CN114991136B - Intelligent penetration pipe pile capable of realizing grouting at different depths and manufacturing method and using method thereof - Google Patents

Intelligent penetration pipe pile capable of realizing grouting at different depths and manufacturing method and using method thereof Download PDF

Info

Publication number
CN114991136B
CN114991136B CN202210708799.4A CN202210708799A CN114991136B CN 114991136 B CN114991136 B CN 114991136B CN 202210708799 A CN202210708799 A CN 202210708799A CN 114991136 B CN114991136 B CN 114991136B
Authority
CN
China
Prior art keywords
pile
grouting
pipe
pipe pile
joint
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202210708799.4A
Other languages
Chinese (zh)
Other versions
CN114991136A (en
Inventor
戴国亮
赵仲新
黄挺
焦澳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Donggu Construction Technology Co ltd
Jiangsu Jiaoshui Construction Intelligent Equipment Research Institute Co ltd
Original Assignee
Nanjing Donggu Construction Technology Co ltd
Jiangsu Jiaoshui Construction Intelligent Equipment Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Donggu Construction Technology Co ltd, Jiangsu Jiaoshui Construction Intelligent Equipment Research Institute Co ltd filed Critical Nanjing Donggu Construction Technology Co ltd
Priority to CN202210708799.4A priority Critical patent/CN114991136B/en
Publication of CN114991136A publication Critical patent/CN114991136A/en
Application granted granted Critical
Publication of CN114991136B publication Critical patent/CN114991136B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/58Prestressed concrete piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • E02D5/523Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01LMEASURING FORCE, STRESS, TORQUE, WORK, MECHANICAL POWER, MECHANICAL EFFICIENCY, OR FLUID PRESSURE
    • G01L5/00Apparatus for, or methods of, measuring force, work, mechanical power, or torque, specially adapted for specific purposes
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/10Geothermal energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses an intelligent sounding pipe pile capable of realizing grouting at different depths, which relates to the technical field of pipe piles, and comprises a pile bottom pipe pile joint, the grouting device comprises a pile bottom pipe pile, an end plate fixedly arranged at the upper end of the pile bottom pipe pile, and a first grouting pipe and a second grouting pipe fixedly arranged in the pile bottom pipe pile; the pile section pipe pile joint comprises a pile section pipe pile, an upper end plate and a lower end plate which are fixedly arranged at two ends of the pile section pipe pile, and a third grouting pipe which is fixedly arranged in the pile section pipe pile joint; the pressure sensor is fixedly arranged at the bottom in the pile bottom pipe pile joint and is used for detecting the soil pressure of the pile bottom pipe pile joint; and the grouting device is used for grouting into the third grouting pipe. The invention also discloses a manufacturing method and a using method of the intelligent touch pipe pile capable of realizing grouting at different depths. The invention can realize the purpose of joint grouting of the pile end and the pile side and comprehensively improve the bearing capacity of the pipe pile.

