CN115198646A - Method for erecting vehicle-running channel for constructing bridge - Google Patents

Method for erecting vehicle-running channel for constructing bridge Download PDF

Info

Publication number
CN115198646A
CN115198646A CN202210831140.8A CN202210831140A CN115198646A CN 115198646 A CN115198646 A CN 115198646A CN 202210831140 A CN202210831140 A CN 202210831140A CN 115198646 A CN115198646 A CN 115198646A
Authority
CN
China
Prior art keywords
jack
steel frame
frame body
prefabricated steel
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210831140.8A
Other languages
Chinese (zh)
Inventor
杨贵柏
范华猛
张崇喜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 19th Metallurgical Group Co ltd
Original Assignee
China 19th Metallurgical Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 19th Metallurgical Group Co ltd filed Critical China 19th Metallurgical Group Co ltd
Priority to CN202210831140.8A priority Critical patent/CN115198646A/en
Publication of CN115198646A publication Critical patent/CN115198646A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to the field of municipal engineering, in particular to a vehicle passage erecting method for constructing a bridge, which has low construction difficulty, short construction period, low cost and high safety, and comprises the following steps: a. a transverse vehicle-driving channel is arranged between the upright posts of the construction bridge, and a section steel column buttress and a jack buttress are firstly constructed under the ground; b. prefabricated steel frame bodies are prefabricated, the prefabricated steel frame bodies are lifted to the jacking elevation of the jacks by a flat-plate truck, then the prefabricated steel frame bodies are bound, firmly and safely transported to the site, four corners at the bottoms of the front unit and the rear unit are respectively placed on the jacks and are firmly clamped, and connection points of the prefabricated steel frame bodies are firmly welded; c. continuously jacking the prefabricated steel frame body to the scheme elevation through the jack, then fixing the prefabricated steel frame body with the section steel column installed between the section steel column buttresses, continuously erecting a scaffold to the bottom of the box girder on the prefabricated steel frame body, and completing erection. This scheme is particularly useful for among the vehicle driving passageway of municipal construction bridge erects.

Description

Method for erecting vehicle-running channel for constructing bridge
Technical Field
The invention relates to the field of municipal engineering, in particular to a method for erecting a vehicle running channel for constructing a bridge.
Background
A vehicle-driving channel erecting system crossing a construction bridge usually erects a plurality of rows of more densely-packed coil buckle type scaffolds at two sides of a vehicle-driving channel of a construction bridge span to bear box girder construction load transmitted by a plurality of layers of coil buckle type scaffolds erected at the upper part; the defects are that the disk buckle type scaffold body of the door-shaped opening is easy to deform and collapse, safety accidents are caused, the construction procedures are multiple, and the construction period is long. This method has plagued construction units. The invention discloses an urban underground road structure form and relates to the technical field of municipal engineering, and the invention is CN 202120254779.5. The underground road frame comprises an underground road frame, wherein the underground road frame comprises two vehicle traveling channels, a rescue channel and a ventilation device, partition walls are arranged on two sides of the rescue channel, a plurality of door openings are formed in the outer surfaces of the partition walls, the ventilation device comprises a plurality of air inlet pipes, a plurality of air outlet pipes, a plurality of exhaust pipes and a plurality of ventilation pipes, and exhaust fans are arranged in the exhaust pipes and the ventilation pipes. According to the invention, the air inlet pipe, the air outlet pipe, the exhaust pipe, the ventilation pipe and the exhaust fan are arranged, the exhaust fan works to suck external air into the ventilation pipe, the air is discharged into the vehicle passage through the air inlet pipe and works through the exhaust fan, and the air is sucked into the exhaust pipe and discharged into the external environment through matching with the air outlet pipe, so that the ventilation effect of the underground road is achieved. However, this underground road structure form cannot be used in a roadway crossing a construction bridge.
Disclosure of Invention
The invention aims to solve the technical problem of providing a method for erecting a vehicle running channel for constructing a bridge, which has low construction difficulty, short construction period, low cost and high safety.
The technical scheme adopted by the invention for solving the technical problem is as follows: the method for erecting the vehicle running passage for constructing the bridge comprises the following steps: a. a transverse vehicle-driving channel is arranged between the upright posts of the construction bridge, a section steel column buttress and a jack buttress are firstly constructed under the ground, a jack is arranged on the jack buttress, and then the road surface construction of the vehicle-driving channel is carried out; b. prefabricating a prefabricated steel frame body in advance, raising the prefabricated steel frame body to the pre-jacking elevation of the jack by using a flat-plate truck, then binding, firmly and safely transporting to the site, respectively transporting to a front on-site point and a rear on-site point of a vehicle passage area, respectively placing four corners at the bottoms of the front unit and the rear unit on the jack, firmly clamping, and firmly welding connection points of the front unit and the rear unit; c. continuously jacking prefabricated steel support body to scheme elevation through the jack, it is fixed with installation shaped steel stand between the shaped steel post buttress immediately under the prefabricated steel support body to continue to set up scaffold frame to the case roof beam bottom on the prefabricated steel support body, and accomplish and erect.
Furthermore, the jack buttress is a long-stroke jack buttress.
Further, the prefabricated steel frame body is a Bailey steel frame body unit.
Further, the jack is a long-stroke jack.
Furthermore, the scaffold is a high-disk-connected buckle scaffold.
The beneficial effects of the invention are: this scheme has solved the conventional vehicle access both sides and the top of taking a journey at the construction bridge span through the process step of optimizing the vehicle access erects, sets up several rows and several layers comparatively intensive dish knot formula scaffold body's construction consumptive material problem. Because the adoption takes bailey steel support body as the material of representative, realize the equipment of top elevation in advance to whole jacking targets in place, has realized the novel technical process that the passageway of going a vehicle was established fast, and this scheme does not warp and collapses, and is safe, with low costs. This scheme is particularly useful for among the vehicle driving passageway of municipal construction bridge erects.
Drawings
FIG. 1 is an elevation view of the pre-jacking elevation assembly of the Bailey steel frame unit of the present invention.
FIG. 2 is an elevation view of the bailey steel frame body integrally lifted in place.
FIG. 3 is a sectional view of the bailey steel frame body of the present invention integrally lifted to a proper position.
Fig. 4 is a sectional view of the construction molding of the running passage of the present invention.
Labeled as: the prefabricated steel frame comprises the ground 1, section steel column buttresses 2, jack buttresses 21, jacks 3, prefabricated steel frame bodies 4, bailey steel frame body units 41, running limiting piles 5, section steel upright columns 6, protective steel plates 7, an extended-section protective shed 71, a scaffold 8, buckling type scaffolds 81, upright columns 9, box girders 10, connecting points 11, pre-jacking height 12 and scheme elevation 121.
Detailed Description
The invention is further described below with reference to the accompanying drawings.
The method for erecting the vehicle running passage for the construction bridge shown in fig. 1, 2, 3 and 4 comprises the following steps: a. a transverse vehicle-driving channel is arranged between the upright posts 9 of the construction bridge, a section steel column buttress 2 and a jack buttress 21 are firstly constructed under the ground 1, a jack 3 is arranged on the jack buttress 21, and then the vehicle-driving channel pavement construction is carried out; b. the prefabricated steel frame body 4 is prefabricated, the prefabricated steel frame body 4 is lifted to a pre-jacking elevation 12 of the jack 3 by a flat-plate truck, then the prefabricated steel frame body 4 is bound, firmly and safely transported to the site, and is respectively transported to a front and a rear on-site points of a vehicle driving channel area, four corners at the bottom of the front and the rear units are respectively placed on the jack 3 and are firmly clamped, and a connecting point 11 of the front and the rear units is firmly welded; c. continuously jacking prefabricated steel frame body 4 to scheme elevation 121 through jack 3, it is fixed with installation shaped steel stand 6 between shaped steel column buttress 2 immediately under prefabricated steel frame body 4 to continue to set up scaffold 8 to box girder 10 bottom on prefabricated steel frame body 4, and accomplish and erect.
The supporting structure for implementing the erection method can be selected from a vehicle running channel arranged between paired stand columns 9, a section steel column buttress 2 and a jack buttress 21 are arranged between the stand columns 9, a jack 3 is arranged at the top of the jack buttress 21, a section steel stand column 6 is arranged at the top of the section steel column buttress 2, and prefabricated steel frame bodies 4 are arranged at the tops of the jack 3 and the section steel stand column 6. Generally, it is preferred that the jack 3 is a long-stroke jack. Generally, as shown in fig. 3, a box girder 10 is arranged at the top of the upright post 9, wherein a scaffold 8 is arranged between the preferable box girder 10 and the prefabricated steel frame body 4, so that the overall structural characteristics are fully utilized, the efficiency of building and using the scaffold 8 is ensured, and the construction efficiency is further improved. In order to further reduce the complexity of the construction, it is preferable that the scaffold 8 is an elevated plate button scaffold. In order to ensure the safety of subsequent use, the bottom of the prefabricated steel frame body 4 is preferably provided with a protective steel plate 7. Further, as shown in fig. 2, it is preferable that the protection steel plate 7 is provided with an extended section of a protection shed 71 at both ends in the direction of the traffic passage, thereby preventing the influence of the splashed construction materials on pedestrians and traffic. Preferably, prefabricated steel support body 4 is bailey steel support body to guarantee the security of high efficiency and the follow-up use of buildding. In order to prevent the collision of the traveling crane against the section steel columns 6, it is preferable that the travel limit piles 5 be provided between the section steel columns 6.
The invention has low construction difficulty, low cost and high safety, is particularly suitable for being used in a vehicle passage of a construction bridge, has obvious technical advantages and has wide market popularization prospect, and the ingenious structure is related.

Claims (5)

1. The method for erecting the vehicle passage for constructing the bridge is characterized by comprising the following steps of:
a. a transverse vehicle-driving channel is arranged between upright posts (9) of a construction bridge, a section steel column buttress (2) and a jack buttress (21) are firstly constructed under the ground (1), a jack (3) is arranged on the jack buttress (21), and then the vehicle-driving channel pavement construction is carried out;
b. prefabricating a prefabricated steel frame body (4) in advance, raising the prefabricated steel frame body (4) to a pre-jacking elevation (12) of a jack (3) by using a flat-plate truck, then binding firmly and safely transporting to the site, respectively transporting to a front and a rear on-site points of a vehicle driving channel area, respectively placing four corners at the bottoms of the front and the rear units on the jack (3) and firmly clamping, and firmly welding connection points (11) of the front and the rear units;
c. continuously jacking prefabricated steel frame body (4) to scheme elevation (121) through jack (3), it is fixed with installation shaped steel stand (6) between shaped steel column buttress (2) under prefabricated steel frame body (4) next to continue to set up scaffold (8) to case roof beam (10) bottom on prefabricated steel frame body (4), and accomplish and erect.
2. The method for erecting a roadway for constructing a bridge of claim 1, wherein: the jack buttress (21) is a long-stroke jack buttress.
3. The method for erecting a roadway for constructing a bridge of claim 1, wherein: the prefabricated steel frame body (4) is a bailey steel frame body unit (41).
4. A method for erecting a roadway for constructing a bridge as claimed in claim 1, 2 or 3, wherein: the jack (3) is a long-stroke jack.
5. A method for erecting a roadway for constructing a bridge as claimed in claim 1, 2 or 3, wherein: the scaffold (8) is a high-disk-connected buckle type scaffold.
CN202210831140.8A 2022-07-14 2022-07-14 Method for erecting vehicle-running channel for constructing bridge Pending CN115198646A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210831140.8A CN115198646A (en) 2022-07-14 2022-07-14 Method for erecting vehicle-running channel for constructing bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210831140.8A CN115198646A (en) 2022-07-14 2022-07-14 Method for erecting vehicle-running channel for constructing bridge

Publications (1)

Publication Number Publication Date
CN115198646A true CN115198646A (en) 2022-10-18

Family

ID=83581624

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210831140.8A Pending CN115198646A (en) 2022-07-14 2022-07-14 Method for erecting vehicle-running channel for constructing bridge

Country Status (1)

Country Link
CN (1) CN115198646A (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003027425A (en) * 2001-07-23 2003-01-29 Taisei Corp Method for constructing elevated type traffic route
CN102220741A (en) * 2011-04-14 2011-10-19 中铁二十局集团第六工程有限公司 Steel-concrete composite girder construction technology striding current lines and being parallel to existing lines
CN202577157U (en) * 2012-04-17 2012-12-05 中交三航局第三工程有限公司 Simple support arch bridge straining beam construction support system
CN103184722A (en) * 2013-03-18 2013-07-03 广州市市政工程机械施工有限公司 Large-span double-layer Bailey truss structure and construction method thereof
CN105133497A (en) * 2015-07-21 2015-12-09 杭州江润科技有限公司 Construction method for diagonal-span low-clearance road-on-duty multi-azimuth adjustable cast-in-place box beam support system
CN207091919U (en) * 2017-06-13 2018-03-13 浙江交工集团股份有限公司 A kind of cast-in-situ box girder door opening formula supporting construction
CN209855263U (en) * 2018-12-20 2019-12-27 中铁二十一局集团第二工程有限公司 Assembling construction support for steel truss girder crossing existing road
CN111719436A (en) * 2020-07-17 2020-09-29 温州市铁路与轨道交通投资集团有限公司 Construction system and construction method for urban railway cast-in-place box girder support in soft foundation area
CN211645998U (en) * 2018-11-30 2020-10-09 杭州江润科技有限公司 Upper-span active highway door opening support dismantling system
CN218712196U (en) * 2022-07-14 2023-03-24 中国十九冶集团有限公司 Supporting structure for erecting vehicle running channel of construction bridge

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003027425A (en) * 2001-07-23 2003-01-29 Taisei Corp Method for constructing elevated type traffic route
CN102220741A (en) * 2011-04-14 2011-10-19 中铁二十局集团第六工程有限公司 Steel-concrete composite girder construction technology striding current lines and being parallel to existing lines
CN202577157U (en) * 2012-04-17 2012-12-05 中交三航局第三工程有限公司 Simple support arch bridge straining beam construction support system
CN103184722A (en) * 2013-03-18 2013-07-03 广州市市政工程机械施工有限公司 Large-span double-layer Bailey truss structure and construction method thereof
CN105133497A (en) * 2015-07-21 2015-12-09 杭州江润科技有限公司 Construction method for diagonal-span low-clearance road-on-duty multi-azimuth adjustable cast-in-place box beam support system
CN207091919U (en) * 2017-06-13 2018-03-13 浙江交工集团股份有限公司 A kind of cast-in-situ box girder door opening formula supporting construction
CN211645998U (en) * 2018-11-30 2020-10-09 杭州江润科技有限公司 Upper-span active highway door opening support dismantling system
CN209855263U (en) * 2018-12-20 2019-12-27 中铁二十一局集团第二工程有限公司 Assembling construction support for steel truss girder crossing existing road
CN111719436A (en) * 2020-07-17 2020-09-29 温州市铁路与轨道交通投资集团有限公司 Construction system and construction method for urban railway cast-in-place box girder support in soft foundation area
CN218712196U (en) * 2022-07-14 2023-03-24 中国十九冶集团有限公司 Supporting structure for erecting vehicle running channel of construction bridge

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
史艳;吴梓敬;: "门式支墩贝雷梁在满堂支架中的应用", 科技创新与应用, no. 23, 31 July 2020 (2020-07-31) *

Similar Documents

Publication Publication Date Title
CN218712196U (en) Supporting structure for erecting vehicle running channel of construction bridge
CN114059825A (en) Structure of road protection shed crossing large flow under limited clearance and construction method thereof
CN209855263U (en) Assembling construction support for steel truss girder crossing existing road
CN109667432B (en) Assembly construction support for steel truss girder crossing existing road
CN115198646A (en) Method for erecting vehicle-running channel for constructing bridge
CN215887884U (en) Be applied to bailey frame steel trestle of deep basal pit construction
CN113775207B (en) Temporary door type passage design and construction method for building
CN102913007B (en) Steel reinforcement processing shed and construction method therefor
CN109797662A (en) Long span cast-in-situ box girder crosses over high-grade highway bracket and construction method
CN214005463U (en) Be applied to bridge and demolish protection rack in construction
CN114961338A (en) Temporary support method for top plate of PC (polycarbonate) assembly type engineering basement
CN210370098U (en) Full-assembly steel structure intelligent parking unit and combined structure thereof
CN113309008A (en) Steel case roof beam temporary support construction safety work platform
CN112523087A (en) A beam lifting station for beam slab erects
CN219010959U (en) Multistage bridge construction platform in V-shaped valley hard rock area
CN214329834U (en) Daylighting roof construction trolley system
CN219059794U (en) Road protective construction platform
CN219731676U (en) Safety channel for opening steel girder
CN219412609U (en) Temporary support system for shield tunnel segments
CN219753024U (en) Assembled double-door type temporary support for installing viaduct steel box girder
CN218346558U (en) Stand structure and inspection hole structure that subway vehicle base inspection was bored
CN215718762U (en) Support structure for synchronous construction of station and shield
CN215669045U (en) Temporary cover beam structure for bridge girder erection machine via hole
CN217949823U (en) Protective shed frame device for crossing existing railway on expressway
CN221095202U (en) Novel steel structure system with floor slab as horizontal support

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination