CN115233752A - Reverse self-balancing pile testing method based on double pile body load boxes - Google Patents

Reverse self-balancing pile testing method based on double pile body load boxes Download PDF

Info

Publication number
CN115233752A
CN115233752A CN202211051830.8A CN202211051830A CN115233752A CN 115233752 A CN115233752 A CN 115233752A CN 202211051830 A CN202211051830 A CN 202211051830A CN 115233752 A CN115233752 A CN 115233752A
Authority
CN
China
Prior art keywords
pile
section
displacement
load
section pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202211051830.8A
Other languages
Chinese (zh)
Other versions
CN115233752B (en
Inventor
刘永莉
徐静
肖衡林
席铭洋
刘志杰
何欢
陈智
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei University of Technology
Original Assignee
Hubei University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei University of Technology filed Critical Hubei University of Technology
Priority to CN202211051830.8A priority Critical patent/CN115233752B/en
Publication of CN115233752A publication Critical patent/CN115233752A/en
Application granted granted Critical
Publication of CN115233752B publication Critical patent/CN115233752B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/10Miscellaneous comprising sensor means
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention discloses a reverse self-balancing pile testing method based on a double-load box of a pile body, which comprises the steps of determining an upper balance point and a lower balance point, and dividing a pile into an upper section pile, a middle section pile and a lower section pile; respectively arranging a load box at the top of the upper section of pile and between adjacent sections of piles, and sequentially marking as a first load box, a second load box and a third load box; the load boxes comprise jacks and pressure sensors; the top of the upper section pile is provided with a counter-force anchoring system which comprises a counter-force end plate and an anchor rope for anchoring and connecting the counter-force end plate and the middle section pile; arranging a displacement monitoring system for respectively monitoring the displacement of the upper section pile, the middle section pile and the lower section pile; sequentially loading a third load box, a second load box and a first load box, and obtaining the positive limit bearing capacity of each section of pile according to a load displacement curve loaded each time; and then adding the bearing capacity values to obtain the total ultimate bearing capacity of the pile foundation. The invention avoids the problem of non-coincidence of pile body loading and pile top loading balance points in the prior art, and the obtained pile foundation bearing capacity is more in line with the actual situation.

Description

Reverse self-balancing pile testing method based on double pile body load boxes
Technical Field
The invention belongs to the field of civil engineering, relates to a reverse self-balancing pile testing method technology, and particularly relates to a reverse self-balancing pile testing method based on a pile body double-load box.
Background
At present, the static load test is considered at home and abroad to be the most accurate and reliable test method for detecting the bearing capacity of the foundation pile. According to different counter-force systems in engineering, static load tests are mainly divided into three types, namely a pile loading method, an anchor pile method and a self-balancing method. The pile loading method is the most reliable method for detecting the bearing capacity of the foundation pile. The counter force of the static load test is provided by a heavy object, but the construction site condition is limited, and higher installation and transportation cost is required; the anchor pile method is to use the anchor pile as a counter-force system, and the method is mainly used for testing the bearing capacity of the large-diameter cast-in-place pile, and usually four or more anchor piles are needed, so that the test cost is increased; the self-balancing method does not need a loading platform and an anchor pile counter-force system, but has extremely high technical requirements on construction technicians, because whether the test can be successful or not is often in a big relation with the correct selection of a 'balance point', and the test load borne by the pile body is only half of the designed load limit bearing capacity, so that the real strength of the pile body of the test pile under the limit bearing capacity and the uncertainty of the value of the negative frictional resistance to the positive frictional resistance cannot be measured. Therefore, a reverse self-balancing pile testing method is provided, and a pile top loading device is added on the basis of the self-balancing pile testing method.
The reverse self-balancing method has the advantages that a loading platform and an anchor pile counter-force system are not needed, and the technical problem that the negative friction of the upper-section pile of the self-balancing test pile needs to be converted into the positive friction is solved.
However, the reverse self-balancing pile test method has a problem that the upper pile section is easily pulled upwards when the pile top is loaded, because the requirements of the pile body loading and the pile top loading on the position of the balance point are different, the pile body loading is suitable for calculating the position of the balance point which is lower, and the pile top loading is suitable for calculating the position of the balance point. Meanwhile, due to the fact that geological survey data are inaccurate, errors exist in the installation position of the load box and the like, the limit cannot be reached simultaneously when the pile body loads the upper pile and the lower pile, and therefore the obtained test result is smaller than the actual test result.
As shown in fig. 1, two sets of loading devices are arranged in the reverse self-balancing pile testing method, namely, pile body loading and pile top loading. The change of the loading sequence causes the distribution of the side frictional resistance of the pile body and the position of the neutral point to change, as shown in the figure, when the pile body is loaded, the
Figure BDA0003823731490000011
Q fd2 + =A p q r ,Q fu - The upper pile section is subjected to vertical downward negative frictional resistance, Q fd1 + The lower section of the pile is subjected to vertical and upward positive frictional resistance, Q fd2 + The lower section of the pile is subjected to vertical upward end resistance, and the requirement of Q is met for achieving balance fu _ +G u =Q fd1 + +Q fd2 + The position of the load box is deviated, the counterforce of the pile end of the lower section pile can be exerted more completely, so that the proper position of the load box is deviated; when pile top is loaded, Q fu + The upper section of the pile is subjected to vertical and upward positive frictional resistance, Q fd _ The lower section of the pile is subjected to vertical downward negative frictional resistance, wherein Q fd1 + +Q fd2 + >Q fd _ Therefore, the balance point can not meet the loading of the pile top when the pile body loading is met; a technology is also urgently needed to eliminate the defects, so that the obtained ultimate bearing capacity of the pile foundation is closer to the real ultimate bearing capacity, and the application of a reverse self-balancing pile test method in foundation pile engineering is expected to be promoted.
Disclosure of Invention
Aiming at the problem that the positions of balance points required by pile body loading and pile top loading in a reverse self-balancing pile testing method are inconsistent, the invention provides a reverse self-balancing pile testing method based on a pile body double-load box.
In order to solve the technical problems, the invention adopts the following technical scheme:
the reverse self-balancing pile testing method based on the double loading boxes of the pile body is characterized by comprising the following steps of:
step 1, determining an upper balance point and a lower balance point through calculation or experience judgment according to geological data, and dividing a pile into an upper section pile, a middle section pile and a lower section pile, wherein the two balance points are respectively positioned between the two adjacent sections of piles;
step 2, respectively arranging a load box at the top of the upper-section pile, between the upper-section pile and the middle-section pile, and between the middle-section pile and the lower-section pile, sequentially marking as a first load box, a second load box and a third load box, wherein each load box comprises a jack and a pressure sensor which are arranged in a stacked manner or a jack with a pressure sensor;
step 3, arranging a counter-force anchoring system at the top of the upper section of pile, wherein the counter-force anchoring system comprises a counter-force end plate arranged at the top of the first load box and an anchor rope for anchoring and connecting the counter-force end plate and the middle section of pile, and the anchor rope freely penetrates through the upper section of pile;
step 4, arranging a displacement monitoring system to monitor the displacement of the upper section pile, the middle section pile and the lower section pile respectively;
step 5, loading a pile body, loading a jack in a third load box to force the middle-section pile and the lower-section pile to move back to back, drawing a load displacement curve graph of the middle-section pile and the lower-section pile according to the displacement of the middle-section pile and the lower-section pile obtained by the displacement monitoring system and the force obtained by a pressure sensor in the third load box, and obtaining the negative limit bearing capacity Q of the middle-section pile through curve trend um - And the positive limit bearing capacity Q of the lower section pile ud +
Step 6, loading the pile body, loading a jack in the second load box, and forcing the upper-section pileMoving back to back with the middle section pile, drawing a load displacement curve graph of the upper section pile and the middle section pile according to the displacement of the upper section pile and the middle section pile obtained by the displacement monitoring system and the force obtained by the pressure sensor in the second load box, and obtaining the negative limit bearing capacity Q of the upper section pile through curve trend uu - And the positive limit bearing capacity Q of the middle section pile um +
And 7, loading a pile top, loading a jack in the first load box to force the upper-section pile and the middle-section pile to move oppositely, drawing a load displacement curve graph of the upper-section pile and the middle-section pile according to the displacement of the upper-section pile and the middle-section pile obtained by the displacement monitoring system and the force obtained by the pressure sensor in the first load box, and obtaining the positive limit bearing capacity Q of the upper-section pile through curve trend uu + And the negative limit bearing capacity Q of the middle section pile um -
And 7, calculating the vertical compression-resistant total ultimate bearing capacity of the pile, wherein the calculation formula is as follows:
Figure BDA0003823731490000031
Q press and press For the vertical resistance to compression total ultimate bearing capacity of stake, G is the total dead weight of stake.
Compared with the prior art, the invention has the following effective effects:
according to the invention, the problem that the positions of the balance points required by pile body loading and pile top loading in the traditional reverse self-balancing pile test method are inconsistent is solved by selecting the mode that two pile body jacks are arranged at two balance points, the ultimate bearing capacity of the pile foundation is obtained by three-time loading segmentation, and then the ultimate bearing capacity of the total pile foundation is calculated, so that the problem that the balance points of pile body loading and pile top loading are not coincident in the original technical scheme is avoided, the obtained bearing capacity of the pile foundation is more consistent with the real ultimate bearing capacity of the pile foundation, and more accurate design basis is provided for the engineering pile.
Drawings
Fig. 1 is a force diagram of a reverse self-balancing method in the prior art.
Fig. 2 is a structural schematic diagram of a reverse self-balancing pile testing device based on a pile body double-load box in the embodiment of the invention.
Fig. 3 is a schematic diagram of pile stress when the third load box is loaded in the embodiment of the invention.
Fig. 4 is a schematic diagram of pile stress when the second load box is loaded in the embodiment of the invention.
Fig. 5 is a schematic diagram of the pile force applied when the first load box is loaded in the embodiment of the invention.
1-a counter-force end plate; 2-dial indicator; 3-a hydraulic oil station; 4-a data acquisition system; 5-upper pile section; 6, anchor cables; 7-a displacement rod; 8-sealing an end plate at the bottom of the upper section pile; 9-sealing an end plate on the top of the middle section pile; 10-steel shaft bolt; 11-middle section pile; 12-middle section pile bottom sealing end plate; 13-a third load box; 14-lower pile top sealing end plate; 15-lower section of pile; 16-a jack; 17-a pressure sensor; 18-upper pile top end sealing plate, 19-second load box and 20-first load box.
Detailed Description
The embodiments of the present invention will be described in further detail with reference to the drawings and examples. The following examples are intended to illustrate the invention but are not intended to limit the scope of the invention.
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
It should be noted that the embodiments and features of the embodiments may be combined with each other without conflict.
The invention is further described with reference to the following drawings and specific examples, which are not intended to be limiting.
As shown in fig. 2, the invention provides a reverse self-balancing pile testing device based on a pile body double-load box, which comprises a pile, a reverse anchoring system, a loading system and a displacement monitoring system; the piles comprise upper piles 5, middle piles 11 and lower piles 15, and end-sealing plates are arranged at the tops of the upper piles 5, the bottoms of the upper piles 5, the tops of the middle piles 11, the bottoms of the middle piles 11 and the tops of the lower piles 15;
the loading system comprises three load boxes and a hydraulic oil station 3, each load box comprises a jack 16 and a pressure sensor 17 which are arranged in a stacked mode, and the pressure sensors 17 are generally arranged at the free telescopic ends of the jacks 16 and used for measuring the actual loading force of the jacks 16; the jacks 16 of the three load boxes are connected with the hydraulic oil station 3 through an oil way control system, the loading and unloading of each jack 16 are controlled through the hydraulic oil station 3, and how to control the loading and unloading of each jack 16 has no influence on solving the technical problem of the invention; the second load box 19 is arranged between the upper-section pile 5 and the middle-section pile 11, and is specifically arranged on the middle-section pile top end sealing plate 9 and between the upper-section pile bottom end sealing plate 8; the third load box is arranged between the middle section pile 11 and the lower section pile 15, and is specifically arranged between the lower section pile top end sealing plate 14 and the middle section pile bottom end sealing plate 12.
The counter-force anchoring system comprises a counter-force end plate 1 and a plurality of anchor cables 6, the counter-force end plate 1 is arranged at the top of the first load box, the tops of the anchor cables 6 are fixedly connected with the counter-force end plate 1, and the lower ends of the anchor cables freely penetrate through the upper-section pile 5 and then are fixed on the sealing end plate 9 at the top of the middle-section pile; through holes for the anchor cable 6 to freely pass through are formed in the upper-section pile top end sealing plate 18 and the upper-section pile bottom end sealing plate 8.
As a preferred embodiment, the anchor cables 6 are uniformly distributed around the first load box, so as to prevent unbalanced loading during the loading process.
As a preferred embodiment, the lower end of the anchor cable 6 is fixed at the bottom of the middle-section pile top end sealing plate 9 through a steel shaft plug 10, so that the fixing is simple and convenient, and the anchoring requirement can be met.
It should be noted that the pile in the invention can be a model pile in a model test or an engineering pile, and the invention is only used for illustrating a principle method, so that the installation sequence of the load box and the displacement monitoring system can be selected according to the requirement, and is not limited to a certain specific form.
The movement monitoring system comprises a data acquisition system 4, four displacement rods 7 and a dial indicator 2 which is arranged at the tops of the corresponding displacement rods 7 and used for measuring the movement displacement of the displacement rods 7, wherein the first displacement rod freely penetrates through the upper section of pile 5 and then is fixed on an upper section of pile bottom end sealing plate 8 and used for measuring the pile bottom displacement of the upper section of pile 5; the second displacement rod freely penetrates through the upper section pile 5 and then is fixed on the middle section pile top end sealing plate 9 and used for measuring the pile top displacement of the middle section pile 11; the third displacement rod freely penetrates through the upper-section pile 5 and the middle-section pile 11 and then is fixed on the middle-section pile bottom sealing end plate 12 and used for measuring the pile bottom displacement of the middle-section pile 11; and the fourth displacement rod freely penetrates through the upper-section pile 5 and the middle-section pile 11 and then is fixed on the lower-section pile top end sealing plate 14 for measuring the pile top displacement of the lower-section pile 15.
Four percentage table 2 hang on external member or set up the independent support fixed, four displacement poles 7 move up and down along with the closed end board of fixing separately in the loading process, can read every displacement pole 7 through percentage table 2 and move the distance up and down, be the displacement of corresponding section stake promptly.
As shown in fig. 3 to 4, the present invention provides a reverse self-balancing pile testing method based on the above-mentioned reverse self-balancing pile testing device, including the following steps:
step 1, determining an upper balance point and a lower balance point through calculation or empirical judgment according to geological data, dividing the pile into three sections, namely an upper section pile 5, a middle section pile 11 and a lower section pile 15, wherein the two balance points are respectively positioned between the two adjacent sections of piles;
step 2, respectively arranging a load box at the top of the upper-section pile 5, between the upper-section pile 5 and the middle-section pile 11, and between the middle-section pile 11 and the lower-section pile 15, sequentially marking as a first load box 20, a second load box 19 and a third load box 13, wherein each load box comprises a jack 16 and a pressure sensor 17 which are arranged in a stacked manner or a jack with a pressure sensor;
step 3, arranging a counter-force anchoring system at the top of the upper-section pile 5, wherein the counter-force anchoring system comprises a counter-force end plate 1 arranged at the top of the first load box 20 and an anchor rope 6 for anchoring and connecting the counter-force end plate 1 and the middle-section pile 11, and the anchor rope 6 freely penetrates through the upper-section pile 5;
step 4, arranging a displacement monitoring system, and respectively monitoring the displacement of the upper section pile 5, the middle section pile 11 and the lower section pile 15;
step 5, loading a pile body, loading a jack 16 in the third load box 13 to force the middle-section pile 11 and the lower-section pile 15 to move back and forth, drawing a load displacement curve graph of the middle-section pile 11 and the lower-section pile 15 according to the displacement of the middle-section pile 11 and the lower-section pile 15 obtained by the displacement monitoring system and the force obtained by a pressure sensor 17 in the third load box 13, and obtaining the negative limit bearing capacity Q of the middle-section pile 11 through curve trend um - And the positive limit bearing capacity Q of the lower section pile 15 ud +
Step 6, loading a pile body, loading a jack 16 in a second load box 19 to force the upper-section pile 5 and the middle-section pile 11 to move back and forth, drawing a load displacement curve graph of the upper-section pile 5 and the middle-section pile 11 according to the displacement of the upper-section pile 11 and the displacement of the middle-section pile 11 obtained by a displacement monitoring system and the force obtained by a pressure sensor 17 in the second load box 19, and obtaining the negative limit bearing capacity Q of the upper-section pile through curve trend uu - And the positive limit bearing capacity Q of the middle section pile um +
Step 7, loading the pile top, loading a jack 16 in the first load box 20 to force the upper-section pile 5 and the middle-section pile 11 to move oppositely, drawing a load-displacement curve graph of the upper-section pile 5 and the middle-section pile 11 according to the displacement of the upper-section pile 11 and the middle-section pile 11 obtained by the displacement monitoring system and the force obtained by the pressure sensor 17 in the first load box 20, and obtaining the positive limit bearing capacity Q of the upper-section pile through curve trend uu + And the negative limit bearing capacity Q of the middle section pile um -
And 7, calculating the vertical compression-resistant total ultimate bearing capacity of the pile, wherein the calculation formula is as follows:
Figure BDA0003823731490000051
Q press and press For the vertical resistance to compression total ultimate bearing capacity of stake, G is the total dead weight of stake.
As a preferred embodiment, in step 1, the two equilibrium points are determined as follows:
step 1.1, firstly, the pile is preliminarily divided into an upper section pile and a lower section pile, and a first balance point is determined through a balance point calculation formula which is as follows:
Figure BDA0003823731490000052
in the above formula, the first and second carbon atoms are,
in the above formula, i represents the number of layered soil layers around the pile, λ i Representing the weighting correction coefficient of the soil layer around the upper pile, taking 0.8 of cohesive soil and silt and 0.7 of sandy soil; u denotes the pile body circumference, l i Representing the length of the corresponding segment of the pile's surrounding soil, q ik Is represented by i The standard value of frictional resistance between the side of the pile with the corresponding length and the soil layer, the dead weight of the pile at the upper section on G, the sectional area of the pile end on Ap, the allowable bearing capacity of the soil at the pile end on qr and the left summation formula
Figure BDA0003823731490000061
The pile side resistance summation and the right side summation formula of the upper pile are expressed
Figure BDA0003823731490000062
The pile side resistance summation of the lower pile is shown.
Step 1.2, after a first balance point is obtained by calculating the length of the upper section pile, selecting a point in the middle of the preliminary lower section pile as a second balance point according to an empirical value (for example, the second balance point selects the length of one third to two thirds of the preliminary lower section pile, the specific position of the balance point is not particularly important, and the calculation inaccuracy of the first balance point can be corrected enough only by setting the second balance point), and dividing the preliminary lower section pile into two sections, so that three sections of upper section pile, middle section pile and lower section pile are obtained.
It should be noted that, the first balance point calculation method may refer to the highway bridge foundation and foundation design specification (JTG D63-2007).
As a preferred embodiment, the central axes of the jacks and the pressure sensors in the three load boxes are coincident with the central axis of the pile.
As a preferred embodiment, the pressure sensor is a cylindrical pressure sensor with the offset load resisting capacity.
In the step 5 to the step 7, the jack 16 in the load box is loaded in a graded loading mode, and each grade of loading is 1/10-1/15 of the estimated limit load.
As a preferred embodiment, in step 5 to step 7,
the displacement of each hour does not exceed 0.1mm and continuously occurs twice, which is considered to be relatively stable, and the next stage of load is added; when one of the download conditions occurs, the loading can be terminated;
(1) The limit loading value has been reached;
(2) Under the action of a certain level of load, the displacement of the pile is 5 times of that of the pile under the action of the previous level of load;
(3) Under the action of a certain level of load, the displacement of the pile is 2 times larger than that of the pile under the action of the previous level of load, and the pile is not relatively stable for 24 hours;
(4) The cumulative amount of pull-up exceeds 100mm.
The above embodiments are merely illustrative of the present invention and are not to be construed as limiting the invention. Although the present invention has been described in detail with reference to the embodiments, it should be understood by those skilled in the art that various combinations, modifications or equivalents may be made to the technical solution of the present invention without departing from the spirit and scope of the technical solution of the present invention, and the technical solution of the present invention is covered by the claims of the present invention.

Claims (9)

1. The utility model provides a reverse self-balancing pile testing method based on two load boxes of pile body which characterized in that includes following steps:
step 1, determining an upper balance point and a lower balance point through calculation or experience judgment according to geological data, and dividing a pile into an upper section pile, a middle section pile and a lower section pile, wherein the two balance points are respectively positioned between the two adjacent sections of piles;
step 2, respectively arranging a load box at the top of the upper-section pile, between the upper-section pile and the middle-section pile, and between the middle-section pile and the lower-section pile, sequentially marking as a first load box, a second load box and a third load box, wherein each load box comprises a jack and a pressure sensor which are arranged in a stacked manner or a jack with a pressure sensor;
step 3, arranging a counter-force anchoring system at the top of the upper section of pile, wherein the counter-force anchoring system comprises a counter-force end plate arranged at the top of the first load box and an anchor rope for anchoring and connecting the counter-force end plate and the middle section of pile, and the anchor rope freely penetrates through the upper section of pile;
step 4, arranging a displacement monitoring system, and respectively monitoring the displacement of the upper section pile, the middle section pile and the lower section pile;
step 5, loading a pile body, loading a jack in a third load box to force the middle-section pile and the lower-section pile to move back to back, drawing a load displacement curve graph of the middle-section pile and the lower-section pile according to the displacement of the middle-section pile and the lower-section pile obtained by the displacement monitoring system and the force obtained by a pressure sensor in the third load box, and obtaining the negative limit bearing capacity Q of the middle-section pile through curve trend um - And the positive limit bearing capacity Q of the lower section pile ud +
Step 6, loading a pile body, loading a jack in a second load box, forcing the upper-section pile and the middle-section pile to move back to back, drawing a load displacement curve graph of the upper-section pile and the middle-section pile according to the displacement of the upper-section pile and the middle-section pile obtained by the displacement monitoring system and the force obtained by a pressure sensor in the second load box, and obtaining the negative limit bearing capacity Q of the upper-section pile through curve trend uu - And the positive limit bearing capacity Q of the middle section pile um +
And 7, loading a pile top, loading a jack in the first load box to force the upper-section pile and the middle-section pile to move oppositely, drawing a load displacement curve graph of the upper-section pile and the middle-section pile according to the displacement of the upper-section pile and the middle-section pile obtained by the displacement monitoring system and the force obtained by the pressure sensor in the first load box, and obtaining the positive limit bearing capacity Q of the upper-section pile through curve trend uu + And the negative limit bearing capacity Q of the middle section pile um -
And 7, calculating the vertical compression-resistant total ultimate bearing capacity of the pile, wherein the calculation formula is as follows:
Figure FDA0003823731480000011
Q pressing and pressing For the vertical resistance to compression total ultimate bearing capacity of stake, G is the total dead weight of stake.
2. The reverse self-balancing pile test method according to claim 1, wherein: in step 1, the two balance points are determined as follows:
step 1.1, firstly, the pile is preliminarily divided into an upper section of pile and a lower section of pile, and a first balance point is determined through a balance point calculation formula which is as follows:
Figure FDA0003823731480000012
in the above formula, i represents the number of layered soil layers around the pile, λ i Expressing the weighted correction coefficient of the upper pile circumference soil layer, u expressing the circumference of the pile body, l i Representing the length of the corresponding segment of the pile's surrounding soil, q ik Is represented by i The standard value of frictional resistance between the pile side and the soil layer with corresponding length is G, the dead weight of the upper pile is shown, ap is the sectional area of the pile end, qr is the allowable bearing capacity of the soil at the pile end, and the left summation formula
Figure FDA0003823731480000021
The pile side resistance summation and the right side summation formula of the upper pile are expressed
Figure FDA0003823731480000022
Showing pile side resistance summation of the lower pile;
and 1.2, after a first balance point is obtained by calculating the length of the upper section pile, selecting a point in the middle of the preliminary lower section pile as a second balance point according to an empirical value, and dividing the preliminary lower section pile into two sections, so as to obtain three sections of upper section piles, middle section piles and lower section piles.
3. The reverse self-balancing pile test method according to claim 1, wherein: the top of the lower section pile, the bottom of the middle section pile, the top of the middle section pile, the bottom of the upper section pile and the top of the upper section pile are all provided with end sealing plates; and the lower end of an anchor rope of the counter-force anchoring system freely penetrates through the anchor rope sleeve and then is fixed on the end sealing plate at the top of the middle-section pile.
4. The reverse self-balancing pile test method according to claim 3, wherein: move monitoring system and include four displacement poles and locate corresponding displacement pole top and be used for measuring the percentage table that the displacement pole removed the displacement, first displacement pole freely passes upper segment stake after-fixing on upper segment stake bottom end seal plate, second displacement pole freely passes upper segment stake after-fixing on middle segment stake top end seal plate, third displacement pole freely passes upper segment stake and middle segment stake after-fixing on middle segment stake bottom end seal plate, fourth displacement pole freely passes upper segment stake and middle segment stake after-fixing on lower segment stake top end seal plate.
5. The reverse self-balancing pile test method according to claim 3, wherein: and the lower end of the anchor cable is fixed on the end sealing plate at the top of the middle section pile through a steel shaft bolt.
6. The reverse self-balancing pile test method according to claim 1, wherein: the central axes of the jacks and the pressure sensors in the three load boxes are coincided with the central axis of the pile.
7. The reverse self-balancing pile test method according to claim 6, wherein: the pressure sensor is a cylindrical pressure sensor with unbalance loading resistance.
8. The reverse self-balancing pile test method according to claim 1, wherein: and 5, in the step 7, the jack in the load box is loaded in a graded loading mode, and each grade of loading is 1/10-1/15 of the estimated limit load.
9. The reverse self-balancing pile test method according to claim 1, wherein: in the step from the step 5 to the step 7,
the displacement of each hour does not exceed 0.1mm and continuously occurs twice, which is considered to be relatively stable, and the next stage of load is added; when one of the download conditions occurs, the loading can be terminated;
(1) The limit loading value has been reached;
(2) Under the action of a certain level of load, the displacement of the pile is 5 times of that of the pile under the action of the previous level of load;
(3) Under the action of a certain level of load, the displacement of the pile is 2 times larger than that of the pile under the action of the previous level of load, and the pile is not relatively stable for 24 hours;
(4) The cumulative amount of pull-up exceeds 100mm.
CN202211051830.8A 2022-08-31 2022-08-31 Reverse self-balancing pile testing method based on pile body double-load box Active CN115233752B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211051830.8A CN115233752B (en) 2022-08-31 2022-08-31 Reverse self-balancing pile testing method based on pile body double-load box

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211051830.8A CN115233752B (en) 2022-08-31 2022-08-31 Reverse self-balancing pile testing method based on pile body double-load box

Publications (2)

Publication Number Publication Date
CN115233752A true CN115233752A (en) 2022-10-25
CN115233752B CN115233752B (en) 2023-04-25

Family

ID=83681060

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211051830.8A Active CN115233752B (en) 2022-08-31 2022-08-31 Reverse self-balancing pile testing method based on pile body double-load box

Country Status (1)

Country Link
CN (1) CN115233752B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117344807A (en) * 2023-10-20 2024-01-05 广州开发区建设工程检测中心有限公司 Vertical bearing capacity device for detecting foundation pile and detection method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105839678A (en) * 2016-04-11 2016-08-10 湖北工业大学 Improved pile foundation vertical bearing capacity test reverse self-balanced method and testing device
CN110453733A (en) * 2019-09-18 2019-11-15 国网安徽省电力有限公司建设分公司 A kind of model test pile foundation bearing capacity self-balancing test device and test method
CN111894051A (en) * 2020-07-31 2020-11-06 湖北工业大学 Reverse self-balancing model test device and test method for pile foundation bearing capacity
CN215947940U (en) * 2021-03-16 2022-03-04 广西岩土新技术有限公司 Double-load-box self-balancing test pile loading device
CN216664253U (en) * 2021-11-11 2022-06-03 中国建筑一局(集团)有限公司 Double-load-box test structure of ultra-long test pile

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105839678A (en) * 2016-04-11 2016-08-10 湖北工业大学 Improved pile foundation vertical bearing capacity test reverse self-balanced method and testing device
CN110453733A (en) * 2019-09-18 2019-11-15 国网安徽省电力有限公司建设分公司 A kind of model test pile foundation bearing capacity self-balancing test device and test method
CN111894051A (en) * 2020-07-31 2020-11-06 湖北工业大学 Reverse self-balancing model test device and test method for pile foundation bearing capacity
CN215947940U (en) * 2021-03-16 2022-03-04 广西岩土新技术有限公司 Double-load-box self-balancing test pile loading device
CN216664253U (en) * 2021-11-11 2022-06-03 中国建筑一局(集团)有限公司 Double-load-box test structure of ultra-long test pile

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王伟等: "双荷载箱自平衡法在大吨位荷载试桩中的应用", 《中国住宅设施》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117344807A (en) * 2023-10-20 2024-01-05 广州开发区建设工程检测中心有限公司 Vertical bearing capacity device for detecting foundation pile and detection method thereof

Also Published As

Publication number Publication date
CN115233752B (en) 2023-04-25

Similar Documents

Publication Publication Date Title
Gaaver Uplift capacity of single piles and pile groups embedded in cohesionless soil
CN105839678A (en) Improved pile foundation vertical bearing capacity test reverse self-balanced method and testing device
CN102943493B (en) Method for measuring internal force and deformation of precast pile
CN204590104U (en) A kind of bath scaled model experimental device of simulating self-balance testing pile method
CN108716225A (en) A kind of novel club-footed pile test device for multifunctional and method
CN115233752A (en) Reverse self-balancing pile testing method based on double pile body load boxes
CN111021440A (en) CPT integrated geotechnical packaging granular pile indoor model test device and method
CN103603381A (en) Detection device and detection method for buttress single-pile vertical uplift static load test
CN104652498B (en) Double-umbrella prestressed pipe pile sectioned dead load test method and device
CN113605467B (en) Pile foundation self-balancing test device with balance point compensation function and test method
CN115753338A (en) Composite bearing capacity test device and method based on power transmission tower anchor cable bearing platform
CN107014670B (en) Testing device for multi-directional horizontal bearing capacity of single pile under composite load
CN113389230A (en) Counter-force system suitable for pile foundation axial large-tonnage static load test
CN109778923B (en) Foundation pile buckling critical load test device and method
CN203594057U (en) Detecting device for vertical extraction-resistant static test of single pile through buttress method
US11591767B2 (en) Device and method for testing compression amount of pile body of rock-socketed cast-in-place pile
CN210737618U (en) Device for verifying internal force test result of foundation pile
CN205958379U (en) Rock stock up -pull testing arrangement
CN212248406U (en) Test device for simulating stress characteristic of bridge pier foundation
CN114965251A (en) Self-balancing concrete and rock friction coefficient measuring system and testing method
CN212275467U (en) Vertical resistance to compression static load test device of engineering stake
CN210342024U (en) Bidirectional counter-force beam uplift test pile device
CN110409519B (en) Device and method for testing bearing capacity of super-large-diameter end bearing pile
CN207092161U (en) A kind of foundation pile static-loading test device
CN105649124A (en) Static load testing device and method for testing bearing force of prestress pipe pile in layering manner

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant