CN114541625A - Cast-in-place building outer wall construction method and outer vertical surface waterproof protection structure - Google Patents

Cast-in-place building outer wall construction method and outer vertical surface waterproof protection structure Download PDF

Info

Publication number
CN114541625A
CN114541625A CN202210004003.7A CN202210004003A CN114541625A CN 114541625 A CN114541625 A CN 114541625A CN 202210004003 A CN202210004003 A CN 202210004003A CN 114541625 A CN114541625 A CN 114541625A
Authority
CN
China
Prior art keywords
construction
water
climbing frame
building
vertical surface
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202210004003.7A
Other languages
Chinese (zh)
Inventor
张强
罗景源
史静
李林林
周宁飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN202210004003.7A priority Critical patent/CN114541625A/en
Publication of CN114541625A publication Critical patent/CN114541625A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/0007Implements for finishing work on buildings for mounting doors, windows or frames; their fitting
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B30/00Energy efficient heating, ventilation or air conditioning [HVAC]
    • Y02B30/90Passive houses; Double facade technology

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Residential Or Office Buildings (AREA)

Abstract

The invention relates to the technical field of building construction, in particular to a construction method of a cast-in-place building outer wall based on a climbing frame, wherein a building main body is sequentially divided into a main structure construction area, a climbing frame auxiliary construction area and a hanging basket auxiliary construction area from the top to the bottom, wherein the main structure construction area at the top of the building is used for building main structure construction operation; formwork dismantling, acceptance, window installation and water spraying tests are carried out in the climbing frame auxiliary construction area; arranging a waterproof measure at the bottom of the climbing frame auxiliary construction area to guide the water flow falling in the upper water spraying test process to be far away from the outer vertical surface of the building; arranging a construction hanging basket in a hanging basket auxiliary construction area; and the upper half part of the hanging basket auxiliary construction area is subjected to heat preservation construction, and the lower half part of the hanging basket auxiliary construction area is subjected to outer facade decoration construction. The construction in the three areas can be carried out simultaneously, so that the construction efficiency is greatly improved, and the construction cost and the construction difficulty are reduced.

Description

Cast-in-place building outer wall construction method and outer vertical surface waterproof protection structure
Technical Field
The invention relates to the technical field of building construction, in particular to a climbing frame-based cast-in-place building outer wall construction method and an outer vertical surface waterproof protection structure used in the construction method.
Background
Current buildings, such as residential buildings or office buildings, all use cast-in-place concrete as the main structural body. During construction, the construction of the main building structure is generally carried out, and the quality inspection is qualified after the main building structure is completely finished. And then, the installation of the main frame and the auxiliary frame of the window and the glass and the water spraying test are started. And finally, performing outer wall facade construction such as waterproof of cast-in-place outer walls, heat preservation of the outer walls, installation of balconies and air-conditioning plates and the like of the outer walls.
The construction process is convenient to manage, and the construction of the main body structure cannot be influenced by other construction steps. But the whole construction period is longer, the labor is more, the material turnover utilization rate is low, and the construction cost is greatly increased. And follow-up a large amount of constructions such as the construction of balcony guardrail installation window frame all need pass through hanging flower basket or tower crane, influence the life cycle of equipment such as tower crane, increase the lease cost.
Disclosure of Invention
The invention aims to provide a construction method of a cast-in-place building outer wall based on a climbing frame, which aims to solve the problems that in the construction of the traditional residential building, the construction of a building main body, the construction and water spraying test of a window, the heat preservation and decoration construction of an outer facade need to be finished and the other construction needs to be carried out, so that the construction period is prolonged integrally and the construction cost is increased.
In order to solve the technical problems, the invention provides a construction method of a cast-in-place building outer wall based on a climbing frame, which adopts the following scheme.
A construction method of cast-in-place building outer wall based on a climbing frame, a building main body is divided into three construction areas of a main structure construction area, a climbing frame auxiliary construction area and a hanging basket auxiliary construction area from the top to the bottom in sequence,
the construction method comprises the following three construction steps which can be carried out simultaneously or in any sequence:
s21, carrying out construction operation on the main structure of the building in the main structure construction area at the top of the building;
s22, carrying out template dismantling, acceptance, window installation and water spraying tests in the climbing frame auxiliary construction area;
arranging a waterproof measure at the bottom of the climbing frame auxiliary construction area to guide the water flow falling in the upper water spraying test process to be far away from the outer vertical surface of the building;
s23, arranging a construction hanging basket in the hanging basket auxiliary construction area; the upper half of the hanging basket auxiliary construction area is subjected to heat preservation construction, and the lower half of the hanging basket auxiliary construction area is subjected to decoration construction.
Preferably, any floor in the climbing frame auxiliary construction area is subjected to template removal, acceptance, window installation and water spraying test in sequence from first to last; the following scheme may be employed:
the template dismantling, acceptance, window installation and water spraying test are sequentially carried out in a climbing frame auxiliary construction area from first to last according to a time sequence or are sequentially carried out on floors from top to bottom according to a space sequence;
the method comprises four procedures of template dismantling, acceptance inspection, window installation and water spraying test, wherein the procedures are carried out in the same floor of the climbing frame auxiliary construction area according to the time sequence, and the procedures are carried out in different floors according to the space sequence.
Preferably, the formwork removal further comprises wall defect repair and screw hole plugging, and the formwork removal is performed on a floor on the top of a climbing frame auxiliary construction area close to the main structure construction area.
Preferably, the window installation comprises the steps of:
a) mounting a window auxiliary frame;
b) painting waterproof window plug seams;
c, mounting the main window frame and the glass;
the steps a), b) and c) are sequentially carried out on different floors from top to bottom.
Preferably, the climbing frame auxiliary construction area is also subjected to air conditioner plate installation, drainage vertical pipe installation and balcony railing installation of the outer vertical surface after acceptance;
when the heat insulation construction is carried out on the balcony part, the installation of the balcony guardrail is completed, and the leveling is completed by once smearing the heat insulation mortar.
Preferably, the waterproof measure is set before the water spraying test; the waterproof measure includes that the reason goes up to lap the diversion board that leans on the wall body below the trickle experiment, and the diversion board lower margin extends to the direction of keeping away from the outer facade, and diversion board and climb a swing joint and move along with climbing the frame.
When the waterproof measure is used, the water-proof measure,
firstly, moving a water diversion plate to be abutted against a wall body before a water spraying test;
then, carrying out a water spraying test, wherein the water diversion plate conducts drainage on water flow falling from the water spraying test to protect the outer vertical surface of the building;
after the water spraying test is finished and before the climbing frame is lifted, the water guide plate is movably separated from the outer wall of the building, and then the climbing frame is lifted;
and finally, after the climbing frame is lifted and before the water spraying test experiment, the water guide plate is moved to be abutted against the wall body from the new water guide plate.
The invention also provides a water-spraying test outer vertical surface waterproof protection structure aiming at the waterproof measure in the step 2 in the cast-in-place building outer wall construction method based on the climbing frame.
The problem of the experimental work process of drenching at the top is carried out, avoids the rivers influence the outer wall heat preservation construction and the outer facade decoration construction that the below is being gone on of drenching.
In order to solve the technical problem, the invention discloses a waterproof protection structure for an outer vertical surface of a water spraying test.
A water-proof protection structure for an outer vertical surface of a water spraying test comprises a water diversion plate which is arranged at the bottom of a climbing frame and moves along with the climbing frame; the top of the diversion plate is leaned on the outer vertical surface of the building, and the diversion plate extends downwards from the outer vertical surface of the building in an inclined mode.
Preferably, the diversion board extends along the bottom horizontal direction of climbing the frame, climbs the frame and goes up the level interval and set up a plurality of diversion boards.
Preferably, the bottom of the diversion plate is provided with a concave diversion groove, the diversion groove horizontally extends along the outer vertical surface of the wall body, and the bottom of the diversion groove is obliquely arranged;
the lowest position of the bottom of the water diversion groove is communicated with a water diversion pipe, and the water diversion pipe is arranged in a cantilever mode towards the direction far away from the outer vertical face.
Preferably, the bottom of diversion board rotates and installs on climbing the frame, and the top of diversion board rotates in proper order and connects a plurality of extension boards, and the extension board can rotate to parallel with the diversion board to insert in the recess and the entrance to a cave of building facade.
The problems existing in the prior art are as follows: after the construction of the window is finished, a water spraying test is needed to test the waterproof performance of the window so as to repair the defects in time. However, during the water spraying test, a large amount of water flows onto the outer vertical surface of the building and then flows downwards along the outer vertical surface of the building. The problem is not great if the concrete is bare at this time. However, if the exterior wall insulation layer and the exterior wall decoration which are already carried out or finished are arranged below the heat insulation layer, the remained sewage can affect the heat insulation performance of the insulation layer and can smear the exterior wall decoration. The heat preservation construction of the outer vertical surface and the decoration construction of the outer vertical surface are necessarily carried out after the water spraying test is finished after the window is installed.
The outer wall which is just poured and demoulded is not suitable for immediately carrying out heat insulation construction on the outer wall, so that the current situation that the installation construction and the water spraying test of a window are carried out after the existing main body construction is capped, and then the heat insulation construction and the decoration construction of the outer facade are carried out is caused.
In addition, in the construction of a window in the prior art, the construction of the window sub-frame is generally earlier, and the window sub-frame is already installed at the lower part when the construction of the building main body is performed at the upper part. And then, the main window frame and the glass are installed after the building is capped, so that the construction interval between the auxiliary window frame and the main window frame is longer, and the installed auxiliary window frame is easy to fall into gravel and pollutants such as rainwater in the groove. When the main frame of the window is constructed, the main frame needs to be cleaned up firstly. And the rainwater of window subframe memory is difficult to complete clean up, when setting up waterproof filler material, the waterproof effect of filler material is influenced to the rainwater that exists. Affecting the water resistance of the whole window.
Compared with the prior art, the cast-in-place building outer wall construction method based on the climbing frame has the following beneficial effects:
the method comprises the following steps of building main structure construction, window construction, water spraying test, external vertical surface heat preservation and decoration construction, which are transferred to three construction areas from top to bottom of a building, namely a main structure construction area, a climbing frame auxiliary construction area and a hanging basket auxiliary construction area. The three construction steps are independently carried out in three construction areas without influencing each other. The three construction steps are changed from the chronological order to the spatial position order, so that the construction period is shortened.
Effectively utilize simultaneously to climb the function of frame and climb the frame and compare in the hanging flower basket convenience that brings the construction, let the installation of window go on in the protective range who climbs the frame in addition the water spraying test, great improvement the efficiency of construction of window installation and the experimental operating efficiency of water spraying. And all installation steps of the window are continuously carried out, so that the adverse effects of water stored in the auxiliary window frame on the construction quality are avoided due to the fact that the installation interval between the auxiliary window frame and the main window frame is too long.
Aiming at the problem that the water flow of a water spraying test can influence the heat preservation and decoration of the outer vertical surface finished in a hanging basket construction area below. And a waterproof measure is arranged at the bottom of the climbing frame, and the water flow falling in the upper water spraying test process is guided to be away from the outer vertical surface of the building.
The waterproof protection structure for the outer vertical surface of the water spraying test has the beneficial effects that:
the waterproof protection structure of the present invention is a specific structure designed for the waterproof measure of the step S22 in the exterior wall construction method of the present invention.
Specifically, a water diversion plate lifted along with the climbing frame is arranged at the bottom of the climbing frame, the upper edge of the water diversion plate is abutted against the outer vertical surface of the building, then the water diversion plate extends downwards and outwards, and water flow falling from an upper water spraying test is guided by the water diversion plate and can be far away from the outer vertical surface.
Drawings
FIG. 1 is a construction model diagram of a concrete embodiment of a construction method of a cast-in-place building outer wall based on a climbing frame;
FIG. 2 is a position relation diagram of different construction areas during actual construction of the cast-in-place building outer wall construction method based on the climbing frame;
FIG. 3 is a schematic structural diagram of a water-proof protection structure for an outer vertical surface of a water spraying test according to the present invention;
fig. 4 is a schematic structural view of fig. 3 after an extension plate inserted into the hole is added.
Description of reference numerals: 1-a main structure construction area; 2-climbing a frame to assist a construction area; 3-hanging basket auxiliary construction area; 4-climbing a frame; 5-a water diversion plate, 5 a-an extension plate; 6-a water diversion groove; 7-water conduit.
Detailed Description
The following detailed description of embodiments of the invention refers to the accompanying drawings. It should be understood that the detailed description and specific examples, while indicating the present invention, are given by way of illustration and explanation only, not limitation.
In the present invention, the use of directional terms such as "upper, lower, left, right" generally means upper, lower, left, right as described with reference to FIG. 3, unless otherwise specified; "inner and outer" refer to the inner and outer relative to the profile of the components themselves. The present invention will be described in detail below with reference to the accompanying drawings in conjunction with embodiments.
Concept interpretation:
as shown in fig. 2, the main structure construction area 1 is a position where the construction of a reinforcing bar binding formwork, concrete pouring, and the like of the main structure of the building is performed on the uppermost side of the building.
Wherein climb the supplementary construction district 2 of frame and refer to and receive the parcel protection of climbing frame 4 on the building, climb the region that frame 4 can help bearing material and constructor. Because the top of the building is an open space during construction of the building, the open space is internally used for construction operation of the building main body. The area where the main construction of the building is being performed on the uppermost floor of the building is called a main structure construction area 1. The scaffold assisted construction zone 2 does not include the uppermost open space and the area where the construction of the main building body is being performed, although this area is also protected and affected by the scaffold 4.
The hanging basket auxiliary construction area 3 refers to an area where people and building materials are conveyed in a hanging basket mode to carry out outer elevation construction after the climbing frame 4 moves upwards to the position.
Major structure construction district 1, climb the supplementary construction district 2 of frame and the supplementary construction district 3 of hanging flower basket are three dynamic region, and along with going on constantly of construction, building subject's height constantly increases, building subject's construction position and climbing frame 4 are also constantly becoming high carrying on, therefore major structure construction district 1 here, climb the supplementary construction district 2 of frame and the supplementary construction district 3 of hanging flower basket and be the position of three construction district and also can dynamic change thereupon, can be along with building subject's construction progress and climb the rising of frame 4 and constantly improve. A certain floor of the building in the early stage is a main structure construction area 1, the subsequent construction is performed and the lifting of the climbing frame 4 becomes a climbing frame auxiliary construction area 2, and the climbing frame 4 is further lifted to be separated from the floor in the future, and becomes a hanging basket auxiliary construction area 3. The position is subjected to main structure construction, window installation and water spraying test, and finally heat preservation construction and outer facade decoration construction are carried out, and three complete construction stages are achieved.
The method aims to solve the problems that in the traditional residential building construction, the construction of a building main body, the construction and water spraying test of a window and the heat preservation and decoration construction of an outer vertical face need to be finished and then another construction is carried out, so that the construction period is prolonged and the construction cost is increased on the whole. The invention firstly provides a construction method of a cast-in-place building outer wall based on a climbing frame, as shown in figures 1 and 2.
A construction method of a cast-in-place building outer wall based on a climbing frame is characterized in that a building main body is sequentially divided into a main structure construction area 1, a climbing frame auxiliary construction area 2 and a hanging basket auxiliary construction area 3 from the top to the bottom,
the construction method comprises the following three construction steps which can be carried out simultaneously or in any sequence:
s21, carrying out construction operation on the main structure of the building in the main structure construction area 1 at the top of the building;
s22, sequentially carrying out template dismantling, acceptance inspection, window installation and water spraying tests in the climbing frame auxiliary construction area 2;
arranging a waterproof measure at the bottom of the climbing frame auxiliary construction area 2 to guide the water flow falling in the upper water spraying test process to be far away from the outer vertical surface of the building;
s23, arranging a construction hanging basket in the hanging basket auxiliary construction area 3; and the upper half part of the hanging basket auxiliary construction area 3 is subjected to heat preservation construction, and the lower half part is subjected to outer facade decoration construction.
The construction of the main structure at the top of the building is not different from the prior art, and the construction operation of the main structure such as reinforcement, formwork erection and concrete pouring is carried out, which is not repeated herein.
The climbing frame auxiliary construction area 2 and the hanging basket auxiliary construction area 3 are isolated through a waterproof measure at the bottom of the climbing frame 4, and when the climbing frame auxiliary construction area 2 is used for a water spraying test, sewage flows to the hanging basket auxiliary construction area 3 below along the outer vertical surface. Therefore, when the climbing frame auxiliary construction area 2 is used for carrying out window installation and a water spraying test on a window, the hanging basket auxiliary construction area 3 below is erected with the hanging basket for carrying out heat preservation construction and decoration construction of the outer vertical surface.
Climb the outer facade outside of the supplementary construction area 2 region of frame and have and climb frame 4, climb frame 4 and can provide the space that stable personnel stood the construction to and bear the used material of construction, consequently climb the construction speed that the outer facade part of the supplementary construction area 2 of frame that accelerates that frame 4 can be great in the utilization, reduce the construction degree of difficulty and improve construction safety nature. Before the water spraying test is needed, a waterproof measure is arranged below the water spraying test.
And the decoration construction of the facade must be carried out after the heat preservation construction is finished. Therefore, in order to accelerate the construction progress, the hanging basket auxiliary construction area 3 is divided into an upper part and a lower part, the upper part is firstly subjected to heat preservation construction on the exposed concrete outer vertical surface, and then the lower part is subjected to decoration construction of the outer vertical surface at the position where the heat preservation construction is finished.
Any floor of the climbing frame auxiliary construction area 2 is subjected to template removal, acceptance, window installation and water spraying tests in sequence from first to last according to time, and the sequence of the four construction projects on the same floor or the same position cannot be changed. Therefore, the template removal, acceptance, window installation and water spraying test are sequentially carried out from first to last in the time sequence or are sequentially carried out from top to bottom in the space sequence in the climbing frame auxiliary construction area 2. Or a mixture of temporal and spatial order. Specifically, the work with high construction speed and short construction time is arranged in the same floor according to the time sequence, the working procedure with long construction time is arranged in a plurality of floors to be continuously carried out, and finally the arranged floors are arranged from top to bottom according to the sequence of four items of template removal, acceptance, window installation and water spraying test. As shown in fig. 1, the formwork removal work is performed by separately setting up N-1 floors, and then the preliminary work of acceptance and window installation is arranged at N-2 floors, and then the installation of windows is performed in three consecutive floors from N-2 floors to N-4 floors. And finally, the final work of the short-time water spraying test and the window installation is installed on the N-4 layers.
In a word, any floor in the climbing frame auxiliary construction area 2 only needs to be guaranteed to sequentially pass through four procedures of template removal, acceptance inspection, window installation and water spraying test from first to last according to the time sequence.
Because materials such as formwork support columns and the like used in the main structure construction need to be circulated as soon as possible, the formwork dismantling is carried out on the floors at the top of the climbing frame auxiliary construction area 2 close to the main structure construction area 1. And meanwhile, after the template is dismantled, wall defect repair and screw hole plugging operation are required.
As shown in fig. 1, the window installation includes the steps of:
a) mounting a window auxiliary frame;
b) painting waterproof window plug seams;
c) installing a main window frame and glass;
the steps a), b) and c) are sequentially carried out on different floors from top to bottom.
Because the climbing frame 4 brings great convenience to the construction of the outer wall, the climbing frame auxiliary construction area 2 also carries out the installation of an air conditioner plate, the installation of a drainage vertical pipe and the installation of balcony rails on the outer vertical surface after acceptance; the air conditioning plate can not be the air conditioning plate which is arranged in a cantilever manner due to the form that the air conditioning plate is retracted into the groove of the outer vertical surface when needed, so that the air conditioning plate is prevented from influencing the lifting of the climbing frame 4.
In the prior art, the heat insulation operation of an outer wall is generally carried out firstly, and then a guardrail is installed. When the heat preservation operation is carried out, the guardrail installation position needs to be avoided, and then the leveling repair needs to be carried out again after the installation of the guardrail is completed. Therefore, the installation of the balcony guardrail is completed when the heat insulation construction is carried out on the balcony part, and the leveling is completed by smearing the heat insulation mortar once.
The waterproof measure is set and finished before the water spraying test, as shown in fig. 3, the left side of fig. 3 is a building outer wall, the right side of fig. 3 is a climbing frame 4, and a water diversion plate 5 is arranged at the bottom of the climbing frame 4. The waterproof measure includes that the upper edge is lapped on the diversion plate 5 on the wall body below the water spraying test, the lower edge of the diversion plate 5 extends towards the direction far away from the outer vertical surface, and the diversion plate 5 is connected with the climbing frame 4 and moves along with the climbing frame 4. Because the diversion plate 5 moves upwards synchronously with the climbing frame 4, the diversion plate 5 can be positioned at the bottom of the climbing frame 4 all the time.
When the waterproof measure is used, the method comprises the following four steps:
firstly, moving a water diversion plate 5 to be abutted against a wall body before a water spraying test;
then, carrying out a water spraying test, wherein the water guide plate 5 guides the water flow falling from the water spraying test to protect the outer vertical surface of the building;
then after the water spraying test is finished and before the climbing frame 4 is lifted, the water guide plate is movably separated from the outer wall of the building, and then the climbing frame 4 is lifted;
and finally, after the climbing frame 4 is lifted and is finished and before a water spraying test experiment, the water guide plate 5 is newly led to move to be abutted against the wall body.
The diversion plate is installed on climbing frame 4, and together the preparation is accomplished when making climbing frame, and once preparation can use the construction completion, and when moving climbing frame 4 at every turn, only need let the diversion plate break away from the facade of wall body, avoid diversion plate 5 to influence the motion of climbing frame 4. Let the diversion board move about at ordinary times and contact with the wall body, performance diversion board's diversion function. The length of the diversion plate 5 is determined according to the concrete building type and the position of the constructed building for carrying out the water spraying test. For example, most of the gable walls on two sides of the building do not have windows, so that the water diversion plates 5 do not need to be installed at the positions of the gable walls on the two sides because of no need of arranging waterproof measures.
Meanwhile, in order to match with the waterproof measure at the bottom of the climbing frame 4, the invention also designs a waterproof protection structure for the outer vertical surface of the water spraying test, as shown in fig. 3 and 4.
Comprises a water diversion plate 5 which is arranged at the bottom of a climbing frame 4 and moves up and down along with the climbing frame 4; the top of the diversion plate 5 is leaned on the outer vertical surface of the building, and the diversion plate 5 extends downwards from the outer vertical surface of the building in an inclined mode. A small amount of sewage can leak from the gap between the water diversion plate 5 and the outer vertical surface, and the small amount of sewage can seep into the outer vertical surface in the process of flowing downwards along the outer vertical surface, so that the heat preservation construction and the decoration construction below cannot be substantially influenced.
The diversion plates 5 are designed according to specific building types, each block is 5-20 m long generally, and the diversion plates 5 extend in the horizontal direction. If the building is longer, a plurality of diversion plates 5 can be continuously arranged at intervals at the bottom of the climbing frame 4. The diversion plates 5 extend along the horizontal direction of the bottom of the climbing frame 4, and a plurality of diversion plates 5 are horizontally arranged on the climbing frame 4 at intervals. In short, the water diversion plate 5 is arranged below the water spraying test. Simultaneously the bottom of diversion board 5 is rotated and is installed on climbing frame 4, when needs promote climbing frame 4, with the upper end bogie 4 of diversion board 5, lets diversion board 5 break away from the outer facade of building. Avoid the diversion board 5 to influence and climb the lift of frame 4.
As shown in fig. 3, the bottom of the diversion plate 5 is provided with a concave diversion groove 5a, the diversion groove 5a extends horizontally along the outer vertical surface of the wall body, the bottom of the diversion groove 5a is arranged obliquely, the lowest part of the bottom of the diversion groove 5a is communicated with a diversion pipe 5a, and the diversion pipe 5a is arranged in a cantilever way in the direction far away from the outer vertical surface. The water diversion plate 5 is wider, the distance for guiding sewage away from the outer vertical surface is limited, a water diversion groove 5a is formed in the bottom of the water diversion plate 5, then the sewage is guided to a position far away from the outer vertical surface through a water drinking pipe or is guided to a drainage vertical pipe, and the water diversion pipe 5a can also be directly hung near the ground.
As shown in fig. 4, the top of the diversion plate 5 is sequentially connected with a plurality of extension plates 5a in a rotating way, and the extension plates 5a can rotate to be parallel to the diversion plate 5 so as to be inserted into the grooves and the holes of the building facade. According to the concrete building type, a plurality of extension plates 5a can be arranged on the diversion plate 5 at intervals. The upper surfaces of the extension board 5a and the water diversion board 5 are covered with a waterproof film.
The above-mentioned embodiments are merely illustrative of the preferred embodiments of the present invention, and do not limit the scope of the present invention, and various modifications and improvements of the technical solution of the present invention by those skilled in the art should fall within the protection scope defined by the claims of the present invention without departing from the spirit of the present invention.

Claims (10)

1. A cast-in-place building outer wall construction method based on a climbing frame is characterized by comprising the following steps:
s1, dividing the building main body into a main structure construction area (1), a climbing frame auxiliary construction area (2) and a hanging basket auxiliary construction area (3) from the top to the bottom in sequence in space;
s2, carrying out corresponding construction operation in three construction areas simultaneously or in any sequence according to the following three steps:
s21, carrying out construction operation of the main structure of the building in the main structure construction area (1) at the top of the building;
s22, carrying out template dismantling, acceptance, window installation and water spraying tests in the climbing frame auxiliary construction area (2); a waterproof measure is arranged at the bottom of the climbing frame auxiliary construction area (2) to guide the water flow falling in the upper water spraying test process to be far away from the outer vertical surface of the building;
s23, arranging a construction hanging basket in the hanging basket auxiliary construction area (3); the upper half part of the hanging basket auxiliary construction area (3) is subjected to heat preservation construction, and the lower half part is subjected to outer facade decoration construction.
2. The construction method of the climbing frame-based cast-in-place building outer wall according to the claim 1, characterized in that the template removal, acceptance, window installation and water spraying test are sequentially carried out in the climbing frame auxiliary construction area (2) from first to last in a time sequence or are sequentially carried out in a floor division manner from top to bottom in a space sequence.
3. The construction method of the climbing frame based cast-in-place building outer wall according to the claim 1, characterized in that the form removal further comprises the repair of wall defects and the screw hole plugging, and the form removal is performed on the top floor of the climbing frame auxiliary construction area (2) adjacent to the main structure construction area (1).
4. The construction method for the cast-in-place building outer wall based on the climbing frame as claimed in claim 1, wherein the window installation comprises the following steps:
a) mounting a window auxiliary frame;
b) painting waterproof window plug seams;
c) installing a main window frame and glass;
the steps a), b) and c) are sequentially carried out on different floors from top to bottom.
5. The construction method for the cast-in-place building outer wall based on the climbing frame is characterized in that the waterproof measure is set before a water spraying test; the waterproof measure includes that the upper edge is lapped on a water diversion plate (5) on a wall body below the water spraying test, the lower edge of the water diversion plate (5) extends towards the direction far away from the outer vertical surface, and the water diversion plate (5) is movably connected with the climbing frame (4) and moves along with the climbing frame (4).
6. The construction method of the cast-in-place building outer wall based on the climbing frame as claimed in claim 5, wherein when the waterproof measure is in use,
firstly, moving a water diversion plate (5) to be abutted against a wall body before a water spraying test;
then, carrying out a water spraying test, and carrying out drainage on the water flow falling from the water spraying test by a water guide plate (5) to protect the outer vertical surface of the building;
then after the water spraying test is finished and before the climbing frame (4) is lifted, the water guide plate is movably separated from the outer wall of the building, and then the climbing frame (4) is lifted;
and finally, after the climbing frame (4) is lifted and before a water spraying test experiment is carried out, the water guide plate (5) is moved to be abutted against the wall body.
7. A water-proof protection structure for an outer vertical surface of a water spraying test is characterized by comprising a water diversion plate (5) which is arranged at the bottom of a climbing frame (4) and moves along with the climbing frame (4); the top of the water diversion plate (5) is abutted against the outer vertical surface of the building, and the water diversion plate (5) extends downwards from the outer vertical surface of the building in an inclined mode.
8. The water-proof protection structure for the outer vertical surface of the water spraying test according to claim 7, wherein the water diversion plates (5) extend along the horizontal direction of the bottom of the climbing frame (4), and a plurality of water diversion plates (5) are horizontally arranged on the climbing frame (4) at intervals.
9. The water-proofing protection structure for the outer vertical surface of the water spraying test according to claim 7, wherein the bottom of the water guide plate (5) is provided with a concave water guide groove (5 a), the water guide groove (5 a) horizontally extends along the outer vertical surface of the wall body, and the bottom of the water guide groove (5 a) is obliquely arranged;
the lowest position of the bottom of the water guide groove (5 a) is communicated with a water guide pipe (5 a), and the water guide pipe (5 a) is arranged in a cantilever mode towards the direction far away from the outer vertical surface.
10. The water-proof protection structure for the facade of the water spraying test according to claim 7, wherein the bottom of the water diversion plate (5) is rotatably installed on the climbing frame (4), the top of the water diversion plate (5) is sequentially and rotatably connected with a plurality of extension plates (5 a), and the extension plates (5 a) can be rotated to be parallel to the water diversion plate (5) so as to be inserted into grooves and holes of the facade of a building.
CN202210004003.7A 2022-01-05 2022-01-05 Cast-in-place building outer wall construction method and outer vertical surface waterproof protection structure Withdrawn CN114541625A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210004003.7A CN114541625A (en) 2022-01-05 2022-01-05 Cast-in-place building outer wall construction method and outer vertical surface waterproof protection structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210004003.7A CN114541625A (en) 2022-01-05 2022-01-05 Cast-in-place building outer wall construction method and outer vertical surface waterproof protection structure

Publications (1)

Publication Number Publication Date
CN114541625A true CN114541625A (en) 2022-05-27

Family

ID=81669558

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210004003.7A Withdrawn CN114541625A (en) 2022-01-05 2022-01-05 Cast-in-place building outer wall construction method and outer vertical surface waterproof protection structure

Country Status (1)

Country Link
CN (1) CN114541625A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110173102A (en) * 2019-05-09 2019-08-27 上海建工一建集团有限公司 The more work surface synchronous construction foot hand systems of super high-rise building and construction method
CN112049237A (en) * 2020-09-04 2020-12-08 珠海华章工程管理咨询有限公司 Vertical penetration construction method for high-rise building
US20210198908A1 (en) * 2019-12-29 2021-07-01 The Third Construction Co., Ltd Of China Construction Third Engneering Bureau Construction building equipment and construction method thereof
CN113323396A (en) * 2021-06-15 2021-08-31 南京工业大学 Integrated construction method for external wall of fabricated building
CN113802845A (en) * 2021-10-28 2021-12-17 云南建投第六建设有限公司 Synchronous reverse construction method for high-rise building outer wall decoration engineering and main body structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110173102A (en) * 2019-05-09 2019-08-27 上海建工一建集团有限公司 The more work surface synchronous construction foot hand systems of super high-rise building and construction method
US20210198908A1 (en) * 2019-12-29 2021-07-01 The Third Construction Co., Ltd Of China Construction Third Engneering Bureau Construction building equipment and construction method thereof
CN112049237A (en) * 2020-09-04 2020-12-08 珠海华章工程管理咨询有限公司 Vertical penetration construction method for high-rise building
CN113323396A (en) * 2021-06-15 2021-08-31 南京工业大学 Integrated construction method for external wall of fabricated building
CN113802845A (en) * 2021-10-28 2021-12-17 云南建投第六建设有限公司 Synchronous reverse construction method for high-rise building outer wall decoration engineering and main body structure

Similar Documents

Publication Publication Date Title
US20210198908A1 (en) Construction building equipment and construction method thereof
CN111926910A (en) Installation method of fabricated building
CN112112418B (en) Construction method of high-rise building aluminum formwork climbing frame combined system
CN113073803B (en) Assembly type external wall board waterproof system and construction method thereof
CN105672664A (en) Integral heat insulation wallboard building system
CN113653272B (en) Archaized eave of steel structure of high-rise building and construction method thereof
CN109339355B (en) Construction method of aluminum plate roof waterproof joint adopting ALC (autoclaved lightweight concrete) plate as structural plate
CN208294122U (en) A kind of structure installing elevator additional on the outside of existing building
CN111119368A (en) Construction method for externally-hung metal rock wool sandwich board of autoclaved sand aerated concrete wallboard
WO2003048469A1 (en) Method for constructing tier building and special jack equipment thereof
CN114541625A (en) Cast-in-place building outer wall construction method and outer vertical surface waterproof protection structure
CN217175304U (en) Tubular well plugging structure
CN108005233A (en) A kind of section construction and construction method
CN115247508B (en) Construction method of large-scale pool structure of sewage treatment station
CN211817210U (en) Steel partition wall structure
CN102051983B (en) Method of reconstructing steel rolling workshop into teaching building
CN109707152B (en) Aluminum alloy formwork system and construction method thereof
CN113323396A (en) Integrated construction method for external wall of fabricated building
CN113585553A (en) EPS (expandable polystyrene) disassembly-free heat-insulation wall formwork framework with fireproof isolation belt and construction method
CN111502277A (en) Efficient alternate running water construction method for high-rise building construction
CN219471636U (en) Capping device for newly-built or rebuilt stairwell
CN204531499U (en) Construction engineering quality model display platform
CN113802775B (en) Construction method for curved surface roof of station
CN114635566B (en) French style dome structure construction method
CN108104472A (en) Intert construction outside complete cast-in-place exterior wall high residential building room and put forward efficacious prescriptions method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20220527

WW01 Invention patent application withdrawn after publication