CN114941401A - Construction method of double-layer appearance special-shaped concrete column - Google Patents
Construction method of double-layer appearance special-shaped concrete column Download PDFInfo
- Publication number
- CN114941401A CN114941401A CN202210607921.9A CN202210607921A CN114941401A CN 114941401 A CN114941401 A CN 114941401A CN 202210607921 A CN202210607921 A CN 202210607921A CN 114941401 A CN114941401 A CN 114941401A
- Authority
- CN
- China
- Prior art keywords
- special
- formwork
- column
- concrete
- shaped
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 29
- 238000009415 formwork Methods 0.000 claims abstract description 23
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 16
- 239000010959 steel Substances 0.000 claims abstract description 16
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 7
- 238000009434 installation Methods 0.000 claims description 14
- 238000004140 cleaning Methods 0.000 claims description 3
- 230000000694 effects Effects 0.000 claims description 3
- 238000005516 engineering process Methods 0.000 claims description 3
- 239000002023 wood Substances 0.000 claims description 3
- 238000000034 method Methods 0.000 abstract description 4
- 238000001125 extrusion Methods 0.000 abstract description 2
- 206010066054 Dysmorphism Diseases 0.000 description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 3
- 238000002360 preparation method Methods 0.000 description 2
- 230000007547 defect Effects 0.000 description 1
- 238000012946 outsourcing Methods 0.000 description 1
- 238000003672 processing method Methods 0.000 description 1
- 230000017260 vegetative to reproductive phase transition of meristem Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/30—Columns; Pillars; Struts
- E04C3/34—Columns; Pillars; Struts of concrete other stone-like material, with or without permanent form elements, with or without internal or external reinforcement, e.g. metal coverings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G13/00—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
- E04G13/02—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for columns or like pillars; Special tying or clamping means therefor
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The invention relates to a construction method of a double-layer appearance special-shaped concrete column; paving a fair-faced formwork of the fair-faced concrete of the outer facing and building a back edge after binding the external fair-faced concrete steel bars; the pre-buried screw is used for reinforcing the post; embedding a screw in the main body column, and wrapping an extruded sheet around the main body column to prevent the concrete of the patterned column from being bonded; erecting a support frame body; constructing the inner column, and then pouring an outer facing; and (5) taking out the extruded sheet. By adopting the special-shaped plate formwork supporting method, the formwork mounting quality of the special-shaped structure can be guaranteed, the single investment is lower than that of a steel formwork, the cost is saved, and the extrusion molding plate is adopted to replace part of the formwork in a narrow space, so that the problems that the structure interval is too small, the inner side formwork is not suitable for construction are solved, and the working efficiency is greatly improved.
Description
Technical Field
The invention relates to the technical field of concrete construction of special-shaped buildings, in particular to a construction method of a special-shaped concrete column with a double-layer appearance.
Background
The existing template reinforcing construction method for common concrete columns is more complex, and the template reinforcing method for the fair-faced concrete blossoming column is more complex than the template processing method for the common concrete columns, and if the fair-faced concrete of the exterior finish needs to adopt a fair-faced template to meet the impression requirement, the details to be paid attention to are more. Aiming at a complex special-shaped concrete structure, a shaped steel template is generally adopted during construction, and the formwork construction of the special-shaped structure is completed through shaped design, processing and template installation, but the shaped steel template has the advantages of heavy weight, high installation difficulty, high requirement on the installation matching degree of the special-shaped structure, and high construction cost.
Disclosure of Invention
The invention aims to overcome the defects and provides a construction method for forming a double-layer appearance special-shaped concrete column by one-step pouring, which can enable the concrete column to meet the requirement of attractive, harmonious and uniform column body.
In order to achieve the above object, the present invention is realized by:
a construction method of a double-layer appearance special-shaped concrete column comprises the following steps
Step 1, pre-burying a counter-pulling screw rod for supporting an external special-shaped plate template during concrete pouring of an internal structural column, and ensuring the template forming effect;
step 2, adopting a digital processing technology to finish the deepening processing of the special-shaped board wooden template and the back edge, arranging serial numbers to facilitate the subsequent template installation operation,
step 3, after the binding of the profiled sheet fair-faced concrete steel bars is finished, paving a fair-faced formwork of the fair-faced concrete of the outer facing and erecting a back ridge, and after the installation of the outer side of the wood back ridge is finished, enabling the outer part of the whole modeling column to be supported in a square shape so as to facilitate the installation of a support frame and a reinforcing system;
step 4, filling an extruded sheet in a narrow space at the bottom of the cavity of the internal and external structures, wherein the position is narrow in size, the formwork supporting operation cannot be completed manually, the extruded sheet is used as an inner side template of the special-shaped plate, and the internal and external structures can be separated without stress connection;
step 5, building a support frame body at the back edge of the template according to stress calculation;
and 6, taking out the extruded sheet after the construction of the special-shaped sheet is finished, and cleaning the cavity.
To having bilayer structure and outward appearance dysmorphism concrete column, if adopt regularization steel form to consolidate the outer facing template of open flower column structure, need carry out the regularization processing preparation of steel form, and only once use, the construction input is huge to the unable installation of the inside steel form in narrow and small space is difficult to guarantee the construction quality of concrete. By adopting the special-shaped plate formwork supporting method, the formwork mounting quality of the special-shaped structure can be guaranteed, the single investment is lower than that of a steel formwork, the cost is saved, and the extrusion molding plate is adopted to replace part of the formwork in a narrow space, so that the problems that the structure interval is too small, the inner side formwork is not suitable for construction are solved, and the working efficiency is greatly improved.
Detailed Description
The invention is further illustrated by the following specific examples.
A construction method of a double-layer appearance special-shaped concrete column comprises the following steps
Step 1, pre-burying a counter-pulling screw rod for supporting an external special-shaped plate template during concrete pouring of an internal structural column, and ensuring the template forming effect;
step 2, adopting a digital processing technology to complete the deepening processing of the special-shaped board wooden template and the back edge, arranging serial numbers so as to facilitate the subsequent template installation operation,
step 3, after the binding of the profiled sheet fair-faced concrete steel bars is finished, paving a fair-faced formwork of the fair-faced concrete of the outer facing and erecting a back ridge, and after the installation of the outer side of the wood back ridge is finished, enabling the outer part of the whole modeling column to be supported in a square shape so as to facilitate the installation of a support frame and a reinforcing system;
step 4, filling an extruded sheet in a narrow space at the bottom of the cavity of the internal and external structures, wherein the position is narrow in size, the formwork supporting operation cannot be completed manually, the extruded sheet is used as an inner side template of the special-shaped plate, and the internal and external structures can be separated without stress connection;
step 5, building a support frame body at the back edge of the template according to stress calculation;
and 6, taking out the extruded sheet after the construction of the special-shaped sheet is finished, and cleaning the cavity.
The construction method of the invention is further illustrated by a construction step of a concrete column with a flower-shaped scattering appearance:
the style of flowering post is double-deck concrete structure, and inside is the rectangle post, and the form structural slab is dispersed to the outsourcing dysmorphism, and interior outer structure is thrown off, and the rectangle post construction is under construction the back in advance, is carrying out outside special-shaped structural slab construction operation, can guarantee the atress and the impression requirement of inside and outside two part structure like this greatly, and outside special-shaped board construction steps are as follows:
step 1, after binding of external clear water concrete steel bars is completed, laying a clear water template of the outer facing clear water concrete and building back ridges.
And 2, pre-burying the screw for reinforcing the post-stage pattern column.
And 3, pre-burying a screw rod in the main body column, and wrapping an extruded plate around the main body column to ensure that the concrete of the patterned column cannot be bonded, so that the patterned column is not in stressed connection with the main body column.
And 4, building a support frame body.
And 5, constructing the inner column, and then pouring the outer facing.
And 6, taking out the extruded sheet.
To having bilayer structure and outward appearance dysmorphism's concrete column, if adopt regularization steel form to consolidate the exterior facing template of open column structure, need carry out the regularization processing preparation of steel form, and only once use, the construction input is huge to the unable installation of the inside steel form in narrow and small space is difficult to guarantee the construction quality of concrete. By adopting the special-shaped plate formwork supporting method, the formwork mounting quality of the special-shaped structure can be guaranteed, the single investment is lower than that of a steel formwork, the cost is saved, and in a narrow space, the extruded sheet is adopted to replace part of the formwork, so that the problems that the structure interval is too small, the inner side formwork is not suitable for construction are solved, and the working efficiency is greatly improved.
Claims (1)
1. A construction method of a double-layer appearance special-shaped concrete column is characterized by comprising the following steps:
step 1, pre-burying a counter-pulling screw rod for supporting an external special-shaped plate template during concrete pouring of an internal structural column, and ensuring the template forming effect;
step 2, adopting a digital processing technology to complete the deep processing of the special-shaped board wooden template and the back edge, arranging serial numbers so as to facilitate the subsequent template installation operation,
step 3, after the binding of the profiled sheet fair-faced concrete steel bars is finished, installing a fair-faced formwork of the fair-faced concrete of the outer facing and erecting a back ridge, and after the installation of the outer side of the wood back ridge is finished, enabling the outer part of the whole modeling column to be supported in a square shape so as to facilitate the installation of a support frame and a reinforcing system;
step 4, filling an extruded sheet in a narrow space at the bottom of the cavity of the internal and external structures, wherein the position is narrow in size, the formwork supporting operation cannot be completed manually, the extruded sheet is used as an inner side template of the special-shaped plate, and the internal and external structures can be separated without stress connection;
step 5, building a support frame body at the back edge of the template according to stress calculation;
and 6, taking out the extruded sheet after the construction of the special-shaped sheet is finished, and cleaning the cavity.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210607921.9A CN114941401A (en) | 2022-05-31 | 2022-05-31 | Construction method of double-layer appearance special-shaped concrete column |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210607921.9A CN114941401A (en) | 2022-05-31 | 2022-05-31 | Construction method of double-layer appearance special-shaped concrete column |
Publications (1)
Publication Number | Publication Date |
---|---|
CN114941401A true CN114941401A (en) | 2022-08-26 |
Family
ID=82909615
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210607921.9A Pending CN114941401A (en) | 2022-05-31 | 2022-05-31 | Construction method of double-layer appearance special-shaped concrete column |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114941401A (en) |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108412208A (en) * | 2018-04-27 | 2018-08-17 | 上海建工四建集团有限公司 | A kind of construction method with special-shaped hole wall |
CN113914605A (en) * | 2021-10-14 | 2022-01-11 | 北京益汇达清水建筑工程有限公司 | Assembling method of special-shaped double-curved-surface bare concrete wall |
-
2022
- 2022-05-31 CN CN202210607921.9A patent/CN114941401A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108412208A (en) * | 2018-04-27 | 2018-08-17 | 上海建工四建集团有限公司 | A kind of construction method with special-shaped hole wall |
CN113914605A (en) * | 2021-10-14 | 2022-01-11 | 北京益汇达清水建筑工程有限公司 | Assembling method of special-shaped double-curved-surface bare concrete wall |
Non-Patent Citations (3)
Title |
---|
江创福: "饰面清水混凝土施工质量控制", 《中国建材科技》 * |
白云生: "参数化设计实践—衢州市体育中心体育场", 《腾讯网-HTTPS://NEW.QQ.COM/RAIN/A/20220222A06Q0L00》 * |
赵资钦等: "大型复杂钢筋混凝土空间结构施工技术", 《广东土木与建筑》 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107143135B (en) | Structure-integrated heat-insulation decorative external template and external wall construction method thereof | |
CN106639068A (en) | Wall formwork infilled wall of cast-in-place reinforced concrete without support and construction method thereof and wall formwork veneer and production method of non-bearing infilled wall | |
CN103046465A (en) | Reinforcing construction method for foam core die precast hollow plate beam | |
CN104831852A (en) | Original version concrete bracket system construction method | |
CN101131009A (en) | Cast-in-place shaping construction method and shaping equipment | |
CN114941401A (en) | Construction method of double-layer appearance special-shaped concrete column | |
CN206591693U (en) | Exempt from the cast in situ ferroconcrete wall mould filling wall of support | |
CN211306731U (en) | Novel prefabricated assembled concrete stair mould | |
CN210216896U (en) | Prefabricated plate skeleton and prefabricated plate | |
CN110027110B (en) | Ring buckle type floating window outer wall prefabricating die and prefabricating method | |
CN217151237U (en) | Bay window aluminum die | |
CN106914984B (en) | Construction method of prefabricated composite structural slab | |
CN206873731U (en) | A kind of concrete hollow double-storied floor | |
CN201627361U (en) | FRP fiber reinforced plastic shell-wood mold combined template system | |
CN101418602B (en) | In-situ casting construction method of reinforced concrete structural system using phosphogypsum as wall material | |
CN210477286U (en) | Fixing device for one-step molding of sandwich heat-insulation PC (polycarbonate) component | |
CN210032346U (en) | Special-shaped composite supporting device | |
CN207296115U (en) | A kind of cast-in-situ floor high accuracy positioning control system | |
CN107268755A (en) | A kind of construction method of inlet for stom water | |
CN101210442B (en) | Construction method for column and architrave cornice | |
CN209179173U (en) | Tooling without mould concrete | |
CN109235709B (en) | Full cast-in-place outer wall structure of building | |
CN110666942A (en) | Manufacturing method of novel prefabricated concrete stair mold | |
CN109930712A (en) | The cast-in-place double mesh sheet of one kind exempt from the plaster dedicated framework of partition wall construction and its construction method | |
CN219732750U (en) | Combined template for roof cast-in-situ deformation joint |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20220826 |
|
RJ01 | Rejection of invention patent application after publication |