Description

Intelligent penetration pipe pile capable of realizing grouting at different depths and manufacturing method and using method thereof
Technical Field
The invention relates to the technical field of pipe piles, in particular to an intelligent touch pipe pile capable of realizing grouting at different depths, and a manufacturing method and a using method thereof.
Background
Along with the rapid development of urban construction, the application field and the use scale of the prestressed concrete pipe pile are continuously enlarged, and the prestressed concrete pipe pile is widely applied to engineering in a plurality of fields such as industrial and civil buildings, highways, railways and the like, is one of important pile foundation forms in supporting the infrastructure construction of China, and has an irreplaceable function.
In the construction engineering, the common use modes of the prestressed concrete pipe pile are three, namely pile foundation, composite foundation and foundation pit support. When applied to actual engineering, weak soil layers often exist around the pile body, for example: a foundation consisting of silt, mucky soil, earth fill or other high-pressure earth layers. The foundation often has engineering characteristics of high natural water content, low bearing capacity and the like, is easy to slide or solidify and subside under the action of load, and has serious influence on the safety and stability of the building. Under similar engineering geological conditions, the strength of the pipe pile is often difficult to exert, and the engineering economy of the pipe pile is affected by a soft soil layer and cannot be fully embodied. In the engineering, a post grouting mode is generally adopted to carry out secondary treatment on soft stratum around the pile foundation, but the construction technology is mainly aimed at a bored pile at present, and the construction technology is rarely related to the field of pipe piles. The main reason is that the pipe pile is usually driven in sections and connected into piles, and the construction process difference of pile foundations makes the grouting method of the filling pile difficult to be applied. In addition, the common tubular pile length is generally shaped in a prefabrication factory, is limited by the current connection mode, and is difficult to effectively realize by combining grouting at the pile side and the pile end of the tubular pile. Moreover, the distribution depth of the actual weak stratum is not opposite to the length of the pipe joint, and how to realize grouting at a specific depth or to realize grouting in the stratum which is not disclosed in the geological survey has no effective method, so that the quality and the efficiency of the development of the pipe pile grouting work in the actual engineering are affected.
Disclosure of Invention
The invention aims to solve the technical problem of overcoming the defects of the prior art and providing an intelligent touch pipe pile capable of realizing grouting at different depths, and a manufacturing method and a using method thereof.
In order to solve the technical problems, the technical scheme of the invention is as follows:
An intelligent sounding pipe pile capable of realizing grouting at different depths, which comprises,
The pile bottom pipe pile joint comprises a pile bottom pipe pile, an end plate fixedly arranged at the upper end of the pile bottom pipe pile, and a first grouting pipe and a second grouting pipe fixedly arranged in the pile bottom pipe pile, wherein grouting openings at the upper ends of the first grouting pipe and the second grouting pipe are communicated with through holes formed in the end plate, a grouting opening at the lower end of the first grouting pipe extends to the lower end of the pile bottom pipe pile, and a grouting opening at the lower end of the second grouting pipe is communicated with the side wall of the pile bottom pipe pile;
The pile section pipe pile joint comprises a pile section pipe pile, an upper end plate, a lower end plate and a third grouting pipe, wherein the upper end plate and the lower end plate are fixedly arranged at two ends of the pile section pipe pile, the third grouting pipe is fixedly arranged in the pile section pipe pile joint, a grouting port at the upper end of the third grouting pipe is communicated with a through hole formed in the upper end plate, the lower end of the third grouting pipe extends out of the lower end plate, the pile section pipe pile joint is provided with a plurality of sections, the pile section pipe pile joint is connected with the pile bottom pipe pile joint after being in butt joint in sequence, and the third grouting pipes in the pile section pipe pile joint are in sequence communicated with the first grouting pipe and the second grouting pipe respectively;
the pressure sensor is fixedly arranged at the bottom in the pile bottom pipe pile joint and is used for detecting the soil pressure at the end part of the pile bottom pipe pile joint; and
And the grouting device is used for grouting into the third grouting pipe.
As a preferable scheme of the intelligent sounding pipe pile capable of realizing grouting at different depths, the intelligent sounding pipe pile comprises the following components: the connecting device is used for connecting adjacent pile section pipe pile joints and comprises an upper fixing support and a lower fixing support which are fixedly installed on the third grouting pipe, at least two support rods are hinged to the lower fixing support, the upper fixing support is connected with the support rods through elastic supporting components, a supporting plate is fixedly installed at the upper end of the support rods, a transmission rod is hinged to the supporting plate, and the other end of the transmission rod is hinged to a movable sleeve pipe arranged outside the third grouting pipe in a sliding sleeve mode and located above the upper fixing support.
As a preferable scheme of the intelligent sounding pipe pile capable of realizing grouting at different depths, the intelligent sounding pipe pile comprises the following components: the elastic supporting assembly comprises a first connecting rod hinged with the supporting rod and a second connecting rod hinged with the upper fixing support, the other end of the first connecting rod and the other end of the second connecting rod are fixedly connected with buckling discs, the two buckling discs are oppositely arranged and connected through a rotating shaft, the rotating shaft coincides with the axes of the two buckling discs, two ends of the rotating shaft are respectively rotatably mounted on the two buckling discs, a spring is sleeved outside the rotating shaft, and two ends of the spring are respectively fixedly connected with the two buckling discs.
As a preferable scheme of the intelligent sounding pipe pile capable of realizing grouting at different depths, the intelligent sounding pipe pile comprises the following components: and the third grouting pipe is fixedly provided with a limiting plate, and the limiting plate is positioned between the movable sleeve and the upper fixed support.
As a preferable scheme of the intelligent sounding pipe pile capable of realizing grouting at different depths, the intelligent sounding pipe pile comprises the following components: the upper end and the lower end of the movable sleeve are respectively fixedly provided with an upper convex edge and a lower convex edge, and the other end of the transmission rod is hinged with the lower convex edge.
As a preferable scheme of the intelligent sounding pipe pile capable of realizing grouting at different depths, the intelligent sounding pipe pile comprises the following components: at least two second grouting pipes are fixedly arranged in the pile bottom pipe pile, the number of the first grouting pipes is identical to that of the second grouting pipes, the first grouting pipes and the second grouting pipes are annularly arranged, and the first grouting pipes and the second grouting pipes are staggered;
The number of the third grouting pipes in any pile section pipe pile section is equal to the sum of the number of the first grouting pipes and the number of the second grouting pipes, and after a plurality of pile section pipe pile sections are sequentially butted and connected with the pile bottom pipe pile section, the first grouting pipes and the second grouting pipes are communicated with the third grouting pipes.
As a preferable scheme of the intelligent sounding pipe pile capable of realizing grouting at different depths, the intelligent sounding pipe pile comprises the following components: the lower end of the pile bottom pipe pile joint is fixedly provided with a pile shoe, the pressure sensor is fixedly arranged in the pile shoe, and the lower end of the pile shoe is provided with an opening communicated with the slurry outlet of the first grouting pipe.
As a preferable scheme of the intelligent sounding pipe pile capable of realizing grouting at different depths, the intelligent sounding pipe pile comprises the following components: the inner walls of the pile bottom pipe pile and the pile section pipe pile are fixedly provided with fixing plates, a data transmission line connected to the pressure sensor is fixed on the inner walls of the pile bottom pipe pile and the pile section pipe pile through the fixing plates, and the data transmission line is electrically connected with a data acquisition device.
The invention also provides a manufacturing method of the intelligent sounding pipe pile capable of realizing grouting at different depths, comprising the following steps of,
Prefabricating a first grouting pipe, a second grouting pipe and a third grouting pipe;
Installing the first grouting pipe and the second grouting pipe in the pile bottom pipe pile, enabling a grouting outlet of the second grouting pipe to be communicated with the side wall of the pile bottom pipe pile joint, and installing the third grouting pipe in the pile section pipe pile;
Mounting the fixing sheets on the inner walls of the pile bottom pipe pile and the pile section pipe pile;
casting concrete, prefabricating pile bottom pipe pile joints and pile section pipe pile joints;
and installing the connecting device on a third grouting pipe extending to the outside of the lower end plate in each pile section pipe pile joint.
The invention also provides a use method of the intelligent sounding pipe pile capable of realizing grouting at different depths, comprising the following steps,
Setting out the pile position, and hoisting and feeding the pile after the pile machine is in place;
Connecting a plurality of pile section pipe pile joints in sequence and then connecting the pile section pipe pile joints with pile bottom pipe pile joints;
a connecting pipe is arranged at a grouting port at the upper end of a third grouting pipe in the uppermost pile section pipe pile joint, so that the third grouting pipe is connected with an external grouting device;
pile pressing is carried out, pile end soil pressure is collected in real time through a pressure sensor in the pile pressing process, and the depth of a weak soil layer is judged through penetration data;
Continuously pressing the pipe pile into the soft soil layer, enabling a slurry outlet of the second grouting pipe to be positioned at the middle section of the soft soil layer measured by sounding, and starting a grouting device to perform grouting at the pile side so as to realize solidification treatment of the soft soil layer at the pile side;
and closing the grouting device, stopping grouting at the pile side, continuously pressing the pipe pile until the designed depth is reached, and starting the grouting device to perform grouting at the pile end so as to realize solidification treatment on the soil layer at the end part of the pipe pile.
The beneficial effects of the invention are as follows:
(1) The second grouting pipe is arranged in the pipe pile, so that grouting at the pile side can be realized, targeted multi-depth grouting can be realized according to the actual distribution condition of a weak soil layer on site, and meanwhile, the first grouting pipe and the third grouting pipe are arranged in the pipe pile, so that grouting at the pile bottom can be realized, the aim of combined grouting at the pile end and the pile side is fulfilled, and the bearing capacity of the pipe pile is comprehensively improved.
(2) According to the invention, the high-efficiency connection between the pile sections of the pile is realized by installing the connecting device on each pile section pipe pile section, and meanwhile, as the supporting plates are arranged around the lower end of the third grouting pipe in each pile section pipe pile section, the direct contact friction between the grouting outlet of the third grouting pipe and the grouting outlet at the upper end of the third grouting pipe in the pile section pipe pile of the previous section is avoided in the process of connecting the adjacent pile section pipe pile sections, and the third grouting pipe is effectively protected.
(3) The pressure sensor is arranged in the pile shoe at the lower end of the pipe pile, and the resistance of the pile end can be monitored in real time in the pile sinking process, so that the distribution position of an actual soft soil layer is judged, the grouting requirement at a certain depth is further defined, the large-scale grouting of a blind object is avoided, the construction efficiency of engineering is improved, and the construction cost is reduced.
(4) According to the invention, the first grouting pipe, the second grouting pipe and the third grouting pipe are all made of steel, so that the reinforcement of the pipe pile can be increased, the reinforced concrete pipe pile is used as a prestressed reinforcement, and the use amount of prestressed reinforcements in prefabrication of the prestressed concrete pipe pile is reduced.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings that are needed in the description of the embodiments will be briefly described below, it being obvious that the drawings in the following description are only some embodiments of the present invention, and that other drawings may be obtained according to these drawings without inventive effort for a person skilled in the art.
Fig. 1 is a schematic structural diagram of an intelligent sounding pipe pile capable of realizing grouting at different depths;
FIG. 2 is a cross-sectional view of a pile bottom tubular pile section in an intelligent penetration tubular pile capable of realizing grouting at different depths;
FIG. 3 is a schematic cross-sectional view of A-A of FIG. 2;
FIG. 4 is a schematic cross-sectional view of B-B of FIG. 2;
FIG. 5 is a schematic cross-sectional view of C-C of FIG. 2;
FIG. 6 is a cross-sectional view of a pile section of an intelligent penetration pipe pile capable of achieving grouting at different depths;
FIG. 7 is a schematic cross-sectional view of D-D of FIG. 6;
FIG. 8 is an enlarged schematic view of FIG. 7 at A;
fig. 9 is an expanded schematic view of a connection device in an intelligent sounding pipe pile capable of realizing grouting at different depths;
FIG. 10 is an enlarged schematic side view of FIG. 9B;
FIG. 11 is an enlarged schematic side view of FIG. 9C;
Fig. 12 is a schematic diagram of pile side grouting of an intelligent sounding pipe pile capable of realizing grouting at different depths;
fig. 13 is a schematic diagram of an intelligent sounding pipe pile capable of realizing grouting at different depths after complete grouting;
fig. 14 is a schematic flow chart of a method for manufacturing an intelligent sounding pipe pile capable of realizing grouting at different depths;
fig. 15 is a schematic flow chart of a method for using the intelligent sounding pipe pile capable of realizing grouting at different depths;
Wherein: 1. pile bottom pipe pile joint; 2. pile bottom pipe pile; 3. an end plate; 4. a first grouting pipe; 5. a second grouting pipe; 6. pile section pipe pile joint; 7. pile section pipe piles; 8. an upper end plate; 9. a lower end plate; 10. a third grouting pipe; 11. a pressure sensor; 12. a grouting device; 13. an upper fixed support; 14. a lower fixed support; 15. a support rod; 16. a transmission rod; 17. a movable sleeve; 18. a first connecting rod; 19. a second connecting rod; 20. a clasp disc; 21. a rotating shaft; 22. a spring; 23. a limiting plate; 24. an upper convex edge; 25. a lower convex edge; 26. pile shoe; 27. a fixing piece; 28. a data transmission line; 29. a data acquisition device; 30. a rubber connecting pipe; 31. grouting pipe; 33. a rotating wheel; 34. a connecting rod; 35. a hinge shaft; 36. a support plate; 37. grouting liquid.
Detailed Description
In order that the invention may be more readily understood, a more particular description thereof will be rendered by reference to specific embodiments that are illustrated in the appended drawings.
Fig. 1 is a schematic structural diagram of an intelligent sounding pipe pile capable of realizing grouting at different depths according to an embodiment of the present application. The pile comprises a pile bottom pile section 1, a plurality of pile section pile sections 6, a pressure sensor 11, a data acquisition device 29 and a grouting device 12. The pile sections 6 are sequentially connected and then connected with the pile bottom pipe pile section 1 to form a pipe pile main body. The pressure sensor 11 is fixedly arranged in the pile bottom pipe pile joint 1 and is electrically connected with the data acquisition device 29. The grouting device 12 is used for grouting into the pipe pile.
Specifically, pile bottom tubular pile section 1 includes pile bottom tubular pile 2. The pile bottom pipe pile 2 is a prestressed concrete pile. An end plate 3 is fixedly arranged at the upper end of the pile bottom pipe pile 2. Three first grouting pipes 4 and three second grouting pipes 5 are fixedly arranged in the pile bottom pipe pile 2. The grouting openings at the upper ends of the first grouting pipe 4 and the second grouting pipe 5 are communicated with through holes formed in the end plate 3. The grout outlet at the lower end of the first grouting pipe 4 extends to the lower end of the pile bottom pipe pile 2. The axis of the first grouting pipe 4 is parallel to the axis of the pile bottom pipe pile 2. The grout outlet of the lower end of the second grouting pipe 5 extends to be communicated with the side wall of the pile bottom pipe pile 2.
Fig. 2 is a schematic cross-sectional view of a pile bottom tubular pile section 1. Wherein, three first slip casting pipes 4 and three second slip casting pipes 5 are annular and arrange, and the centre of a circle of place circumference is located the axis of stake end tubular pile festival 1. The first grouting pipe 4 and the second grouting pipe 5 are sequentially staggered.
A shoe 26 is fixedly installed at the lower end of the pile bottom pipe pile 2. The pressure sensor 11 is fixedly mounted in the shoe 26. The lower end of the pile shoe 26 is provided with an opening communicated with the grout outlet of the first grouting pipe 4. Grouting liquid 37 in the first grouting pipe 4 can enter the soil layer of the pile end through the opening, so that pile bottom grouting is realized.
The pile section tubular pile section 6 comprises a pile section tubular pile 7. The pile section pipe pile 7 is also a prestressed concrete pile. An upper end plate 8 and a lower end plate 9 are respectively fixedly arranged at the upper end and the lower end of the pile section pipe pile 7. Six third grouting pipes 10 are fixedly arranged in the pile section pipe pile 7. The grouting opening at the upper end of the third grouting pipe 10 is communicated with the through hole formed in the upper end plate 8, and the grouting opening at the lower end of the third grouting pipe 10 extends to the lower side of the lower end plate 9.
Fig. 6 is a schematic cross-sectional view of pile section tube 7. Six third grouting pipes 10 are arranged in an annular mode. The circle center of the circumference where the six third grouting pipes 10 are located is located on the axis of the pile section pipe pile 7, and the diameter of the circumference is equal to the diameters of the circumferences where the first grouting pipe 4 and the second grouting pipe are located. When the pile section pipe pile 7 joint 6 is in butt joint with the pile bottom pipe pile joint 1, six third grouting pipes 10 can be aligned with and communicated with the first grouting pipe 4 and the second grouting pipe 5 respectively.
A connecting device is fixedly arranged at the lower end of each pile section pipe pile joint 6 and is used for connecting the adjacent pile section pipe pile joints 6. Wherein the connecting device is arranged on a third grouting pipe 10 extending to the outside of the lower end plate 9 in each pile section pipe pile section 6. Referring to fig. 9, the connection means includes an upper fixing support 13 and a lower fixing support 14 fixedly installed on the third grouting pipe 10. The lower fixing support 14 is fixedly welded to the lower end of the third grouting pipe 10. Four hinge seats are fixedly provided at the side of the lower fixing support 14. Each hinge seat is hinged with a supporting rod 15. Each support bar 15 is connected to the upper fixed support 13 by an elastic support assembly. When the support rod 15 rotates around the hinge seat, the support rod 15 approaches to or departs from the upper fixed support 13, and in the process, the elastic supporting component can elastically deform and apply force to the support rod 15 to reset the support rod 15. A support plate 36 is fixedly connected to the upper end of the support rod 15. The upper end of each supporting plate 36 is fixedly provided with a connecting rod 34, the upper end of each connecting rod 34 is hinged with a transmission rod 16 through a hinge shaft 35, and the other end of each transmission rod 16 is hinged with a movable sleeve 17 which is sleeved outside the third grouting pipe 10 in a sliding manner. The movable sleeve 17 is located above the upper fixed support 13.
When an external force is applied to slide the movable sleeve 17 upward along the third grouting pipe 10, the transmission rod 16 and the connecting rod 34 drive the four support plates 36 to move toward the third grouting pipe 10, so that the distance between the support plates 36 and the third grouting pipe 10 is reduced, namely, the four support plates 36 simultaneously move inward. The support plate 36 moves and drives the support rod 15 to move towards the third grouting pipe 10, so that the elastic support assembly deforms. Referring to fig. 8, the lower part of the connecting device can extend into the grouting opening at the upper end of the third grouting pipe 10 in the pipe pile 7 joint 6 of the adjacent pile section. When the external force is removed, the elastic supporting component between the supporting rod 15 and the upper fixed support 13 can be reset, and drives the supporting rod 15 to rotate outwards, so that the supporting plate 36 is driven to be far away from the third grouting pipe 10, the distance between the supporting plate 36 and the third grouting pipe 10 is increased, namely, four supporting plates 36 simultaneously move outwards, the lower part of the connecting device can be spread in the grouting opening of the third grouting pipe 10 in the adjacent pile section pipe pile section 6, and the connection between the adjacent pile section pipe pile sections 6 is realized.
Referring to fig. 10, the elastic support assembly includes a first connecting rod 18, a second connecting rod 19, and two snap discs 20. One end of the first connecting rod 18 is hinged with the inner side of the adjacent supporting rod 15, and the other end of the first connecting rod 18 is fixedly connected with a clamping disc 20. One end of the second connecting rod 19 is hinged on the upper fixed support 13, and the other end of the second connecting rod 19 is fixedly connected with the other clamping disc 20. The two catch discs 20 are arranged opposite each other and are connected by a rotation shaft 21. The rotation shaft 21 coincides with the axes of the two catch discs 20, and both ends of the rotation shaft 21 are rotatably mounted on the two catch discs 20, respectively. A spring 22 is sleeved outside the rotating shaft 21, and two ends of the spring 22 are fixedly connected with the two buckling discs 20 respectively.
When the support rod 15 moves toward the third grouting pipe 10, the two catch disks 20 are reversely rotated, so that the spring 22 between the two catch disks 20 is tightened, and the spring 22 generates elastic force. When the external force is removed, the spring 22 is restored, and the generated elastic force makes the two catch discs 20 reversely rotate, so that the upper end of the support rod 15 gradually gets away from the third grouting pipe 10.
Wherein, a rotating wheel 33 is rotatably installed at a hinge point where the connecting rod 34 and the transmission rod 16 are hinged to each other, and a hinge shaft 35 is penetrated at an axis of the rotating wheel 33, so that the rotating wheel 33 can rotate around the hinge shaft 35, as shown in fig. 11. When the connection device is in the initial state, referring to the figure, the distance between the side of the runner 33 remote from the third grouting pipe 10 and the third grouting pipe 10 is larger than the distance between the outside of the support plate 36 and the third grouting pipe 10. When the lower part of the connecting device extends into the grouting opening at the upper end of the third grouting pipe 10 in the adjacent pile section pipe pile section 6 and the external force is removed, the supporting plates 36 are mutually far away, and at the moment, the side surfaces of the rotating wheels 33 are firstly contacted with the inner side walls of the third grouting pipes 10 in the adjacent pile section pipe pile section 6, so that the supporting plates 36 are prevented from being rubbed with the inner walls of the third grouting pipes 10 in a direct contact manner, the third grouting pipes 10 are protected, and labor is saved in the connecting process.
Preferably, an upper protruding edge 24 and a lower protruding edge 25 are fixedly arranged at the upper end and the lower end of the movable sleeve 17, respectively. The other end of the transmission rod 16 is hinged with a lower convex edge 25. The upper flange 24 and the lower flange 25 can serve as a baffle to prevent relative sliding between the operator's hand and the movable sleeve 17 when the operator drives the sliding sleeve to slide along the third grouting pipe 10.
In addition, an annular limiting plate 23 is fixedly mounted on the third grouting pipe 10, and the limiting plate 23 is positioned between the movable sleeve 17 and the upper fixed support 13. The limiting plate 23 may act as a limit to the movable sleeve 17 to limit excessive displacement of the movable sleeve 17.
Fixing pieces 27 are fixedly arranged on the inner walls of the pile bottom pipe pile 2 and the pile section pipe pile 7. The data transmission line 28 connected to the pressure sensor 11 is fixed to the inner walls of the pile bottom pipe pile 2 and the pile section pipe pile 7 through the fixing pieces 27. The other end of the data transmission line 28 extends out of the pipe pile and is electrically connected with a data acquisition device 29.
The grouting device 12 is located outside the pipe pile and is used for grouting into the pipe pile. The grouting device 12 is connected with a power supply through a power line. When grouting is needed, a rubber connecting pipe 30 is arranged at a grouting opening at the upper end of the third grouting pipe 10 in the uppermost pile section pipe pile 7 joint 6, and the rubber connecting pipe 30 is connected with a grouting pipe 31 of the grouting device 12.
Fig. 14 is a schematic flow chart of a method for manufacturing an intelligent touch pipe pile capable of realizing grouting at different depths according to an embodiment of the present application. The manufacturing method comprises the steps S101-S105, and the specific steps are as follows:
step S101: prefabricating a first grouting pipe, a second grouting pipe and a third grouting pipe.
Step S102: and installing the first grouting pipe and the second grouting pipe in the pile bottom pipe pile, enabling a grouting outlet of the second grouting pipe to be communicated with the side wall of the pile bottom pipe pile joint, and installing the third grouting pipe in the pile section pipe pile.
Step S103: and installing the fixing sheets on the inner walls of the pile bottom pipe pile and the pile section pipe pile.
Step S104: and casting concrete, and prefabricating pile bottom pipe pile joints and pile section pipe pile joints.
Step S105: and installing the connecting device on a third grouting pipe extending to the outside of the lower end plate in each pile section pipe pile joint.
Fig. 15 is a flow chart of a method for using an intelligent sounding pipe pile capable of realizing grouting at different depths according to an embodiment of the present application. The manufacturing method comprises the steps S201-S206, and the specific steps are as follows:
Step S201: and (5) setting out the pile position, and hoisting and feeding the pile after the pile machine is in place.
Step S202: and connecting the pile sections with the pile bottom pipe pile sections after sequentially connecting the pile sections.
Step S203: and a rubber connecting pipe is arranged at a grouting port at the upper end of a third grouting pipe in the uppermost pile section pipe pile joint, so that the third grouting pipe is connected with an external grouting device.
Step S204: pile pressing is carried out, pile end soil pressure is collected in real time through a pressure sensor in the pile pressing process, and the depth of the weak soil layer is judged through penetration data.
Step S205: and continuously pressing the pipe pile, enabling a slurry outlet of the second grouting pipe to be positioned in the middle section of the weak soil layer measured by sounding, starting a grouting device to perform pile side grouting, and realizing solidification treatment on the weak soil layer on the pile side.
Step S206: and closing the grouting device, stopping grouting at the pile side, continuously pressing the pipe pile until the designed depth is reached, and starting the grouting device to perform grouting at the pile end so as to realize solidification treatment on the soil layer at the end part of the pipe pile.
Therefore, the technical scheme of the application is that the second grouting pipe is arranged in the pipe pile, so that grouting at the side of the pipe pile can be realized, multi-depth grouting can be realized according to the actual distribution condition of the weak soil layer on site, meanwhile, the first grouting pipe and the third grouting pipe are arranged in the pipe pile, grouting at the bottom of the pipe pile can be realized, the purpose of joint grouting at the pile end and the pile side is realized, and the bearing capacity of the pipe pile is comprehensively improved.
In addition to the above embodiments, the present invention may have other embodiments; all technical schemes formed by equivalent substitution or equivalent transformation fall within the protection scope of the invention.

Claims (6)

1. Can realize intelligent feeler pipe pile of different degree of depth slip casting, its characterized in that: comprising the steps of (a) a step of,
The pile bottom pipe pile joint (1) comprises a pile bottom pipe pile (2), an end plate (3) fixedly arranged at the upper end of the pile bottom pipe pile (2), and a first grouting pipe (4) and a second grouting pipe (5) fixedly arranged in the pile bottom pipe pile (2), wherein grouting openings at the upper ends of the first grouting pipe (4) and the second grouting pipe (5) are communicated with through holes formed in the end plate (3), a grouting opening at the lower end of the first grouting pipe (4) extends to the lower end of the pile bottom pipe pile (2), and a grouting opening at the lower end of the second grouting pipe (5) is communicated with the side wall of the pile bottom pipe pile (2);
The pile section pipe pile joint (6) comprises a pile section pipe pile (7), an upper end plate (8) and a lower end plate (9) which are fixedly arranged at two ends of the pile section pipe pile (7) and a third grouting pipe (10) which is fixedly arranged in the pile section pipe pile joint (6), a grouting opening at the upper end of the third grouting pipe (10) is communicated with a through hole formed in the upper end plate (8), the lower end of the third grouting pipe (10) extends out of the lower end plate (9), the pile section pipe pile joint (6) is provided with a plurality of sections, the pile section pipe pile joint (6) is connected with the pile bottom pipe pile joint (1) after being sequentially butted, and the third grouting pipes (10) in the pile section pipe pile joint (6) are sequentially communicated with the first grouting pipe (4) and the second grouting pipe (5) respectively;
The pressure sensor (11) is fixedly arranged at the bottom in the pile bottom pipe pile joint (1) and is used for detecting the soil pressure at the end part of the pile bottom pipe pile joint (1); and
Grouting means (12) for grouting into the third grouting pipe (10);
the third grouting pipe (10) extending to the outside of the lower end plate (9) is further provided with a connecting device for connecting adjacent pile section pipe piles (7) sections (6), the connecting device comprises an upper fixed support (13) and a lower fixed support (14) which are fixedly installed on the third grouting pipe (10), at least two support rods (15) are hinged on the lower fixed support (14), the upper fixed support (13) is connected with the support rods (15) through elastic support components, the upper ends of the support rods (15) are fixedly provided with support plates (36), the support plates (36) are hinged with transmission rods (16), the other ends of the transmission rods (16) are hinged with movable sleeves (17) which are sleeved outside the third grouting pipe (10) in a sliding mode, and the movable sleeves (17) are located above the upper fixed support (13);
The elastic supporting assembly comprises a first connecting rod (18) hinged with the supporting rod (15) and a second connecting rod (19) hinged with the upper fixed support (13), the other ends of the first connecting rod (18) and the second connecting rod (19) are fixedly connected with buckling discs (20), the two buckling discs (20) are oppositely arranged and are connected through a rotating shaft (21), the rotating shaft (21) coincides with the axes of the two buckling discs (20), two ends of the rotating shaft (21) are respectively rotatably arranged on the two buckling discs (20), springs (22) are sleeved on the outer sides of the rotating shaft (21), and two ends of each spring (22) are respectively fixedly connected with the two buckling discs (20);
a limiting plate (23) is fixedly arranged on the third grouting pipe (10), and the limiting plate (23) is positioned between the movable sleeve (17) and the upper fixed support (13);
The upper end and the lower end of the movable sleeve (17) are respectively fixedly provided with an upper convex edge (24) and a lower convex edge (25), and the other end of the transmission rod (16) is hinged with the lower convex edge (25).
2. The intelligent penetration pipe pile capable of realizing grouting at different depths according to claim 1, wherein: at least two second grouting pipes (5) are fixedly arranged in the pile bottom pipe pile (2), the number of the first grouting pipes (4) is consistent with that of the second grouting pipes (5), the first grouting pipes (4) and the second grouting pipes (5) are annularly arranged, and the first grouting pipes (4) and the second grouting pipes (5) are staggered;
The number of the third grouting pipes (10) in any pile section pipe pile joint (6) is equal to the sum of the number of the first grouting pipes (4) and the number of the second grouting pipes (5), and after a plurality of pile section pipe pile joints (6) are sequentially butted and connected with the pile bottom pipe pile joint (1), the first grouting pipes (4) and the second grouting pipes (5) are communicated with the third grouting pipes (10).
3. The intelligent penetration pipe pile capable of realizing grouting at different depths according to claim 1, wherein: pile shoe (26) is fixedly arranged at the lower end of the pile bottom pipe pile joint (1), the pressure sensor (11) is fixedly arranged in the pile shoe (26), and an opening communicated with the grouting outlet of the first grouting pipe (4) is formed at the lower end of the pile shoe (26).
4. The intelligent penetration pipe pile capable of realizing grouting at different depths according to claim 1, wherein: the inner walls of the pile bottom pipe pile (2) and the pile section pipe pile (7) are fixedly provided with fixing plates (27), a data transmission line (28) connected to the pressure sensor (11) is fixed on the inner walls of the pile bottom pipe pile (2) and the pile section pipe pile (7) through the fixing plates (27), and the data transmission line (28) is electrically connected with a data acquisition device (29).
5. The manufacturing method of the intelligent touch pipe pile capable of realizing grouting at different depths is characterized by comprising the following steps of: an intelligent sounding pipe pile for realizing grouting with different depths according to claim 1, comprising,
Prefabricating a first grouting pipe, a second grouting pipe and a third grouting pipe;
Installing the first grouting pipe and the second grouting pipe in the pile bottom pipe pile, enabling a grouting outlet of the second grouting pipe to be communicated with the side wall of the pile bottom pipe pile joint, and installing the third grouting pipe in the pile section pipe pile;
Mounting the fixing sheets on the inner walls of the pile bottom pipe pile and the pile section pipe pile;
casting concrete, prefabricating pile bottom pipe pile joints and pile section pipe pile joints;
and installing the connecting device on a third grouting pipe extending to the outside of the lower end plate in each pile section pipe pile joint.
6. The application method of the intelligent penetration pipe pile capable of realizing grouting at different depths is characterized by comprising the following steps of: use of the intelligent penetration pipe pile capable of realizing grouting at different depths according to claim 1, comprising,
Setting out the pile position, and hoisting and feeding the pile after the pile machine is in place;
Connecting a plurality of pile section pipe pile joints in sequence and then connecting the pile section pipe pile joints with pile bottom pipe pile joints;
a connecting pipe is arranged at a grouting port at the upper end of a third grouting pipe in the uppermost pile section pipe pile joint, so that the third grouting pipe is connected with an external grouting device;
pile pressing is carried out, pile end soil pressure is collected in real time through a pressure sensor in the pile pressing process, and the depth of a weak soil layer is judged through penetration data;
Continuously pressing the pipe pile into the soft soil layer, enabling a slurry outlet of the second grouting pipe to be positioned at the middle section of the soft soil layer measured by sounding, and starting a grouting device to perform grouting at the pile side so as to realize solidification treatment of the soft soil layer at the pile side;
and closing the grouting device, stopping grouting at the pile side, continuously pressing the pipe pile until the designed depth is reached, and starting the grouting device to perform grouting at the pile end so as to realize solidification treatment on the soil layer at the end part of the pipe pile.
CN202210708799.4A 2022-06-22 2022-06-22 Intelligent penetration pipe pile capable of realizing grouting at different depths and manufacturing method and using method thereof Active CN114991136B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210708799.4A CN114991136B (en) 2022-06-22 2022-06-22 Intelligent penetration pipe pile capable of realizing grouting at different depths and manufacturing method and using method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210708799.4A CN114991136B (en) 2022-06-22 2022-06-22 Intelligent penetration pipe pile capable of realizing grouting at different depths and manufacturing method and using method thereof

Publications (2)

Publication Number Publication Date
CN114991136A CN114991136A (en) 2022-09-02
CN114991136B true CN114991136B (en) 2024-05-28

Family

ID=83037913

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210708799.4A Active CN114991136B (en) 2022-06-22 2022-06-22 Intelligent penetration pipe pile capable of realizing grouting at different depths and manufacturing method and using method thereof

Country Status (1)

Country Link
CN (1) CN114991136B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115977097A (en) * 2023-01-18 2023-04-18 上海勘察设计研究院(集团)有限公司 Grouting device capable of screwing out pile bottom of hollow pile and pile bottom grouting method

Citations (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0312927U (en) * 1989-06-12 1991-02-08
CN101182716A (en) * 2007-12-05 2008-05-21 中北大学 Pile sinking method of Synchronization grouting static pressure precast pile
CN102691296A (en) * 2012-05-22 2012-09-26 广州市建筑科学研究院有限公司 Pipe pile foundation for static-pressure grouting on pile side and rotary jet grouting at pile bottom and construction method thereof
CN203213101U (en) * 2013-03-19 2013-09-25 浙江天润建设有限公司 Embedding grouting combined pile
CN104594357A (en) * 2015-01-19 2015-05-06 赵连平 Grouting device after statically pressing or hammering concrete precast tubular pile base and grouting method
CN107268613A (en) * 2017-07-31 2017-10-20 袁雪峰 Lock-bit jump ring Prefabricated Concrete joint and Hybrid connections structure
CN107460869A (en) * 2017-07-26 2017-12-12 大成科创基础建设股份有限公司 Extra high load bearing capacity large-diameter tubular pile and quick pile sinking secondary grouting method
CN108797587A (en) * 2018-07-09 2018-11-13 江苏地基工程有限公司 A kind of novel sinking construction technology of static pressed pile
CN208472705U (en) * 2018-06-11 2019-02-05 北京市地质工程公司 It is a kind of can slip casting prefabricated pile and application this can slip casting prefabricated pile support construction
CN109706984A (en) * 2019-01-31 2019-05-03 沙焕焕 The construction method for dredging long composite pile system based on measured data
CN208953739U (en) * 2018-11-06 2019-06-07 杭州麦田通信技术有限公司 A kind of anti-connector of tower
KR102019956B1 (en) * 2018-10-22 2019-09-11 홍석희 Bulb Anchor by synchronizing the expansion and tightness, and construction method using it
CN211948389U (en) * 2019-12-11 2020-11-17 四会市华誉联合管桩建材有限公司 Prestressed pipe pile joint
CN212612454U (en) * 2020-06-30 2021-02-26 中冶建工集团有限公司 Recoverable hollow anchor pipe barb top pressing device
CN112627175A (en) * 2020-12-18 2021-04-09 中铁第五勘察设计院集团有限公司 Cement mixing pile construction system and method
CN112832235A (en) * 2021-01-08 2021-05-25 翟宇思 Construction method and construction device for precast pile post-grouting
CN113266013A (en) * 2021-04-21 2021-08-17 隋付仁 Pile end pressure grouting construction process for prestressed concrete pipe pile
CN113622418A (en) * 2021-08-10 2021-11-09 上海市机械施工集团有限公司 Prestressed concrete pipe pile structure and construction method
CN114215045A (en) * 2022-01-14 2022-03-22 湖北捷固筑工科技有限公司 Precast concrete pile and using method thereof
CN114351688A (en) * 2021-12-30 2022-04-15 浙江坤德创新岩土工程有限公司 Pile side grouting and pile end extrusion grouting system for cast-in-place pile and construction method thereof
CN114541472A (en) * 2022-03-21 2022-05-27 湖南城市学院 Reinforced retaining wall structure

Patent Citations (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0312927U (en) * 1989-06-12 1991-02-08
CN101182716A (en) * 2007-12-05 2008-05-21 中北大学 Pile sinking method of Synchronization grouting static pressure precast pile
CN102691296A (en) * 2012-05-22 2012-09-26 广州市建筑科学研究院有限公司 Pipe pile foundation for static-pressure grouting on pile side and rotary jet grouting at pile bottom and construction method thereof
CN203213101U (en) * 2013-03-19 2013-09-25 浙江天润建设有限公司 Embedding grouting combined pile
CN104594357A (en) * 2015-01-19 2015-05-06 赵连平 Grouting device after statically pressing or hammering concrete precast tubular pile base and grouting method
CN107460869A (en) * 2017-07-26 2017-12-12 大成科创基础建设股份有限公司 Extra high load bearing capacity large-diameter tubular pile and quick pile sinking secondary grouting method
CN107268613A (en) * 2017-07-31 2017-10-20 袁雪峰 Lock-bit jump ring Prefabricated Concrete joint and Hybrid connections structure
CN208472705U (en) * 2018-06-11 2019-02-05 北京市地质工程公司 It is a kind of can slip casting prefabricated pile and application this can slip casting prefabricated pile support construction
CN108797587A (en) * 2018-07-09 2018-11-13 江苏地基工程有限公司 A kind of novel sinking construction technology of static pressed pile
KR102019956B1 (en) * 2018-10-22 2019-09-11 홍석희 Bulb Anchor by synchronizing the expansion and tightness, and construction method using it
CN208953739U (en) * 2018-11-06 2019-06-07 杭州麦田通信技术有限公司 A kind of anti-connector of tower
CN109706984A (en) * 2019-01-31 2019-05-03 沙焕焕 The construction method for dredging long composite pile system based on measured data
CN211948389U (en) * 2019-12-11 2020-11-17 四会市华誉联合管桩建材有限公司 Prestressed pipe pile joint
CN212612454U (en) * 2020-06-30 2021-02-26 中冶建工集团有限公司 Recoverable hollow anchor pipe barb top pressing device
CN112627175A (en) * 2020-12-18 2021-04-09 中铁第五勘察设计院集团有限公司 Cement mixing pile construction system and method
CN112832235A (en) * 2021-01-08 2021-05-25 翟宇思 Construction method and construction device for precast pile post-grouting
CN113266013A (en) * 2021-04-21 2021-08-17 隋付仁 Pile end pressure grouting construction process for prestressed concrete pipe pile
CN113622418A (en) * 2021-08-10 2021-11-09 上海市机械施工集团有限公司 Prestressed concrete pipe pile structure and construction method
CN114351688A (en) * 2021-12-30 2022-04-15 浙江坤德创新岩土工程有限公司 Pile side grouting and pile end extrusion grouting system for cast-in-place pile and construction method thereof
CN114215045A (en) * 2022-01-14 2022-03-22 湖北捷固筑工科技有限公司 Precast concrete pile and using method thereof
CN114541472A (en) * 2022-03-21 2022-05-27 湖南城市学院 Reinforced retaining wall structure

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
桩侧注浆技术在预应力混凝土管桩中的应用;游兆源;;山西建筑(11);第120-121页 *
梁建锋 ; 周培康 ; 王新泉 ; 崔允亮 ; 乔文开 ; .超长摩擦桩桩端桩侧联合注浆工艺研究.山西建筑.2016,(12),第133-134页. *
游兆源 ; .桩侧注浆技术在预应力混凝土管桩中的应用.山西建筑.2007,(11),第120-121页. *
超长摩擦桩桩端桩侧联合注浆工艺研究;梁建锋;周培康;王新泉;崔允亮;乔文开;;山西建筑(12);第133-134页 *

Also Published As

Publication number Publication date
CN114991136A (en) 2022-09-02

Similar Documents

Publication Publication Date Title
CN114991136B (en) Intelligent penetration pipe pile capable of realizing grouting at different depths and manufacturing method and using method thereof
WO2024001680A1 (en) Waterproof uplift-resistant pile and construction method
CN109653682A (en) Bore the adjustable drill bit of diameter and hole digging machine
CN105350531A (en) Pipe pile-anchor rod composite foundation capable of bearing pulling and pressing bidirectional loads and construction technology
CN103485347A (en) Batter pile used for building foundation pit support and construction method thereof
CN111576446A (en) In-situ protection device for pressure pipeline in underground foundation pit and construction method
CN112982472B (en) Power transmission tower foundation structure suitable for regions without bedrock and construction method
CN201077988Y (en) Hidden beam-column type prestressing force earth nail wall
CN1912253A (en) Construction method of prestressed tubular pile
CN111877365A (en) H-shaped steel combined steel sheet pile continuous wall combined supporting system and construction method thereof
CN114892672B (en) Foundation pit supporting construction process method
CN214695645U (en) Supporting structure capable of applying prestress
WO2023131936A2 (en) Bioinspired skirted footing and its method of installation
CN111101509A (en) Prefabricated root type pile structure and construction method
CN206616602U (en) A kind of outdoor construction elevator strengthening of foundation device
CN114045815A (en) PRC (prestressed concrete pipe) pipe pile for deep foundation pit supporting and pile splicing method thereof
CN113668555A (en) Deep foundation pit supporting construction method for large-pipe-diameter prestressed row piles
CN202266065U (en) Heliostat pillar
CN111455979A (en) PHC pile construction process for bottom mud treatment plant
CN101761097A (en) Device for testing pile bottom stress of bored concrete pile
Gispert Prefabricated foundations for housing applied to room modules
CN220953523U (en) Pressure type filling-free underground structure
CN201649059U (en) Bottom stress testing device of bored concrete pile
Cox et al. Static and cyclic axial load tests on two 762 mm diameter pipe piles in clays
CN115478548B (en) Expansion soil cutting side slope expansion-reducing anti-seismic disaster-preventing combined retaining structure and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant