CN114991818A - Advanced grouting construction method for tunnel penetrating active fault - Google Patents

Advanced grouting construction method for tunnel penetrating active fault Download PDF

Info

Publication number
CN114991818A
CN114991818A CN202210541970.7A CN202210541970A CN114991818A CN 114991818 A CN114991818 A CN 114991818A CN 202210541970 A CN202210541970 A CN 202210541970A CN 114991818 A CN114991818 A CN 114991818A
Authority
CN
China
Prior art keywords
grouting
gradient
tunnel
advanced
area
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210541970.7A
Other languages
Chinese (zh)
Other versions
CN114991818B (en
Inventor
陶志刚
毛玉铤
丁佳旭
何满潮
孙晓明
石富坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology Beijing CUMTB
Original Assignee
China University of Mining and Technology Beijing CUMTB
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology Beijing CUMTB filed Critical China University of Mining and Technology Beijing CUMTB
Priority to CN202210541970.7A priority Critical patent/CN114991818B/en
Publication of CN114991818A publication Critical patent/CN114991818A/en
Application granted granted Critical
Publication of CN114991818B publication Critical patent/CN114991818B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention provides an advanced grouting construction method for a tunnel penetrating active fault, which comprises the following steps: step 1, detecting a surrounding rock area, determining a grouting reinforcement area, and performing grouting design; step 2, spraying a concrete cover, and marking drilling point positions of a first gradient grouting area; step 3, implementing a first gradient drilling operation and a first gradient grouting operation; step 4, implementing a second gradient detection drilling operation, and checking a first gradient grouting result; step 5, implementing second gradient drilling operation, implementing second gradient grouting operation, and implementing middle and lower step anchor rod and anchor cable installation operation; step 6, after the advanced grouting of the first gradient grouting area and the second gradient grouting area is completed, carrying out mounting operation on the anchor rod and the anchor cable of the full-section anchor rod; and 7, constructing a secondary lining structure to complete the supporting operation of the tunnel. The advanced grouting construction method for the tunnel penetrating active fault enables the tunnel to be more stable, so that the safety of the tunnel and the safety of constructors are guaranteed.

Description

Advanced grouting construction method for tunnel penetrating active fault
Technical Field
The invention belongs to the technical field of advanced grouting of tunnels, and particularly relates to an advanced grouting technology for a tunnel penetrating active fault.
Background
In the tunneling process, water damage, surrounding rock breakage, serious active fault and the like can seriously affect the tunnel construction quality and the construction progress. The situation that surrounding rocks are seriously broken due to active faults often occurs, and in order to solve the influence caused by the broken surrounding rocks and other reasons, the prior art adopts an advanced grouting reinforcement technology to advance reinforce un-excavated rock mass above the front of a tunnel face so as to ensure the tunnel construction quality and the construction progress; the prior art has certain drawbacks.
For example: the main defect of the advanced small conduit grouting technology is that the conduit is short in length and cannot support active faults and severely broken surrounding rocks. Because the length of the conduit is not suitable to be too long, the range of the supporting function of the technology is very small, and the supporting range required by the broken surrounding rock cannot be formed.
The main disadvantage of the forward sectional grouting technology is that for deep hole grouting, the working efficiency of the technology is too low, and the working cycle continuation is seriously affected. Since the method is to drill a distance and then to perform grouting for a distance, and the distance is used for forming a stable structure and then the grouting for the next cycle is performed, the working efficiency is seriously affected.
The main defects of the drill rod backward type advanced grouting technology are that as the slurry is filled in the hole between the drill rod and the drill hole, the drill rod is tightly held and the drill bit is clamped after solidification (the diameter of the drill bit is larger than that of the drill rod), a high-power and high-torque drill unit head is required to realize backward movement of the drill rod, repeated rotation and hammering are carried out, the slurry solidified body is broken by vibration and then pulled out, the requirement on equipment is high, the abrasion is large, the maintenance and replacement cost of key parts such as a spline shaft in the unit head is expensive, and the risk of backward escaping failure exists in the process of deep hole grouting which is larger than 20 m.
The above advanced grouting techniques all face one of the most important disadvantages: under the condition that the surrounding rock is broken due to the active fault, effective grouting reinforcement can not be carried out on the surrounding rock through one-time grouting, repeated grouting reinforcement is needed for many times, the working efficiency is greatly reduced, and the grouting cost is increased.
Therefore, there is a need to provide an improved solution to the above-mentioned deficiencies of the prior art.
Disclosure of Invention
The invention aims to provide an advanced grouting construction method for a tunnel penetrating active fault, which at least solves the problems of low working efficiency, high grouting cost and the like of the existing grouting technology.
In order to achieve the above purpose, the invention provides the following technical scheme:
a construction method for advanced grouting of a tunnel penetrating active fault comprises the following steps:
step 1, detecting a tunnel broken surrounding rock area, determining a grouting reinforcement area, and performing grouting design; the grouting reinforcement area comprises a first gradient grouting area and a second gradient grouting area, and the grouting reinforcement area is positioned at the peripheral position in front of the tunnel face;
step 2, spraying a concrete cover on the tunnel face of the tunnel, manufacturing an artificial grout stopping wall, and marking drilling point positions required by a first gradient grouting area on the artificial grout stopping wall;
step 3, implementing a first gradient drilling operation and a first gradient grouting operation;
step 4, after the first gradient grouting is finished, implementing second gradient detection drilling operation, drilling a hole to the first gradient grouting area through the second gradient detection, and checking a first gradient grouting result;
step 5, implementing second gradient drilling operation, implementing second gradient grouting operation, and simultaneously implementing middle and lower step anchor rod and anchor cable installation operation;
step 6, after the advanced grouting of the first gradient grouting area and the second gradient grouting area is completed, the mounting operation of the anchor rod and the anchor cable of the full-section anchor rod is carried out;
and 7, drilling a secondary lining structure to complete the supporting operation of the tunnel.
According to the construction method for the advanced grouting of the tunnel penetrating active fault, preferably, the first gradient grouting area is positioned at the front periphery of the tunnel face; the second gradient grouting area is positioned at the periphery of the first gradient grouting area.
In the advanced grouting construction method for a tunnel-through active fault as described above, preferably, the first gradient grouting region and the second gradient grouting region are staggered from each other in the front-rear direction, the second gradient grouting region is advanced from the first gradient grouting region, and the second gradient grouting region and the first gradient grouting region have an overlapping region in the vertical direction.
In the construction method for advanced grouting of the tunnel through active fault, preferably, the grouting design includes determining a grouting range, determining a first gradient grouting length and a second gradient grouting length, a grout diffusion radius, drilling parameters, grouting parameters and grouting material model selection.
In the construction method of the advanced grouting for the tunnel penetrating active fault, preferably, the drilling angle is alpha,
Figure BDA0003648670360000031
in the formula: alpha is the drilling angle;
L 1n the radial length of the nth gradient drill hole is obtained;
L 2n axial length of the nth gradient bore;
L Z is the borehole length.
In the method for constructing advanced grouting for a tunnel penetrating active fault, preferably, the grouting parameters include grouting amount, and the estimation formula of the grouting amount is as follows:
V=πr 2 l
Figure BDA0003648670360000032
in the formula: s-total amount of grouting, m 3
V-grouting volume, m 3
P-porosity,%;
lambda-slurry fill factor (selected in the range of 0.7-0.9);
Figure BDA0003648670360000033
-slurry loss factor.
l-the length of the hole to be drilled, m.
r-radius of the grouting hole, m.
In the construction method for the advanced grouting of the tunnel-through active fault, preferably, the first gradient grouting area adopts an advanced sectional advanced grouting technology, and the first gradient advanced grouting length is 10 to 13 m.
In the advanced grouting construction method for the tunnel through active fault, preferably, in step 4, when the second gradient drilling operation is performed, a detection hole with the same depth as the first gradient is drilled to check the effect of the first gradient grouting, and the detection hole needs to have the same eversion angle as the second gradient grouting hole.
In the construction method for advanced grouting of the tunnel penetrating active fault, preferably, in step 5, the stable structure formed by the first gradient grouting can be used as a grout stop wall of the second gradient grouting, the second gradient grouting adopts a sleeve type grouting technology, and the second gradient advanced grouting range is from the end point of the first gradient grouting to the designed full grouting range.
According to the construction method for the advanced grouting of the tunnel penetrating active fault, preferably, the anchor rod or the anchor cable is an NPR anchor rod or an NPR anchor cable.
Has the advantages that: according to the construction method for the advanced grouting of the tunnel through active fault, the surrounding rock is reinforced by the advanced grouting, the active fault can be realized, the adverse effect of underground water and unstable surrounding rock on tunnel construction can be reduced, and meanwhile, the safety of constructors and equipment can be effectively ensured. By adopting the double-gradient advanced grouting technology, the defect of insufficient grouting of the existing one-time grouting technology can be overcome, so that the surrounding rock is ensured to form a complete stable structure. By adopting the double-gradient grouting and NPR anchor rod cable supporting technology, the primary lining of the tunnel can be more stable, so that the safety of the tunnel and the safety of constructors are ensured.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of this application, illustrate embodiments of the invention and, together with the description, serve to explain the invention and not to limit the invention. Wherein:
FIG. 1 is a schematic flow chart of an advanced grouting construction method for a tunnel penetrating active fault in an embodiment of the invention;
FIG. 2 is a cross-sectional view of a first gradient advanced grouting along an axial direction of a tunnel in an embodiment of the present invention;
FIG. 3 is a cross-sectional view of a second gradient pre-grouting along the axial direction of a tunnel in an embodiment of the present invention;
FIG. 4 is a cross-sectional view of a first gradient pre-grouting along a radial direction of a tunnel in an embodiment of the present invention;
FIG. 5 is a cross-sectional view of a second gradient leading grouting along a radial direction of a tunnel in an embodiment of the invention.
In the figure: 1. NPR anchor rods or NPR anchor cables; 2. a second gradient grouting area; 3. a first gradient grouting area; 4. a first gradient slip casting pipe; 5. crushing the belt; 6. grouting pump; 7. a second liner structure; 8. and a second gradient grouting pipe.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely below, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all embodiments. All other embodiments that can be derived by one of ordinary skill in the art from the embodiments given herein are intended to be within the scope of the present invention.
In the description of the present invention, the terms "longitudinal", "lateral", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, which are for convenience of description of the present invention only and do not require that the present invention must be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention. The terms "connected" and "connected" used herein should be interpreted broadly, and may include, for example, a fixed connection or a detachable connection; they may be directly connected or indirectly connected through intermediate members, and specific meanings of the above terms will be understood by those skilled in the art as appropriate.
The present invention will be described in detail below with reference to the embodiments with reference to the attached drawings. It should be noted that the embodiments and features of the embodiments of the present invention may be combined with each other without conflict.
According to the specific embodiment of the invention, as shown in fig. 1-5, the invention provides a construction method for advanced grouting of a tunnel penetrating active fault, which is characterized by comprising the following steps:
step 1, detecting a tunnel broken surrounding rock area, determining a grouting reinforcement area, and performing grouting design; the grouting reinforcement area comprises a first gradient grouting area and a second gradient grouting area, and the grouting reinforcement area is located at the peripheral position in front of the tunnel face.
In the embodiment, the first gradient grouting area is positioned at the front periphery of the tunnel face; the second gradient grouting area is positioned at the periphery of the first gradient grouting area.
The first gradient grouting area and the second gradient grouting area are staggered in the front-back direction, the second gradient grouting area is ahead of the first gradient grouting area, and the second gradient grouting area and the first gradient grouting area are provided with an overlapping area in the vertical direction; therefore, a part of a stable structure formed by the first gradient grouting can be used as a grout stop wall of the second gradient grouting, meanwhile, the second gradient grouting area is ahead of the second gradient grouting area and can also be used as a grout stop wall of the first gradient grouting area in the next period, the first gradient grouting area and the second gradient grouting area are staggered to form a part, the second gradient grouting area in the previous period and the first gradient grouting area in the next period have mutually overlapped parts, the grouting areas in any two adjacent periods can be mutually overlapped, the grouting areas in all grouting periods can be better connected into a whole, the ahead grouting area has enough overall structural strength, and the construction method is guaranteed to have a better ahead grouting effect.
In the embodiment, the grouting depth and the grouting area are determined by crushing the surrounding rock area and the length of the anchor rod and the anchor cable, and then the first gradient grouting area and the second gradient grouting area are divided. The grouting design comprises the steps of determining a grouting range, determining a first gradient grouting length and a second gradient grouting length, a slurry diffusion radius, drilling parameters, grouting parameters (including grouting efficiency, grouting final pressure and single-hole grouting amount) and grouting material model selection.
The angle of the drilled hole is alpha,
Figure BDA0003648670360000061
in the formula: alpha is the drilling angle;
L 1n the radial length of the nth gradient drill hole is obtained;
L 2n axial length of the nth gradient bore;
L Z is the borehole length.
The grouting parameters comprise grouting amount, and an estimation formula of the grouting amount is as follows:
V=πr 2 l
Figure BDA0003648670360000062
in the formula: s-total amount of grouting, m 3
V-grouting volume, m 3
P-porosity,%;
lambda-slurry fill factor (selected in the range of 0.7-0.9);
Figure BDA0003648670360000063
-slurry loss factor.
l-the length of the hole to be drilled, m.
r-radius of the grouting hole, m.
Step 2, spraying a concrete cover on the tunnel face of the tunnel, manufacturing an artificial grout stopping wall, and marking drilling point positions required by a first gradient grouting area on the artificial grout stopping wall; the thickness of the sprayed concrete is 20-40 cm. The hole sites are all designed on the face of the upper step, the first gradient hole site is arranged on the outer periphery of the manual grout stopping wall, the second gradient hole site is arranged on the inner periphery of the manual grout stopping wall, and as the second gradient grouting area is arranged above the first gradient grouting area and part of the second gradient grouting area is in advance, the hole sites on the inner periphery extend to the position of the grouting area and are in advance of the hole sites on the outer periphery.
Step 3, implementing a first gradient drilling operation and a first gradient grouting operation; the first gradient grouting adopts a forward sectional forward grouting technology to perform grouting reinforcement on broken surrounding rocks near the face, so that the front of the face can have a self-stabilizing structure. The segment length of the grouting area can be obtained by looking up a table according to the surrounding rock crushing grade, and in the embodiment, the first gradient advanced grouting length is 10-13 m; a grouting pump 6 is used to inject grouting material into the fractured zone 5 through the first gradient grouting pipe 4, thereby forming a first gradient grouting region 3 in the near-palm surface region.
Step 4, after the first gradient grouting is finished, implementing second gradient detection drilling operation, drilling a hole to the first gradient grouting area through the second gradient detection, and checking a first gradient grouting result; in step 4, when the second gradient drilling operation is performed, a detection hole with the same depth as the first gradient is drilled firstly to check the first gradient grouting effect, and the detection hole needs to be the same as the eversion angle of the second gradient grouting hole; therefore, the second gradient advanced grouting can use the detection hole for further punching, and the utilization rate of the detection hole is improved.
And 5, implementing second gradient drilling operation, implementing second gradient grouting operation, and simultaneously implementing middle and lower step anchor rod and anchor cable installation operation.
In the embodiment, the second gradient grouting adopts a sleeve type grouting technology to perform grouting reinforcement on deep broken surrounding rock, and the second gradient advanced grouting range is from a first gradient grouting end point to a designed full grouting range; adopt bushing type slip casting technique, can pass first gradient slip casting region, directly carry out the slip casting to second gradient slip casting region to avoid the repeated slip casting to shallow position, and deep position slip casting is insufficient problem. Specifically, a grouting material is injected into the fractured zone 5 through the second gradient grouting pipe 8 using a grouting pump 6, thereby forming the second gradient grouting region 2 outside the first gradient grouting region 3.
And after the first gradient grouting is finished, the surrounding rock near the tunnel face forms a stable structure, so that the bolting operation can be carried out on the surrounding rock which is grouted and reinforced in the previous cycle at the middle and lower steps, and the anchoring section of an anchor rod or an anchor cable is required to be ensured to be positioned in the grouting reinforcement area.
In this embodiment, the anchor rod or the anchor cable is an NPR anchor rod or an NPR anchor cable 1, and the NPR anchor rod or the NPR anchor cable 1 is anchored in the second gradient grouting area. The first gradient grouting area is used for reinforcing surrounding rocks outside the adjacent tunnel face, a safe construction environment is provided for construction, advanced grouting is performed on the deep part through the second gradient, the purpose is to effectively combine an NPR anchor rod cable technology, grouting reinforcement is performed on the surrounding rocks near an NPR anchor rod cable anchoring section, failure of the NPR anchor rod cable due to anchoring failure is avoided, the constant-resistance large-deformation characteristic of the NPR material is fully exerted, the double-gradient grouting technology is combined with the NPR anchor rod cable technology, deformation of a broken surrounding rock tunnel is effectively controlled, the overhaul rate is reduced, and construction tunneling efficiency is improved.
And 6, after the advanced grouting of the first gradient grouting area and the second gradient grouting area is finished, installing the full-section NPR anchor rod or the NPR anchor cable 1.
And 7, constructing a secondary lining structure 7 to finish the supporting operation of the tunnel.
In conclusion, in the technical scheme of the advanced grouting construction method for the tunnel penetrating active fault, the advanced pre-grouting is divided into two gradients for grouting, so that the tunnel surrounding rock strength is effectively improved, the surrounding rock deformation is reduced, and the construction environment safety is ensured. Form nearly face through first gradient slip casting and stabilize nos crack structure, can ensure that second gradient slip casting can be absorbed in slip casting deep position, avoid the repeated slip casting to shallow position, and deep position slip casting is abundant problem, and to activity fault and extremely broken country rock, the face is extremely unstable moreover, and first gradient slip casting can be fast slip casting and consolidate nearly face country rock, makes near face form stable structure to provide safe operational environment for the construction. Therefore, the problem of insufficient grouting is solved, the method can adapt to the environment with extremely poor surrounding rock conditions, and the working efficiency can be greatly improved.
It should be understood that the above description is only exemplary, and the embodiments of the present application do not limit the present invention.
The above description is only exemplary of the invention and should not be taken as limiting the invention, as any modification, equivalent replacement, or improvement made within the spirit and principle of the invention is intended to be covered by the appended claims.

Claims (10)

1. The construction method for the advanced grouting of the tunnel penetrating active fault is characterized by comprising the following steps of:
step 1, detecting a tunnel broken surrounding rock area, determining a grouting reinforcement area, and performing grouting design; the grouting reinforcement area comprises a first gradient grouting area and a second gradient grouting area, and the grouting reinforcement area is positioned at the peripheral position in front of the tunnel face;
step 2, spraying a concrete cover on the tunnel face of the tunnel, manufacturing an artificial grout stopping wall, and marking drilling point positions required by a first gradient grouting area on the artificial grout stopping wall;
step 3, implementing a first gradient drilling operation and a first gradient grouting operation;
step 4, after the first gradient grouting is finished, implementing second gradient detection drilling operation, drilling a hole to the first gradient grouting area through the second gradient detection, and checking a first gradient grouting result;
step 5, implementing a second gradient drilling operation, implementing a second gradient grouting operation, and simultaneously implementing middle and lower step anchor rod and anchor cable installation operations;
step 6, after the advanced grouting of the first gradient grouting area and the second gradient grouting area is completed, carrying out mounting operation on the anchor rod and the anchor cable of the full-section anchor rod;
and 7, constructing a secondary lining structure to complete the supporting operation of the tunnel.
2. The advanced grouting construction method for the tunnel penetrating active fault according to claim 1, wherein a first gradient grouting area is positioned at the front periphery of a tunnel face; the second gradient grouting area is positioned at the periphery of the first gradient grouting area.
3. A method of advanced grouting construction for a tunnel-through active fault as claimed in claim 2, characterized in that the first and second gradient grouting regions are staggered from each other in the fore-and-aft direction, the second gradient grouting region is advanced from the first gradient grouting region, and the second gradient grouting region and the first gradient grouting region have an overlapping region in the vertical direction.
4. The advanced grouting construction method for the tunnel penetrating active fault according to claim 1, wherein grouting design comprises the steps of determining a grouting range, determining a first gradient grouting length and a second gradient grouting length, a grout diffusion radius, drilling parameters, grouting parameters and grouting material model selection.
5. The advanced grouting construction method of a tunnel penetrating active fault according to claim 4, characterized in that the drilling angle is alpha,
Figure FDA0003648670350000021
in the formula: alpha is the drilling angle;
L 1n a radial length for the nth gradient borehole;
L 2n axial length of the nth gradient bore;
L Z is the borehole length.
6. The advanced grouting construction method for the tunnel penetrating active fault according to claim 4, wherein the grouting parameters comprise grouting amount, and the estimation formula of the grouting amount is as follows:
V=πr 2 l
Figure FDA0003648670350000022
in the formula: s-total amount of grouting, m 3
V-grouting volume, m 3
P-porosity,%;
lambda-slurry fill factor (selected in the range of 0.7-0.9);
Figure FDA0003648670350000023
-slurry loss factor.
l-the length of the hole to be drilled, m.
r-radius of the grouting hole, m.
7. The advanced grouting construction method for the tunnel penetrating active fault according to claim 1, characterized in that a first gradient grouting area adopts an advanced subsection advanced grouting technology, and the length of the first gradient advanced grouting is 10-13 m.
8. The advanced grouting construction method of a tunnel penetrating active fault according to claim 1, wherein in step 4, when the second gradient drilling operation is performed, a probe hole with the same depth as the first gradient is drilled to check the effect of the first gradient grouting, and the probe hole needs to have the same eversion angle as the second gradient grouting hole.
9. The advanced grouting construction method for the tunnel penetrating active fault according to claim 1, wherein in step 5, the stable structure formed by the first gradient grouting can be used as a grout stop wall of the second gradient grouting, the second gradient grouting adopts a sleeve type grouting technology, and the second gradient advanced grouting range is from the end point of the first gradient grouting to the designed full grouting range.
10. A method for advanced grouting construction of a tunnel through active fault as claimed in any one of claims 1 to 9, characterized in that the anchor rod or anchor cable is selected from NPR anchor rods or NPR anchor cables.
CN202210541970.7A 2022-05-17 2022-05-17 Advanced grouting construction method for tunnel penetrating fault Active CN114991818B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210541970.7A CN114991818B (en) 2022-05-17 2022-05-17 Advanced grouting construction method for tunnel penetrating fault

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210541970.7A CN114991818B (en) 2022-05-17 2022-05-17 Advanced grouting construction method for tunnel penetrating fault

Publications (2)

Publication Number Publication Date
CN114991818A true CN114991818A (en) 2022-09-02
CN114991818B CN114991818B (en) 2023-09-08

Family

ID=83026295

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210541970.7A Active CN114991818B (en) 2022-05-17 2022-05-17 Advanced grouting construction method for tunnel penetrating fault

Country Status (1)

Country Link
CN (1) CN114991818B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864967A (en) * 2010-06-13 2010-10-20 中国矿业大学 Strengthening and reinforcing method of high-ground-pressure soft rock laneway by hierarchical grouting
CN109209443A (en) * 2018-11-12 2019-01-15 山东大学 A kind of construction method of breaking surrounding rock tunnel structure
CN109854252A (en) * 2019-02-01 2019-06-07 王�琦 Underground engineering complete control method stage by stage
CN110005442A (en) * 2019-04-26 2019-07-12 中铁二十三局集团第六工程有限公司 Under wear existing building Urban Underground mining sectbn surrounding rock consolidation technique
CN110424971A (en) * 2019-08-20 2019-11-08 中国电建集团成都勘测设计研究院有限公司 The method for handling jacked piles with small section landslide
CN112228082A (en) * 2020-10-29 2021-01-15 中铁一局集团有限公司 Tunnel collapse treatment method by combined grouting of pipe shed and advanced small guide pipe
CN112627860A (en) * 2021-03-08 2021-04-09 中铁五局集团第一工程有限责任公司 Advanced grouting method for tunnel face of cement-rich rock stratum
CN112855223A (en) * 2021-04-06 2021-05-28 中国矿业大学 Integrated grouting method for coal roadway penetrating through goaf wall rear-advance curtain space

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864967A (en) * 2010-06-13 2010-10-20 中国矿业大学 Strengthening and reinforcing method of high-ground-pressure soft rock laneway by hierarchical grouting
CN109209443A (en) * 2018-11-12 2019-01-15 山东大学 A kind of construction method of breaking surrounding rock tunnel structure
CN109854252A (en) * 2019-02-01 2019-06-07 王�琦 Underground engineering complete control method stage by stage
CN110005442A (en) * 2019-04-26 2019-07-12 中铁二十三局集团第六工程有限公司 Under wear existing building Urban Underground mining sectbn surrounding rock consolidation technique
CN110424971A (en) * 2019-08-20 2019-11-08 中国电建集团成都勘测设计研究院有限公司 The method for handling jacked piles with small section landslide
CN112228082A (en) * 2020-10-29 2021-01-15 中铁一局集团有限公司 Tunnel collapse treatment method by combined grouting of pipe shed and advanced small guide pipe
CN112627860A (en) * 2021-03-08 2021-04-09 中铁五局集团第一工程有限责任公司 Advanced grouting method for tunnel face of cement-rich rock stratum
CN112855223A (en) * 2021-04-06 2021-05-28 中国矿业大学 Integrated grouting method for coal roadway penetrating through goaf wall rear-advance curtain space

Also Published As

Publication number Publication date
CN114991818B (en) 2023-09-08

Similar Documents

Publication Publication Date Title
CN101614125B (en) Construction method of V-level surrounding rock tunnel
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN101624910B (en) Method for reinforcing concealed tunnel
CN107355226B (en) Broken area hole section processing structure of TBM construction tunnel fault
CN107965341A (en) A kind of large-section underground pipe canopy pipe network concrete support method
CN112855223A (en) Integrated grouting method for coal roadway penetrating through goaf wall rear-advance curtain space
CN113137235B (en) Construction method of high-ground-stress soft rock extrusion large-deformation tunnel
CN112196582A (en) Method for controlling severe deformation of strong-earthquake deep-buried soft rock stratum tunnel
CN110230497A (en) A kind of positive barrel double -side approach construction method in threaded list road
CN111364449A (en) Construction method and structure for penetrating karst cave of precast tubular pile
CN112855029B (en) Goaf drilling external pipe expansion construction method
CN110439582A (en) Unfavorable geology method of disposal, TBM, which support to tunnel when happening suddenly unfavorable geology at boots, at TBM support boots passes through method
CN112145203A (en) Full-face advancing type sectional grouting construction method and overlapped tunnel construction method
CN116804369A (en) TBM (Tunnel boring machine) combined construction method for crossing bad stratum
CN217438921U (en) Anchor rod and isolation pile combined reinforcing structure for protecting excavation of side tunnel of foundation pit
CN114233374B (en) Ground grouting construction method for reinforcing cavity collapse area of inclined shaft after mud burst and water burst
CN114737979B (en) Construction method for continuously passing large-diameter water conveying pipeline downwards in shield region
CN114991818A (en) Advanced grouting construction method for tunnel penetrating active fault
CN115726792A (en) Basement rock and boulder pretreatment method for large-section rectangular jacking pipe
CN114263171A (en) Construction method for root pile top drive pipe following drilling splitting grouting pile forming
CN210459265U (en) Reinforced structure of high-voltage line tower
CN109707394B (en) Construction method for subway tunnel shield receiving end tunnel portal
CN208330410U (en) A kind of Tunnel Passing crushed zone canopy protection structure
CN112813989A (en) Anchor cable supporting structure for foundation pit and construction method
CN114991819B (en) Three-super control technology for water damage tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant