CN114753361A - Pile foundation steel casing capable of controlling stratum deformation and construction method thereof - Google Patents

Pile foundation steel casing capable of controlling stratum deformation and construction method thereof Download PDF

Info

Publication number
CN114753361A
CN114753361A CN202210463811.XA CN202210463811A CN114753361A CN 114753361 A CN114753361 A CN 114753361A CN 202210463811 A CN202210463811 A CN 202210463811A CN 114753361 A CN114753361 A CN 114753361A
Authority
CN
China
Prior art keywords
steel casing
grouting
steel
pile foundation
pressure sensor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210463811.XA
Other languages
Chinese (zh)
Other versions
CN114753361B (en
Inventor
陈福斌
许岩
李鹏
阮世强
刘源
陈仁朋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Traffic Utility Construction Center
Original Assignee
Shenzhen Traffic Utility Construction Center
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Traffic Utility Construction Center filed Critical Shenzhen Traffic Utility Construction Center
Priority to CN202210463811.XA priority Critical patent/CN114753361B/en
Publication of CN114753361A publication Critical patent/CN114753361A/en
Application granted granted Critical
Publication of CN114753361B publication Critical patent/CN114753361B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D33/00Testing foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/385Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with removal of the outer mould-pipes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • E02D5/665Mould-pipes or other moulds for making piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/10Miscellaneous comprising sensor means

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a pile foundation steel casing capable of controlling stratum deformation, which comprises a steel casing, a grouting pipe, an outer horizontal pressure sensor and an inner grouting pressure sensor, wherein the steel casing comprises an inner steel wall, an outer steel wall and connecting reinforcing ribs, the grouting pipe is arranged between the inner steel wall and the outer steel wall of the steel casing, the connecting reinforcing ribs comprise longitudinal reinforcing ribs and transverse reinforcing ribs which are attached to the outer peripheral surface of the inner steel wall and the inner peripheral surface of the outer steel wall in a staggered mode, the steel casing positioned at the lowermost end of the pile foundation steel casing is a drilling section, the steel casing above the drilling section is a connecting section, the outer peripheral surface of the steel casing of the drilling section is sunken inwards to form an assembling groove, and the outer horizontal pressure sensor and the inner grouting pressure sensor are installed in the drilling section. The invention also provides a construction method of the pile foundation steel casing capable of controlling the formation deformation. The invention has the beneficial effects that: through dynamic implementation of synchronous grouting, different amounts of slurry can be injected according to the change of soil layer pressures at different depths during pipe drawing, and therefore horizontal deformation of a stratum soil body can be effectively controlled.

Description

Pile foundation steel casing capable of controlling stratum deformation and construction method thereof
[ technical field ] A method for producing a semiconductor device
The invention relates to the technical field of constructional engineering, in particular to a pile foundation steel casing capable of controlling stratum deformation and a construction method thereof.
[ background of the invention ]
In recent years, as underground constructions/structures are increasingly dense, cases of constructing rotary-digging cast-in-place piles around the underground constructions/structures are increasing. When the rotary excavating cast-in-place pile is constructed, in order to prevent hole collapse, a steel pile casing is needed to protect the hole pile. However, the steel casing has a certain thickness, and after the steel casing is lifted, a gap exists between the pile foundation and the soil layer, and the gap can cause soil displacement, so that the deformation of surrounding buildings such as subways and underground pipe galleries is caused. Therefore, a technical measure which can overcome the collapse of the soil body around the pile foundation caused by the lifting of the steel casing and further control the deformation of the stratum is needed.
Through the search of the prior art documents, the Chinese patent with the patent number of 202011108302.2 discloses a method for grouting and protecting walls of weak stratum pile foundations by using steel pile casings. Aiming at the problem that a soft soil layer on the top of the pile is easy to collapse, the steel casing with the outer wall provided with the grouting pipe is embedded at the top of the pile, the steel casing is recycled after grouting filling, and pile foundation construction is carried out. In fact, the rotary excavating cast-in-place pile is often long, and multiple sections of steel casing barrels need to be respectively put down and welded. The steel protects a section of thick bamboo and can't solve the grouting pipe stifled hole of hammering in-process and the connection problem of a multisection steel protects a section of thick bamboo. Meanwhile, deformation and hole collapse risks still exist in pile foundation construction after the weak stratum retaining wall is formed, and deformation control of adjacent buildings is not facilitated.
Therefore, it is necessary to invent a pile foundation steel casing capable of controlling formation deformation and a construction method thereof for pile foundation construction.
[ summary of the invention ]
The invention discloses a pile foundation steel casing capable of controlling stratum deformation, which can effectively solve the technical problems related to the background technology.
In order to achieve the purpose, the technical scheme of the invention is as follows:
a pile foundation steel casing capable of controlling stratum deformation comprises at least two sections of steel casings which are connected up and down, grouting pipes, an outer side horizontal pressure sensor and an inner side grouting pressure sensor, wherein the grouting pipes, the outer side horizontal pressure sensor and the inner side grouting pressure sensor are respectively assembled on the steel casings, each section of steel casing comprises an inner layer steel wall, an outer layer steel wall which is sleeved on the inner layer steel wall and is spaced from the inner side steel wall by a certain distance, and connecting reinforcing ribs which are connected with the inner layer steel wall and the outer layer steel wall, the grouting pipes are respectively arranged between the inner layer steel wall and the outer layer steel wall of each section of steel casing, the adjacent grouting pipes in the steel casings are communicated, each connecting reinforcing rib comprises a longitudinal reinforcing rib and a transverse reinforcing rib which is attached to the outer peripheral surface of the inner layer steel wall and the inner peripheral surface of the outer layer steel wall in a staggered mode, the left end part and the right end part of the transverse reinforcing rib on the outer peripheral surface of the inner layer steel wall are respectively connected with the end part of the transverse reinforcing rib on the inner peripheral surface of the adjacent outer layer steel wall through the longitudinal reinforcing rib, the steel casing at the lowermost end of the pile foundation steel casing is a drilling section, the steel casing above the drilling section is a connecting section, the outer peripheral surface of the steel casing of the drilling section is inwards recessed to form an assembly groove, the outer horizontal pressure sensor is accommodated in the assembly groove, and the inner grouting pressure sensor is installed on the inner surface of the steel casing of the drilling section.
As a preferable improvement of the invention, a plurality of grouting ports are arranged at the top of the steel casing, a plurality of vertically arranged grouting pipes are arranged in the steel casing, and each grouting pipe is connected with one grouting port.
As a preferable improvement of the invention, the steel casing cylinders are fixedly connected through a lock catch.
As a preferable improvement of the invention, eight grouting pipes are arranged in each steel casing, and the eight grouting pipes are uniformly arranged at intervals of 45 ° along the circumferential direction of the inner steel wall.
As a preferable improvement of the present invention, the connection reinforcing rib further includes a partition plate, the partition plate divides the transverse reinforced rib and the longitudinal reinforced rib into a non-hole reinforced rib located above the partition plate and a perforated reinforced rib located below the partition plate, and a plurality of flow holes are vertically penetrated through a longitudinal reinforced rib of the perforated reinforced ribs.
As a preferable improvement of the present invention, the transverse reinforcing ribs on the inner steel wall are provided at every 5 ° intervals in the circumferential direction of the inner steel wall, and the transverse reinforcing ribs on the outer steel wall are provided at every 5 ° intervals in the circumferential direction of the outer steel wall.
As a preferable improvement of the present invention, three assembly grooves are uniformly arranged along the circumferential direction of the inner steel wall, and one of the outside horizontal pressure sensors is arranged in each assembly groove; the number of the inner side grouting pressure sensors is three, and the three inner side grouting pressure sensors are correspondingly arranged below the three assembly grooves respectively.
As a preferable improvement of the invention, the bottom end of the steel casing is hinged with a hinged cover plate for preventing soil from entering the steel casing.
The invention also provides a construction method of the pile foundation steel casing based on the controllable stratum deformation, which comprises the following steps:
step one, embedding a drilling section of a pile foundation steel casing, and checking the working state of a pressure sensor;
step two, connect gradually the linkage segment of a transferred pile foundation steel casing, specifically include the following steps:
slowly burying soil in the drilling section, measuring and verifying the burying verticality and the position precision after the burying of the drilling section is finished, and adjusting if the precision is not sufficient; if the precision requirement is met, fixing the drilling section by using the guide groove;
embedding connecting sections in sequence, and rotating the grouting pipes in the connecting sections to connect the grouting pipes in the steel casing connected below; the steel casing connected with the connecting section through the lock catch ensures that the connecting section is connected and fastened with the drilling section and the connecting section; perpendicularity needs to be measured at each connecting section, and deviation is avoided;
in the connection process of all the connection sections, the data transmission wires of the outer horizontal pressure sensors are sequentially connected, and in the connection process, the wires are not disconnected at the same time, so that at least one group of signals are ensured to be transmitted;
recording the initial lateral soil pressure P of the soil layer along different depths in real time through an outer horizontal pressure sensor0The pressure transmission consists of three groups of data, and the average value is taken when the maximum error between the three groups of data does not exceed 30 percent; when the maximum error among the three groups of data exceeds 30%, averaging the results based on the two groups of data with smaller errors;
step three, pile foundation construction;
step four, drawing the steel casing and dynamically implementing synchronous grouting according to real-time monitoring pressure, and specifically comprises the following steps:
continuously grouting through a grouting opening, and simultaneously, pulling out the steel casing in sections at a speed of not less than 0.1m/s and not more than 0.3m/s and sequentially dismantling grouting pipes in the steel casing; sequentially adjusting the length of a transmission lead of the pressure sensor, finally loosening the lock catch, and removing the section of steel casing, wherein when the length of the transmission lead of the pressure sensor is adjusted, the lead is not disconnected at the same time, so that at least one group of signals are ensured to be transmitted;
lateral soil pressure P of soil layers along different depths is recorded in real time through an outer horizontal pressure sensor arranged on an outer steel wall of a drilling section1Meanwhile, the synchronous grouting pressure P is recorded in real time by an inner side grouting pressure sensor arranged in the drilling section2(ii) a According to the measured different pressure values, dynamically adjusting the grouting pressure of the grout at the grouting opening above the steel casing, and synchronously grouting pressure P in the pipe drawing process2The following conditions should always be satisfied:
1.05P1≤P2≤1.2P0
the grouting pressure of each grouting opening along different depths can be preliminarily set according to the following formula and then according to P2Adjusting the control effect:
Figure BDA0003622748960000031
wherein, K0Taking the lateral pressure coefficient of the stratum as 0.3-0.5; gamma rayiIs the i-th layer soil gravity, HiIs the i-th soil gravity, alphapFor the grouting pressure empirical coefficient, 1.1-1.2 of soft soil is suitable, and 1.3-1.8 of dense cohesive soil, sandy soil and weathered rock are suitable;
the grouting amount of each grouting opening is as follows:
Figure BDA0003622748960000041
wherein R is the outer diameter of the steel casing, R is the inner diameter of the steel casing, n is the number of grouting holes, and alphasThe method is an empirical coefficient of grouting amount, the range of the empirical coefficient is 1.2-1.8, and higher values are taken for eggs, gravels and medium coarse sand.
In a preferred improvement of the invention, in the fourth step, the slurry for grouting is a two-fluid slurry, and the slurry mixing ratio is as follows: solution A: the liquid B is 1:1, wherein the mixing ratio of the liquid A is as follows: cement: fly ash: bentonite 1:0.66: 0.55; the B liquid is neutral water glass with Baume degree of 35-40 degrees, and the viscosity of the double-liquid slurry is more than 35 percent.
The invention has the following beneficial effects:
1. gaps generated during pipe drawing can be filled, so that transverse displacement generated by spontaneous filling of the gaps of soil bodies is prevented, a traction effect is generated on an underground structure, and the lateral displacement of the underground structure is avoided;
2. filling anti-friction and anti-drag materials to prevent the side frictional resistance of the pile from generating additional internal force on the pile foundation;
3. the filled material can enable the pile foundation to be combined with the soil body more tightly, and the bearing capacity of the pile foundation of the friction pile can be improved;
4. by arranging a plurality of pressure sensors and averaging the measured pressure values, the measurement result can be more accurate;
5. by dynamically implementing synchronous grouting, different amounts of slurry can be injected according to the change of soil layer pressures at different depths during pipe drawing, so that the horizontal deformation of a stratum soil body can be effectively controlled;
6. the method has the advantages that the formation pressure data are directly obtained through the pressure sensor to guide the setting of grouting parameters, so that the problems that design or constructors are lack of experience and the setting of grouting pressure or grouting amount is wrong during pipe drawing due to wrong estimated parameters are effectively avoided, and the method is wider in applicability;
7. the two groups of pressure sensors are uniformly distributed in the range of the steel casing of the drilling section and are vertically aligned, so that the situation that the sensors are damaged by peripheral soil when the drilling section is buried or pulled out can be avoided, and the stable output of the numerical value of the pressure sensors is ensured;
8. eight slip casting pipes evenly arrange along the circumferencial direction interval 45 of inlayer steel wall, during the slip casting, the steel protects the vibrational force that a section of thick bamboo received evenly, can show the horizontal rocking that reduces a steel when the slip casting and protect a section of thick bamboo, like this, not only can reduce the steel and protect and connect not hard up risk between the section of thick bamboo, can also make the steel protect a section of thick bamboo and be difficult to produce the slope to the grout of injection also can receive even oscillating force, the grout solidifies the back, the texture is more compact and uniform, structural strength is higher.
[ description of the drawings ]
In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings needed to be used in the description of the embodiments are briefly introduced below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and other drawings can be obtained by those skilled in the art without inventive efforts, wherein:
FIG. 1 is a schematic vertical sectional structural view of a pile foundation steel casing of the present invention;
FIG. 2 is a schematic cross-sectional structural view of a pile foundation steel casing of the present invention;
FIG. 3 is an enlarged view of portion A of FIG. 2;
FIG. 4 is a schematic diagram of a pressure sensor arrangement in a drilling section of the present invention;
FIG. 5 is a schematic view of the structure of a longitudinal ribbed bar of the present invention with holes;
FIG. 6 is a schematic view of the construction of the hinged lid of the present invention;
fig. 7 is a construction flow chart of the construction method of the pile foundation steel casing capable of controlling formation deformation.
[ detailed description ] embodiments
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the following embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
It should be noted that all the directional indicators (such as up, down, left, right, front, and rear … …) in the embodiment of the present invention are only used to explain the relative position relationship between the components, the movement situation, etc. in a specific posture (as shown in the drawing), and if the specific posture is changed, the directional indicator is changed accordingly.
In addition, the descriptions related to "first", "second", etc. in the present invention are only for descriptive purposes and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include at least one of the feature. In the description of the present invention, "a plurality" means at least two, e.g., two, three, etc., unless specifically limited otherwise.
In the present invention, unless otherwise expressly stated or limited, the terms "connected," "secured," and the like are to be construed broadly, and for example, "secured" may be a fixed connection, a removable connection, or an integral part; can be mechanically or electrically connected; they may be directly connected or indirectly connected through intervening media, or they may be connected internally or in any other suitable relationship, unless expressly stated otherwise. The specific meanings of the above terms in the present invention can be understood by those skilled in the art according to specific situations.
In addition, the technical solutions in the embodiments of the present invention may be combined with each other, but it must be based on the realization of those skilled in the art, and when the technical solutions are contradictory or cannot be realized, such a combination of technical solutions should not be considered to exist, and is not within the protection scope of the present invention.
Referring to fig. 1-3, the invention provides a pile foundation steel casing capable of controlling formation deformation, which includes at least two sections of steel casings 100 connected up and down, and grouting pipes 3, an outer horizontal pressure sensor 10 and an inner grouting pressure sensor 11 respectively assembled on the steel casings 100, wherein the steel casings 100 are fixedly connected through a lock catch 9. Each section of the steel casing 100 comprises an inner steel wall 2, an outer steel wall 1 sleeved on the inner steel wall 2 and spaced from the inner steel wall 2 by a certain distance, and a connecting reinforcing rib for connecting the inner steel wall 2 and the outer steel wall 1.
Specifically, the thickness of the inner layer steel wall 2 and the outer layer steel wall 1 is 2mm, and the interval is 80 mm.
The inner diameter of the grouting pipe 3 is 50mm, the grouting pipes are respectively arranged between the inner layer steel wall 2 and the outer layer steel wall 1 of each section of the steel casing 100, and the grouting pipes 3 in the adjacent steel casing 100 are communicated.
The top of the steel casing 100 is provided with a plurality of grouting ports (not numbered), the steel casing 100 is internally provided with a plurality of vertically arranged grouting pipes 3, and each grouting pipe 3 is connected with one grouting port.
Each steel protects and sets up eight in the section of thick bamboo 100 slip casting pipe 3, and eight slip casting pipe 3 is followed the circumferencial direction interval 45 of inlayer steel wall 2 is evenly arranged.
The connecting reinforcing ribs comprise longitudinal reinforcing ribs 5 and transverse reinforcing ribs 4 attached to the outer peripheral surface of the inner steel wall 2 and the inner peripheral surface of the outer steel wall 1 in a staggered mode, and the left end and the right end of each transverse reinforcing rib 4 on the outer peripheral surface of the inner steel wall 2 are connected with the end portions of the transverse reinforcing ribs 4 on the inner peripheral surface of the outer steel wall 1 adjacent to each other through the longitudinal reinforcing ribs 5.
Specifically, the transverse reinforcing ribs 4 on the inner steel wall 2 are arranged at intervals of 5 degrees in the circumferential direction of the inner steel wall 2, and the transverse reinforcing ribs 4 on the outer steel wall 1 are arranged at intervals of 5 degrees in the circumferential direction of the outer steel wall 1.
Further, as shown in fig. 4, the steel casing 100 located at the lowest end of the steel casing of the pile foundation is a drilling section, the steel casing 100 above the drilling section is a connection section, the outer circumferential surface of the steel casing 100 of the drilling section is recessed inwards to form an assembly groove (not numbered), the outer horizontal pressure sensor 10 is accommodated in the assembly groove, and the inner grouting pressure sensor 11 is installed on the inner surface of the steel casing 100 of the drilling section.
In order to facilitate the routing of the pressure sensor, the inner side surface of the steel casing 100 is further provided with a wire groove 12, and a data transmission wire of the pressure sensor is routed along the wire groove 12, so that the transmission wire can be prevented from being damaged in the construction process.
As shown in fig. 5, the connecting reinforcing rib further includes a partition plate 13, the partition plate 13 divides the transverse reinforcing rib 4 and the longitudinal reinforcing rib 5 into a non-porous reinforcing rib located above the partition plate 13 and a perforated reinforcing rib located below the partition plate 13, and the longitudinal reinforcing rib 5 of the perforated reinforcing rib penetrates through a plurality of flow holes 6 in the vertical direction, so that slurry can flow through each other.
The number of the assembling grooves is three along the circumferential direction of the inner steel wall 2, and one outer horizontal pressure sensor 10 is arranged in each assembling groove; the number of the inner side grouting pressure sensors 11 is three, and the inner side grouting pressure sensors 11 are correspondingly arranged below the three assembling grooves respectively.
Further, the outer horizontal pressure sensor 10 is vertically aligned with the inner grouting pressure sensor 11 therebelow.
Further, as shown in fig. 6, the bottom end of the steel casing 100 is hinged with a hinged cover plate 8 for preventing soil from entering the steel casing, and the hinged cover plate 8 is arranged to prevent soil from entering the cylinder wall to cause blockage.
With reference to fig. 7, the invention further provides a construction method of the pile foundation steel casing based on the controllable formation deformation, and the construction method comprises the following steps:
step one, burying the drilling section of pile foundation steel casing underground, checking the working state of a pressure sensor, and specifically comprising the following steps:
the equipment enters a field and comprises a drilling section, a connecting section and piling equipment of the pile foundation steel casing;
measuring, paying off and positioning, wherein the allowable deviation between the center of the steel casing and the center of the pile position is required to be not more than 50 mm;
checking the working states of an outer side horizontal pressure sensor and an inner side grouting pressure sensor which are arranged on a drilling section, and requiring each pressure sensor to be electrified for testing;
embedding a drilling section of the pile foundation steel casing to ensure that the hinged cover plate is in a closed state;
a drilling section is tried, initial data are monitored in real time, the pressure sensor is required to normally output signals, and the signals are stable and do not break;
step two, connect gradually the linkage segment of a transferred pile foundation steel casing, specifically include the following steps:
slowly burying soil in the drilling section, measuring and verifying the burying verticality and the position precision after the burying of the drilling section is finished, and adjusting if the precision is not sufficient; if the precision requirement is met, fixing the drilling section by using the guide groove;
embedding the connecting sections in sequence, and rotating the grouting pipes in the connecting sections to connect the grouting pipes in the steel casing connected below; the steel casing connected with the connecting section through the lock catch ensures that the connecting section is connected and fastened with the drilling section and the connecting section; perpendicularity of each connecting section needs to be measured, and deviation is avoided;
in the connection process, the data transmission leads of the outer horizontal pressure sensors are sequentially connected, and in the connection process, the leads are not detached at the same time, so that at least one group of signals are ensured to be transmitted, and in addition, the data transmission leads are arranged in the lead grooves, so that the damage in the construction process is avoided;
by means of outside horizontal pressure sensorsRecording the initial lateral soil pressure P of the soil layer along different depths in real time0The pressure transmission consists of three groups of data, and the average value is taken when the maximum error among the three groups of data does not exceed 30 percent; when the maximum error among the three groups of data exceeds 30%, averaging the results based on the two groups of data with smaller errors;
step three, pile foundation construction, which specifically comprises the following steps:
forming a pile hole by means of mechanical drilling or manual excavation and the like, and cleaning the hole in time after the pile hole reaches a specified elevation to ensure that no sediment is left at the bottom of the hole; if the stratum conditions are poor, mud can be adopted for hole protection;
a reinforcement cage is placed downwards, a guide pipe is arranged below the reinforcement cage, and underwater concrete is poured to form a pile foundation by adopting a mud-down vertical lifting guide pipe method;
step four, drawing the steel casing and dynamically implementing synchronous grouting according to real-time monitoring pressure, and specifically comprises the following steps:
continuously grouting through a grouting opening, and simultaneously, pulling out the steel casing in sections at a speed of not less than 0.1m/s and not more than 0.3m/s and sequentially dismantling grouting pipes in the steel casing; sequentially adjusting the length of a transmission lead of the pressure sensor, finally loosening the lock catch, and removing the section of steel casing, wherein when the length of the transmission lead of the pressure sensor is adjusted, the leads are not disconnected at the same time, so that at least one group of signals are ensured to be transmitted;
it should be further explained that, when the steel casing 100 is drawn, the pile body should reach over 70% of the design strength index.
Lateral soil pressure P of soil layers along different depths is recorded in real time through an outer horizontal pressure sensor arranged on an outer steel wall of a drilling section1Meanwhile, the synchronous grouting pressure P is recorded in real time by an inner side grouting pressure sensor arranged in the drilling section2(ii) a Dynamically adjusting the grouting pressure P of the grout at the grouting opening above the steel casing according to the measured different pressure values1、P2The data processing mode is same as P0Synchronous grouting pressure P in the pipe drawing process2The following conditions should always be satisfied:
1.05P1≤P2≤1.2P0
the grouting pressure of each grouting opening along different depths can be preliminarily set according to the following formula and then according to P2And (3) adjusting the control effect:
Figure BDA0003622748960000081
wherein, K0Taking the lateral pressure coefficient of the stratum as 0.3-0.5; gamma rayiIs the i-th layer soil gravity, HiIs the i-th soil gravity, alphapFor the grouting pressure empirical coefficient, the soft soil is preferably 1.1-1.2, and the dense cohesive soil, sandy soil and weathered rock are preferably 1.3-1.8;
the grouting amount of each grouting opening is as follows:
Figure BDA0003622748960000082
wherein R is the outer diameter of the steel casing, R is the inner diameter of the steel casing, n is the number of grouting holes, and alphasThe method is an empirical coefficient of grouting amount, the range of the empirical coefficient is 1.2-1.8, and higher values are taken for eggs, gravels and medium-coarse sand.
It needs to be further explained that the deformation of the adjacent building/structure is monitored in real time during the pulling process of the pile foundation steel casing, and the displacement of the building/structure towards the pile foundation direction is found, so that the grouting amount is increased properly.
Furthermore, the slurry for grouting adopts double-slurry, and the slurry mixing ratio is as follows: solution A: the liquid B is 1:1, wherein the mixing ratio of the liquid A is as follows: cement: fly ash: bentonite 1:0.66: 0.55; the B liquid is neutral water glass with Baume degree of 35-40 degrees, and the viscosity of the double-liquid slurry is more than 35 percent. The slurry should be well stirred.
The following describes in detail the pile foundation steel casing capable of controlling formation deformation and the construction method thereof according to the present invention in specific example 1.
Example 1
The side of the coarse sand layer subway shield tunnel in Guangdong province is used for pile foundation construction, the diameter of a pile foundation is 500mm, the length of the pile is 13m, and the distance from the pile foundation to a subway is 3.1 m. The ground stratum is composed of silty clay, medium coarse sand and thickness from top to bottomRespectively 4m, 5m and 5m, and the gravity is respectively 18.4kN/m3、19.1kN/m3、20.8kN/m3. In order to control the influence of pile foundation construction pipe drawing on the subway shield tunnel, pile foundation steel casing construction with controllable stratum deformation is adopted on site.
Pile foundation steel casing with inner diameter of 500mm and outer diameter of 584mm is adopted, and the thickness of the inner layer steel wall and the outer layer steel wall is 2mm and the interval is 80 mm. The total number of the grouting pipes is 8, the grouting pipes are uniformly arranged at intervals of 45 degrees along the annular direction, and the inner diameter of each grouting pipe is 50 mm. And transverse reinforced ribs and longitudinal reinforced ribs are arranged between the inner layer steel wall and the outer layer steel wall. And 3 outer horizontal pressure sensors and inner grouting pressure sensors are uniformly arranged at the drilling section close to the hinged cover plate at intervals of 120 degrees in the circumferential direction, and each group of pressure sensors is provided. The bottom of the drilling section is provided with a clapboard, and 3 circulation holes are arranged on the longitudinal reinforced ribs below the clapboard. The bottom end of the steel casing is provided with a hinged cover plate, and the hinged cover plate can prevent soil from entering the cylinder wall to cause blockage when the steel casing is embedded.
The construction process is as follows:
the method comprises the following steps of firstly, embedding a pile foundation steel casing drilling section, and checking the working state of a sensor, wherein the method specifically comprises the following steps:
1) the equipment enters a field and comprises a pile foundation steel casing drilling section, a connecting section and piling equipment;
2) measuring and setting and positioning to enable the center of the pile foundation steel casing to coincide with the center of the pile position;
3) leveling the field;
4) checking the working states of an outer side horizontal pressure sensor and an inner side grouting pressure sensor which are arranged in the drilling section, and electrifying each pressure sensor for testing;
5) embedding a drilling section of the pile foundation steel casing, and closing the hinged cover plate;
6) trial drilling of a drilling section of the steel casing, monitoring initial data in real time, enabling the pressure sensor to normally output signals, and enabling the signals to be stable;
the second step, connect gradually and transfer the steel and protect a connecting section, specifically include following step:
1) slowly burying the drilling section, measuring and verifying the burying verticality and position precision after the burying of the drilling section is finished, meeting the precision requirement, and fixing the drilling section by using a guide groove;
2) when one section is driven in, the connecting section is buried in sequence, and the grouting pipe of the connecting section is rotated to be connected with the grouting pipe of the lower section; connecting the lock catches, and measuring the verticality of the connecting sections;
3) in the process of connecting the connecting sections, the pressure sensor data transmission leads are connected in sequence, one group of leads are disconnected and connected in the connecting process, one group of signals are always transmitted, and the leads are arranged in a lead groove;
4) slowly burying the drilling section, and recording the initial lateral soil pressure P of the soil layer along different depths in real time by means of a first group of horizontal pressure sensors arranged outside the drilling section0The pressure transmission consists of three groups of data, the maximum error among the three groups of data is 23 percent, and an average value is taken;
5) the depth of the drill section into the soil is consistent with the designed elevation of the pile bottom;
and thirdly, pile foundation construction, which specifically comprises the following steps:
1) forming a pile hole through mechanical drilling, and cleaning the hole in time after reaching a specified elevation, wherein no sediment is left at the bottom of the hole;
2) a reinforcement cage is lowered, a guide pipe is arranged below the reinforcement cage, and underwater concrete is poured by adopting a mud downward direct-rising guide pipe method to form a pile foundation;
step four, pile foundation steel protects a section of thick bamboo tube drawing and implements synchronous slip casting according to real-time supervision pressure developments, specifically includes following step:
1) when the pile foundation steel casing is drawn, the pile body reaches 70% of the design strength index;
2) uniformly and slowly pulling out the steel pile casing at the speed of 0.3 m/s;
3) when the pipe is pulled out, injecting double-liquid slurry through a grouting opening above the steel casing, wherein the grouting process is continuous;
4) pulling out the steel casing section by section, sequentially dismantling the grouting pipes, sequentially adjusting the length of a transmission lead of the pressure sensor, and finally loosening the lock catch to remove the section connecting section; when the length of the transmission lead of the pressure sensor is adjusted, one group of leads is disconnected and connected, and a group of signals are always transmitted;
5) each grouting opening is preset with initial grouting pressure P, the grouting pressure is controlled according to the depth and then is controlled according to P2The control effect is adjusted, and the initial pressure p is as follows:
p=1.5×0.45×(18.4×4+19.1×5+20.8×4)=170.3kPa
6) lateral soil pressure P of soil layers along different depths is recorded in real time by means of an outer horizontal pressure sensor arranged on an outer steel wall of a drilling section1Meanwhile, the synchronous grouting pressure P is recorded in real time by an inner side grouting pressure sensor arranged in the cavity of the drilling section2;P1、P2The maximum errors of the data are respectively 25% and 16%, the average values are obtained, the grouting pressure of the grout at the grouting opening above the pile casing is dynamically adjusted according to the measured different pressure values, and the grouting pressure P is synchronized in the pipe drawing process2The following conditions should always be satisfied:
1.05P1≤P2≤1.2P0
7) synchronous grouting slurry mixing ratio: solution A: the liquid B is 1:1, wherein the mixing ratio of the liquid A is as follows: cement: fly ash: bentonite 1:0.66: 0.55; the B liquid is neutral water glass with the Baume degree of 35-40 degrees, the viscosity of the double-liquid slurry is 35 percent, the slurry is fully and uniformly stirred, and the grouting amount of each grouting opening is as follows:
Figure BDA0003622748960000111
the deformation of the subway tunnel is monitored in real time in the pile foundation steel casing pulling process, the maximum displacement of the subway tunnel towards the pile foundation direction is 0.8mm, and the horizontal deformation of the stratum soil body can be effectively controlled by adopting a dynamic monitoring and adjusting synchronous grouting pressure construction method.
The invention has the following beneficial effects:
1. gaps generated during pipe drawing can be filled, so that transverse displacement generated by spontaneous filling of the gaps of soil bodies is prevented, a traction effect is generated on an underground structure, and the lateral displacement of the underground structure is avoided;
2. filling an anti-friction and anti-drag material to prevent the side frictional resistance of the pile from generating additional internal force on the pile foundation;
3. the filled material can enable the pile foundation to be combined with the soil body more tightly, and the bearing capacity of the pile foundation of the friction pile can be improved;
4. by arranging a plurality of pressure sensors and averaging the measured pressure values, the measurement result can be more accurate;
5. by dynamically implementing synchronous grouting, different amounts of slurry can be injected according to the change of soil layer pressures at different depths during pipe drawing, so that the horizontal deformation of a stratum soil body can be effectively controlled;
6. the method has the advantages that the formation pressure data are directly obtained through the pressure sensor to guide the setting of grouting parameters, so that the problems that design or constructors are lack of experience and the setting of grouting pressure or grouting amount is wrong during pipe drawing due to wrong estimated parameters are effectively avoided, and the method is wider in applicability;
7. the two groups of pressure sensors are uniformly distributed in the range of the steel casing of the drilling section and are vertically arranged in an aligned manner, so that the sensors can be prevented from being damaged by peripheral soil when the drilling section is buried or pulled out, and the stable output of the numerical values of the pressure sensors is ensured;
8. eight slip casting pipes evenly arrange along the circumferencial direction interval 45 of inlayer steel wall, during slip casting, the vibrational force that a steel protected a section of thick bamboo and received is even, can show the horizontal rocking that reduces a steel when the slip casting protected a section of thick bamboo, like this, not only can reduce the steel and protect the risk that connects not hard up between the section of thick bamboo, can also make the steel protect a section of thick bamboo and be difficult to produce the slope, and the grout of pouring into also can receive even oscillating force, the grout solidifies the back, the texture is more compact and uniform, structural strength is higher.
While embodiments of the invention have been disclosed above, it is not limited to the applications set forth in the specification and the embodiments, which are fully applicable to various fields of endeavor for which the invention pertains, and further modifications may readily be made by those skilled in the art, it being understood that the invention is not limited to the details shown and described herein without departing from the general concept defined by the appended claims and their equivalents.

Claims (10)

1. The pile foundation steel casing capable of controlling stratum deformation is characterized by comprising at least two sections of steel casings which are connected up and down, and a grouting pipe, an outer horizontal pressure sensor and an inner grouting pressure sensor which are respectively assembled on the steel casings, wherein each section of steel casing comprises an inner steel wall, an outer steel wall which is sleeved on the inner steel wall and is spaced from the inner steel wall by a certain distance, and connecting reinforcing ribs which are used for connecting the inner steel wall and the outer steel wall, the grouting pipe is respectively arranged between the inner steel wall and the outer steel wall of each section of steel casing, the adjacent grouting pipes in the steel casings are communicated, the connecting reinforcing ribs comprise longitudinal reinforcing ribs and transverse reinforcing ribs which are attached to the outer peripheral surfaces of the inner steel wall and the outer steel wall in a staggered manner, and the left ends and the right ends of the transverse reinforcing ribs on the outer peripheral surfaces of the inner steel wall are respectively connected with the ends of the transverse reinforcing ribs on the inner peripheral surfaces of the adjacent outer steel walls through the longitudinal reinforcing ribs The steel casing is a drilling section, the steel casing above the drilling section is a connecting section, the outer peripheral surface of the steel casing of the drilling section is inwards recessed to form an assembly groove, the outer horizontal pressure sensor is accommodated in the assembly groove, and the inner grouting pressure sensor is installed on the inner side surface of the steel casing of the drilling section.
2. The pile foundation steel casing of claim 1, wherein the pile foundation steel casing is characterized in that: the top of a steel casing is provided with a plurality of grouting openings, a plurality of vertically arranged grouting pipes are arranged in the steel casing, and each grouting pipe is connected with one grouting opening.
3. The pile foundation steel casing of claim 1, wherein the pile foundation steel casing is characterized in that: the steel casing is fixedly connected through a lock catch.
4. The pile foundation steel casing of claim 1, wherein the pile foundation steel casing is characterized in that: and eight grouting pipes are arranged in each steel casing and are uniformly arranged at intervals of 45 degrees along the circumferential direction of the inner steel wall.
5. The pile foundation steel casing of claim 1, wherein the pile foundation steel casing is characterized in that: the connecting reinforcing rib further comprises a partition board, the partition board divides the transverse reinforcing rib and the longitudinal reinforcing rib into a hole-free reinforcing rib and a hole-containing reinforcing rib, the hole-free reinforcing rib is located above the partition board, the hole-containing reinforcing rib is located below the partition board, and a plurality of circulation holes penetrate through the longitudinal reinforcing rib in the hole-containing reinforcing rib along the vertical direction.
6. The pile foundation steel casing of claim 1, wherein the pile foundation steel casing is characterized in that: the transverse reinforcing ribs on the inner steel wall are arranged at intervals of 5 degrees along the circumferential direction of the inner steel wall, and the transverse reinforcing ribs on the outer steel wall are arranged at intervals of 5 degrees along the circumferential direction of the outer steel wall.
7. The pile foundation steel casing of claim 6, wherein the pile foundation steel casing is characterized in that: the number of the assembling grooves is three, and the outer side horizontal pressure sensor is arranged in each assembling groove; the number of the inner side grouting pressure sensors is three, and the three inner side grouting pressure sensors are correspondingly arranged below the three assembling grooves respectively.
8. The pile foundation steel casing of claim 1, wherein the pile foundation steel casing is characterized in that: the bottom of the steel casing is hinged with a hinged cover plate used for preventing soil from entering the steel casing.
9. A construction method of a pile foundation steel casing capable of controlling formation deformation based on any one of claims 1 to 9, characterized by comprising the following steps:
step one, embedding a drilling section of a pile foundation steel casing, and checking the working state of a pressure sensor;
step two, connect gradually the linkage segment of a transferred pile foundation steel casing, specifically include the following steps:
slowly burying soil in the drilling section, measuring and verifying the burying verticality and the position precision after the burying of the drilling section is finished, and adjusting if the precision is not sufficient; if the precision requirement is met, fixing the drilling section by using the guide groove;
embedding the connecting sections in sequence, and rotating the grouting pipes in the connecting sections to connect the grouting pipes in the steel casing connected below; the steel casing connected through the lock catch ensures that the connection section is connected and fastened with the drilling section and the connection section; perpendicularity needs to be measured at each connecting section, and deviation is avoided;
in the connection process of all the connection sections, data transmission wires of the horizontal pressure sensors at the outer sides are sequentially connected, and in the connection process, the wires are not detached at the same time, so that at least one group of signals are ensured to be transmitted;
recording the initial lateral soil pressure P of the soil layer along different depths in real time through an outer horizontal pressure sensor0The pressure transmission consists of three groups of data, and the average value is taken when the maximum error among the three groups of data does not exceed 30 percent; when the maximum error among the three groups of data exceeds 30%, taking the two groups of data with smaller errors as a reference, and averaging the results;
step three, pile foundation construction;
step four, drawing the steel casing and dynamically implementing synchronous grouting according to real-time monitoring pressure, and specifically comprises the following steps:
continuously grouting through a grouting opening, and simultaneously, pulling out the steel casing in sections at a speed of not less than 0.1m/s and not more than 0.3m/s and sequentially dismantling grouting pipes in the steel casing; sequentially adjusting the length of a transmission lead of the pressure sensor, finally loosening the lock catch, and removing the section of steel casing, wherein when the length of the transmission lead of the pressure sensor is adjusted, the lead is not disconnected at the same time, so that at least one group of signals are ensured to be transmitted;
lateral soil pressure P of soil layers along different depths is recorded in real time through an outer horizontal pressure sensor arranged on an outer steel wall of a drilling section1Meanwhile, the synchronous grouting pressure P is recorded in real time by an inner side grouting pressure sensor arranged inside the drilling section2(ii) a According to the measured different pressure values, dynamically adjusting the grouting pressure of the grout at the grouting opening above the steel casing, and synchronously grouting pressure P in the pipe drawing process2Should beginThe following conditions are finally satisfied:
1.05P1≤P2≤1.2P0
the grouting pressure of each grouting opening along different depths can be preliminarily set according to the following formula and then according to P2And (3) adjusting the control effect:
Figure FDA0003622748950000031
wherein, K0Taking the lateral pressure coefficient of the stratum as 0.3-0.5; gamma rayiIs the i-th layer soil gravity, HiIs the i-th soil gravity, alphapFor the grouting pressure empirical coefficient, the soft soil is preferably 1.1-1.2, and the dense cohesive soil, sandy soil and weathered rock are preferably 1.3-1.8;
the grouting amount of each grouting opening is as follows:
Figure FDA0003622748950000032
wherein R is the outer diameter of the steel casing, R is the inner diameter of the steel casing, n is the number of grouting holes, and alphasThe method is an empirical coefficient of grouting amount, the range of the empirical coefficient is 1.2-1.8, and higher values are taken for eggs, gravels and medium-coarse sand.
10. The construction method of the pile foundation steel casing capable of controlling the formation deformation according to claim 9, characterized by comprising the following steps: in the fourth step, the slurry for grouting adopts double-slurry, and the slurry mixing ratio is as follows: solution A: the liquid B is 1:1, wherein the mixing ratio of the liquid A is as follows: cement: fly ash: bentonite 1:0.66: 0.55; the B liquid is neutral water glass with Baume degree of 35-40 degrees, and the viscosity of the double-liquid slurry is more than 35 percent.
CN202210463811.XA 2022-04-29 2022-04-29 Pile foundation steel pile casing capable of controlling stratum deformation and construction method thereof Active CN114753361B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210463811.XA CN114753361B (en) 2022-04-29 2022-04-29 Pile foundation steel pile casing capable of controlling stratum deformation and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210463811.XA CN114753361B (en) 2022-04-29 2022-04-29 Pile foundation steel pile casing capable of controlling stratum deformation and construction method thereof

Publications (2)

Publication Number Publication Date
CN114753361A true CN114753361A (en) 2022-07-15
CN114753361B CN114753361B (en) 2024-04-30

Family

ID=82333601

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210463811.XA Active CN114753361B (en) 2022-04-29 2022-04-29 Pile foundation steel pile casing capable of controlling stratum deformation and construction method thereof

Country Status (1)

Country Link
CN (1) CN114753361B (en)

Citations (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB370795A (en) * 1931-08-24 1932-04-14 Andrew Hood Improvements in or relating to the construction of "in situ" concrete piles
CN1928251A (en) * 2006-09-26 2007-03-14 徐东强 Pipe pile hole maker with concrete bottom sealing, pipe cover and wings and construction process thereof
KR20100079506A (en) * 2008-12-31 2010-07-08 대림산업 주식회사 Post grouting system of cast-in-place concrete piles and the post grouting method for increasing end bearing capacity at pile base
WO2011126170A1 (en) * 2010-04-09 2011-10-13 Kim Sung-Kyu Construction method of pre-stressed cast-in -place concrete pile and structure thereof
JP2015187373A (en) * 2014-03-14 2015-10-29 大亜ソイル株式会社 Method for reinforcing hole wall for construction of cast-in-place concrete pile
JP5932124B1 (en) * 2015-11-18 2016-06-08 株式会社オーク Steel pipe pile construction method
CN109853606A (en) * 2019-04-10 2019-06-07 四川路桥华东建设有限责任公司 A kind of construction system and method for bored pile construction mud automatic-discharging
CN109944236A (en) * 2019-03-22 2019-06-28 中国建筑第八工程局有限公司 Root pile actively follows track delamination pour slurry system and construction method
CN110144901A (en) * 2019-05-22 2019-08-20 宁波大学 A kind of prefabricated high-pressure gasbag isolation pilework and construction method with slip casting function
CN110952533A (en) * 2019-11-26 2020-04-03 浙江大学城市学院 Underwater anti-slip bored pile foundation and construction method thereof
CN111636420A (en) * 2020-07-06 2020-09-08 湖南科技学院 Construction equipment and construction method of anti-necking sinking pipe cast-in-place pile
CN111794218A (en) * 2020-06-19 2020-10-20 河海大学 Construction quality control device for solidified soil pile and construction method thereof
CN212104042U (en) * 2019-11-26 2020-12-08 浙江大学城市学院 Underwater anti-sliding bored pile foundation
CN112144517A (en) * 2020-10-16 2020-12-29 中铁十五局集团第五工程有限公司 Method for grouting retaining wall by using steel retaining cylinder for pile foundation in weak stratum
KR20210009509A (en) * 2019-07-17 2021-01-27 에스오씨기술지주 주식회사 Cast-in-place pile using reinforced grouting and construction method
WO2021017984A1 (en) * 2019-07-31 2021-02-04 青岛理工大学 Soil pressure and displacement monitoring system and method for miniature steel pipe pile body
CN112323782A (en) * 2020-11-16 2021-02-05 安徽省新路建设工程集团有限责任公司 Construction method and structure for forming full casing cast-in-situ bored pile
KR102259376B1 (en) * 2020-10-12 2021-06-03 (주)태화개발 Grouting device equipped with double helix screw
CN113404044A (en) * 2021-06-24 2021-09-17 中建科工集团有限公司 Hierarchical pore-forming construction method for rotary digging cast-in-place pile
CN113699981A (en) * 2021-09-07 2021-11-26 中冶建工集团有限公司 Construction method for preventing necking of rotary-digging cast-in-place pile in high-fill field
CN113863289A (en) * 2021-10-01 2021-12-31 浙大城市学院 Double-layer sleeve concrete pile and construction method thereof
CN114108694A (en) * 2021-11-11 2022-03-01 中冶集团武汉勘察研究院有限公司 Micro-disturbance anti-floating underground cylindrical structure and construction method thereof
CN114278310A (en) * 2021-12-06 2022-04-05 中交一公局集团有限公司 Construction method for micro steel pipe pile lattice beam at shallow buried section of tunnel
CN114351688A (en) * 2021-12-30 2022-04-15 浙江坤德创新岩土工程有限公司 Pile side grouting and pile end extrusion grouting system for cast-in-place pile and construction method thereof

Patent Citations (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB370795A (en) * 1931-08-24 1932-04-14 Andrew Hood Improvements in or relating to the construction of "in situ" concrete piles
CN1928251A (en) * 2006-09-26 2007-03-14 徐东强 Pipe pile hole maker with concrete bottom sealing, pipe cover and wings and construction process thereof
KR20100079506A (en) * 2008-12-31 2010-07-08 대림산업 주식회사 Post grouting system of cast-in-place concrete piles and the post grouting method for increasing end bearing capacity at pile base
WO2011126170A1 (en) * 2010-04-09 2011-10-13 Kim Sung-Kyu Construction method of pre-stressed cast-in -place concrete pile and structure thereof
JP2015187373A (en) * 2014-03-14 2015-10-29 大亜ソイル株式会社 Method for reinforcing hole wall for construction of cast-in-place concrete pile
JP5932124B1 (en) * 2015-11-18 2016-06-08 株式会社オーク Steel pipe pile construction method
CN109944236A (en) * 2019-03-22 2019-06-28 中国建筑第八工程局有限公司 Root pile actively follows track delamination pour slurry system and construction method
CN109853606A (en) * 2019-04-10 2019-06-07 四川路桥华东建设有限责任公司 A kind of construction system and method for bored pile construction mud automatic-discharging
CN110144901A (en) * 2019-05-22 2019-08-20 宁波大学 A kind of prefabricated high-pressure gasbag isolation pilework and construction method with slip casting function
KR20210009509A (en) * 2019-07-17 2021-01-27 에스오씨기술지주 주식회사 Cast-in-place pile using reinforced grouting and construction method
WO2021017984A1 (en) * 2019-07-31 2021-02-04 青岛理工大学 Soil pressure and displacement monitoring system and method for miniature steel pipe pile body
CN212104042U (en) * 2019-11-26 2020-12-08 浙江大学城市学院 Underwater anti-sliding bored pile foundation
CN110952533A (en) * 2019-11-26 2020-04-03 浙江大学城市学院 Underwater anti-slip bored pile foundation and construction method thereof
CN111794218A (en) * 2020-06-19 2020-10-20 河海大学 Construction quality control device for solidified soil pile and construction method thereof
CN111636420A (en) * 2020-07-06 2020-09-08 湖南科技学院 Construction equipment and construction method of anti-necking sinking pipe cast-in-place pile
KR102259376B1 (en) * 2020-10-12 2021-06-03 (주)태화개발 Grouting device equipped with double helix screw
CN112144517A (en) * 2020-10-16 2020-12-29 中铁十五局集团第五工程有限公司 Method for grouting retaining wall by using steel retaining cylinder for pile foundation in weak stratum
CN112323782A (en) * 2020-11-16 2021-02-05 安徽省新路建设工程集团有限责任公司 Construction method and structure for forming full casing cast-in-situ bored pile
CN113404044A (en) * 2021-06-24 2021-09-17 中建科工集团有限公司 Hierarchical pore-forming construction method for rotary digging cast-in-place pile
CN113699981A (en) * 2021-09-07 2021-11-26 中冶建工集团有限公司 Construction method for preventing necking of rotary-digging cast-in-place pile in high-fill field
CN113863289A (en) * 2021-10-01 2021-12-31 浙大城市学院 Double-layer sleeve concrete pile and construction method thereof
CN114108694A (en) * 2021-11-11 2022-03-01 中冶集团武汉勘察研究院有限公司 Micro-disturbance anti-floating underground cylindrical structure and construction method thereof
CN114278310A (en) * 2021-12-06 2022-04-05 中交一公局集团有限公司 Construction method for micro steel pipe pile lattice beam at shallow buried section of tunnel
CN114351688A (en) * 2021-12-30 2022-04-15 浙江坤德创新岩土工程有限公司 Pile side grouting and pile end extrusion grouting system for cast-in-place pile and construction method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
曾波: "断层破碎带大直径深桩基础的施工", 中外公路, no. 05, 29 October 2002 (2002-10-29), pages 82 - 83 *

Also Published As

Publication number Publication date
CN114753361B (en) 2024-04-30

Similar Documents

Publication Publication Date Title
CN106284313B (en) Long spire based on circulating mud retaining wall is squeezed into rock filling pile construction method
CN105275381B (en) Impact drill drilling construction method in rich water pebble layer
CN110424381A (en) A kind of process for rotary digging drilling hole stake
CN203846485U (en) Long pile percussion drill hole forming construction device
JP2022502586A (en) Grouting consolidation method of ready-made piles guided by all-casing excavation, and the ready-made piles
CN108166483A (en) Bored pile construction method
CN106087997A (en) A kind of high latitude, high and cold Permafrost Area drilled pile construction engineering method
CN107905221A (en) A kind of method for being accurately positioned percussive drilling bored concrete pile
CN106930276A (en) The deep hole blasting of rotary digging bored concrete pile and the construction method of conduit rotary digging removing obstacles
CN111877329A (en) Pile-in-pile broken pile and pile-splicing construction method
CN114753348A (en) Construction method of complex stratum ultra-deep ultra-thick underground diaphragm wall
CN113216148B (en) Construction method for pile foundation of pressure-bearing underground air-raid shelter collapse section
CN109024657B (en) Construction method of super high-rise core tube deep pit edge tower crane foundation under complex conditions
CN107178088A (en) A kind of basement waterproofing foundation pit structure and its construction method
CN114753361A (en) Pile foundation steel casing capable of controlling stratum deformation and construction method thereof
CN110896644A (en) Grouting consolidation method for full-casing drilling guide precast pile and precast pile thereof
CN114753354A (en) Water-rich sandy gravel geological pile forming construction method
CN112343051B (en) Method for rotary digging implantation pile sinking in high backfill region
CN107675700A (en) The construction method of diaphram wall
CN113668555A (en) Deep foundation pit supporting construction method for large-pipe-diameter prestressed row piles
CN109778873A (en) Ejection for water plugging method and device between a kind of fender post
CN216788421U (en) Reinforcement construction system of tunnel business turn over hole portal
CN115652970B (en) Construction method of bidirectional water-stop cofferdam structure
CN217298895U (en) Sand bed geological pile foundation hole bottom grouting device
CN106087995A (en) The method of stake is built in a kind of boring

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant