CN114250778A - Method for anchoring middle anti-pulling ring electric tower foundation pit - Google Patents

Method for anchoring middle anti-pulling ring electric tower foundation pit Download PDF

Info

Publication number
CN114250778A
CN114250778A CN202011036543.0A CN202011036543A CN114250778A CN 114250778 A CN114250778 A CN 114250778A CN 202011036543 A CN202011036543 A CN 202011036543A CN 114250778 A CN114250778 A CN 114250778A
Authority
CN
China
Prior art keywords
foundation pit
pulling
pit
ring
electric tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011036543.0A
Other languages
Chinese (zh)
Inventor
韩恺
史卓鹏
刘继武
王亚臣
张鑫
张骁健
闫炜炀
马杰
闫先伟
智生龙
牛园
张嘉
何晓东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Shanxi Electric Power Survey And Design Institute Co ltd
Original Assignee
State Grid Shanxi Electric Power Survey And Design Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Shanxi Electric Power Survey And Design Institute Co ltd filed Critical State Grid Shanxi Electric Power Survey And Design Institute Co ltd
Priority to CN202011036543.0A priority Critical patent/CN114250778A/en
Publication of CN114250778A publication Critical patent/CN114250778A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Foundations (AREA)

Abstract

The method for anchoring a foundation pit with a middle pulling-resistant ring and an electric tower discloses a method for placing the pulling-resistant ring in the middle of the foundation pit and reinforcing the pulling-resistant ring by using an anchor rod. Firstly, digging a foundation pit to the middle part, properly manufacturing a retaining wall at the upper section 1 of the foundation pit, and nailing an anchor rod 2 at the bottom. Then, the four-point expansion is carried out to form the anti-pulling ring 3. And then digging the lower section 4 of the foundation pit. Upper section h12m high; height h of anti-pulling ring21m, and the depth b of the pit is 1 m; lower segment depth h3According to the design of the installed electric tower. The usage amount of the wall protection concrete is reduced by 20 percent, and the usage amount of the reinforcing steel bar is reduced by 12 percent; the construction is safe, and the difficulty is reduced; the construction period is short. The method is used for foundation engineering of the electric tower.

Description

Method for anchoring middle anti-pulling ring electric tower foundation pit
Technical Field
A method for placing an anti-pulling ring in an anchored foundation pit of an electric tower relates to the electric power engineering construction technology, in particular to a method for placing an anti-pulling ring in the middle of the foundation pit of the tower.
Background
The existing foundation pit of the electric tower is shaped like a cylindrical straight pit, and the bottom of the straight pit is provided with an annular uplift-resistant ring protruding into the pit wall. The manual digging has the advantages of simple apparatus, convenient construction, small vibration, quick construction, low cost and the like, the engineering application is common, and particularly, in rugged hilly and mountainous areas with inconvenient traffic, mechanical equipment is difficult to reach, and manual digging has to be adopted. Practice shows that when the deep foundation pit is expanded to form the uplift-resistant ring, accidents that the pit wall collapses to endanger the safety of workers are increasingly appeared. The uplift ring has the functions of electric tower uplift resistance, tower weight support and tower body inclination resistance, and the design of pit depth should comprehensively consider the 'uplift resistance, load bearing, overturn resistance' and 'construction safety and convenience'.
Disclosure of Invention
The technical problem to be solved by the method for anchoring the foundation pit of the mid-set anti-pulling coil electric tower is as follows: the hidden trouble that the pit wall collapses caused by the construction of the anti-pulling ring arranged at the bottom of the pit is avoided.
The technical scheme is as follows: the bottom anti-pulling ring moves to the middle part of the foundation pit and is anchored.
The method for anchoring the foundation pit of the mid-positioned anti-pulling coil electric tower (shown in figure 1) comprises the following steps:
step 1, digging a foundation pit to the middle of the pit depth by adopting a mechanical Luoyang shovel.
And 2, according to the soil hardness degree above the middle part of the foundation pit, taking the pit wall above the middle part as a retaining wall as appropriate.
And 3, uniformly nailing a group of anchor rods 2 into the vertical pit wall at the bottom of the upper section 1 of the foundation pit so as to prevent the cliff of the uplift-resistant ring 3 from collapsing.
And 4, performing four-expansion on the middle part to form an anti-pulling ring 3.
And 5, after the fourth expansion is performed to form the pulling-resistant ring 3, continuously using a mechanical Luoyang shovel to dig to the full depth of the foundation pit. And the lower section 4 of the foundation pit below the anti-pulling ring 3 is omitted as a protective wall. But according to the geological actual condition of the foundation pit and the foundation acting force, the diameter a and the depth h3 of the foundation pit under the uplift resistant ring 3 can be adjusted.
The beneficial effects of the method for anchoring the foundation pit of the centrally-mounted anti-pulling coil electric tower are as follows: firstly, the anti-pulling ring 3 moves from the bottom of the foundation pit to the middle part, so that the wall protection material consumption is reduced, and the concrete consumption is saved by 20 percent and the reinforcing steel bar consumption is saved by 12 percent; secondly, the upper section of the foundation pit is only 2m, and the anchor rod 2 and the retaining wall are used for protection, so that the hidden danger of personal accidents caused by pit wall collapse is avoided, and the construction safety is ensured. Even if the upper section 1 of the pit wall is accidentally collapsed, the height is only 2m, so that a serious accident of people burying cannot be caused. And thirdly, the construction difficulty is reduced, and the construction period is shortened.
Drawings
FIG. 1 is a schematic diagram of the shape of an anchoring mid-positioned anti-pulling-out coil electric tower foundation pit.
In the figure: 1-upper section; 2-anchor rod; 3-pulling-resistant ring; 4-lower section; a-the diameter of the foundation pit; b, deeply penetrating the bottom of the anti-pulling ring; h is1-upper section depth; h is2-a pull-out resistance loop height; h is3Lower section deep.
Detailed Description
Referring to FIG. 1, a preferred mode of carrying out the above method is detailed as follows:
height h of upper section of foundation pit 12 m. Height h of anti-pulling ring 21 m; the bottom of the anti-pulling ring penetrates into the pit wall to a depth b of 1 m. The diameter a of the foundation pit and the depth h3 of the lower section are designed according to the installed electric tower. The anchor rod 2 is 500mm long, 10mm in diameter and is provided with a disc head and a tip tail.

Claims (2)

1. Put resistance to plucking circle electricity tower foundation ditch way in the anchor, characterized by: step 1, digging a foundation pit to the middle part of a pit body by adopting a mechanical Luoyang shovel; 2. according to the degree of soil hardness above the middle part of the foundation pit, taking the pit wall above the middle part as a retaining wall as appropriate; 3. a group of anchor rods (2) are uniformly nailed into the upper section (1) of the foundation pit and vertical to the pit wall; 4. the middle part is expanded to form an anti-pulling ring (3); 5. after the four-hole expansion forms the pulling-resistant ring (3), the mechanical Luoyang shovel is continuously used for digging to the full depth of the foundation pit, and the lower section (4) of the foundation pit below the pulling-resistant ring (3) is saved as a protective wall.
2. The method for manufacturing the foundation pit of the anchored mid-positioned anti-pulling coil electric tower as claimed in claim 1, wherein the method comprises the following steps: height h of upper section of foundation pit12 m; height h of anti-pulling ring21m, the bottom of the anti-pulling ring penetrates into the pit wall to a depth b of 1 m; the diameter a of the foundation pit and the depth h3 of the lower section are designed according to the installed electric tower. The method for manufacturing the foundation pit of the anchored mid-positioned anti-pulling coil electric tower as claimed in claim 1, wherein the method comprises the following steps: the anchor rod (2) is 500mm long, 10mm in diameter and is provided with a disc head and a tip tail.
CN202011036543.0A 2020-09-23 2020-09-23 Method for anchoring middle anti-pulling ring electric tower foundation pit Pending CN114250778A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011036543.0A CN114250778A (en) 2020-09-23 2020-09-23 Method for anchoring middle anti-pulling ring electric tower foundation pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011036543.0A CN114250778A (en) 2020-09-23 2020-09-23 Method for anchoring middle anti-pulling ring electric tower foundation pit

Publications (1)

Publication Number Publication Date
CN114250778A true CN114250778A (en) 2022-03-29

Family

ID=80790790

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011036543.0A Pending CN114250778A (en) 2020-09-23 2020-09-23 Method for anchoring middle anti-pulling ring electric tower foundation pit

Country Status (1)

Country Link
CN (1) CN114250778A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009007844A (en) * 2007-06-28 2009-01-15 Kyushu Dengi Kaihatsu Kk Inverted t-shape foundation and its constructing method, and power transmission steel tower system
CN101446088A (en) * 2008-11-11 2009-06-03 中国电力科学研究院 Construction method for pole and tower foundation in Gobi Desert gravelly soil area
CN102912798A (en) * 2012-11-06 2013-02-06 山东兴华建设集团有限公司 Compound soil nail wall foundation pit supporting method
CN203947468U (en) * 2014-06-30 2014-11-19 河北省电力勘测设计研究院 A kind of Near Ground place expands the compacted bearing disk pile of section
CN104499501A (en) * 2014-12-08 2015-04-08 国家电网公司 Narrow-foundation-tower single-pile pier-type self-stabilized foundation for power transmission line

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009007844A (en) * 2007-06-28 2009-01-15 Kyushu Dengi Kaihatsu Kk Inverted t-shape foundation and its constructing method, and power transmission steel tower system
CN101446088A (en) * 2008-11-11 2009-06-03 中国电力科学研究院 Construction method for pole and tower foundation in Gobi Desert gravelly soil area
CN102912798A (en) * 2012-11-06 2013-02-06 山东兴华建设集团有限公司 Compound soil nail wall foundation pit supporting method
CN203947468U (en) * 2014-06-30 2014-11-19 河北省电力勘测设计研究院 A kind of Near Ground place expands the compacted bearing disk pile of section
CN104499501A (en) * 2014-12-08 2015-04-08 国家电网公司 Narrow-foundation-tower single-pile pier-type self-stabilized foundation for power transmission line

Similar Documents

Publication Publication Date Title
CN101408023A (en) Method for supporting and protecting row pile pit
CN214530750U (en) Bridge pile foundation structure suitable for rock mass abrupt slope
CN104532868A (en) Anchored high bearing platform grouped pile foundation building method for high-steep deformation slope area bridge
CN204139197U (en) Bottom enlarging prestress anchoring pile wind energy conversion system basis
CN111364494B (en) Offshore high-pile bearing platform foundation supported by anchor cables and inclined straight piles and construction method thereof
CN111021402A (en) Grouting type anchoring foundation with inner bag and outer bag and construction method thereof
CN110565657A (en) Supporting structure for reinforcing landslide and construction method
CN201232193Y (en) Wind motor tower foundation anchor pile structure on rock foundation
CN112982472B (en) Power transmission tower foundation structure suitable for regions without bedrock and construction method
CN104711991A (en) Foundation near foundation pit slope and reinforcement method thereof
CN114250778A (en) Method for anchoring middle anti-pulling ring electric tower foundation pit
CN206034427U (en) Mountain area hinders smooth anti -floating pile
CN111395411A (en) Be used for interim engineering pile foundation scour prevention device on water
CN208328968U (en) A kind of upper stake suitable for large-scale cyclic load is casted anchor novel foundation
CN101481910B (en) Construction method of foundation pit slope supported independent pile tower crane foundation
CN203684222U (en) Pile-anchor combined supporting structure with rotary jet enlarging head pre-stressed anchor rods
CN212506362U (en) Offshore high-rise pile cap foundation supported by anchor cables and inclined straight piles
CN205116239U (en) Engineering pile foundation static load detects resistance anchor hoe
CN113047333A (en) Land flood control fan foundation structure
CN212801551U (en) Rectangular shape deep basal pit supporting device
CN211006645U (en) Drilling bored concrete pile reinforced structure
CN206986915U (en) A kind of fan platform installation foundation
CN210597018U (en) Steel trestle stabilizing device for deep water bare rock area
CN217758971U (en) Mountain region photovoltaic pile foundation pore wall is strutted
CN205712128U (en) A kind of Pile-Anchor Supporting for Deep Excavation device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20220329