CN114791056A - Buried PE pipe mobile intelligent detection method based on 5G and GPS technologies - Google Patents

Buried PE pipe mobile intelligent detection method based on 5G and GPS technologies Download PDF

Info

Publication number
CN114791056A
CN114791056A CN202210320202.9A CN202210320202A CN114791056A CN 114791056 A CN114791056 A CN 114791056A CN 202210320202 A CN202210320202 A CN 202210320202A CN 114791056 A CN114791056 A CN 114791056A
Authority
CN
China
Prior art keywords
data
pipeline
intelligent detection
mobile intelligent
gps
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210320202.9A
Other languages
Chinese (zh)
Inventor
赵妍妍
黄厚明
贡志林
刘玉良
雷玉兰
张伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Special Equipment Safety Supervision Inspection Institute of Jiangsu Province
Original Assignee
Special Equipment Safety Supervision Inspection Institute of Jiangsu Province
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Special Equipment Safety Supervision Inspection Institute of Jiangsu Province filed Critical Special Equipment Safety Supervision Inspection Institute of Jiangsu Province
Priority to CN202210320202.9A priority Critical patent/CN114791056A/en
Publication of CN114791056A publication Critical patent/CN114791056A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/06Accessories therefor, e.g. anchors
    • F16L1/11Accessories therefor, e.g. anchors for the detection or protection of pipes in the ground
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17DPIPE-LINE SYSTEMS; PIPE-LINES
    • F17D5/00Protection or supervision of installations
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17DPIPE-LINE SYSTEMS; PIPE-LINES
    • F17D5/00Protection or supervision of installations
    • F17D5/005Protection or supervision of installations of gas pipelines, e.g. alarm
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F17STORING OR DISTRIBUTING GASES OR LIQUIDS
    • F17DPIPE-LINE SYSTEMS; PIPE-LINES
    • F17D5/00Protection or supervision of installations
    • F17D5/02Preventing, monitoring, or locating loss
    • F17D5/06Preventing, monitoring, or locating loss using electric or acoustic means

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Acoustics & Sound (AREA)
  • Pipeline Systems (AREA)

Abstract

The invention provides a mobile intelligent detection method of a buried PE pipe based on 5G and GPS technologies, wherein mobile intelligent detection equipment comprises an active sound wave device, a directional sound wave receiver, a GPS map positioning device, a 5G network, a gas acquisition and analysis sensor, a camera, a laser radar and an equipment computer.

Description

Mobile intelligent detection method for buried PE pipe based on 5G and GPS technology
Technical Field
The invention belongs to the technical field of PE pipe detection, and particularly relates to a mobile intelligent detection method for a buried PE pipe based on 5G and GPS technologies
Background
The French buried Gas PE pipeline detector Gas Tracker2 is the earliest developed equipment for detecting PE pipelines in the world by adopting a sound wave method, and has the advantages of reliable performance, international large brands, digital display, intuition and objectivity. The RAMAC X3M engineering detection type ground penetrating radar is a product released by the Swedish MALA company in 2000, and has the advantages that the display is visual and simple, and the detected image is displayed on a screen in real time, so that the depth of a pipeline can be directly detected.
The PE pipeline detection solution provided by Wuhan Hua Tongzhengchang detection technology Limited company consists of an active sound source detector (AAD-GAS-X), a broadband dual-frequency antenna ground penetrating radar and a drill rod, and integrates the functions of a French buried GAS PE pipeline detector GAS Tracker2 and a RAMAC X3M engineering detection type ground penetrating radar. The AAD detector combines the initiative sound principle, exerts sound wave vibration signal in pipeline gas, makes gas and pipeline produce the vibration in the pipeline, gathers and calculates on vertical pipeline with the receiver, cooperates dual-frenquency ground penetrating radar and borer probe again, can realize under complicated road surface environment, and to burying the accurate location depthkeeping of ground PE pipeline.
The PE pipeline detection solution of Xian' agile Tong intelligent instrument and equipment Limited company is also an active sound source method, the whole system consists of a sound wave emitter, a gas vibrator and a sound wave receiver 3, the artificial listening technology and the digital quantitative analysis technology are integrated, namely listening and digital display two-in-one products, the instrument integrates the prior digital display receiver and listening receiver technologies, the pipeline can be positioned more quickly and more easily through the artificial listening technology in the listening mode, and the pipeline can also be positioned more accurately through the non-listening vibration signal quantitative analysis technology in the detection mode.
PE pipeline solutions all have the following problems that the number of components is large, and the components usually consist of 3-4 different functional components; the workload is huge and the manual operation is too slow, in order to realize the detection and positioning functions, 3 field operators are usually needed for daily detection, 1 operator needs to identify the direction by contrasting a pipeline layout drawing, 1 operator carries a GPS device, and the other 1 operator carries a leakage detection device, the realization function is single, and only the positioning function of the PE pipeline can be realized; the interference of manual operation is too large, and judgment errors are easily caused by the difference of the individual sound resolving power in the operation process; after the detection finds a problem, the on-site operation personnel can only judge the problem, if the on-site judgment can not be carried out, the situation can not be fed back in time, and the feedback is carried out after the detection is finished, so that the repetition of the detection work and the waste of manpower and material resources are caused.
Disclosure of Invention
The invention aims to solve the defects of the prior art and provides a mobile intelligent detection method of a buried PE pipe based on 5G and GPS technologies.
Further, the steps are as follows;
a. installing an acoustic wave generating device at a corresponding position of the PE pipeline;
b. inputting a detection path on a control interface of a mobile intelligent detection platform, moving to an appointed position, manually controlling, putting down a detection receiver, collecting a first data point, moving to a corresponding position, collecting a second data point, moving again to collect a third data point to form a normal data datum line, defining a normal value interval, setting intervals between the collection points and alarming abnormal data;
c. starting automatic detection, moving the intelligent detection platform to a data acquisition process, operating to a specified interval position, lowering a detection receiver, acquiring real-time data, comparing the acquired real-time data with a reference line, normally recording data in a normal value interval, forming a real-time measurement curve, storing the real-time measurement curve in a local computer,
d. the GPS is used for positioning and marking the position of the pipeline, when the pipeline is abnormal, an alarm is triggered, the mobile intelligent detection platform stops at the abnormal position, the abnormal data point is manually rechecked, and the automatic detection process is started;
e. the mobile intelligent detection platform analyzes combustible gas in the air, and collects and records the combustible gas content of corresponding point positions;
f. the high-definition camera records the detection process and monitors the surrounding environment;
g. and uploading the acquired data of all point positions, the GPS positioning and gas analysis content data to a remote platform for storage through 5G and Internet of things technology.
h. And the remote platform simultaneously scores the data for the failure possibility and the failure consequence.
Further, the classification of the failure probability score includes technical archive data, operation condition data, safety management data and environment survey data, wherein the technical archive data include installation monitoring, operation starting data, design files, pipe element control, welding and inspection thereof, strength tests, tightness tests, concealed works, pass-through works and completion reports, the safety management conditions include annual inspection and comprehensive inspection, data storage, service life of pipes, line patrol system, line patrol frequency, line patrol mode, safety responsibility system, public education, maintenance of equipment and information management system, and the environment survey includes frequent degree of bottom surface activities, agricultural production activities and ground marks;
the grading content of the installation monitoring comprises that after the pipeline installation time is 2014.1.1 years without monitoring and inspection, before the pipeline installation time is 2014.1.1 years without monitoring and inspection, the quality of the monitoring and inspection unit does not meet the requirement, and the quality of the monitoring and inspection unit meets the requirement;
the grading content of the start-up data comprises the qualification of an installation unit, whether a project approval table exists, whether a construction contract exists, whether a construction organization design or a construction scheme exists, whether a construction technology exists and a safety transaction record exists;
the grading content of the design file comprises the qualification of a design unit, whether the design file exists or not, and the complete design change or incomplete design change is not needed;
the grading content of the control of the pipeline element comprises the qualification of a pipeline element manufacturing unit, the quality certification document of the pipeline element, the acceptance record of the pipeline element and the monitoring certificate of the pipe;
the grading content of welding and detection comprises the existence of a welding certificate of a welding operator, the existence of a welding process evaluation, the existence of a welding record, the existence of a welding appearance inspection record and the existence of welding quality detection;
the grading content of the strength test is whether a strength test record exists or not;
the grading content of the tightness test is whether a tightness test record exists or not;
the grading content of the hidden project comprises whether hidden project construction records exist, whether hidden project acceptance records exist, whether tracer line conductivity inspection records exist, whether grooves exist and backfilling qualified records exist;
the grading content of the crossing project comprises a directional crossing record or no crossing project and no corresponding record, a crossing acceptance record or no crossing project and no acceptance record;
the grading content of the completion report is whether an engineering completion acceptance report exists or not.
The scoring content of the operation condition data comprises whether the pressure of a conveying medium is overpressure, whether the pressure of the conveying medium is required to be transformed and maintained or whether the data is complete or deficient, whether the records of daily operation and maintenance are complete or deficient, whether the records of hidden danger investigation and treatment are complete or deficient, whether the records of faults and accidents are complete or deficient, whether a conveying medium analysis report exists, whether an operator is on duty or not, whether a training system is established or not, and whether the training system is established or not;
the grading content of annual inspection and comprehensive inspection comprises that the grading content is implemented according to the standard requirements, is implemented only when a problem is found, and is not implemented;
the grading content of the data storage is whether the technology file data and the operation condition data are stored completely;
the grading content of the service life of the pipeline comprises 0-15 years (including 15 years), 15-25 years (including 25 years) and 25-50 years (including 50 years);
the scoring content of the line patrol system comprises whether a pipeline patrol system exists or not, whether a specially-assigned person patrols the line or not and whether a line patrol report is accurate and credible or not;
the scoring content of the line patrol frequency comprises at least one time per day, one time per day to twice per week, less than two times per week and no line patrol;
the grading content of the line patrol mode comprises that only pipe sections which are frequently constructed and excavated are patrolled step by step along the line and the line is not patrolled;
the grading content of the safety responsibility system comprises whether a safety management regulation system is established or not, whether safety mechanisms and personnel exist or not and whether the personnel are actually found or not;
the scoring content of the public education comprises whether public education data pipeline safety knowledge education exists or not, whether peripheral residents are clear in pipeline cognition or not, and whether third-party construction has a cross record or not;
the scoring content of the maintenance of the equipment device comprises whether a maintenance plan exists or not, whether the maintenance is carried out regularly or not and parts are replaced;
the grading content of the information management system is whether the information management system such as a GIS (geographic information System) and a PIMS (particle image management System) exists or not;
the scoring content of the ground activity frequency degree comprises a main road of a railway or a road, a common road, a pedestrian path and a green belt cell;
the grading content of the agricultural production activities is whether the agricultural production activities exist or not;
the grading content of the ground mark comprises that the ground mark is complete and clearly visible, the ground mark is damaged or unclear, and no ground mark exists;
further, the items for scoring the failure consequences include medium combustibility, medium toxicity, maximum operating pressure, maximum leakage, terrain, wind speed, population density, environment along the line, leakage cause, repair time, extent and degree of influence of supply interruption, dependence of users on the medium conveyed by the pipeline;
the scoring content of the combustibility of the medium comprises that if the medium is natural gas, artificial gas and liquefied petroleum gas;
the scoring content of the medium toxicity comprises if the medium is natural gas, if the medium is artificial gas, and if the medium is liquefied petroleum gas;
the grading content of the highest working pressure comprises that if the highest working pressure is more than 0.1MPa and less than or equal to 0.2MPa, if the highest working pressure is more than 0.2MPa and less than or equal to 0.4MPa, and if the highest working pressure is more than 0.4MPa and less than or equal to 0.7 MPa;
the scoring content of the maximum workload comprises the maximum possible medium leakage quantity which is less than or equal to 45kg, the maximum possible medium leakage quantity which belongs to the group (450kg, 4500 kg), the maximum possible medium leakage quantity which belongs to the group (4500kg, 45000 kg), the maximum possible medium leakage quantity which belongs to the group (45000kg, 450000 kg) and the maximum possible medium leakage quantity which is more than 450000 kg;
the grading content of the terrain comprises possible terrain occlusion at a leakage position and possible terrain widening at the leakage position;
the scoring content of the wind speed comprises that the annual average wind speed at the possible leakage position is low, the annual average wind speed at the possible leakage position is medium, and the annual average wind speed at the possible leakage position is high;
the scoring content of the population density comprises that the possible leakage position is a waste people smoke region, the number of population in the range of 200m at two sides of the pipeline section in the range of 1.6km length of the possible leakage position is E [1, 100 ], the number of population in the range of 200m at two sides of the pipeline section in the range of 1.6km length of the possible leakage position is E [100, 300 ], the number of population in the range of 200m at two sides of the pipeline section in the range of 1.6km length of the possible leakage position is E [300, 500 ], and the number of population in the range of 200m at two sides of the pipeline section in the range of 1.6km length of the possible leakage position is more than or equal to 500;
the grading content of the environment along the line comprises that possible leaking parts are absentee tobacco areas, the areas of 200m at two sides of the pipeline section in the range with the length of 1.6km of the possible leaking parts are mostly agricultural production areas, the areas of 200m at two sides of the pipeline section in the range with the length of 1.6km of the possible leaking parts are mostly residential hotel entertainment areas, the areas of 200m at two sides of the pipeline section in the range with the length of 1.6km of the possible leaking parts are mostly commercial areas, the areas of 200m at two sides of the pipeline section in the range with the length of 1.6km of the possible leaking parts are mostly warehouse wharf stations and the like, and the areas of 200m at two sides of the pipeline section in the range with the length of 1.6km of the possible leaking parts are mostly industrial production residential areas;
the scoring content of the leakage reasons comprises that the most probable leakage reason is misoperation, the most probable leakage reason is welding quality, and the most probable leakage reason is third party damage or natural disaster;
the grading content of the emergency repair time comprises that if the emergency repair time is less than 1 day, if the emergency repair time belongs to [1 day, 2 days ], if the emergency repair time belongs to [2 days, 4 days ], if the emergency repair time belongs to [4 days, 7 days ], and if the emergency repair time is more than or equal to 7 days;
the grading content of the influence range and degree of the supply interruption comprises that if no important user has supply interruption, the influence on other units is general, if the supply interruption influences the industrial fuel in small towns of small cities, if the supply interruption influences the life of the small cities of small enterprises, if the supply interruption influences the life of medium-sized cities in general industrial production, and if the supply interruption influences the production life of large central cities of national important large enterprises;
the scoring of the user's dependence on the medium transported by the pipeline includes if the effect of the supply interruption is small, if there is a replacement medium available, if there is a self-contained storage facility, if the user has an absolute dependence on the medium transported by the pipeline.
The equipment computer is provided with a memory chip.
The camera is provided with a laser radar.
Has the advantages that:
integrate complete pipeline detection equipment through multiple equipment, use initiative sound source method, the trend line that forms carries out the pipeline location through GPS and carries out automatic line location of patrolling to the PE pipeline simultaneously, will in time upload to detection monitoring cloud system through the 5G signal, and report to the police to unusual data, the camera can take notes the all ring edge border of testing process, can realize remote control operation, remote platform simultaneously carries out the possibility of failure to grade and the consequence of failure is graded with data simultaneously, the score after grading conveniently reports, gather.
Drawings
FIG. 1 is a flow chart of a mobile intelligent detection method for buried PE pipes based on 5G and GPS technologies;
detailed description of the preferred embodiments
For the purpose of enhancing the understanding of the present invention, the present invention will be further described in detail with reference to the following examples and the accompanying drawings, which are only used for explaining the present invention and are not to be construed as limiting the scope of the present invention.
An implementation example;
a mobile intelligent detection method for a buried PE pipe based on 5G and GPS technologies is characterized in that mobile intelligent detection equipment comprises an active sound wave device, a directional sound wave receiver, a GPS map positioning device, a 5G network, a gas collection and analysis sensor, a camera, a laser radar and an equipment computer.
Further, the steps are as follows;
a. installing an acoustic wave generating device at a corresponding position of the PE pipeline;
b. inputting a detection path on a control interface of a mobile intelligent detection platform, moving to an appointed position, manually controlling, putting down a detection receiver, collecting a first data point, moving to a corresponding position, collecting a second data point, moving again to collect a third data point to form a normal data datum line, defining a normal value interval, setting intervals between the collection points and alarming abnormal data;
c. starting automatic detection, moving the intelligent detection platform to a data acquisition process, operating to a specified interval position, lowering a detection receiver, acquiring real-time data, comparing the acquired real-time data with a reference line, normally recording the data in a normal value interval, forming a real-time measurement curve, storing the real-time measurement curve in a local computer,
d. the GPS is used for positioning and marking the position of the pipeline, when the pipeline is abnormal, an alarm is triggered, the mobile intelligent detection platform stops at the abnormal position, the abnormal data point is manually rechecked, and the automatic detection process is started;
e. the mobile intelligent detection platform analyzes the combustible gas in the air, and collects and records the combustible gas content of the corresponding point;
f. recording the detection process by the high-definition camera, and monitoring the surrounding environment;
g. and uploading the acquired data of all point positions, the GPS positioning data and the gas analysis content data to a remote platform for storage through 5G and the Internet of things technology.
h. And the remote platform simultaneously scores the data for the failure possibility and the failure consequence.
Furthermore, the classification of the failure probability score comprises technical archive data (40%), operation condition data (14%), safety management data (34%) and environment survey data (12%), wherein the technical archive data comprises installation monitoring (10%), operation data (6%), design files (4%), pipeline element control (5%), welding and inspection (6%), strength test (1%), tightness test (1%), concealed engineering (4%), crossing engineering (2%) and completion report (1%), and the safety management conditions comprise annual inspection and comprehensive inspection (3%), data storage (2%), pipeline service life (5%), line patrol system (4%), line patrol frequency (3%), line patrol mode (3%), safety responsibility system (4%), public education (5%), Maintenance of equipment devices (2%) and an information management system (3%), wherein the environmental survey comprises the frequency of ground surface activities (5%), agricultural production activities (3%) and ground marks (4%);
the grading content of installation monitoring comprises that the pipeline installation time is 2014.1.1 years (10%) after the pipeline installation time is not monitored, the pipeline installation time is 2014.1.1 years (5%) before the pipeline installation time is monitored, the pipeline installation time is monitored but the qualification of a monitoring unit does not meet the requirement (2%), and the pipeline installation time is monitored and the qualification of the monitoring unit meets the requirement (0%);
the grading content of the start-up data comprises the qualification (2%) of an installation unit, whether a project approval table (1%) exists, whether a construction contract (1%) exists, whether a construction organization design or a construction scheme (1%) exists, whether a construction technology and a safety transaction record (1%);
the scoring content of the design file comprises the qualification (2%) of the design unit, the design file (1%) and the complete design change or the incomplete design change (1%);
the grading content controlled by the pipeline elements comprises the conditions (1%) of the manufacturing unit of the pipeline elements, the quality document (1%) of the pipeline elements, the acceptance record (1%) of the pipeline elements and the monitoring certificate (2%) of the pipes;
the grading contents of welding and inspection thereof comprise the existence of a welding employee certificate (2%) of a welding operator, the existence of a welding process evaluation (1%), the existence of a welding record (1%), the existence of a welding appearance inspection record (1%) and the welding quality inspection (1%);
the content of the score of the strength test is whether the strength test record (1%) exists;
the scoring content of the tightness test is whether the record of the tightness test is recorded (1%);
the scoring content of the hidden project comprises whether a hidden project construction record (1%) exists, whether a hidden project acceptance record (1%) exists, whether a tracer line conductivity check record (1%) exists, whether a groove exists and whether a backfill qualified record (1%);
the scoring content of the crossing project comprises a directional crossing record or no corresponding record (%) of the crossing project, a crossing acceptance record or no crossing project (1%), and an acceptance record (1%);
the grading content of the completion report is the completion acceptance report (1%);
the scoring content of the operation condition data comprises whether the pressure of a conveying medium is overpressure (2%), whether the pressure of the conveying medium is required to be transformed and maintained or whether the data is complete or deficient (2%), whether the records of daily operation and maintenance are complete or deficient (2%), whether the records of hidden danger investigation and treatment are complete or deficient (2%), whether the records of faults and accidents are complete or deficient (1%), whether an analysis report of the conveying medium exists (1%), whether an operator is on duty (2%), whether a training system is established (1%) and whether a training system is established (1%);
the scoring contents of the annual inspection and the comprehensive inspection comprise implementation according to the specification requirements (0%), implementation after finding problems (2%), and non-implementation (3%);
the scoring content of the data storage is whether the technical file data and the operation condition data are stored completely (2%);
the evaluation content of the service life of the pipeline comprises 0-15 years (including 15 years) (1%), 15-25 years (including 25 years) (3%), 25-50 years (including 50 years) (5%);
the scoring content of the line patrol system comprises whether a pipeline patrol system (1%) exists, whether a specially-assigned person patrols the line (1%) exists, and whether a line patrol report is accurate and credible (2%);
the scoring content of the line patrol frequency comprises at least once a day (0%), once a day to twice a week (1%), less than twice a week (2%), no line patrol (3%);
the scoring content of the line patrol mode comprises the steps of (0%) line routing, only routing and constructing frequently-excavated pipe sections (2%) and not routing (3%);
the grading content of the safety responsibility system comprises the existence of the established safety management regulation (1%), the existence of safety organizations and personnel (1%), and whether the people are actually fallen (2%);
the grading content of the public education comprises whether public education materials, pipeline safety knowledge education and the like exist (2%), whether peripheral residents know pipelines clearly (1%), and whether third-party construction has a bottom-meeting record or not (2%);
the scoring content of the maintenance of the equipment device comprises the existence of a maintenance plan (1%), whether to regularly maintain the maintenance and replace the component (1%);
the scoring content of the information management system is whether the information management system such as GIS, PIMS and the like exists or not (3 percent);
the scoring content of the ground activity frequency degree comprises a main road (5%) of a railway or a highway, a common highway (4%), a pedestrian road (2%) and a green belt cell (1%);
the scoring content of the agricultural production activity is whether the agricultural production activity exists (3%);
the scoring content of the ground mark comprises that the ground mark is complete and clearly visible (0%), the ground mark is damaged or unclear (2%) and the ground mark is not present (4%);
and if the pipeline is subjected to a pressure resistance test in the inspection process and the result is qualified, directly inspecting to obtain a score of 0. If the following conditions occur in the pipeline, the failure possibility score value is adjusted to be 100 points; and (3) directly checking that the pipeline cannot be implemented and is not subjected to the pressure test, performing the pressure test on the pipeline, and obtaining a unqualified result, and performing the material performance test on the pipeline, and obtaining an unqualified result.
Further, the items of the failure consequence score comprise medium combustibility (20%), medium toxicity (10%), highest working pressure (6%), maximum leakage (20%), terrain (6%), wind speed (9%), population density (20%), line environment (15%), leakage reason (8%), first-aid repair time (9%), influence range and degree of supply interruption (15%), and dependence of a user on a medium conveyed by a pipeline (12%);
the content of the medium flammability score includes if the medium is natural gas or artificial gas or liquefied petroleum gas (20%);
the scoring of medium toxicity includes if the medium is natural gas (4%), if the medium is artificial gas (10%), if the medium is liquefied petroleum gas (4%);
the grading content of the highest working pressure comprises that if the highest working pressure is more than 0.1MPa and less than or equal to 0.2MPa (2%), if the highest working pressure is more than 0.2MPa and less than or equal to 0.4MPa (4%), and if the highest working pressure is more than 0.4MPa and less than or equal to the highest working pressure
0.7MPa(6%);
The scoring content of the maximum working capacity comprises the maximum possible medium leakage quantity less than or equal to 45kg (4%), the maximum possible medium leakage quantity E (450kg, 4500 kg) (8%), the maximum possible medium leakage quantity E (4500kg (%), 45000kg (12%), the maximum possible medium leakage quantity E (45000kg, 450000kg (16%), and the maximum possible medium leakage quantity greater than 450000kg (20%);
the grade content of the terrain comprises the occlusion (1%) of the terrain at the possible leakage, the opening (6%) of the terrain at the possible leakage;
the scoring content of the wind speed comprises that the annual average wind speed at the possible leakage position is low (2%), the annual average wind speed at the possible leakage position is medium (6%), and the annual average wind speed at the possible leakage position is high (9%);
the scoring content of the population density comprises that the possible leakage position is a barren smoking area (0%), the number of population in the range of 200m at two sides of the pipeline section in the range of 1.6km length at the possible leakage position is an element [1, 100 ] (6%), the number of population in the range of 200m at two sides of the pipeline section in the range of 1.6km length at the possible leakage position is an element [100, 300 ] (12%), the number of population in the range of 200m at two sides of the pipeline section in the range of 1.6km length at the possible leakage position is an element [300, 500 ] (16%), and the number of population in the range of 200m at two sides of the pipeline section in the range of 1.6km length at the possible leakage position is more than or equal to 500 (20%);
the scoring content of the environment along the line comprises that possible leakage places are barren smoke areas (0%), most agricultural production areas (3%) in the range of 200m at two sides of the pipeline section in the range of 1.6km length of the possible leakage places are agricultural production areas (3%), most residential hotel entertainment and leisure areas in the range of 200m at two sides of the pipeline section in the range of 1.6km length of the possible leakage places are residential hotel entertainment and leisure areas (6%), most commercial areas (9%) in the range of 200m at two sides of the pipeline section in the range of 1.6km length of the possible leakage places are warehouse wharf stations and the like (12%), and most industrial production residential areas in the range of 200m at two sides of the pipeline section in the range of 1.6km length of the possible leakage places are industrial production residential areas (15%);
the scored contents of the leak causes include that the most likely leak cause is an operator error (1%), the most likely leak cause is weld quality (5%), and the most likely leak cause is a third party damage or natural disaster (8%);
the scoring content of the emergency repair time comprises that if the emergency repair time is less than 1 day (1%), if the emergency repair time belongs to [1 day, 2 days ] (3%), if the emergency repair time belongs to [2 days, 4 days ] (5%), if the emergency repair time belongs to [4 days, 7 days ] (7%), and if the emergency repair time is more than or equal to 7 days (9%);
the scoring content of the influence range and degree of the supply interruption comprises that if no important user supply interruption has no influence on other units, the influence is general (3%), if the supply interruption influences industrial fuel of small towns of small cities (6%), if the supply interruption influences the life of small cities of small enterprises (9%), if the supply interruption influences the life of general industrial production medium-sized cities (12%), and if the supply interruption influences the production life of large central cities of national important large enterprises (15%);
the content of the user's score on the dependence of the medium transported by the pipeline includes if the impact of the supply interruption is small (3%), if there is a replacement medium available (6%), if there is a self-contained storage facility (9%), if the user is absolutely dependent on the medium transported by the pipeline (12%).
The equipment computer is provided with a memory chip.
The camera is provided with a laser radar.
As shown in fig. 1;
when the mobile intelligent detection equipment finds an abnormal signal, the mobile intelligent detection equipment stops automatically cruising, stops at an abnormal signal point position, performs sound and light alarm, performs abnormal signal alarm to a remote intelligent control analysis center, and automatically sends GPS positioning.
And calling the background storage data by the remote intelligent control analysis center, analyzing the positioning point, calling the data such as municipal pipe network layout, geological environment, current inspection data and the like in the cloud database, and comparing and analyzing the acquired data with the acquired basic geological conditions, the operating conditions (temperature, pressure and medium) of the PE pipe and the season and temperature of the data acquisition.
Firstly, whether the abnormity is a common abnormity or a past year abnormity is judged through historical data stored by the system.
And secondly, judging whether the alarm signal is abnormal due to leakage or misinformation caused by the influence of pipe network coincidence, geological factors and the like through a system.
And finally, filing the data and establishing an independent file, and performing abnormal investigation on the spot by later-stage organization experts according to the data.
When the field detection personnel can not judge or need to further determine, the video communication can be carried out between the built-in 5G module carried by the mobile intelligent detection platform and the remote intelligent control analysis center. The remote intelligent control center records the video communication, operates the video communication equipment to survey the surrounding environment, combines the data acquired by the gas acquisition module, organizes a background professional technical team to perform real-time discussion and analysis, and obtains a necessary detection conclusion. If the detection conclusion cannot be obtained on site and further detection is determined to be necessary, the abnormal points can be collected, and a professional technical team is organized to perform on-site secondary inspection on the abnormal points.
The signals collected by the mobile intelligent detection platform are automatically stored in a cloud database for automatic filing, and according to the set detection data weight, the geological conditions of the data base, the operating conditions (temperature, pressure and medium) of the PE pipe and the season and temperature of the data collection at that time are combined, and the collected data are automatically classified and sorted by the above points.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents, improvements and the like that fall within the spirit and principle of the present invention are intended to be included therein.

Claims (6)

1. A mobile intelligent detection method for a buried PE pipe based on 5G and GPS technologies is characterized in that mobile intelligent detection equipment comprises an active sound wave device, a directional sound wave receiver, GPS map positioning, a 5G network, a gas acquisition and analysis sensor, a camera, a laser radar and an equipment computer.
2. The mobile intelligent detection method for the buried PE pipe based on the 5G and GPS technologies is characterized by comprising the following steps of;
a. installing an acoustic wave generating device at a corresponding position of the PE pipeline;
b. inputting a detection path on a control interface of a mobile intelligent detection platform, moving to an appointed position, manually controlling, putting down a detection receiver, collecting a first data point, moving to a corresponding position, collecting a second data point, moving again to collect a third data point to form a normal data datum line, defining a normal value interval, setting intervals between the collection points and alarming abnormal data;
c. starting automatic detection, moving the intelligent detection platform to enter a data acquisition process, operating to a specified interval position, lowering a detection receiver, acquiring real-time data, comparing the acquired real-time data with a reference line, normally recording data in a normal value interval, forming a real-time measurement curve, and storing the real-time measurement curve in a local computer;
d. the GPS is used for positioning and marking the position of the pipeline, when the pipeline is abnormal, an alarm is triggered, the mobile intelligent detection platform stops at the abnormal position, the abnormal data point is manually rechecked, and the automatic detection process is started;
e. the mobile intelligent detection platform analyzes combustible gas in the air, and collects and records the combustible gas content of corresponding point positions;
f. recording the detection process by the high-definition camera, and monitoring the surrounding environment;
g. and uploading the acquired data of all point positions, the GPS positioning data and the gas analysis content data to a remote platform for storage through 5G and the Internet of things technology.
h. And the remote platform simultaneously scores the data for the failure possibility and the failure consequence.
3. The intelligent detection method for the buried PE pipe mobile according to claim 2 based on 5G and GPS technology, characterized in that the classification of the failure probability score comprises technical file data, operation condition data, safety management data and environment survey data, the technical archive data comprises installation monitoring, operation data, design files, pipeline element control, welding and inspection, strength test, tightness test, concealed engineering, crossing engineering and completion report, the safety management conditions comprise annual inspection and comprehensive inspection, data storage, pipeline service life, line patrol system, line patrol frequency, line patrol mode, safety responsibility system, public education, maintenance of equipment and an information management system, the environmental survey comprises the frequency of ground surface activities, agricultural production activities and ground marks.
4. The mobile intelligent detection method for the buried PE pipe based on the 5G and GPS technology as claimed in claim 2, wherein the items of the failure outcome score comprise medium combustibility, medium toxicity, highest working pressure, maximum workload, terrain, wind speed, population density, environment along the pipeline, leakage reasons, emergency repair time, influence range and degree of supply interruption, and dependence of users on the medium conveyed by the pipeline.
5. The mobile intelligent detection method for the buried PE pipe based on the 5G and GPS technology as claimed in claim 1, wherein the equipment computer is provided with a memory chip.
6. The mobile intelligent detection method for the buried PE pipe based on the 5G and GPS technology as claimed in claim 1, wherein the camera is provided with a laser radar.
CN202210320202.9A 2022-03-29 2022-03-29 Buried PE pipe mobile intelligent detection method based on 5G and GPS technologies Pending CN114791056A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210320202.9A CN114791056A (en) 2022-03-29 2022-03-29 Buried PE pipe mobile intelligent detection method based on 5G and GPS technologies

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210320202.9A CN114791056A (en) 2022-03-29 2022-03-29 Buried PE pipe mobile intelligent detection method based on 5G and GPS technologies

Publications (1)

Publication Number Publication Date
CN114791056A true CN114791056A (en) 2022-07-26

Family

ID=82462256

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210320202.9A Pending CN114791056A (en) 2022-03-29 2022-03-29 Buried PE pipe mobile intelligent detection method based on 5G and GPS technologies

Country Status (1)

Country Link
CN (1) CN114791056A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116986555A (en) * 2023-09-27 2023-11-03 江苏省特种设备安全监督检验研究院 Sulfur incinerator for preparing acid from sulfur

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050026445A (en) * 2005-02-14 2005-03-15 엠텍코리아 주식회사 Automatic pressure and spot sound transmission device for waterworks
WO2010072324A1 (en) * 2008-12-23 2010-07-01 Rosen Swiss Ag Security device and system for monitoring pipes
CN106779286A (en) * 2016-11-16 2017-05-31 中国特种设备检测研究院 A kind of city gas polyethylene pipe risk data processes realization method and system
KR20180012888A (en) * 2016-07-27 2018-02-07 한국가스공사 Third-party damage monitoring system and method using analysis of sound
CN109325645A (en) * 2017-11-16 2019-02-12 中国石油化工股份有限公司 A kind of analysis method for LNG long distance pipeline environmental risk
CN208886405U (en) * 2018-07-27 2019-05-21 东莞市三航军民融合创新研究院 Sensor array system for the detection positioning of underground gas pipeline minute leakage source
CN111879358A (en) * 2020-07-14 2020-11-03 江苏云聚汇科技有限公司 Remote quality control monitoring platform for online monitoring of flue gas
CN112254015A (en) * 2020-09-21 2021-01-22 汕头大学 Heterogeneous multi-agent under-pressure leakage blocking method and system based on 5G communication
CN112765805A (en) * 2021-01-14 2021-05-07 南京工业大学 Polyethylene buried pipe risk evaluation method
CN113379280A (en) * 2021-06-24 2021-09-10 南宁师范大学 Method and system for judging risks of buried high-molecular polyethylene pipeline for gas
CN113915449A (en) * 2021-10-22 2022-01-11 安庆师范大学 Robot system and method suitable for detecting defects of inner wall of pipeline
CN114162723A (en) * 2021-12-14 2022-03-11 江苏省特种设备安全监督检验研究院 Transmission chain monitoring method and system and application thereof in crane

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050026445A (en) * 2005-02-14 2005-03-15 엠텍코리아 주식회사 Automatic pressure and spot sound transmission device for waterworks
WO2010072324A1 (en) * 2008-12-23 2010-07-01 Rosen Swiss Ag Security device and system for monitoring pipes
KR20180012888A (en) * 2016-07-27 2018-02-07 한국가스공사 Third-party damage monitoring system and method using analysis of sound
CN106779286A (en) * 2016-11-16 2017-05-31 中国特种设备检测研究院 A kind of city gas polyethylene pipe risk data processes realization method and system
CN109325645A (en) * 2017-11-16 2019-02-12 中国石油化工股份有限公司 A kind of analysis method for LNG long distance pipeline environmental risk
CN208886405U (en) * 2018-07-27 2019-05-21 东莞市三航军民融合创新研究院 Sensor array system for the detection positioning of underground gas pipeline minute leakage source
CN111879358A (en) * 2020-07-14 2020-11-03 江苏云聚汇科技有限公司 Remote quality control monitoring platform for online monitoring of flue gas
CN112254015A (en) * 2020-09-21 2021-01-22 汕头大学 Heterogeneous multi-agent under-pressure leakage blocking method and system based on 5G communication
CN112765805A (en) * 2021-01-14 2021-05-07 南京工业大学 Polyethylene buried pipe risk evaluation method
CN113379280A (en) * 2021-06-24 2021-09-10 南宁师范大学 Method and system for judging risks of buried high-molecular polyethylene pipeline for gas
CN113915449A (en) * 2021-10-22 2022-01-11 安庆师范大学 Robot system and method suitable for detecting defects of inner wall of pipeline
CN114162723A (en) * 2021-12-14 2022-03-11 江苏省特种设备安全监督检验研究院 Transmission chain monitoring method and system and application thereof in crane

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
贵州省市场监督管理局: "运行管理", 原子能出版社, pages: 122 - 125 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116986555A (en) * 2023-09-27 2023-11-03 江苏省特种设备安全监督检验研究院 Sulfur incinerator for preparing acid from sulfur
CN116986555B (en) * 2023-09-27 2023-12-12 江苏省特种设备安全监督检验研究院 Sulfur incinerator for preparing acid from sulfur

Similar Documents

Publication Publication Date Title
Pecoraro et al. Monitoring strategies for local landslide early warning systems
Shafer et al. Quality assurance procedures in the Oklahoma Mesonetwork
CN102044094B (en) Line polling management system and method
Bell et al. Evaluation of next generation emission measurement technologies under repeatable test protocols
US20160071059A1 (en) Infrastructure management, model, and deliverable creation system and method of use
CN107817744A (en) Communal facility safety monitoring system
CN109711645B (en) Pipeline construction data management system and method based on two-dimensional code
CN107450426A (en) Foundation pit construction deformable statistical analysis method and system
CN101255950A (en) Intelligent warning system for computation and pipe monitoring of oil transportation collection and transmission system
CN1491375A (en) Reporting regulator for managing gas transportation system
CN113313387A (en) Enterprise major safety risk grading intelligent management and control method and system
CN111536429A (en) Decision fusion-based oil and gas pipeline early warning system and method
CN112525977B (en) Method and system for on-line monitoring and tracing leakage of non-organized VOCs (volatile organic Compounds)
CN109737309A (en) A kind of risk source based on risk identification leaks source tracing method and its system surely
CN114791056A (en) Buried PE pipe mobile intelligent detection method based on 5G and GPS technologies
CN110070242B (en) Gas pipeline high consequence area identification and evaluation system and method
CN111520614B (en) Ecological pipe network digital management system and method
CN115585403A (en) Safety early warning system for monitoring buried natural gas pipeline in multiple dimensions
CN100480662C (en) Gas leakage automatic detecting method
CN114186825A (en) Natural gas inspection planning method
CN201142127Y (en) Landslide monitoring apparatus
CN114925980A (en) Production safety management system
CN106980926A (en) Intelligent water reticulation system and its application method
CN112116220A (en) Artificial intelligent early warning and monitoring method for earthquake damage of large-scale building group
CN110610244A (en) Water supply pipeline hidden danger troubleshooting integrated operation method, computer readable storage medium and terminal

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination