of the industry pipeline asset on the private cloud server.
The working principle of the urban underground pipeline asset management method and system provided by the application is as follows: the method comprises the steps that a public cloud server is provided with a database, only workers with legal authorization can log in the public cloud server to perform corresponding data management operation, data acquisition is firstly performed to obtain three-dimensional modeling basic data, and therefore an underground civil engineering space three-dimensional information model is constructed according to the three-dimensional modeling basic data, and it can be understood that the underground civil engineering space three-dimensional information model only contains basic structure data of an underground civil engineering space and can be displayed to professional industry users or the public, and exposure of sensitive information is avoided; the method comprises the steps of establishing an industry pipeline asset model in an underground civil engineering space three-dimensional information model of the urban underground pipeline, wherein the industry pipeline asset model comprises specific detail information of the positions, the forms and the attributes of some key industry asset components, such as the industry pipeline asset component relation in the three-dimensional civil engineering space model, the industry asset component relation among different civil engineering space three-dimensional information models, the approach points of the industry asset components and the like. It is understood that the units of industrial use include a variety of, for example, electrical, communications, heating, gas, water supply and drainage, mining, civil air defense (civil air defense), and the like. Each industry use unit stores an underground pipeline asset three-dimensional information model, when the industry use unit needs to check the underground civil engineering space three-dimensional information model or needs to update the industry pipeline asset three-dimensional information model, the underground civil engineering space three-dimensional information model in the public cloud server needs to be obtained, specifically, the industry use unit sends access authority to the public cloud server through the private cloud server, the access authority of the underground civil engineering space three-dimensional information model is obtained after the access authority passes, the underground civil engineering space three-dimensional information model and the industry pipeline asset three-dimensional information model are combined, displayed and applied, and it can be understood that complete current data of the underground pipeline can be obtained only by combining the data in the public cloud server and the private cloud server, so that different industry asset users can achieve the purposes of accurate and efficient sharing and right separation of the underground pipeline data on the premise of not exposing sensitive pipeline information.
In some embodiments, a certain range of extension regions outside the boundary of the underground civil space three-dimensional information model is predicted to calculate a corresponding spatial data structure buffer region, and the range represented by the data structure of the buffer region extends outwards for a certain distance in the direction of the surface normal of the civil space three-dimensional information model; the real space range corresponding to the buffer area is set according to the corresponding regulations of the underground civil engineering space ownership unit, and the extending distances of the buffer area are different in different normal directions.
In some embodiments, the obtaining the access right of the three-dimensional information model of the underground civil engineering space after the request of the access right passes includes:
after the access permission request is determined to pass, setting a buffer area range of the underground civil engineering space three-dimensional information model according to the access permission of the user;
and opening access authority of the underground civil engineering space three-dimensional information model provided with the buffer area to an industry use unit, so that the industry use unit can perform visual combined display on the underground civil engineering space three-dimensional information model and the industry pipeline asset three-dimensional information model. When the underground civil engineering space three-dimensional information model needs to be updated, the authorized user uploads the updated underground civil engineering space three-dimensional information model to the public cloud server, and the updated data is confirmed by a worker authorized by the public cloud server and then stored in the public cloud server. When the pipeline asset three-dimensional information model needs to be updated, the private cloud server updates the change part of the pipeline asset three-dimensional model based on the underground civil engineering space three-dimensional model acquired online from the public cloud server, and the change part is stored in the private cloud server after the update is finished.
As a specific implementation mode, in the application, a buffer area is set for the boundary of the underground civil engineering space three-dimensional information model in order to enhance the efficiency of data acquisition and updating cooperation of the underground space, and guarantee desensitization integrity of data sharing. The buffer area range extends in the boundary normal direction, and after the buffer area range is set, the underground civil engineering space three-dimensional information model can independently perform random position deviation and scale expansion change according to individuals in the range, so that the data display range is changed; it should be noted that the attribute information in the buffer area range is prohibited from being accessed, the larger the buffer area is, the larger the data change range is, and the smaller the buffer area is, the more accurate the model information is, and different buffer areas may affect the data content displayed by the three-dimensional civil engineering space model. This protects the security of the underground civil space data and the internal pipeline asset data.
After the access authority passes, an industry use unit can call the underground civil engineering space three-dimensional model limited by the range of the buffer area, collected data are recorded in key components and hierarchical information in the civil engineering space three-dimensional model according to the monomer requirement on the basis of the underground civil engineering space three-dimensional model, after the industry asset component model is built, the relationship among the industry asset components in the civil engineering space three-dimensional model needs to be further associated, and the access points of the same industry asset component are recorded and used as line patrol bases. And after the processes of data acquisition, component construction and information input are finished, the related data are stored in the private cloud servers of respective units.
In some embodiments, the access rights include user identity information and a range of data desired to be accessed;
the public cloud server is internally provided with a user identity verification strategy and an access authority strategy which are specified by a legally authorized worker to the public cloud server, and the user identity verification strategy and the access authority strategy are used for carrying out user identity authentication and determining access authority when the public cloud server is communicated with the private cloud server;
wherein the access right policy comprises an access right classification, the access right classification comprising: accessing a buffer zone, accessing an underground civil engineering space three-dimensional information model, editing the underground civil engineering space three-dimensional information model, editing a pipeline asset three-dimensional information model and performing combined setting on the authority according to the ownership relation between the user identity and the underground civil engineering space.
In some embodiments, when the public cloud server fails to authenticate the user identity of the private cloud server, access is denied;
and when the public cloud server successfully authenticates the user identity of the private cloud server, verifying the access authority of the industry use unit, if the verification fails, refusing the access, if the verification succeeds, establishing a safety protocol, and opening the access authority of the underground civil engineering space three-dimensional information model data to the industry use unit.
It can be understood that the authentication strategies and the access authority strategies corresponding to different industry use units are set in advance in the public cloud server, the identities of the industry use units are verified by the authentication strategies, the access authorities are verified after the identities are verified, the access authorities are different in the application, and the buffer areas set by the model are different in range.
In some embodiments, different industry use units acquire access rights of the underground civil engineering space three-dimensional model corresponding to the industry use units, each industry use unit is limited by a corresponding buffer area range, only the limited model is displayed, non-industry use units access industry asset component model information, and the model is changed by a public cloud service setting buffer area and the range of the industry use unit setting buffer area is shielded.
Different trade use units of this application are equipped with the underground civil engineering space three-dimensional model that corresponds, perhaps different trade use units correspond different parts in the underground civil engineering space three-dimensional model, and different trade use units have different buffer ranges, and different trade use units pass through private cloud server to when public cloud server sends access right, this application can set up the buffer of underground civil engineering space three-dimensional model on underground three-dimensional model according to different trade use units, and the model can independently carry out random position skew according to the individual at this buffer range, and the flexible change of yardstick to realize the data sharing of different scopes, perhaps this application can carry out the setting of buffer according to the different access rights of different trade use units.
In some embodiments, the constructing a three-dimensional model of a subsurface civil space based on measured data comprises:
acquiring point cloud data scanned by three-dimensional laser, and generating a panoramic image by taking the center of a scanner as a viewpoint and the gray level of the scanned point cloud as a pixel;
and constructing an underground civil engineering space three-dimensional information model and a pipeline asset three-dimensional information model based on the space coordinates and the panoramic image of the laser point cloud.
As a specific implementation mode, the method and the device scan the underground civil engineering space in multiple angles through the three-dimensional laser scanner to obtain the point cloud data of the three-dimensional space.
Specifically, the method adopts the three-dimensional laser scanner to scan the underground space at multiple angles to obtain a panoramic image and three-dimensional laser point cloud data of a shot object, performs fusion processing on the panoramic image data and the laser point cloud data, unifies the position coordinates of the panoramic image and the laser point cloud coordinates into the same coordinate system, and then constructs the underground civil engineering space three-dimensional model based on the mapping relation between the position coordinates in the panoramic image data and the laser point cloud coordinates. It is understood that other methods may be used to construct the three-dimensional model of the underground civil engineering space, and the present application is not limited thereto.
The method and the device solve the problems of data island management and mass data desensitization, realize authority and responsibility separation on different data sources, prevent data from being excessively concentrated, shield sensitive data at the source, and avoid the high time cost of establishing integrity desensitization rules and desensitizing mass data.
In some embodiments, each industry use unit obtains the access right of the underground civil engineering space three-dimensional information model belonging to the industry use unit, each industry use unit is limited by the corresponding buffer area range, only the limited model is displayed, non-industry use units access industry asset component model information, and the public cloud service setting buffer area conversion and the industry use unit setting buffer area range shielding are carried out.
As a specific embodiment, it can be understood that each industry use unit can obtain the access right of the underground civil engineering space three-dimensional information model of each industry use unit, but different industry use units can only access or view, and cannot edit and update the underground civil engineering space three-dimensional information model of other industry use units. For example, although the water conservancy department can see the three-dimensional information model of the underground civil engineering space to which the electric power department belongs, the three-dimensional information model can only be obtained, and cannot be edited and updated. Only the power department can acquire the underground civil engineering space three-dimensional information model of the power department and combine and display the underground civil engineering space three-dimensional information model with the industry pipeline asset three-dimensional information model of the power department stored in the power department, so that the power of the underground civil engineering space three-dimensional information model of the power pipeline and the change part of the pipeline asset three-dimensional information model are updated, after the updating is completed, the underground civil engineering space three-dimensional information model of the power pipeline is stored in a public cloud server, and the power pipeline asset three-dimensional information model is stored in a power private cloud server.
The embodiment of the application provides a city underground pipeline asset management system, the city underground pipeline asset management system comprises a public cloud server and a private cloud server which are provided by any one of the embodiments, wherein the public cloud server provides a cloud server computing and storing platform for government service operation, and the private cloud server provides a server for computing and storing data for each industry use unit.
In summary, the present invention provides a method for managing urban underground pipeline assets, which is applied to an urban underground pipeline asset management system, wherein the urban underground pipeline asset management system comprises a public cloud server and a private cloud server, wherein the public cloud server provides a cloud server computing platform for supporting government service operations, and the private cloud server is a private server for storing data for each industry use unit; the method comprises the steps of constructing an underground civil construction space three-dimensional information model based on point cloud and panoramic images, and storing the underground civil construction space three-dimensional information model in a public cloud server; an industry using unit acquires a civil engineering space three-dimensional model of an urban underground pipeline according to a preset requirement, constructs an industry asset component model in the underground three-dimensional model according to the underground civil engineering space three-dimensional model, and stores the industry asset component model in a private cloud server; the underground three-dimensional space model comprises an underground three-dimensional space model structure and a position relation between models, and the industry asset component model comprises the relation between the property and the component of an industry asset component in the underground three-dimensional space model, the relation between the industry asset components of different underground three-dimensional space models and the approach point of the industry asset component; when the urban underground pipelines need to be subjected to data sharing, an industry using unit sends access authority to the public cloud server through the private cloud server, acquires the underground three-dimensional space model after the access authority passes, and correspondingly combines and calls the underground three-dimensional space model and the industry asset component model. The underground pipeline data acquisition system has the advantages that the underground space is integrally separated from the collected data of the respective industry use units, so that the data can be combined to call and display according to the authority range, and the whole model is subjected to random position, scale deviation transformation and information shielding through a buffer area mechanism, so that the exposure of sensitive information such as space-time information, right information, ground characteristic information and the like is effectively solved, and accurate and efficient sharing of underground pipeline data is realized on the premise that different personnel do not influence the use of the data.
It is to be understood that the method embodiments provided above correspond to the apparatus embodiments, and the corresponding specific contents may be referred to each other, which is not described herein again.
As will be appreciated by one skilled in the art, embodiments of the present application may be provided as a method, system, or computer program product. Accordingly, the present application may take the form of an entirely hardware embodiment, an entirely software embodiment or an embodiment combining software and hardware aspects. Furthermore, the present application may take the form of a computer program product embodied on one or more computer-usable storage media (including, but not limited to, disk storage, optical storage, and the like) having computer-usable program code embodied therein.
The present application is described with reference to flowchart illustrations and/or block diagrams of methods, apparatus (systems), and computer program products according to embodiments of the application. It will be understood that each flow and/or block of the flow diagrams and/or block diagrams, and combinations of flows and/or blocks in the flow diagrams and/or block diagrams, can be implemented by computer program instructions. These computer program instructions may be provided to a processor of a general purpose computer, special purpose computer, embedded processor, or other programmable data processing apparatus to produce a machine, such that the instructions, which execute via the processor of the computer or other programmable data processing apparatus, create means for implementing the functions specified in the flowchart flow or flows and/or block diagram block or blocks.
These computer program instructions may also be stored in a computer-readable memory that can direct a computer or other programmable data processing apparatus to function in a particular manner, such that the instructions stored in the computer-readable memory produce an article of manufacture including instruction means which implement the function specified in the flowchart flow or flows and/or block diagram block or blocks.
These computer program instructions may also be loaded onto a computer or other programmable data processing apparatus to cause a series of operational steps to be performed on the computer or other programmable apparatus to produce a computer implemented process such that the instructions which execute on the computer or other programmable apparatus provide steps for implementing the functions specified in the flowchart flow or flows and/or block diagram block or blocks.
The above description is only for the specific embodiments of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art can easily conceive of the changes or substitutions within the technical scope of the present invention, and all the changes or substitutions should be covered within the scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the protection scope of the appended claims.

Claims (8)

1. A method for managing urban underground pipeline assets is characterized by comprising the following steps:
constructing an underground civil construction space three-dimensional information model based on the measured data, and storing the model in a public cloud server;
the method comprises the steps that an industry using unit acquires an underground civil engineering space three-dimensional information model of an urban underground pipeline on line according to a preset requirement, constructs an industry pipeline asset three-dimensional information model in the underground civil engineering space three-dimensional information model according to position, form and topological resource attribute information data of an industry pipeline asset in the underground civil engineering space, which are recorded and presented by measured data, and stores the industry pipeline asset three-dimensional information model in a private cloud server of each industry using unit; the underground civil engineering space three-dimensional information model comprises an underground working well three-dimensional information model and an inter-well channel three-dimensional information model, wherein the underground working well three-dimensional information model comprises the structure and the direction of a working well, and the inter-well channel three-dimensional information model is formed by communicating three-dimensional section parts corresponding to adjacent working wells as starting and stopping sections; the industry pipeline asset three-dimensional information model comprises a civil engineering space three-dimensional information model and a three-dimensional information model, wherein the three-dimensional information model comprises a spatial topological connection relation between industry pipeline asset components inside the civil engineering space three-dimensional information model;
when the three-dimensional information model data of the urban underground civil engineering space needs to be accessed, an industry using unit requests an access authority to the public cloud server, acquires the access authority of the three-dimensional information model of the underground civil engineering space after the request is passed, and performs combined display and application on the three-dimensional information model of the underground civil engineering space and the three-dimensional information model of the industry pipeline asset on the private cloud server.
2. The method of claim 1, wherein a certain range of extension regions outside the boundary of the three-dimensional information model of the underground civil space is expected to calculate a corresponding spatial data structure buffer region, and the range of the data structure representation of the buffer region extends outwards for a certain distance in the direction of the surface normal of the three-dimensional information model of the civil space; the real space range corresponding to the buffer area is set according to the corresponding regulations of the underground civil engineering space ownership unit, and the extending distances of the buffer area are different in different normal directions.
3. The method of claim 2, wherein obtaining access rights to the three-dimensional information model of the underground civil space after the request for access rights passes comprises:
after the access permission of the request is determined to pass, accessing, editing and updating the underground civil engineering space three-dimensional information model and the buffer area according to the access permission of the user;
the method comprises the steps that an access right is opened to an industry using unit for an underground civil engineering space three-dimensional information model with a buffer area, the industry using unit can visually combine and display the underground civil engineering space three-dimensional information model and an industry pipeline asset three-dimensional information model, when the underground civil engineering space three-dimensional information model needs to be updated, an authorized user uploads the updated underground civil engineering space three-dimensional information model to a public cloud server, updated data are confirmed by workers authorized by the public cloud server and then stored in the public cloud server, when the pipeline asset three-dimensional information model needs to be updated, a changing part of the pipeline asset three-dimensional model is updated by a private cloud server based on the underground civil engineering space three-dimensional model obtained on line from the public cloud server, and the updated changing part is stored in the private cloud server.
4. The method of claim 1, wherein the access rights include user identity information and a range of data desired to be accessed;
the public cloud server is internally provided with a user identity verification strategy and an access authority strategy which are specified by a legally authorized worker to the public cloud server and are used for carrying out user identity authentication and determining access authority when the public cloud server is communicated with the private cloud server;
wherein the access permission policy includes an access permission classification, the access permission classification including: accessing a buffer zone, accessing an underground civil engineering space three-dimensional information model, editing the underground civil engineering space three-dimensional information model, editing a pipeline asset three-dimensional information model and performing combined setting on the authority according to the ownership relation between the user identity and the underground civil engineering space.
5. The method of claim 4,
when the public cloud server fails to authenticate the user identity of the private cloud server, access is denied;
and when the public cloud server successfully authenticates the user identity of the private cloud server, verifying the access authority of the industry use unit, if the verification fails, refusing the access, if the verification succeeds, establishing a safety protocol, and opening the access authority of the underground civil engineering space three-dimensional information model data to the industry use unit.
6. The method of claim 1, wherein constructing the three-dimensional information model of the subsurface civil space based on the measured data comprises:
acquiring point cloud data scanned by three-dimensional laser, and generating a panoramic image by taking the center of a scanner as a viewpoint and the gray level of the scanned point cloud as a pixel;
and constructing an underground civil engineering space three-dimensional information model and a pipeline asset three-dimensional information model based on the space coordinates and the panoramic image of the laser point cloud.
7. The method of claim 1,
and each industry use unit obtains the access authority of the underground civil engineering space three-dimensional information model of the right of the industry use unit, different industry use units are limited by the range of the corresponding buffer area, only the limited model is displayed, and non-industry use units access the information of the industry asset part model, and are subjected to public cloud service setting buffer area conversion and the range shielding of the industry use unit setting buffer area.
8. An urban underground pipeline asset management system, which comprises the public cloud server and the private cloud server of any one of claims 1 to 7, wherein the public cloud server provides a cloud server computing and storage platform for government service operation, and the private cloud server provides a server for computing and storing data for each industry use unit.
CN202211237323.3A 2022-10-11 2022-10-11 Urban underground pipeline asset management method and system Active CN115330266B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211237323.3A CN115330266B (en) 2022-10-11 2022-10-11 Urban underground pipeline asset management method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211237323.3A CN115330266B (en) 2022-10-11 2022-10-11 Urban underground pipeline asset management method and system

Publications (2)

Publication Number Publication Date
CN115330266A true CN115330266A (en) 2022-11-11
CN115330266B CN115330266B (en) 2022-12-20

Family

ID=83914154

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211237323.3A Active CN115330266B (en) 2022-10-11 2022-10-11 Urban underground pipeline asset management method and system

Country Status (1)

Country Link
CN (1) CN115330266B (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20150249709A1 (en) * 2014-02-28 2015-09-03 Vmware, Inc. Extending cloud storage with private devices
CN108399652A (en) * 2018-02-12 2018-08-14 广州市城市规划勘测设计研究院 Method, apparatus, storage medium and the terminal device of City Buried Pipeline three-dimension monitor model foundation
CN108597020A (en) * 2018-01-24 2018-09-28 苏州星宇测绘科技有限公司 A kind of three-dimensional underground utilities detection data quick mapping method and system
CN108694244A (en) * 2018-05-15 2018-10-23 国网新疆电力有限公司乌鲁木齐供电公司 A kind of electric network synthetic application platform based on three-dimensional data
CN108845601A (en) * 2018-05-04 2018-11-20 四川通普科技有限公司 Urban Underground water channel monitoring system based on NB-IoT
CN110159929A (en) * 2019-05-31 2019-08-23 万基泰科工集团西南科技有限公司 Subdrainage pipe network intelligently manages big data processing method
CN111027834A (en) * 2019-12-02 2020-04-17 浙江华云电力工程设计咨询有限公司 Power cable informatization management system and method based on three-dimensional detection technology
CN112565427A (en) * 2020-12-07 2021-03-26 北京无线电计量测试研究所 Perspective intelligent pipeline inspection method and system
US20220012270A1 (en) * 2020-07-08 2022-01-13 Worster Construction Management, LLC Comprehensive utility line database and user interface for excavation sites
CN114936441A (en) * 2022-06-09 2022-08-23 中国标准化研究院 Planning construction method of intelligent pipe network

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20150249709A1 (en) * 2014-02-28 2015-09-03 Vmware, Inc. Extending cloud storage with private devices
CN108597020A (en) * 2018-01-24 2018-09-28 苏州星宇测绘科技有限公司 A kind of three-dimensional underground utilities detection data quick mapping method and system
CN108399652A (en) * 2018-02-12 2018-08-14 广州市城市规划勘测设计研究院 Method, apparatus, storage medium and the terminal device of City Buried Pipeline three-dimension monitor model foundation
CN108845601A (en) * 2018-05-04 2018-11-20 四川通普科技有限公司 Urban Underground water channel monitoring system based on NB-IoT
CN108694244A (en) * 2018-05-15 2018-10-23 国网新疆电力有限公司乌鲁木齐供电公司 A kind of electric network synthetic application platform based on three-dimensional data
CN110159929A (en) * 2019-05-31 2019-08-23 万基泰科工集团西南科技有限公司 Subdrainage pipe network intelligently manages big data processing method
CN111027834A (en) * 2019-12-02 2020-04-17 浙江华云电力工程设计咨询有限公司 Power cable informatization management system and method based on three-dimensional detection technology
US20220012270A1 (en) * 2020-07-08 2022-01-13 Worster Construction Management, LLC Comprehensive utility line database and user interface for excavation sites
CN112565427A (en) * 2020-12-07 2021-03-26 北京无线电计量测试研究所 Perspective intelligent pipeline inspection method and system
CN114936441A (en) * 2022-06-09 2022-08-23 中国标准化研究院 Planning construction method of intelligent pipe network

Also Published As

Publication number Publication date
CN115330266B (en) 2022-12-20

Similar Documents

Publication Publication Date Title
Zheng et al. bcBIM: A Blockchain‐Based Big Data Model for BIM Modification Audit and Provenance in Mobile Cloud
CN108830601B (en) Smart city information safe use method and system based on block chain
CN108921491B (en) Building contract payment method based on block chain technology
US11048228B2 (en) System and method to protect items associated with additive manufacturing
CN108960594A (en) The more SC collaboration system and methods of building based on block chain Yu BIM model
CN109214197A (en) The method, apparatus and storage medium of private data are handled based on block chain
CN105450669B (en) Data-oriented security system method and system
Guo et al. A blockchain-driven electronic contract management system for commodity procurement in electronic power industry
CN116310238B (en) Multi-user virtual avatar interaction behavior safety protection method and system
Ding et al. Manufacturing system under I4. 0 workshop based on blockchain: Research on architecture, operation mechanism and key technologies
CN115330266B (en) Urban underground pipeline asset management method and system
Miao et al. The study of data-oriented and ownership-based security architecture in open internet environment
Jaskula et al. Conceptual framework for decentralised information management along the entire lifecycle of a built asset.
CN112258373B (en) Data processing method and device
Banoth et al. A survey on decentralized application based on blockchain platform
CN109033882A (en) A kind of safe dissemination method of retrospective big data and system
Guo et al. CPAS: a copyright-protected autonomous sharing scheme by blockchain and smart contract for BIM data
Jiang et al. Framework for blockchain-enabled building information modeling
CN116956332B (en) BIM data processing method, BIM data processing equipment and computer readable storage medium
CN112927080A (en) Block chain technology-based multi-party information sharing method for power industry
Miao et al. The architecture for data, security and application in digital earth platform
Rajasekar et al. Blackchain-based Identity Management Systems in Digital Forensics
CN114627254B (en) Composite geographic information data plane coordinate decryption method and model
Jiang et al. Research and modeling electronic data tracing scheme based on blockchain
Wang et al. Geo-information security technology research progress and suggestions for development ideas

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240112

Address after: Building 2, No. 26 Chengtong Street, Shijingshan District, Beijing, 100043, 1609

Patentee after: Beijing Zhilian Xuntang Technology Co.,Ltd.

Address before: Room 202-14, Floor 2, No. 127-1, Zhongguancun North Street, Haidian District, Beijing 100089

Patentee before: Beijing Boya Smart Information Technology Co.,Ltd.