Prior art keywords
steel bar
bar structure
supporting
opposite sides
adjustable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210656343.8A
Other languages
Chinese (zh)
Inventor
董志成
李华飞
吴松华
刘天旭
吕何伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Rail Transit Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Rail Transit Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Rail Transit Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Rail Transit Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN202210656343.8A priority Critical patent/CN114961114A/en
Publication of CN114961114A publication Critical patent/CN114961114A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • E04C5/20Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups of material other than metal or with only additional metal parts, e.g. concrete or plastics spacers with metal binding wires
    • E04C5/206Spacers having means to adapt the spacing distance
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/06Tying means; Spacers ; Devices for extracting or inserting wall ties
    • E04G17/065Tying means, the tensional elements of which are threaded to enable their fastening or tensioning

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses a steel bar installation device with adjustable spacing and a construction method thereof, wherein the device comprises: the opposite-pulling screw rod penetrates through the steel bar structure and is pulled and connected between the two formworks on the two opposite sides of the steel bar structure, and a gap is formed between the steel bar structure and the formworks; the two screwing pieces are screwed on the counter-pulling screw respectively and are arranged in gaps on two opposite sides of the steel bar structure respectively; and the supporting and jacking pieces can wind the counter-pulling screw rods and are rotatably arranged on the screwing pieces, two limiting through grooves are respectively formed in the opposite sides of the supporting and jacking pieces, and the reinforcing steel bars on the two opposite sides of the reinforcing steel bar structure are respectively embedded in the two limiting through grooves of the supporting and jacking pieces so as to prevent the distance between the reinforcing steel bar structure and the two templates from changing. The invention solves the problem that the space between the protection layers of the existing vertical steel bars is mainly controlled by the cushion block, but the cushion block is easy to damage.

Description

Steel bar installation device with adjustable spacing and construction method thereof
Technical Field
The invention relates to the technical field of building construction, in particular to a steel bar installation device with adjustable spacing and a construction method thereof.
Background
With the continuous development of building construction technology, reinforced concrete is a conventional construction technology. Conventional reinforcement, especially the reinforcing bar more than 20mm in diameter, vertical steel bar protective layer interval is difficult for adjusting, relies on the cushion completely to carry out protective layer interval and controls, then is difficult for carrying out the secondary adjustment if after the steel bar welded fastening, especially at the special position reinforcing bar, the cushion still damages easily.
The information disclosed in this background section is only for enhancement of understanding of the general background of the invention and should not be taken as an acknowledgement or any form of suggestion that this information forms the prior art already known to a person skilled in the art.
Disclosure of Invention
In order to overcome the defects in the prior art, the invention provides the steel bar installation device with the adjustable interval and the construction method thereof, so as to solve the problems that the interval of the conventional vertical steel bar protective layer is not easy to adjust, is mainly controlled by a cushion block, but the cushion block is easy to damage.
In order to achieve the above object, there is provided a reinforcement installation device with adjustable interval, comprising:
the opposite-pulling screw rod penetrates through the steel bar structure and is pulled and connected between the two formworks on the two opposite sides of the steel bar structure, and a gap is formed between the steel bar structure and the formworks;
the two screwing pieces are screwed on the counter-pulling screw respectively and are arranged in gaps on two opposite sides of the steel bar structure respectively; and
the supporting and jacking pieces can be rotatably arranged on the screwing piece around the opposite-pulling screw rods, limiting through grooves are formed in the opposite sides of the supporting and jacking pieces respectively, and reinforcing steel bars on the two opposite sides of the reinforcing steel bar structure are embedded in the limiting through grooves of the supporting and jacking pieces respectively so as to prevent the distance between the reinforcing steel bar structure and the two templates from changing.
Furthermore, the screw-thread part is provided with a screw-thread through hole, and the screw-thread through hole is screwed in the counter-pulling screw rod.
Furthermore, an annular sliding groove is formed in one end, facing the steel bar structure, of the screwing piece, the supporting and ejecting piece is connected with a rotating piece, and the rotating piece is arranged in the annular sliding groove in a sliding mode.
Further, the annular chute is circular and is coaxial with the threaded through hole.
Furthermore, the rotating part is a sleeve, one end of the sleeve can be embedded in the annular sliding groove in a rotating mode around the axis of the sleeve, and the other end of the sleeve extends to the outside of the annular sliding groove and is connected with the supporting and ejecting part.
Furthermore, the supporting and ejecting piece comprises two pressing plates, the two pressing plates are respectively connected to two opposite sides of the other end of the sleeve, notches are formed in the pressing plates, and the notches of the two pressing plates are communicated to form the limiting through groove.
The invention provides a construction method of a steel bar installation device with adjustable spacing, which comprises the following steps:
after binding the steel bar structure, respectively installing templates on two opposite sides of the steel bar structure, so that a gap is formed between the steel bar structure and the templates;
installing split screws on the formworks at two sides of the steel bar structure;
rotate two spiral shell closes the piece in order to adjust the position of spiral shell closes the piece, make the spiral shell close the piece set up in the clearance of steel bar structure's both sides, just the reinforcing bar of steel bar structure's relative both sides inlays respectively to locate in the spacing logical groove of two back-ups in order to prevent steel bar structure and two distance between the template changes.
The space-adjustable steel bar installation device has the advantages that the split screw rods arranged on the template are of the main structure, the threaded parts and the supporting and ejecting parts are arranged on the split screw rods, the steel bar structure is locked through the supporting and ejecting parts on the two opposite sides of the steel bar structure, the thickness of the vertical protective layers on the two sides of the steel bar structure is kept unchanged, and the space-adjustable steel bar installation device meets design requirements. The steel bar installation device with the adjustable interval is suitable for reinforced concrete structures with different protective layer thickness requirements, and the distance between the screwing piece and the template can be adjusted so as to be adapted to different protective layer thicknesses.
Drawings
Other features, objects and advantages of the present application will become more apparent upon reading of the following detailed description of non-limiting embodiments thereof, made with reference to the accompanying drawings in which:
fig. 1 is a schematic structural view of a space-adjustable rebar installation device according to an embodiment of the invention.
Fig. 2 is a front view of a support member of an embodiment of the present invention.
Fig. 3 is a cross-sectional view taken at a-a in fig. 2.
Fig. 4 is a schematic structural view of a counter screw according to an embodiment of the present invention.
Detailed Description
The present application will be described in further detail with reference to the following drawings and examples. It is to be understood that the specific embodiments described herein are merely illustrative of the relevant invention and not restrictive of the invention. It should be noted that, for convenience of description, only the portions related to the present invention are shown in the drawings.
It should be noted that the embodiments and features of the embodiments in the present application may be combined with each other without conflict. The present application will be described in detail below with reference to the embodiments with reference to the attached drawings.
Referring to fig. 1 to 4, the present invention provides an adjustable-pitch reinforcing bar installation apparatus, including: the device comprises a split screw rod 1, two screw elements 2 and two top elements 3.
The opposite-pulling screw rod 1 penetrates through the steel bar structure 5. The opposite-pulling screw rods 1 are pulled and connected between the two formworks 4 on the two opposite sides of the steel bar structure 5. A gap B is formed between the rebar structure 5 and the form 4.
The two screw pieces 2 are respectively screwed at two ends of the counter-pulling screw rod 1. The two screw pieces 2 are respectively arranged in the gaps B at two opposite sides of the steel bar structure 5.
Each of the supporting members 3 is rotatably mounted to a screw member 2 about a counter screw 1. The opposite sides of the two supporting pieces 3 are respectively provided with a limiting through groove 30. The reinforcing steel bars on two opposite sides of the reinforcing steel bar structure 5 are respectively embedded in the limiting through grooves 30 of the two supporting pieces 3 so as to prevent the distance between the reinforcing steel bar structure 5 and the two formworks 4 from changing.
Referring to fig. 1, in the construction of the steel bar structure, after the counter pull screw is installed between the two formworks, the position of the screw on the counter pull screw is adjusted by rotating the screw, so that the screw is disposed in the gap. And then the supporting and ejecting piece is rotated around the counter-pulling screw rod, so that the limiting through grooves of the supporting and ejecting piece are aligned to the reinforcing steel bars on two sides of the reinforcing steel bar structure. After the limiting through groove is aligned to the steel bar of the steel bar structure, the screwing piece is rotated, so that the steel bar of the steel bar structure is embedded in the limiting through groove of the supporting and ejecting piece. Because the relative both sides of steel bar structure have respectively to prop up the piece from steel bar structure's relative both sides and carry out the top in order to lock steel bar structure, and then ensure that the clearance is indeformable, then the distance of steel bar structure's both sides to the template remains unchanged, and that limit is behind the concreting, and the thickness of the vertical protective layer of steel bar structure's both sides also can remain unchanged.
According to the spacing-adjustable steel bar installation device, the split screw rods arranged on the template are of the main structure, the screwing pieces and the supporting pieces are arranged on the split screw rods, and the steel bar structure is locked through the supporting pieces on the two opposite sides of the steel bar structure so as to ensure that the thickness of the vertical protective layers on the two sides of the steel bar structure is kept unchanged, and the design requirements are met. The steel bar installation device with the adjustable interval is suitable for reinforced concrete structures with different protective layer thickness requirements, and the distance between the screwing piece and the template can be adjusted so as to be adapted to different protective layer thicknesses.
In this embodiment, the screw member 2 is provided with a threaded through hole. The threaded through hole is screwed with the counter-pulling screw rod 1.
As a preferred embodiment, an annular sliding groove is formed at one end of the screw member 2 facing the reinforcing steel bar structure 5. The supporting member 3 is connected with a rotating member 32. The rotating member 32 is slidably disposed in the annular slide groove.
In this embodiment, the annular sliding groove is circular and is disposed on an end surface of the screw member facing one end of the steel bar structure. The annular sliding groove and the threaded through hole are coaxially arranged.
Referring to fig. 3, in the present embodiment, the rotating member 32 is a sleeve. The size of the sleeve pipe orifice is matched with the size of the annular sliding groove. One end of the sleeve can be embedded in the annular sliding groove in a rotating mode around the axis of the sleeve, and the other end of the sleeve extends to the outside of the annular sliding groove and is connected with the supporting and jacking piece 3.
With continued reference to fig. 2 and 3, the supporting member 3 includes two pressing plates 31 disposed opposite to each other. Two pressing plates 31 are respectively connected to opposite sides of the other end of the sleeve. The pressing plate 31 is provided with a notch 310. The notches 310 of the two pressure plates 31 are communicated to form a limiting through groove 30.
The invention provides a construction method of a steel bar installation device with adjustable spacing, which comprises the following steps:
s1: after the reinforcing steel bar structure 5 is bound, the formworks 4 are respectively installed on two opposite sides of the reinforcing steel bar structure 5, so that a gap B is formed between the reinforcing steel bar structure 5 and the formworks 4.
S2: opposite-pulling screw rods 1 are arranged on formworks 4 on two sides of the steel bar structure 5.
S3: two spiral shell spares 2 are rotated in order to adjust the position of spiral shell spares 2 for spiral shell spares 2 set up in the clearance B of the both sides of steel bar structure 5, and the reinforcing bar of the relative both sides of steel bar structure 5 inlays respectively and locates in the spacing logical groove 30 of two top elements 3 in order to prevent that the distance between steel bar structure 5 and two templates 4 from changing.
The interval-adjustable steel bar installation device is applied to steel bar binding in the engineering construction process. When the space or region limited high and large template steel bar binding and steel bar positioning are difficult to control, or the diameter of the steel bar is too large and difficult to adjust, especially when the installation template is in a counter-pulling type reinforcement mode, the steel bar installation device with the adjustable space can be used under the condition that the thickness of the steel bar protection layer is difficult to control and adjust, the problem of steel bar space adjustment can be well solved, and the adjustment can be carried out at any time.
The steel bar installation device with the adjustable space is convenient to operate and quick to install; the material usage is reduced; the labor time and the cost are reduced; adjusting at any time; high rigidity and no space limitation.
The above description is only a preferred embodiment of the application and is illustrative of the principles of the technology employed. It will be appreciated by a person skilled in the art that the scope of the invention as referred to in the present application is not limited to the embodiments with a specific combination of the above-mentioned features, but also covers other embodiments with any combination of the above-mentioned features or their equivalents without departing from the inventive concept. For example, the above features may be replaced with (but not limited to) features having similar functions disclosed in the present application.

Claims (7)

1. The utility model provides a reinforcing bar installation device of adjustable interval which characterized in that includes:
the opposite-pulling screw rod penetrates through the steel bar structure and is pulled and connected between the two formworks on the two opposite sides of the steel bar structure, and a gap is formed between the steel bar structure and the formworks;
the two screwing pieces are screwed on the counter-pulling screw respectively and are arranged in gaps on two opposite sides of the steel bar structure respectively; and
the supporting and jacking pieces can be rotatably arranged on the screwing piece around the opposite-pulling screw rods, limiting through grooves are formed in the opposite sides of the supporting and jacking pieces respectively, and reinforcing steel bars on the two opposite sides of the reinforcing steel bar structure are embedded in the limiting through grooves of the supporting and jacking pieces respectively so as to prevent the distance between the reinforcing steel bar structure and the two templates from changing.
2. The adjustable-pitch reinforcing bar installation device according to claim 1, wherein the screw member is provided with a threaded through hole, and the threaded through hole is screwed with the split screw.
3. The adjustable-pitch reinforcing steel bar installation device according to claim 2, wherein one end of the screwing piece facing the reinforcing steel bar structure is provided with an annular sliding groove, the supporting and ejecting piece is connected with a rotating piece, and the rotating piece is slidably arranged in the annular sliding groove.
4. A device for installing adjustable-pitch rebars according to claim 3, wherein said annular runner is circular and is disposed coaxially with said threaded through-hole.
5. The adjustable-pitch reinforcing steel bar mounting device according to claim 4, wherein the rotating member is a sleeve, one end of the sleeve is rotatably embedded in the annular sliding groove around an axis thereof, and the other end of the sleeve extends to the outside of the annular sliding groove and is connected with the supporting member.
6. The adjustable-pitch rebar installation device according to claim 5, wherein the supporting and jacking piece comprises two pressing plates, the two pressing plates are respectively connected to two opposite sides of the other end of the sleeve, notches are formed in the pressing plates, and the notches of the two pressing plates are communicated to form the limiting through groove.
7. A construction method of an adjustable-pitch reinforcing bar installation device according to any one of claims 1 to 6, comprising the steps of:
after binding the steel bar structure, respectively installing templates on two opposite sides of the steel bar structure, so that a gap is formed between the steel bar structure and the templates;
installing split screws on the formworks on two sides of the steel bar structure;
rotate two closure in order to adjust the position of closure makes the closure set up in the clearance of steel bar structure's both sides, just the reinforcing bar of steel bar structure's relative both sides inlays respectively to locate in the spacing logical groove of two top elements to prevent steel bar structure and two distance between the template changes.
CN202210656343.8A 2022-06-10 2022-06-10 Steel bar installation device with adjustable spacing and construction method thereof Pending CN114961114A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210656343.8A CN114961114A (en) 2022-06-10 2022-06-10 Steel bar installation device with adjustable spacing and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210656343.8A CN114961114A (en) 2022-06-10 2022-06-10 Steel bar installation device with adjustable spacing and construction method thereof

Publications (1)

Publication Number Publication Date
CN114961114A true CN114961114A (en) 2022-08-30

Family

ID=82961525

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210656343.8A Pending CN114961114A (en) 2022-06-10 2022-06-10 Steel bar installation device with adjustable spacing and construction method thereof

Country Status (1)

Country Link
CN (1) CN114961114A (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09268708A (en) * 1996-03-28 1997-10-14 Fujita Corp Separator with retaining metal tool for reinforcements
CN103061505A (en) * 2013-01-14 2013-04-24 河北省第四建筑工程公司 Multifunctional split bolt and application thereof
CN204186001U (en) * 2014-10-28 2015-03-04 中冶建工集团有限公司 Shear wall protective layer thickness control device
CN205502619U (en) * 2016-01-06 2016-08-24 中国建筑第八工程局有限公司 A unilateral component mode structure for strengthening cross -section reinforcing construction
CN106639327A (en) * 2016-10-10 2017-05-10 中国冶集团有限公司 Positioning and reinforcing system and method for assembly type building cast-in-place connection layer reserved reinforcing steel bar
CN107724677A (en) * 2017-10-18 2018-02-23 宁波建工工程集团有限公司 Steel bar template positioning constructing structure and its construction method in reinforced concrete member
CN211923539U (en) * 2020-02-14 2020-11-13 四川省建筑机械化工程有限公司 Opposite-pulling screw rod replacing wall tie bar
CN215164588U (en) * 2021-05-06 2021-12-14 中交路桥建设有限公司 Pier stud steel bar protective layer thickness control device
CN216074792U (en) * 2021-10-20 2022-03-18 中交一公局第二工程有限公司 Reinforcing steel bar protection device fixed with structural object template
CN216196045U (en) * 2021-10-15 2022-04-05 中国葛洲坝集团第一工程有限公司 Accurate stop device of vertical reinforcing bar is contained to water delivery box

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09268708A (en) * 1996-03-28 1997-10-14 Fujita Corp Separator with retaining metal tool for reinforcements
CN103061505A (en) * 2013-01-14 2013-04-24 河北省第四建筑工程公司 Multifunctional split bolt and application thereof
CN204186001U (en) * 2014-10-28 2015-03-04 中冶建工集团有限公司 Shear wall protective layer thickness control device
CN205502619U (en) * 2016-01-06 2016-08-24 中国建筑第八工程局有限公司 A unilateral component mode structure for strengthening cross -section reinforcing construction
CN106639327A (en) * 2016-10-10 2017-05-10 中国冶集团有限公司 Positioning and reinforcing system and method for assembly type building cast-in-place connection layer reserved reinforcing steel bar
CN107724677A (en) * 2017-10-18 2018-02-23 宁波建工工程集团有限公司 Steel bar template positioning constructing structure and its construction method in reinforced concrete member
CN211923539U (en) * 2020-02-14 2020-11-13 四川省建筑机械化工程有限公司 Opposite-pulling screw rod replacing wall tie bar
CN215164588U (en) * 2021-05-06 2021-12-14 中交路桥建设有限公司 Pier stud steel bar protective layer thickness control device
CN216196045U (en) * 2021-10-15 2022-04-05 中国葛洲坝集团第一工程有限公司 Accurate stop device of vertical reinforcing bar is contained to water delivery box
CN216074792U (en) * 2021-10-20 2022-03-18 中交一公局第二工程有限公司 Reinforcing steel bar protection device fixed with structural object template

Similar Documents

Publication Publication Date Title
CN101949213A (en) Special support system of building structure deformed seam template
CN114961114A (en) Steel bar installation device with adjustable spacing and construction method thereof
CN103161313A (en) Connection method of main reinforcement of constructional column of infilled wall and framed girder
CN207420036U (en) Steel bar template positions constructing structure in reinforced concrete member
CN111809861B (en) Formwork supporting die for construction of building components on two sides of deformation joint and working method
CN218092018U (en) Be used for cast-in-place concrete beam, post regularization anchor clamps
CN210190135U (en) Prefabricated plate hoist and mount built-in fitting positioner
CN206591641U (en) A kind of fixing device of concrete column joint steel pipe post
CN212773439U (en) Assembly type structure outer wall PC component top reinforcing assembly
CN214144790U (en) Device suitable for vertical reinforcing bar location of wall post
CN113279565A (en) Tool type supporting structure for reinforcing ultra-thick inner wall and construction method
CN105369897A (en) Support of seismic isolation cushion
CN202755674U (en) Positioning installation component for embedded bolts
CN208309643U (en) A kind of adjustable diameter easily detachable inspection shaft well head steel form
CN219634119U (en) I-steel anchor ring embedded part for prefabricated laminated slab system
CN221346968U (en) Reinforcing bar interval and protective layer adjusting device
CN201874234U (en) Dedicated support system for deformation joint template of building structure
CN217711890U (en) Post-cast strip supporting component
CN217105839U (en) Reinforced concrete protective layer control device
CN215177440U (en) Building site measuring device convenient to adjust
CN211137618U (en) Horizontal reinforcing bar installation positioner of cross slab
CN210031877U (en) Embedded part for fixing foundation bolt
CN218029030U (en) Template reinforcing apparatus
CN219445474U (en) Adjusting device for gap of diaphragm wall
AU2021102887A4 (en) Prop locking device and method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination