CN115075234B - Tubular pile joint and tubular pile construction method - Google Patents

Tubular pile joint and tubular pile construction method Download PDF

Info

Publication number
CN115075234B
CN115075234B CN202210696590.0A CN202210696590A CN115075234B CN 115075234 B CN115075234 B CN 115075234B CN 202210696590 A CN202210696590 A CN 202210696590A CN 115075234 B CN115075234 B CN 115075234B
Authority
CN
China
Prior art keywords
pile
piece
limiting
section
end plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202210696590.0A
Other languages
Chinese (zh)
Other versions
CN115075234A (en
Inventor
王浩
高兴
龙天宝
梁晓波
徐小明
周华杰
牛文克
宋文奇
高远
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING CHONGJIAN ENGINEERING CO LTD
China 22MCC Group Corp Ltd
Original Assignee
BEIJING CHONGJIAN ENGINEERING CO LTD
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING CHONGJIAN ENGINEERING CO LTD, China 22MCC Group Corp Ltd filed Critical BEIJING CHONGJIAN ENGINEERING CO LTD
Priority to CN202210696590.0A priority Critical patent/CN115075234B/en
Publication of CN115075234A publication Critical patent/CN115075234A/en
Application granted granted Critical
Publication of CN115075234B publication Critical patent/CN115075234B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • E02D5/523Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments
    • E02D5/526Connection means between pile segments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/04Guide devices; Guide frames
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • E02D13/08Removing obstacles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/20Placing by pressure or pulling power

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention belongs to the technical field of pile construction, and discloses a tubular pile joint and a tubular pile construction method. The lower extreme of connecting piece passes the lower end plate to in embedding lower festival stake, the upper end of connecting piece passes the upper end plate, in embedding the festival stake, is provided with spacing hole on the connecting piece. Be provided with the guide way on the upper segment stake, the guide way extends along the horizontal direction, and the upper end plate closing cap is in the notch of guide way, and the locating part sets up in the guide way to have dodge position and locking position, the locating part is located dodges the position time, and the connecting piece can pass the guide way, and in the embedding upper segment stake, afterwards, the locating part is by dodging position translation to locking position, in order to wear to locate the spacing downthehole of connecting piece. Through this tubular pile joint can connect two adjacent tubular piles about convenient and fast, need not the welding procedure, simplifies the construction step, improves whole construction quality, reduces construction cost.

Description

Tubular pile joint and tubular pile construction method
Technical Field
The invention relates to the technical field of pile construction, in particular to a tubular pile joint and a tubular pile construction method.
Background
Pile foundations are extremely important foundation forms of modern buildings and are widely applied to constructional engineering, traffic engineering, coastal engineering and ocean engineering. Compared with the common tubular pile, the bamboo joint pile has the advantages that the section is changeable, the friction resistance is larger compared with the tubular pile with the same pile diameter, the pulling resistance is stronger, and the resistance is generally improved by 10% -30% compared with the tubular pile with the same pile diameter.
When in construction, the upper bamboo joint pile and the lower bamboo joint pile are usually connected. In the prior art, after the construction of the lower section bamboo joint pile is completed, the pile is hung and planted on the upper section bamboo joint pile, and then, the upper bamboo joint pile and the lower bamboo joint pile are connected. The traditional welding process is adopted during connection, namely, the bottom end of the upper section bamboo joint pile is welded at the top end of the lower section bamboo joint pile. And after pile splicing of the upper bamboo joint pile and the lower bamboo joint pile is completed, subsequent procedures such as pile body centering and straightening, pile pressing (pile sinking) and pile conveying are carried out. The traditional mode of welding and fixing the upper bamboo joint pile and the lower bamboo joint pile is large in welding surface, long in operation time and uncontrollable in construction site quality, wastes a large amount of manpower and material resources and is high in construction cost.
Disclosure of Invention
The invention aims to provide a tubular pile joint and a tubular pile construction method, which can conveniently and rapidly connect two adjacent tubular piles, simplify construction procedures, improve overall construction quality and reduce construction cost.
To achieve the purpose, the invention adopts the following technical scheme:
in a first aspect, a tubular pile joint is provided for connecting adjacent upper section stake and lower section stake, the bottom surface of upper section stake is provided with the upper end plate, the top surface of lower section stake is provided with the lower end plate, tubular pile joint includes:
the lower end of the connecting piece penetrates through the lower end plate and is embedded into the lower section pile, the upper end of the connecting piece penetrates through the upper end plate and is embedded into the upper section pile, and a limiting hole is formed in the connecting piece;
the upper end plate seals the notch of the guide groove, and the limiting piece is arranged in the guide groove and is provided with an avoidance position and a locking position;
when the limiting piece is located at the avoiding position, the connecting piece can penetrate through the guide groove and be embedded into the upper section pile, and the limiting piece can translate from the avoiding position to the locking position so as to penetrate through the limiting hole.
As the preferable scheme of the tubular pile joint provided by the invention, the upper section pile is internally provided with the embedded hole communicated with the guide groove, the embedded hole is used for penetrating the connecting piece, the top wall of the embedded hole is connected with the elastic stop piece, the elastic stop piece can extend out of the embedded hole so as to stop the limiting piece at the avoiding position, and the connecting piece can compress the elastic stop piece so as to release the limiting piece.
As a preferable scheme of the tubular pile joint, the elastic stop piece comprises a first elastic piece and a stop piece which are connected, one end of the first elastic piece, which is far away from the stop piece, is connected to the top wall of the embedded hole, and the stop piece at least partially extends out of the embedded hole so as to stop the stop piece.
As the preferable scheme of the tubular pile joint provided by the invention, the limiting part comprises a limiting body and a protruding part protruding on the limiting body, the guide groove comprises a large groove section matched with the limiting body and a small groove section matched with the protruding part, stop steps are respectively formed on two opposite sides of the small groove section on the upper section pile, and the stop steps are used for stopping one side of the elastic stop part, which is opposite to the limiting part.
As the preferable scheme of the tubular pile joint provided by the invention, the cross section of the limiting body and the cross section of the protruding part are rectangular, and the cross section of the protruding part is smaller than the cross section of the limiting body.
As the preferable scheme of the tubular pile joint provided by the invention, a second elastic piece is arranged between the limiting piece and the groove wall of the guide groove, the expansion direction of the second elastic piece is the same as the translation direction of the limiting piece, and the limiting piece can translate from the avoiding position to the locking position under the action of the elasticity of the second elastic piece.
As the preferable scheme of the tubular pile joint provided by the invention, the lower section pile is embedded with the fixing piece, the fixing piece is positioned below the lower end plate, and the lower end of the connecting piece is in threaded connection with the fixing piece.
As the preferable scheme of the tubular pile joint provided by the invention, the fixing piece comprises a fixing sleeve, the bottom surface of the fixing sleeve is closed, a connecting flange is arranged at the top end opening of the fixing sleeve along the circumferential direction, the connecting flange is connected with the lower end plate, and an internal thread structure for connecting the connecting piece is arranged in the fixing sleeve.
As the preferable scheme of the tubular pile joint provided by the invention, the upper section pile is embedded with the installation box body, the guide groove is arranged on the installation box body, the upper end of the connecting piece is embedded into the installation box body, and the installation box body is made of metal materials.
In a second aspect, there is provided a tubular pile construction method, constructed using the tubular pile joint as described above, comprising the steps of:
positioning the pile machine, and aligning the center of a clamping opening of the pile machine to the center of the pile position;
pile detection to remove obstacles;
the lower section pile is hoisted and inserted in place;
the upper section pile and the lower section pile are connected through the pipe pile joint;
centering and straightening the upper section pile and the lower section pile, and coating sealing materials at the connection position of the upper section pile and the lower section pile;
and (5) pile sinking and pile feeding under static pressure.
The invention has the beneficial effects that:
the invention provides a tubular pile joint which is used for connecting an adjacent upper section pile and a lower section pile, wherein an upper end plate is arranged on the bottom surface of the upper section pile, a lower end plate is arranged on the top surface of the lower section pile, and the tubular pile joint comprises a connecting piece and a limiting piece. The lower extreme of connecting piece passes the lower end plate to in embedding lower festival stake, the upper end of connecting piece passes the upper end plate, in embedding the festival stake, is provided with spacing hole on the connecting piece. Be provided with the guide way on the upper segment stake, the guide way extends along the horizontal direction, and the upper end plate closing cap is in the notch of guide way, and the locating part sets up in the guide way to have dodge position and locking position, the locating part can be by dodging position translation to locking position. When connecting section pile and lower section pile, at first with the lower extreme embedding of connecting piece in the section pile down, at this moment, the locating part is located dodges the position, and it can dodge out the connecting piece and stretch into the passageway in the section pile of going up, so that the connecting piece can pass the guide way, and it is inside to embed section pile smoothly, afterwards, the locating part translates to the locking position by dodging the position, with wear to locate the spacing downthehole of connecting piece, thereby the locking connecting piece, the section pile is unable horizontal migration relatively lower section pile this moment, also unable vertical migration, thereby the butt joint of section pile and lower section pile has been realized and is fixed. Compared with the construction mode of connecting an upper section pile and a lower section pile by welding in the prior art, the tubular pile joint can conveniently and rapidly connect the upper tubular pile and the lower tubular pile adjacently without welding procedures, so that the construction steps are simplified, the overall construction quality is improved, and the construction cost is reduced.
The invention also provides a tubular pile construction method, which is characterized in that the tubular pile joint is used for connecting the adjacent upper section pile and lower section pile, the working procedure is simple, the construction efficiency is high, welding is not needed, the construction quality is good, centering and straightening of the upper section pile and the lower section pile are convenient, and the subsequent steps of coating sealing materials and the like at the connecting position of the upper section pile and the lower section pile are convenient.
Drawings
FIG. 1 is a schematic view of an installation box provided in an embodiment of the present invention in an upper pile section;
fig. 2 is a schematic structural view of a tubular pile joint according to an embodiment of the present invention;
FIG. 3 is a schematic view of a connector according to an embodiment of the present invention;
FIG. 4 is a schematic view of a guide groove on a mounting box according to an embodiment of the present invention;
fig. 5 is a front view of a stop member according to an embodiment of the present invention.
Fig. 6 is a side view of a stop member provided in accordance with an embodiment of the present invention.
Fig. 7 is a top view of a stop member according to an embodiment of the present invention.
In the figure:
100. a pile is arranged on the upper section; 200. a lower section pile; 101. an upper end plate; 201. a lower end plate;
1. a connecting piece; 2. a limiting piece; 3. installing a box body; 4. an elastic stopper; 5. a second elastic member; 6. a fixing member;
11. a limiting hole;
21. a limit body; 22. a boss;
31. a guide groove; 32. an insertion hole; 311. a large trough section; 312. a small groove section; 313. a stop step;
41. a first elastic member; 42. a stopper;
61. a fixed sleeve; 62. and a connecting flange.
Detailed Description
The invention is described in further detail below with reference to the drawings and examples. It is to be understood that the specific embodiments described herein are merely illustrative of the invention and are not limiting thereof. It should be further noted that, for convenience of description, only some, but not all of the structures related to the present invention are shown in the drawings.
In the description of the present invention, unless explicitly stated and limited otherwise, the terms "connected," "connected," and "fixed" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally formed; can be mechanically or electrically connected; can be directly connected or indirectly connected through an intermediate medium, and can be communicated with the inside of two elements or the interaction relationship of the two elements. The specific meaning of the above terms in the present invention will be understood in specific cases by those of ordinary skill in the art.
In the present invention, unless expressly stated or limited otherwise, a first feature "above" or "below" a second feature may include both the first and second features being in direct contact, as well as the first and second features not being in direct contact but being in contact with each other through additional features therebetween. Moreover, a first feature being "above," "over" and "on" a second feature includes the first feature being directly above and obliquely above the second feature, or simply indicating that the first feature is higher in level than the second feature. The first feature being "under", "below" and "beneath" the second feature includes the first feature being directly under and obliquely below the second feature, or simply means that the first feature is less level than the second feature.
In the description of the present embodiment, the terms "upper", "lower", "left", "right", and the like are orientation or positional relationships based on those shown in the drawings, merely for convenience of description and simplicity of operation, and do not indicate or imply that the apparatus or elements referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus should not be construed as limiting the invention. Furthermore, the terms "first," "second," and the like, are used merely for distinguishing between descriptions and not for distinguishing between them.
As shown in fig. 1 and 2, the present embodiment provides a pipe pile joint for connecting adjacent upper section piles 100 and lower section piles 200. The bottom surface of the upper section pile 100 is provided with an upper end plate 101, the top surface of the lower section pile 200 is provided with a lower end plate 201, and the tubular pile joint comprises a connecting piece 1 and a limiting piece 2.
Referring to fig. 2, the lower end of the connector 1 passes through the lower end plate 201 and is embedded in the lower section pile 200, and the upper end of the connector 1 passes through the upper end plate 101 and is embedded in the upper section pile 100. Referring to fig. 3, the connector 1 is provided with a limiting hole 11. Be provided with guide slot 31 on the upper segment stake 100, guide slot 31 extends along the horizontal direction, and upper end plate 101 closing cap is in the notch of guide slot 31, and locating part 2 sets up in guide slot 31 to have dodge position and locking position, locating part 2 can be by dodging the position translation to the locking position.
When connecting the upper section pile 100 and the lower section pile 200, the lower end of the connecting member 1 is first inserted into the lower section pile 200. At this time, the limiting member 2 is located at the avoiding position, and can avoid the passage of the connecting member 1 extending into the upper pile 100, so that the connecting member 1 can pass through the guiding groove 31 and be smoothly embedded into the upper pile 100. Subsequently, the limiting piece 2 translates from the avoiding position to the locking position so as to penetrate through the limiting hole 11 of the connecting piece 1, thereby locking the connecting piece 1, and at the moment, the upper section pile 100 cannot horizontally move relative to the lower section pile 200 and cannot vertically move, so that the butt joint and fixation of the upper section pile 100 and the lower section pile 200 are realized.
Compared with the construction mode of connecting the upper section pile 100 and the lower section pile 200 by welding in the prior art, the pipe pile joint can conveniently and rapidly connect the upper pipe pile and the lower pipe pile adjacently without welding procedures, so that the construction steps are simplified, the overall construction quality is improved, and the construction cost is reduced.
The upper end plate 101 and the lower end plate 201 are usually made of steel plates, the upper section pile 100 and the lower section pile 200 are formed by concrete pouring, before pouring, the upper end plate 101 and the lower end plate 201 are arranged on the framework structures of the upper section pile 100 and the lower section pile 200, after pouring and forming, the concrete of the upper section pile 100 and the upper end plate 101 are formed into a whole, and the lower section pile 200 and the concrete and the lower end plate 201 are formed into a whole.
An insertion hole 32 communicating with the guide groove 31 is provided in the upper section pile 100, and the insertion hole 32 is used for penetrating the connecting piece 1, that is, the upper end of the connecting piece 1 penetrates through the guide groove 31 and extends into the insertion hole 32.
Referring to fig. 1 and 2, the upper section pile 100 is embedded with a mounting box body 3, and the mounting box body 3 is made of a metal material. Because the upper pile 100 made of concrete is inconvenient to form the guide groove 31 and the hole allowing the connecting piece 1 to penetrate (i.e. the embedded hole 32), the installation box body 3 made of metal material is arranged inside the upper pile 100, and the guide groove 31 and the embedded hole 32 are formed on the installation box body 3, so that the operation is more convenient and the implementation is easier. Optionally, the mounting box 3 is made of steel material.
Illustratively, as with the upper end plate 101, the mounting box 3 may be integrally formed with the concrete structure of the upper section pile 100 at the stage of casting the upper section pile 100.
Referring to fig. 2, an elastic stopper 4 is connected to the top wall of the insertion hole 32, and the elastic stopper 4 can protrude out of the insertion hole 32 to stop the stopper 2 at the escape position so that the connector 1 passes through the guide groove 31 and protrudes into the insertion hole 32. During the extension of the connecting element 1 into the insertion hole 32, the connecting element 1 compresses the elastic stop 4 to release the stop 2. When the connecting piece 1 moves to the position where the limiting hole 11 is aligned with the limiting piece 2, the limiting piece 2 can penetrate into the limiting hole 11.
Specifically, referring to fig. 2, the elastic stopper 4 includes a first elastic member 41 and a stopper 42 connected, one end of the first elastic member 41 remote from the stopper 42 is connected to the top wall of the insertion hole 32, and the stopper 42 at least partially protrudes out of the insertion hole 32 to stop the stopper 2. Referring to the orientation shown in fig. 2, the first elastic member 41 is naturally configured such that the right side of the stopper 42 serves to stop the stopper 2, and the left side of the stopper 42 can be brought into contact with the wall surface of the mounting case 3 to ensure that the stopper 2 is stably at the escape position.
Illustratively, the first elastic member 41 is a spring, and the stopper 42 is a cylindrical steel plate having a diameter slightly smaller than that of the insertion hole 32.
Referring to fig. 2, a second elastic member 5 is disposed between the limiting member 2 and the groove wall of the guide groove 31, and the expansion direction of the second elastic member 5 is the same as the translation direction of the limiting member 2, and the limiting member 2 can translate from the avoiding position to the locking position under the action of the elastic force of the second elastic member 5. When the stopper 42 stops the stopper 2, the second elastic member 5 is in a compressed state, and when the limiting hole 11 of the connecting member 1 is aligned with the stopper 2, the stopper 2 can move leftwards under the elastic action of the second elastic member 5 so as to penetrate into the limiting hole 11. The second elastic member 5 is illustratively a spring.
Referring to fig. 5, 6 and 7, the limiting member 2 includes a limiting body 21 and a protruding portion 22 protruding from the limiting body 21, wherein the cross section of the limiting body 21 and the cross section of the protruding portion 22 are rectangular, and the cross section of the protruding portion 22 is smaller than the cross section of the limiting body 21. Correspondingly, referring to fig. 4, the guide groove 31 includes a large groove section 311 cooperating with the limit body 21 and a small groove section 312 cooperating with the boss 22, the cross sections of the large groove section 311 and the small groove section 312 are also rectangular, and the cross section area of the small groove section 312 is smaller than the cross section area of the large groove section 311. The two opposite sides of the small groove section 312 on the mounting box body 3 are respectively provided with a stop step 313, and the stop step 313 is used for stopping one side of the elastic stop piece 4, which is opposite to the limiting piece 2.
In this embodiment, the first elastic member 41 is in a natural state, and the stop member 42 below the first elastic member extends out of the insertion hole 32, and the top surface of the first elastic member is flush with the bottommost end of the insertion hole 32. At this time, the left side of the stopper 42 is limited by the stop steps 313 at both sides of the small groove section 312, so that the stopper 42 can reliably stop the stopper 2 at the right side, and the stopper 2 is ensured to be at a position of avoiding the connecting member 1.
Further, the protruding portion 22 is protruding at the middle position of the top of the limiting body 21, and the small groove section 312 is located at the middle position of the top of the large groove section 311.
Referring to fig. 2, the lower section pile 200 is embedded with a fixing member 6, the fixing member 6 is located below the lower end plate 201, and the lower end of the connecting member 1 passes through the lower end plate 201 and is in threaded connection with the fixing member 6, so that the connection is firm and convenient. Further, the fixing member 6 includes a fixing sleeve 61, the bottom surface of the fixing sleeve 61 is closed, a connecting flange 62 is provided at the top end opening of the fixing sleeve 61 in the circumferential direction, the connecting flange 62 is connected with the lower end plate 201, and an internal thread structure for connecting the connecting member 1 is provided in the fixing sleeve 61. The fixing member 6 is made of steel material, and can be poured into the lower pile 200. The lower pile 200 of the concrete structure cannot be provided with the threaded hole, so that the fixing piece 6 which is made of steel materials and provided with the threaded hole is embedded in the lower pile, and the connection with the connecting piece 1 is facilitated. By providing the connecting flange 62, the attachment of the fixing member 6 to the lower end plate 201 can be facilitated, both of which can be welded or fastened by threaded fasteners.
The embodiment also provides a tubular pile construction method, which adopts the tubular pile joint for construction, and comprises the following steps:
s1, positioning a pile machine, and enabling the center of a clamping opening of the pile machine to be aligned with the center of a pile position;
s2, pile detection is carried out to remove obstacles;
s3, hoisting the lower section pile 200 to insert the pile into place;
s4, connecting the upper section pile 100 and the lower section pile 200 through tubular pile joints;
s5, centering and straightening the upper section pile 100 and the lower section pile 200, and coating sealing materials at the connection position of the upper section pile 100 and the lower section pile 200;
s6, pile sinking and pile feeding under static pressure.
In step S5, the sealing material may be epoxy. The upper section pile 100 and the lower section pile 200 are mechanically connected through the pipe pile joint and are sealed by a sealing material, so that the upper section pile 100 and the lower section pile 200 are formed into a continuous and complete whole, the erosion of the external environment can be resisted, and the durability is higher than that of a common pipe pile.
According to the tubular pile construction method provided by the embodiment, the tubular pile joint is used for connecting the adjacent upper section pile 100 and the lower section pile 200, the working procedure is simple, the construction efficiency is high, welding is not needed, the construction quality is good, centering and straightening of the upper section pile 100 and the lower section pile 200 are facilitated, and the subsequent steps of coating sealing materials on the connecting positions of the upper section pile 100 and the lower section pile 200 are facilitated.
It is to be understood that the above examples of the present invention are provided for clarity of illustration only and are not limiting of the embodiments of the present invention. Various obvious changes, rearrangements and substitutions can be made by those skilled in the art without departing from the scope of the invention. It is not necessary here nor is it exhaustive of all embodiments. Any modification, equivalent replacement, improvement, etc. which come within the spirit and principles of the invention are desired to be protected by the following claims.

Claims (6)

1. A tubular pile joint for connecting adjacent upper section pile (100) and lower section pile (200), characterized in that, the bottom surface of upper section pile (100) is provided with upper end plate (101), the top surface of lower section pile (200) is provided with lower end plate (201), the tubular pile joint includes:
the lower end of the connecting piece (1) penetrates through the lower end plate (201) and is embedded into the lower section pile (200), the upper end of the connecting piece (1) penetrates through the upper end plate (101) and is embedded into the upper section pile (100), and a limiting hole (11) is formed in the connecting piece (1);
the upper pile (100) is provided with a guide groove (31), the guide groove (31) extends along the horizontal direction, the upper end plate (101) covers the notch of the guide groove (31), and the limiting piece (2) is arranged in the guide groove (31) and is provided with an avoidance position and a locking position;
when the limiting piece (2) is positioned at the avoiding position, the connecting piece (1) can penetrate through the guide groove (31) and be embedded into the upper section pile (100), and the limiting piece (2) can translate from the avoiding position to the locking position so as to penetrate into the limiting hole (11);
an embedded hole (32) communicated with the guide groove (31) is formed in the upper section pile (100), the embedded hole (32) is used for penetrating the connecting piece (1), the top wall of the embedded hole (32) is connected with an elastic stop piece (4), the elastic stop piece (4) can extend out of the embedded hole (32) so as to stop the limiting piece (2) at the avoidance position, and the connecting piece (1) can compress the elastic stop piece (4) so as to release the limiting piece (2);
the elastic stop piece (4) comprises a first elastic piece (41) and a stop piece (42) which are connected, one end of the first elastic piece (41) away from the stop piece (42) is connected to the top wall of the embedded hole (32), and the stop piece (42) at least partially extends out of the embedded hole (32) to stop the limiting piece (2);
the limiting piece (2) comprises a limiting body (21) and a protruding portion (22) protruding on the limiting body (21), the guide groove (31) comprises a large groove section (311) matched with the limiting body (21) and a small groove section (312) matched with the protruding portion (22), stop steps (313) are respectively formed on two opposite sides of the small groove section (312) of the upper section pile (100), and the stop steps (313) are used for stopping one side, opposite to the limiting piece (2), of the elastic stop piece (4);
the cross section of the limiting body (21) and the cross section of the protruding portion (22) are rectangular, and the cross section of the protruding portion (22) is smaller than the cross section of the limiting body (21).
2. The tubular pile joint according to claim 1, characterized in that a second elastic member (5) is arranged between the limiting member (2) and the groove wall of the guide groove (31), the extending and contracting direction of the second elastic member (5) is the same as the translating direction of the limiting member (2), and the limiting member (2) can translate from the avoiding position to the locking position under the action of the elastic force of the second elastic member (5).
3. The tubular pile joint according to claim 1, characterized in that a fixing piece (6) is embedded in the lower section pile (200), the fixing piece (6) is located below the lower end plate (201), and the lower end of the connecting piece (1) is in threaded connection with the fixing piece (6).
4. A tubular pile joint according to claim 3, characterized in that the fixing member (6) comprises a fixing sleeve (61), the bottom surface of the fixing sleeve (61) is closed, a connecting flange (62) is circumferentially arranged at the top end opening of the fixing sleeve (61), the connecting flange (62) is connected with the lower end plate (201), and an internal thread structure for connecting the connecting member (1) is arranged in the fixing sleeve (61).
5. A tubular pile joint according to any one of claims 1-3, characterized in that the upper pile (100) is embedded with an installation box body (3), the guide groove (31) is arranged on the installation box body (3), the upper end of the connecting piece (1) is embedded into the installation box body (3), and the installation box body (3) is made of metal materials.
6. A method of pipe pile construction, characterised in that the construction is carried out using a pipe pile joint according to any one of claims 1 to 5, comprising the steps of:
positioning the pile machine, and aligning the center of a clamping opening of the pile machine to the center of the pile position;
pile detection to remove obstacles;
the lower section pile (200) is used for hoisting the pile inserting in place;
connecting the upper section pile (100) and the lower section pile (200) by the tubular pile joint;
the upper section pile (100) and the lower section pile (200) are aligned in a centering way, and sealing materials are coated at the connecting position of the upper section pile (100) and the lower section pile (200);
and (5) pile sinking and pile feeding under static pressure.
CN202210696590.0A 2022-06-20 2022-06-20 Tubular pile joint and tubular pile construction method Active CN115075234B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210696590.0A CN115075234B (en) 2022-06-20 2022-06-20 Tubular pile joint and tubular pile construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210696590.0A CN115075234B (en) 2022-06-20 2022-06-20 Tubular pile joint and tubular pile construction method

Publications (2)

Publication Number Publication Date
CN115075234A CN115075234A (en) 2022-09-20
CN115075234B true CN115075234B (en) 2023-10-20

Family

ID=83253187

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210696590.0A Active CN115075234B (en) 2022-06-20 2022-06-20 Tubular pile joint and tubular pile construction method

Country Status (1)

Country Link
CN (1) CN115075234B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101429768A (en) * 2008-11-28 2009-05-13 湖南省第二工程有限公司 Pre-stress high-strength concrete pipe pile static-pressure construction method
CN102409673A (en) * 2011-08-18 2012-04-11 李宏涛 Elastic pin type mechanical quick connector for connecting prestressed concrete pipe piles
CN203782695U (en) * 2014-03-03 2014-08-20 重庆电子工程职业学院 Reinforced tube pile concrete structure
CN208899474U (en) * 2018-09-21 2019-05-24 苏州安省建筑设计有限公司 A kind of anti-floating pile pile extension connection structure for building
CN110016913A (en) * 2019-05-23 2019-07-16 青岛理工大学 Meshing type tubular pile quick joint structure
CN110670581A (en) * 2019-10-25 2020-01-10 南京金宸建筑设计有限公司 Bolt type connecting structure for prefabricated hollow uplift pile
CN214301718U (en) * 2020-12-16 2021-09-28 河北全通建材有限公司 Anti-corrosion easily-spliced tubular pile
CN214832618U (en) * 2021-07-05 2021-11-23 江苏苏南建设集团有限公司 Uplift pile capable of quickly connecting pile

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FI128431B (en) * 2018-11-07 2020-05-15 Leimet Oy Pile joint

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101429768A (en) * 2008-11-28 2009-05-13 湖南省第二工程有限公司 Pre-stress high-strength concrete pipe pile static-pressure construction method
CN102409673A (en) * 2011-08-18 2012-04-11 李宏涛 Elastic pin type mechanical quick connector for connecting prestressed concrete pipe piles
CN203782695U (en) * 2014-03-03 2014-08-20 重庆电子工程职业学院 Reinforced tube pile concrete structure
CN208899474U (en) * 2018-09-21 2019-05-24 苏州安省建筑设计有限公司 A kind of anti-floating pile pile extension connection structure for building
CN110016913A (en) * 2019-05-23 2019-07-16 青岛理工大学 Meshing type tubular pile quick joint structure
CN110670581A (en) * 2019-10-25 2020-01-10 南京金宸建筑设计有限公司 Bolt type connecting structure for prefabricated hollow uplift pile
CN214301718U (en) * 2020-12-16 2021-09-28 河北全通建材有限公司 Anti-corrosion easily-spliced tubular pile
CN214832618U (en) * 2021-07-05 2021-11-23 江苏苏南建设集团有限公司 Uplift pile capable of quickly connecting pile

Also Published As

Publication number Publication date
CN115075234A (en) 2022-09-20

Similar Documents

Publication Publication Date Title
CN115075234B (en) Tubular pile joint and tubular pile construction method
CN111485634A (en) Novel prefabricated part wall-column connecting structure and mounting method thereof
CN115288206A (en) Settlement joint sealing structure and construction method thereof
CN112112156A (en) Tubular pile connecting device and connecting method
CN113187668B (en) Equipment hoisting and grouting installation method for wind power generation mixed tower
CN110485577A (en) Precast wall body mounting structure
CN111997204B (en) Transverse position-adjustable assembled vertical component connecting structure and construction method thereof
CN212612906U (en) Prefabricated assembled escape canal
CN113756471B (en) Connecting structure of thin-wall steel concrete shear wall and lower steel reinforced concrete shear wall
CN213596972U (en) Prestressed concrete pipe pile joint
CN110453690B (en) Recyclable foundation pit pile anchor supporting structure and construction method
CN115369857B (en) Vertical connecting structure of pre-buried spiral lock type prefabricated underground continuous wall
CN214383920U (en) Environment-friendly tubular pile with stake point
CN216553937U (en) Conduit sealing device
CN115387326B (en) Curved bolt connection type prefabricated underground continuous wall
CN215857839U (en) Underground combined structure
CN218437009U (en) Sleeve and precast pile
CN219137777U (en) Device for controlling tubular pile to float upwards
CN114250770B (en) Mechanical connecting joint of end-buckling type precast concrete anti-pulling pipe pile
CN218667650U (en) Intelligent articulated well wall working well construction system
CN214363449U (en) Corrosion-resistant bamboo joint pile
CN114411704B (en) Assembled precast concrete square pile
CN212835359U (en) A installation section of thick bamboo for stake attach fitting
CN218758299U (en) New-type underground continuous wall reinforcing bar device of plugging into
CN214993749U (en) Quick connecting structure of prestressed concrete precast pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant