CN114737674A - Construction method for building beam-column dry connection - Google Patents

Construction method for building beam-column dry connection Download PDF

Info

Publication number
CN114737674A
CN114737674A CN202210369696.XA CN202210369696A CN114737674A CN 114737674 A CN114737674 A CN 114737674A CN 202210369696 A CN202210369696 A CN 202210369696A CN 114737674 A CN114737674 A CN 114737674A
Authority
CN
China
Prior art keywords
precast
column
section steel
precast beam
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210369696.XA
Other languages
Chinese (zh)
Inventor
刘毅
赵宏康
张宝利
董运超
潘�清
戴雅萍
华迅
郑钰
陈磊
徐方磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tus-Design Group Co ltd
Wuxi Metro Group Co ltd
Wuxi Tianying Construction Technology Co ltd
Original Assignee
Tus-Design Group Co ltd
Wuxi Metro Group Co ltd
Wuxi Tianying Construction Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tus-Design Group Co ltd, Wuxi Metro Group Co ltd, Wuxi Tianying Construction Technology Co ltd filed Critical Tus-Design Group Co ltd
Priority to CN202210369696.XA priority Critical patent/CN114737674A/en
Publication of CN114737674A publication Critical patent/CN114737674A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • E04B1/215Connections specially adapted therefor comprising metallic plates or parts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • E04C5/06Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
    • E04C5/0604Prismatic or cylindrical reinforcement cages composed of longitudinal bars and open or closed stirrup rods
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • E04C5/06Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
    • E04C5/0604Prismatic or cylindrical reinforcement cages composed of longitudinal bars and open or closed stirrup rods
    • E04C5/0609Closed cages composed of two or more coacting cage parts, e.g. transversally hinged or nested parts

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention discloses a construction method for building beam-column dry connection, which comprises the following steps: s1: preparing a prefabricated column, and pre-burying section steel joints at the top and the bottom of the prefabricated column; s2: preparing a precast beam, and embedding section steel joints at two ends of the precast beam; s3: embedding a base section steel joint on a base layer; the prefabricated concrete structure is spliced at the splicing speed of the steel structure, so that the construction period is greatly shortened, the financial cost is greatly reduced, meanwhile, the number of required personnel on site is greatly reduced, the investment of human resources is greatly saved, and the economic benefit is greatly improved.

Description

Construction method for building beam-column dry connection
Technical Field
The invention relates to the technical field of building structures, in particular to a construction method for building beam-column dry connection.
Background
With the gradual development of assembly type buildings, the prefabricated parts can ensure the supply on site; but the assembly speed of the on-site prefabricated parts seriously restricts the construction progress and the production circulation of a factory; the assembling speed is mainly limited by the connection mode of the nodes, the traditional wet connection is adopted, the upper-layer construction can be continued only after the strength is met, otherwise, the problems of potential safety hazards and unqualified construction quality can be caused, the construction period is long, more workers are required for field operation in the traditional wet connection, and the cost of human resources is high.
Disclosure of Invention
The invention aims to provide a construction method for building beam-column dry connection, aiming at the problems that the construction period is longer and the human resource input is higher due to the fact that a wet connection mode is adopted for building beams-columns in the prior art.
The technical scheme for realizing the purpose of the invention is as follows: a construction method for building beam-column dry connection comprises the following steps:
s1: preparing a prefabricated column, and pre-burying section steel joints at the top and the bottom of the prefabricated column;
s2: preparing a precast beam, and embedding section steel joints at two ends of the precast beam;
s3: pre-burying a base section steel joint on a base;
s4: installing a first layer of prefabricated column, and performing bolt welding on a section steel joint at the bottom of the prefabricated column and a base layer section steel joint;
s5: installing a first layer of precast beam, and respectively performing bolt welding on the section steel joints at two ends of the first layer of precast beam and the section steel joints at the tops of two first layer of precast columns;
s6: installing the upper prefabricated column, and performing bolt welding on the section steel joint at the bottom of the upper prefabricated column and the section steel joint at the top of the lower prefabricated column;
s7: installing an upper-layer precast beam, and respectively bolting and welding profile steel joints at two ends of the upper-layer precast beam with profile steel joints at the tops of two upper-layer precast columns;
s8: pouring concrete in the node area to complete connection;
s9: and repeating S6-S8 until all the prefabricated columns reach the designed elevation.
The main body part of the prefabricated column is made of prefabricated reinforced concrete, the section size of the prefabricated column is 450mm multiplied by 450mm, and the reinforcement type is 12C 20; the stirrup is C10@ 100.
The precast beam main body is a precast superposed beam; the size of the section of the precast beam is 500mm multiplied by 250 mm; the reinforcement formula of precast beam main part does: the main rib 4C 16; 3C16, N2C 16; c10; the stirrup is C10@ 50; the prefabricated beam ends are double-encryption areas, and the stirrups are 5C10@50 and C10@100 respectively.
The section steel joint is a dog-bone type section steel joint.
The concrete installation steps of the precast beams in the S5 and S7 are as follows:
a 1: hoisting the precast beam to enable bolt holes on the section steel joints at two ends of the precast beam to respectively correspond to bolt holes on the section steel joints at the top of the precast column;
a 2: connecting a web plate of the section steel joint on the precast beam with a web plate of the section steel joint at the top of the precast column through a bolt;
a 3: and connecting the section steel joint on the precast beam with the upper flange and the lower flange of the section steel joint at the top of the precast column in a welding mode.
The material of shaped steel joint is Q235B.
By adopting the technical scheme, the invention has the following beneficial effects: (1) the prefabricated concrete structure is spliced at the splicing speed of the steel structure, so that the construction period is greatly shortened, the financial cost is greatly reduced, meanwhile, the number of required personnel on site is greatly reduced, the investment of human resources is greatly saved, and the economic benefit is greatly improved.
(2) The prefabricated column adopts reinforced concrete, the section size of the prefabricated column is 450mm multiplied by 450mm, and the reinforcing bar type is 12C 20; the stirrup is C10@100, so that the structural stability of the prefabricated column is greatly improved, and the building quality is ensured.
(3) The main body of the precast beam is a precast superposed beam; the size of the section of the precast beam is 500mm multiplied by 250 mm; the reinforcing bar formula of precast beam main part does: a main rib 4C 16; 3C16, N2C 16; c10; the stirrup is C10@ 50; the end part of the precast beam is a double-encryption area, and the stirrups are respectively 5C10@50 and C10@100, so that the stability of the whole structure of the precast beam is greatly improved, and the building quality is further ensured.
(4) The steel section joint can adopt a dog-bone type steel section joint, and the anti-seismic performance of the steel section joint can be improved.
(5) The section steel joint of the precast beam and the section steel joint at the top of the precast column are firstly connected through the bolt and then fixed in a welding connection mode, so that the firmness of connection between the precast beam and the precast column is ensured, and the building quality is further ensured.
(6) The material of the section steel joint adopts Q235B to meet the bolt welding requirement.
Drawings
In order that the present disclosure may be more readily and clearly understood, reference is now made to the following detailed description of the present disclosure taken in conjunction with the accompanying drawings, in which
FIG. 1 is a schematic structural diagram of the present invention.
Fig. 2 is a sectional view taken along line a-a of fig. 1.
Fig. 3 is a sectional view taken along line B-B in fig. 1.
Fig. 4 is a cross-sectional view taken along line C-C of fig. 1.
Fig. 5 is a cross-sectional view taken along line D-D of fig. 1.
Fig. 6 is a cross-sectional view taken along line E-E of fig. 1.
The reference numbers in the drawings are:
precast columns 1 and precast beams 2.
Detailed Description
(example 1)
Referring to fig. 1 to 6, the construction method for building beam-column dry connection of the embodiment includes the following steps:
s1: preparing a prefabricated column 1, and pre-burying section steel joints at the top and the bottom of the prefabricated column 1;
s2: preparing a precast beam 2, and pre-burying section steel joints at two ends of the precast beam 2;
s3: pre-burying a base section steel joint on a base;
s4: installing a first layer of prefabricated column 1, and performing bolt welding on a section steel joint at the bottom of the prefabricated column 1 and a base section steel joint;
s5: installing a first layer of precast beam 2, and respectively bolting and welding profile steel joints at two ends of the first layer of precast beam 2 with profile steel joints at the tops of two first layer of precast columns 1;
s6: installing the upper prefabricated column 1, and bolting and welding the section steel joint at the bottom of the upper prefabricated column 1 and the section steel joint at the top of the lower prefabricated column 1;
s7: installing an upper-layer precast beam 2, and respectively bolting and welding profile steel joints at two ends of the upper-layer precast beam 2 with profile steel joints at the tops of two upper-layer precast columns 1;
s8: pouring concrete in the node area to complete connection;
s9: and repeating the steps from S6 to S8 until all the prefabricated columns 1 reach the designed elevation.
Furthermore, the main body part of the prefabricated column 1 adopts prefabricated reinforced concrete, the section size of the prefabricated column 1 is 450mm multiplied by 450mm, and the reinforcement type is 12C 20; the stirrup is C10@ 100.
Further, the main body of the precast beam 2 is a precast composite beam; the size of the section of the precast beam 2 is 500mm multiplied by 250 mm; the reinforcement formula of 2 main parts of precast beam does: a main rib 4C 16; 3C16, N2C 16; c10; the stirrup is C10@ 50; the end parts of the precast beams 2 are double-encryption areas, and the stirrups are respectively 5C10@50 and C10@ 100.
Furthermore, the section steel joint is a dog-bone type section steel joint so as to improve the anti-seismic performance of the section steel joint.
Further, the specific installation steps of the precast beam 2 in S5 and S7 are as follows:
a 1: hoisting the precast beam 2 so that bolt holes on the section steel joints at two ends of the precast beam 2 respectively correspond to bolt holes on the section steel joints at the top of the precast column 1;
a 2: connecting a web plate of the section steel joint on the precast beam 2 with a web plate of the section steel joint at the top of the precast column 1 through a bolt;
a 3: and connecting the section steel joint on the precast beam 2 with the upper and lower flanges of the section steel joint at the top of the precast column 1 in a welding mode.
Preferably, the material of the steel section joint is Q235B to meet the bolt welding requirement.
The section steel joints at the bottom of the prefabricated column 1 and on the base layer are cross-shaped section steel, the cross-shaped section steel is fixedly connected with a bolt through a web plate and then welded, and the section steel joints at two ends of the prefabricated beam 2 are all H-shaped section steel; the concrete structure of the section steel at the top of the prefabricated column 1 comprises square pipe section steel, two cross section steel and H-shaped steel; square pipe shaped steel hypomere is pre-buried at prefabricated post 1's top through with a cross shaped steel bolt after welding, and the upper segment stretches out prefabricated post 1 top, and on H shaped steel located the side that steel pipe shaped steel stretches out prefabricated post 1 top, concrete mode of setting was: h-shaped steel is arranged on two adjacent side surfaces, H-shaped steel is arranged on three side surfaces, and H-shaped steel is arranged on four side surfaces, so that the use of all positions can be ensured; the other cross-shaped steel is fixed inside the square pipe-shaped steel, extends out of the upper part of the square pipe-shaped steel, is fixedly connected with the cross at the bottom of the upper prefabricated column 1 through a web and a bolt, and is welded; the H-shaped steel on the precast beam 2 is fixedly connected with the H-shaped steel on the square tube-shaped steel through a web plate and a bolt, and then welded.
The construction method of building beam column dry-type connection of this embodiment, through the pre-buried shaped steel joint in prefabricated post 1 and the both ends of precast beam 2, through the connection of shaped steel joint, simple to operate's advantage not only has, and adopt the floor of assembled, on-the-spot scaffold frame and support die block no longer need be set up, shaped steel joint is assembled and is connected for full dry-type, the technology is ripe, the installation rate is fast, can realize assembling prefabricated concrete structure with the speed of assembling of steel construction, thereby great the construction cycle that has shortened, reduce financial cost by a wide margin, simultaneously, the required personnel of on-the-spot reduce by a wide margin, the input of manpower resources has been practiced thrift greatly, economic benefits improves greatly.
The above-mentioned embodiments are intended to illustrate the objects, technical solutions and advantages of the present invention in further detail, and it should be understood that the above-mentioned embodiments are only exemplary embodiments of the present invention, and are not intended to limit the present invention, and any modifications, equivalents, improvements and the like made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (5)

1. A construction method for building beam-column dry connection is characterized by comprising the following steps:
s1: preparing a prefabricated column (1), and pre-burying section steel joints at the top and the bottom of the prefabricated column (1);
s2: preparing a precast beam (2), and embedding section steel joints at two ends of the precast beam (2);
s3: pre-burying a base section steel joint on a base;
s4: installing a first layer of prefabricated column (1), and performing bolt welding on a section steel joint at the bottom of the prefabricated column (1) and a base layer section steel joint;
s5: installing a first layer of precast beam (2), and respectively bolting and welding profile steel joints at two ends of the first layer of precast beam (2) with profile steel joints at the tops of two first layer of precast columns (1);
s6: installing the upper prefabricated column (1), and bolting and welding the section steel joint at the bottom of the upper prefabricated column (1) with the section steel joint at the top of the lower prefabricated column (1);
s7: installing an upper-layer precast beam (2), and respectively bolting and welding profile steel joints at two ends of the upper-layer precast beam (2) with profile steel joints at the tops of two upper-layer precast columns (1);
s8: pouring concrete in the node area to complete connection;
s9: and repeating the steps from S6 to S8 until all the prefabricated columns (1) reach the designed elevation.
2. The construction method for building beam-column dry type connection according to claim 1, characterized in that: the main body part of the prefabricated column (1) adopts prefabricated reinforced concrete, the section size of the prefabricated column (1) is 450mm multiplied by 450mm, and the reinforcement type is 12C 20; the stirrup is C10@ 100.
3. The construction method for building beam-column dry connection according to claim 1, wherein: the main body of the precast beam (2) is a precast superposed beam; the section size of the precast beam (2) is 500mm multiplied by 250 mm; the reinforcing bar formula of precast beam (2) main part does: the main rib 4C 16; 3C16, N2C 16; c10; the stirrup is C10@ 50; the end parts of the precast beams (2) are double-encryption areas, and the stirrups are respectively 5C10@50 and C10@ 100.
4. The construction method for building beam-column dry connection according to claim 1, wherein: the concrete installation steps of the precast beam (2) in the S5 and S7 are as follows:
a 1: hoisting the precast beam (2) to enable bolt holes on section steel joints at two ends of the precast beam (2) to respectively correspond to bolt holes on section steel joints at the top of the precast column (1);
a 2: connecting a web plate of the section steel joint on the precast beam (2) with a web plate of the section steel joint on the top of the precast column (1) through a bolt;
a 3: and connecting the section steel joint on the precast beam (2) with the upper and lower flanges of the section steel joint at the top of the precast column (1) in a welding mode.
5. The construction method for building beam-column dry connection according to claim 1, wherein: the material of shaped steel joint is Q235B.
CN202210369696.XA 2022-04-08 2022-04-08 Construction method for building beam-column dry connection Pending CN114737674A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210369696.XA CN114737674A (en) 2022-04-08 2022-04-08 Construction method for building beam-column dry connection

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210369696.XA CN114737674A (en) 2022-04-08 2022-04-08 Construction method for building beam-column dry connection

Publications (1)

Publication Number Publication Date
CN114737674A true CN114737674A (en) 2022-07-12

Family

ID=82278778

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210369696.XA Pending CN114737674A (en) 2022-04-08 2022-04-08 Construction method for building beam-column dry connection

Country Status (1)

Country Link
CN (1) CN114737674A (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104499568A (en) * 2014-12-19 2015-04-08 东南大学 Square steel pipe fabricated column-prefabricated superposed beam integrally-fabricated frame and construction method
CN106149873A (en) * 2016-08-18 2016-11-23 佛山电力设计院有限公司 Prefabricated assembled concrete frame construction and preparation method thereof
CN106759873A (en) * 2017-03-25 2017-05-31 河北合创建筑节能科技有限责任公司 A kind of new prefabricated integral frame structure prefabricated post is constructed with prefabricated beam connecting node
CN107882175A (en) * 2017-11-29 2018-04-06 厦门合立道工程设计集团股份有限公司 Dry type is rigidly connected fabricated assembly overall frame structure and its construction method
CN109372130A (en) * 2018-11-08 2019-02-22 合肥工业大学 The novel full assembly concrete shaped section steel frame node of one kind and its construction method
KR102182536B1 (en) * 2019-10-10 2020-11-24 동서 피, 씨, 씨 주식회사 Combined structure of precast columns and beams for construction of warehouse, precast beams used for the same
CN111997193A (en) * 2020-07-27 2020-11-27 河北工业大学 Assembly type prefabricated beam column connecting joint and construction method
CN112112265A (en) * 2020-08-18 2020-12-22 中建三局绿色产业投资有限公司 Connecting joint of dry-type connected precast beam column and construction method
CN113585456A (en) * 2021-08-26 2021-11-02 中国建筑科学研究院有限公司 Precast concrete beam column connection node structure and construction method
CN113863494A (en) * 2021-09-30 2021-12-31 广东普发建筑有限公司 Assembly type concrete beam column connecting node and mounting method thereof

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104499568A (en) * 2014-12-19 2015-04-08 东南大学 Square steel pipe fabricated column-prefabricated superposed beam integrally-fabricated frame and construction method
CN106149873A (en) * 2016-08-18 2016-11-23 佛山电力设计院有限公司 Prefabricated assembled concrete frame construction and preparation method thereof
CN106759873A (en) * 2017-03-25 2017-05-31 河北合创建筑节能科技有限责任公司 A kind of new prefabricated integral frame structure prefabricated post is constructed with prefabricated beam connecting node
CN107882175A (en) * 2017-11-29 2018-04-06 厦门合立道工程设计集团股份有限公司 Dry type is rigidly connected fabricated assembly overall frame structure and its construction method
CN109372130A (en) * 2018-11-08 2019-02-22 合肥工业大学 The novel full assembly concrete shaped section steel frame node of one kind and its construction method
KR102182536B1 (en) * 2019-10-10 2020-11-24 동서 피, 씨, 씨 주식회사 Combined structure of precast columns and beams for construction of warehouse, precast beams used for the same
CN111997193A (en) * 2020-07-27 2020-11-27 河北工业大学 Assembly type prefabricated beam column connecting joint and construction method
CN112112265A (en) * 2020-08-18 2020-12-22 中建三局绿色产业投资有限公司 Connecting joint of dry-type connected precast beam column and construction method
CN113585456A (en) * 2021-08-26 2021-11-02 中国建筑科学研究院有限公司 Precast concrete beam column connection node structure and construction method
CN113863494A (en) * 2021-09-30 2021-12-31 广东普发建筑有限公司 Assembly type concrete beam column connecting node and mounting method thereof

Similar Documents

Publication Publication Date Title
CN107090925B (en) Reinforced precast reinforced concrete shear wall, structural system and construction method thereof
CN107288218B (en) Beam column node of assembled reinforced concrete frame structure and manufacturing method thereof
CN103850363B (en) Prefabricated through hole assembly type reinforced concrete shear wall and construction method of prefabricated through hole assembly type reinforced concrete shear wall
CN105649360A (en) Integral assembling type building system and installing method
CN109339229B (en) Prefabricated assembled concrete-filled steel tube frame structure of perforation thick liquid anchor
CN112112264A (en) Prefabricated column connecting joint for dry connection and construction method
CN112502714B (en) Assembled shaft barrel structure and design and construction method
CN203769116U (en) Prefabricated through hole assembly type reinforced concrete shear wall
CN104631629A (en) Assembling type frame structure
CN109424072A (en) The connecting node and construction method of spacer bar concrete column on a kind of girder steel
CN108104310B (en) Assembled frame shear structure column staggered connection structure and assembling method
CN212689211U (en) Prefabricated column connecting joint for dry-type connection
CN113718753A (en) Anchorage underground diaphragm wall foundation assembled type mid-partition wall and construction method
CN110359580B (en) Prefabricated rigid concrete column member node connecting structure and supporting method
CN116752631A (en) Prefabricated honeycomb type steel reinforced concrete beam column joint and construction method
CN215483097U (en) Integrally-assembled pillarless underground structure
CN215759633U (en) Concrete beam and wall, post connected node
CN111749366B (en) Assembled composite wall based on steel pipes and construction method thereof
CN115075405A (en) Construction method of I-shaped flange section type steel concrete beam column joint
CN104453013A (en) Prefabricated wall component and fabricated reinforced concrete shear wall
CN114737674A (en) Construction method for building beam-column dry connection
KR100578641B1 (en) Steel-Concrete Hybrid Column, Hybrid Structure System Using the Same, and Construction Method Thereof
CN114108808A (en) PVC-FRP (polyvinyl chloride-fiber reinforced plastic) pipe concrete column and concrete composite beam combined structure with adjustable connecting nodes and installation method thereof
CN210066816U (en) Assembled vault is striden no post underground structure greatly
CN106088398A (en) A kind of combined wall board

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination