CN114118842A - Sponge city construction engineering design examination system - Google Patents

Sponge city construction engineering design examination system Download PDF

Info

Publication number
CN114118842A
CN114118842A CN202111458483.6A CN202111458483A CN114118842A CN 114118842 A CN114118842 A CN 114118842A CN 202111458483 A CN202111458483 A CN 202111458483A CN 114118842 A CN114118842 A CN 114118842A
Authority
CN
China
Prior art keywords
design
examination
review
stage
sponge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111458483.6A
Other languages
Chinese (zh)
Inventor
韩素华
曹倩男
陆敏博
陈浩东
何伶俊
朱建国
朱晓娟
钱冬旭
杨烨
陈天放
高欣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCDI Suzhou Exploration and Design Consultant Co Ltd
Original Assignee
CCDI Suzhou Exploration and Design Consultant Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCDI Suzhou Exploration and Design Consultant Co Ltd filed Critical CCDI Suzhou Exploration and Design Consultant Co Ltd
Priority to CN202111458483.6A priority Critical patent/CN114118842A/en
Publication of CN114118842A publication Critical patent/CN114118842A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/10Services
    • G06Q50/26Government or public services

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Marketing (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Game Theory and Decision Science (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The application provides a sponge city construction engineering design inspection system, includes: the examination material storage module is used for storing all the materials to be examined, and the materials to be examined comprise a design scheme, a construction drawing, a basic information table of the design scheme and a basic information table of the construction drawing; a related material providing module for providing related examination materials to an examiner; and the examination main point providing module is used for providing the corresponding examination main points to the examiners in each examination stage. According to the method and the device, the basic information table of the design scheme and the basic information table of the construction drawing are arranged in the material to be examined, and the associated examination material and the corresponding examination key points are provided for examiners, so that the relevance of the scheme design and the construction drawing design examination in stages can be enhanced, the synchronous examination of the main body design examination and the sponge special design examination and the fusion examination of each professional design and the sponge facility design examination are realized, and the coordination of multiple dimensions and multiple professions and the unification of the examination standards are realized.

Description

Sponge city construction engineering design examination system
Technical Field
The invention relates to a sponge city construction project examination technology, in particular to a sponge city construction project design examination system.
Background
The sponge city is defined as a novel city development mode and has obvious benefits for environment, society and economy. However, in the specific design and construction process, the technical standards and guidelines that can be referred to for sponge city construction are very limited, and the standard guidelines in the aspect of design review are rather missing. Each city successively sends corresponding local examination points to guide local design and examination work, but the compilation depth and the emphasis of the examination points are not consistent. The obvious problems brought by inconsistency and inconsistency of the examination standards are that the depth of the sponge city design files is inconsistent, the requirements are inconsistent, and the practice of 'five-door and eight-door' is presented, including various core index calculation processes, and various expression modes of section forms, plane diagrams and vertical diagrams of sponge facilities, which brings great difficulty to the work of examiners, and what and how the sponge city design files are examined become the check, the examiners and even the designers need to understand urgently.
Disclosure of Invention
The invention aims to provide a sponge city construction engineering design examination system, which is used for coordinating and unifying scheme examination and construction drawing examination and improving examination association.
The following presents a simplified summary of one or more aspects in order to provide a basic understanding of such aspects. This summary is not an extensive overview of all contemplated aspects, and is intended to neither identify key or critical elements of all aspects nor delineate the scope of any or all aspects. Its sole purpose is to present some concepts of one or more aspects in a simplified form as a prelude to the more detailed description that is presented later.
According to an aspect of the present invention, there is provided a sponge city construction engineering design review system, comprising: the examination material storage module is used for storing all the materials to be examined, and the materials to be examined comprise a design scheme, a construction drawing, a basic information table of the design scheme and a basic information table of the construction drawing; a related material providing module for providing related examination materials to an examiner; and the examination main point providing module is used for providing the corresponding examination main points to the examiners in each examination stage.
In one embodiment, the design plan basic information table and the construction drawing basic information table both include sponge setting control volume, the recurrence period of drainage facilities, annual runoff total amount control rate and annual SS total amount removal rate information.
In an embodiment, the description of the construction drawing further includes a summary of the design and feedback information.
In one embodiment, the inspection stage comprises a scheme design form inspection stage, a scheme design overall inspection stage, a scheme design detail inspection stage, a construction diagram form inspection stage, a construction diagram overall inspection stage and a construction diagram professional inspection stage.
In one embodiment, the review gist providing module provides corresponding review gist to a reviewer from four aspects of building and cell engineering, urban road engineering, urban green land and square engineering and urban water system engineering in a scheme design overall review stage.
In one embodiment, in the detailed review stage of the scheme design, the review key point providing module provides specific review key points for basic situation, problem and demand analysis, design target and principle, design scheme, target and index accessibility analysis, investment estimation and benefit evaluation in the sponge city design description.
In one embodiment, in the detailed review stage of the project design, the review key point providing module provides specific review key points for a project area diagram, a project general plan, a project vertical design diagram, a sponge facility catchment partition diagram, a sponge facility plane arrangement diagram, a rainwater pipe network general plan, a pipeline comprehensive plan, a rainwater utilization diagram, a landscape effect diagram or an intention diagram in a project drawing.
In one embodiment, in the professional review stage of the construction drawing, the review key point providing module provides review key points aiming at eight aspects of a geological survey report, a water supply and drainage professional, a garden landscape professional, a building professional, a road professional, a water conservancy and hydropower professional, a structure professional and an electrical professional.
In one embodiment, the examination main point providing module provides specific examination main points for a design calculation book of a water supply and drainage professional, a sponge city construction diagram and a construction diagram drawing.
In one embodiment, the review gist in the review gist providing module includes mandatory and general treaties.
The embodiment of the invention has the beneficial effects that: by setting the design plan basic information table and the construction drawing basic information table in the material to be inspected and providing the related inspection material to the inspector, the relevance of the staged inspection of the design plan and the construction drawing design can be enhanced. The corresponding examination key points are provided for examiners in each examination stage through the examination key point providing module, synchronous examination of main body design examination and sponge special item design examination and fusion examination of each professional design and sponge facility design examination can be realized, and multi-dimensional multi-professional coordination and unification of examination standards are realized.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings needed to be used in the embodiments will be briefly described below, it should be understood that the following drawings only illustrate some embodiments of the present invention and therefore should not be considered as limiting the scope, and for those skilled in the art, other related drawings can be obtained according to the drawings without inventive efforts.
The above features and advantages of the present disclosure will be better understood upon reading the detailed description of embodiments of the disclosure in conjunction with the following drawings. In the drawings, components are not necessarily drawn to scale, and components having similar relative characteristics or features may have the same or similar reference numerals.
Fig. 1 is a schematic block diagram of a system according to an embodiment of the present application.
Detailed Description
The invention is described in detail below with reference to the figures and specific embodiments. It is noted that the aspects described below in connection with the figures and the specific embodiments are only exemplary and should not be construed as imposing any limitation on the scope of the present invention.
The phenomena of 'two layers of leather' and 'pseudo sponge' appear in schemes and construction drawings caused by the lack of the examination process or the relevance problem. For example, the examination of a part of cities on sponge city design mainly occurs in a project planning scheme approval link and is executed by a local sponge office or a planning bureau, but because of lack of clearance in a construction drawing examination stage, a set of 'sponge special documents' is added outside a main project for approval of the planning scheme, and the sponge concept, the sponge facility, the plane vertical optimization and the like are not reflected in the design data of the main project; the examination of partial cities on the sponge city design mainly occurs in a construction drawing examination link and is executed by examination centers of all regions, and the problems in the situation are that firstly, the technical strength of the examination centers is limited, the concern is more in mandatory provisions, the examination on the sponge city design is weakened, secondly, as the control of a scheme stage is not available, the specialty for implementing the sponge city is generally auxiliary specialties such as water supply and drainage or landscapes, particularly land parcel projects, the general design has confirmed large directions such as plane arrangement, vertical design and the like in the scheme stage, the sponge city design in the construction drawing stage is often designed for making sponge, the vertical direction is unreasonable, catchment subareas are unreasonable, rain pipes are not disconnected, two sets of drainage systems and the like occur; certainly, some cities with better control have examination on sponge city design in the project reporting stage, namely the construction drawing examination stage, but due to two departments and two examination systems, due to the factors such as insufficient association degree and insufficient examination force, a large amount of problems of insufficient professional coordination and insufficient association of the project and the construction drawing still occur.
Aiming at the typical sponge city design problem of 'concept and construction drawing are pieced together by means of scheme', as shown in fig. 1, the embodiment of the application provides a sponge city construction engineering design examination system, which comprises:
the examination material storage module 101 is configured to store all the examination materials, where the examination materials include a design scheme, a construction drawing, a basic information table of the design scheme, and a basic information table of the construction drawing. If the engineering project is an engineering project for carrying out model simulation, the material to be examined also comprises a model construction process description file (comprising various adopted parameters, a defined catchment partition and the like) and a model source file.
And an associated material providing module 102 for providing the associated review material to the reviewer. For example, in the design review, the basic information sheet of the design and the related materials such as the design are submitted to the review specialist organized by the sponge office or the planning office together. During construction drawing examination, the construction drawing basic information table and relevant materials such as construction drawings are submitted to an examination expert of a drawing examination organization together.
The review point providing module 103 is used for providing corresponding review points to the reviewers in each review stage. The examination key points are obtained by systematically analyzing the design depth key points, the project overall design key points and the sponge facility parameter setting key points of the sponge city through researching typical error cases and typical excellent cases in the sponge city construction process. The project inspection technique, the construction drawing inspection technique, and the sponge facility inspection technique can be coupled by providing corresponding inspection points to an inspector at each inspection stage.
The basic information table of the design scheme and the basic information table of the construction drawing are submitted by a construction unit together when the pending materials are submitted. In a possible embodiment, the design basic information table may be as follows:
Figure BDA0003387279860000051
Figure BDA0003387279860000061
in a possible embodiment, the basic information table of the construction drawing is shown in the following table:
Figure BDA0003387279860000062
by adding the basic information table of the design scheme and the basic information table of the construction drawing in the material to be examined, the relevance between scheme examination and construction drawing examination can be increased, and examiners can be familiar with project overview, design indexes and content quickly. Basic information tables of the scheme and the construction drawing show basic information such as sponge facility control volume, the recurrence period of drainage facilities, annual runoff total amount control rate, annual SS total amount removal rate and the like, and are convenient for examiners in two stages to check the relevance and standard reaching performance of the scheme and the construction drawing.
In order to further realize the association between the scheme stage and the construction drawing stage, in a possible embodiment, the construction drawing description also comprises design scheme summary and feedback information, the summary and feedback of the design scheme are added in the construction drawing description, the scheme design and the construction drawing design are coordinated and unified, the defects that the scheme design cannot fall to the ground, the construction drawing neglects the scheme design and the like are avoided, and the unification, specialization and falling to the ground from the scheme to the construction drawing of the sponge city design are realized.
In addition, aiming at the phenomenon of 'two layers of leather' that the existing main project and the sponge special project are inconsistent, the sponge special project falls into a tool for scheme stage planning approval passing, specific sponge design cannot be reflected to the design drawing of the main project, and the like, and the application provides an examination technology for synchronously examining the scheme examination stage by carrying out project main subjects and the sponge special project.
Specifically, the examination stage is divided into a scheme design form examination stage, a scheme design overall examination stage, a scheme design detail examination stage, a construction drawing form examination stage, a construction drawing overall examination stage and a construction drawing professional examination stage.
In the overall inspection stage of the scheme design, the inspection point providing module provides corresponding inspection points to the inspectors from four aspects of (1) building and cell engineering, (2) urban road engineering, (3) urban green land and square engineering and (4) urban water system engineering. In the stage, the examiner checks whether the sponge city design concept is integrated into the whole planning and design process or not by combining the examination key points provided by the examination key point providing module, and whether the sponge city design concept requirements of high safety, ecological priority, local conditions and overall consideration are met or not is met; on the other hand, whether the main project reasonably arranges the sponge facilities in the sponge special article into the general plane arrangement diagram or not is examined, and whether the vertical design meets the requirement that the site rainwater smoothly flows into the sponge facilities or not is met.
Specifically, (1) the censorship points of the building and cell engineering can be shown in the following table:
Figure BDA0003387279860000081
(2) urban road engineering
Figure BDA0003387279860000082
(3) Urban green land and square engineering
Figure BDA0003387279860000083
Figure BDA0003387279860000091
(4) Urban water system engineering
Figure BDA0003387279860000092
In providing the censorship with censorship points, considering the difference between different projects, the censorship points which need to be focused on can be marked by 'zhao' for convenient operation.
In the detailed review stage of the scheme design, the review key point providing module provides specific review key points aiming at basic conditions, problem and demand analysis, design targets and principles, design schemes, accessibility analysis of targets and indexes, investment estimation and benefit evaluation in the sponge city design description.
1) Sponge city design description review points example:
Figure BDA0003387279860000093
Figure BDA0003387279860000101
Figure BDA0003387279860000111
in the detailed review stage of the scheme design, the review key point providing module provides specific review key points aiming at a project area diagram, a project general plan, a project vertical design diagram, a sponge facility catchment partition diagram, a sponge facility plane arrangement diagram, a rainwater pipe network general plan, a pipeline comprehensive plan, a rainwater utilization diagram, a landscape effect diagram or an intention diagram in a scheme drawing.
2) Scheme drawing review gist examples:
Figure BDA0003387279860000112
Figure BDA0003387279860000121
in the construction drawing professional examination stage, the examination key point providing module provides examination key points aiming at eight aspects of a geological survey report, a water supply and drainage professional, a landscape professional, a building professional, a road professional, a water conservancy and hydropower professional, a structure professional and an electrical professional, aims to integrate the design of the sponge city construction drawing into the project main body design and the examination into the project main body examination, weakens the existence of the special examination, and normalizes the sponge. The possible examination points of each specialty are as follows:
geological survey report
Figure BDA0003387279860000122
② speciality in water supply and drainage
1) Designing a computer book
Figure BDA0003387279860000123
Figure BDA0003387279860000131
2) Sponge city construction diagram
Figure BDA0003387279860000132
3) Construction drawing
Figure BDA0003387279860000133
Figure BDA0003387279860000141
Figure BDA0003387279860000151
Figure BDA0003387279860000161
③ Garden landscape major
Figure BDA0003387279860000162
Figure BDA0003387279860000171
Construction specialty
Figure BDA0003387279860000172
Figure BDA0003387279860000181
Fifth road speciality
Figure BDA0003387279860000182
Water conservancy project
Figure BDA0003387279860000183
Figure BDA0003387279860000191
Seventh, structure speciality
Serial number Reviewing content Review the points
1 Calculation book And whether the load value and calculation related to the sponge facility are correct or not.
2 Big sample picture Sponge facility need when structurally the trompil, whether mark and satisfy relevant requirement.
[ electric speciality ]
Figure BDA0003387279860000192
Preferably, for the convenience of using by examiners, the examination points in the examination point providing module are divided into mandatory and general terms, and are divided into six chapters of "construction standard", "building and cell sponge city design examination points", "urban road sponge city design examination points", "urban green land and square sponge city design examination points", "urban water system sponge city design examination points", "sponge facility examination points", so as to facilitate reference.
In summary, the present application provides a sponge city construction engineering design review system, which can help to realize staged review of scheme design review and construction drawing design review, synchronous review of main body design review and sponge special design review, and fusion review of each professional design review and sponge facility design review by providing related review materials and providing review points by stages. By setting the design plan basic information table and the construction drawing basic information table in the material to be inspected and providing the related inspection material to the inspector, the relevance of the staged inspection of the design plan and the construction drawing design can be enhanced. The corresponding examination key points are provided for examiners in each examination stage through the examination key point providing module, synchronous examination of main body design examination and sponge special item design examination and fusion examination of each professional design and sponge facility design examination can be realized, and multi-dimensional multi-professional coordination and unification of examination standards are realized. Therefore, by matching the system, project sponge city scheme and construction drawing design examination can be enhanced, the closed-loop supervision of the scheme design examination, the construction drawing design examination and the acceptance link is realized from source management and control, and the ground rooting of the sponge city concept is effectively promoted.
The embodiments in the present description are described in a progressive manner, each embodiment focuses on differences from other embodiments, and the same and similar parts among the embodiments are referred to each other.
The previous description of the disclosure is provided to enable any person skilled in the art to make or use the disclosure. Various modifications to the disclosure will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other variations without departing from the spirit or scope of the disclosure. Thus, the disclosure is not intended to be limited to the examples and designs described herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.
The above description is only a preferred example of the present application and should not be taken as limiting the present application, and any modifications, equivalents, improvements and the like made within the spirit and principle of the present application should be included in the scope of the present application.

Claims (10)

1. A sponge city construction engineering design inspection system is characterized by comprising:
the examination material storage module is used for storing all the materials to be examined, and the materials to be examined comprise a design scheme, a construction drawing, a basic information table of the design scheme and a basic information table of the construction drawing;
a related material providing module for providing related examination materials to an examiner; and
and the examination main point providing module is used for providing the corresponding examination main points to the examiners in each examination stage.
2. The sponge city construction engineering design review system of claim 1, wherein the design plan basic information sheet and the construction drawing basic information sheet each include sponge setup control volume, recurring period of drainage facility, annual runoff total amount control rate and annual SS total amount removal rate information.
3. The sponge city construction project design review system of claim 2, wherein the description of the construction drawing further includes a summary of design schemes and feedback information.
4. The sponge city construction engineering design review system of claim 1, wherein the review stage comprises a scheme design form review stage, a scheme design overall review stage, a scheme design detail review stage, a construction drawing form review stage, a construction drawing overall review stage and a construction drawing professional review stage.
5. The sponge city construction project design review system of claim 4, wherein in a scheme design overall review stage, the review point providing module provides corresponding review points to reviewers from four aspects of building and community engineering, urban road engineering, urban green land and square engineering and urban water system engineering.
6. The sponge city construction engineering design review system of claim 4, wherein in the detailed review stage of the scheme design, the review points providing module provides specific review points for basic situation, problem and demand analysis, design target and principle, design scheme, target and index accessibility analysis, investment estimation and benefit evaluation in the sponge city design description.
7. The sponge city construction engineering design review system of claim 4, wherein in the detailed review stage of the project design, the review key point providing module provides specific review key points for project area diagrams, project general plan diagrams, project vertical design diagrams, sponge facility catchment partition diagrams, sponge facility plane arrangement diagrams, rainwater pipe network general plan diagrams, pipeline comprehensive plan diagrams, rainwater utilization diagrams, landscape effect diagrams or intention diagrams in the project drawings.
8. The sponge city construction engineering design inspection system of claim 4, wherein in the construction drawing professional inspection stage, the inspection main point providing module provides inspection main points for eight aspects of land survey reports, water supply and drainage specialties, garden landscape specialties, building specialties, road specialties, water conservancy and hydropower specialties, structure specialties and electrical specialties.
9. The sponge city construction engineering design review system of claim 8, wherein the review key points providing module provides specific review key points for design calculation books, sponge city construction drawing diagrams and construction drawing drawings of water supply and drainage professions.
10. The sponge city construction engineering design review system of claim 1, wherein the review points provided by the review point providing module comprise mandatory and general treaties.
CN202111458483.6A 2021-12-01 2021-12-01 Sponge city construction engineering design examination system Pending CN114118842A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111458483.6A CN114118842A (en) 2021-12-01 2021-12-01 Sponge city construction engineering design examination system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111458483.6A CN114118842A (en) 2021-12-01 2021-12-01 Sponge city construction engineering design examination system

Publications (1)

Publication Number Publication Date
CN114118842A true CN114118842A (en) 2022-03-01

Family

ID=80365310

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111458483.6A Pending CN114118842A (en) 2021-12-01 2021-12-01 Sponge city construction engineering design examination system

Country Status (1)

Country Link
CN (1) CN114118842A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114429638A (en) * 2022-04-06 2022-05-03 四川省大数据中心 Construction drawing examination management system
CN116822923A (en) * 2023-06-08 2023-09-29 深圳市城市规划设计研究院股份有限公司 Intelligent full-flow management system for sponge city construction project

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109657948A (en) * 2018-12-04 2019-04-19 昆山市建设工程质量检测中心 Plot sponge urban construction performance comprehensive estimation method
CN110378611A (en) * 2019-07-25 2019-10-25 泰华智慧产业集团股份有限公司 Sponge control index based on GIS examines and appraisal procedure and system
CN110378620A (en) * 2019-07-29 2019-10-25 四川省建筑设计研究院 The low influence exploitation design of one kind and appraisal procedure and system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109657948A (en) * 2018-12-04 2019-04-19 昆山市建设工程质量检测中心 Plot sponge urban construction performance comprehensive estimation method
CN110378611A (en) * 2019-07-25 2019-10-25 泰华智慧产业集团股份有限公司 Sponge control index based on GIS examines and appraisal procedure and system
CN110378620A (en) * 2019-07-29 2019-10-25 四川省建筑设计研究院 The low influence exploitation design of one kind and appraisal procedure and system

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
徐州市住房和城乡建设局: "江苏省建设工程海绵城市设计审查要点(试行)", Retrieved from the Internet <URL:http://zj.xz.gov.cn/zt/006010/20210430/0d08f70f-9eb6-4498-93e3-392235217ed8.html> *
蔡斯琴;: "数字技术智能辅助海绵城市建设设计审批工作的应用探究――以南宁市为例", 企业科技与发展, no. 01, pages 65 - 66 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114429638A (en) * 2022-04-06 2022-05-03 四川省大数据中心 Construction drawing examination management system
CN114429638B (en) * 2022-04-06 2022-07-08 四川省大数据中心 Construction drawing examination management system
CN116822923A (en) * 2023-06-08 2023-09-29 深圳市城市规划设计研究院股份有限公司 Intelligent full-flow management system for sponge city construction project

Similar Documents

Publication Publication Date Title
Du et al. Impact of prefabrication technology on the cradle-to-site CO 2 emissions of residential buildings
Gerrish et al. Using BIM capabilities to improve existing building energy modelling practices
CN114118842A (en) Sponge city construction engineering design examination system
Xue et al. BIM integrated LCA for promoting circular economy towards sustainable construction: an analytical review
Menzies et al. Life-cycle assessment and embodied energy: a review
Teng et al. A systematic review of the integration of building information modeling into life cycle assessment
Chow et al. Using a systematic, multi-criteria decision support framework to evaluate sustainable drainage designs
Zhang Estimation of eco‐efficiency and identification of its influencing factors in China's Yangtze River Delta urban agglomerations
US20130338833A1 (en) System and Method for Calculating and Reporting Maximum Allowable Operating Pressure
Yang et al. Estimating the regional eco-efficiency in China based on bootstrapping by-production technologies
CN113705984A (en) Green construction evaluation method and system for foundation pit engineering
CN111046476A (en) Method and system for coding information model and exchanging data of building foundation pit component
Zhang Effects of electricity consumption on carbon intensity across Chinese manufacturing sectors
CN111311173B (en) National county level unit economic arrangement and spatialization method
Sun et al. Safety evaluation of urban underground utility tunnel with the grey clustering method based on the whole life cycle theory
CN112926106A (en) Power transmission and transformation project collaborative design method and system based on six-level system
Esram et al. Knowledge Infrastructure: The Critical Path to Advance Embodied Carbon Building Codes
CN102842088A (en) Intelligent business address selection system
KR20190087784A (en) Development of BIM based LID Facilities Supply Auto-checking system and Auto-checking method using the same
Kamali et al. Sustainability performance assessment: A life cycle based framework for modular buildings
CN116011157A (en) Automatic desk CAD and Revit secondary development-based pipeline rapid extraction modeling method
Davitti et al. Project cost modelling for Hydropower schemes in developing countries
CN113408854A (en) BIM technology-based building full-life-cycle environmental impact evaluation management method
Tam et al. State-of-the-Art of BIM-Based LCA in the Building Sector
Lee et al. Integrated assessment system of sustainable communities using BIM technology

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination