Prior art keywords
adjusting frame
limiting ring
frame
base
tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202111127994.XA
Other languages
Chinese (zh)
Other versions
CN113997226A (en
Inventor
李晓洪
王晓南
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengxi Shipyard Co Ltd
Original Assignee
Chengxi Shipyard Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengxi Shipyard Co Ltd filed Critical Chengxi Shipyard Co Ltd
Priority to CN202111127994.XA priority Critical patent/CN113997226B/en
Publication of CN113997226A publication Critical patent/CN113997226A/en
Application granted granted Critical
Publication of CN113997226B publication Critical patent/CN113997226B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B25HAND TOOLS; PORTABLE POWER-DRIVEN TOOLS; MANIPULATORS
    • B25BTOOLS OR BENCH DEVICES NOT OTHERWISE PROVIDED FOR, FOR FASTENING, CONNECTING, DISENGAGING OR HOLDING
    • B25B11/00Work holders not covered by any preceding group in the subclass, e.g. magnetic work holders, vacuum work holders
    • B25B11/02Assembly jigs
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B25HAND TOOLS; PORTABLE POWER-DRIVEN TOOLS; MANIPULATORS
    • B25BTOOLS OR BENCH DEVICES NOT OTHERWISE PROVIDED FOR, FOR FASTENING, CONNECTING, DISENGAGING OR HOLDING
    • B25B11/00Work holders not covered by any preceding group in the subclass, e.g. magnetic work holders, vacuum work holders
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Wind Motors (AREA)

Abstract

The invention discloses a vertical installation and delivery integrated tool which comprises a base and a fixed tower, wherein a limiting ring is arranged at the top of the base, the fixed tower is arranged at the top of the limiting ring, an annular block is fixedly arranged at the top of the fixed tower, a first adjusting frame is arranged at the front end of a second adjusting frame, and a second adjusting frame is arranged at one side of a connecting frame; according to the invention, the first adjusting frame moves to the positioning grooves at the two ends of the second adjusting frame for adjustment, so that the first adjusting frame slides to the side, away from the two ends, of the connecting frame, and the second adjusting frame slides to the side, away from the movable groove, of the connecting frame, so that the tooling can expand to the periphery of the base, the limiting ring can expand to the outer ring, the limiting ring can be suitable for fixing fixed tower barrels with different diameter values, and the problem that wind tower barrels with different calibers are difficult to distribute due to the fact that the wind towers cannot be movably adjusted in the shipment base of shipment assembly is solved.

Description

Vertical installation and delivery integrated tool
Technical Field
The invention relates to the technical field of integrated tools, in particular to a vertically-installed and shipping integrated tool.
Background
According to statistics, the tower barrels at the bottom of the existing offshore wind tower need to be vertically installed and vertically loaded and shipped on land so as to meet the hoisting process of the tower barrel machine position, the installation and fixation are carried out on land, the loading is carried out through hoisting to assemble a specific sea surface area, and tools are needed to be used for installation and shipment in the loading process.
In the prior art, the wind tower is assembled and transported by using a tool in the installation and transportation process, the angle is required to be continuously adjusted through manual experience in the process, and the wind tower barrel is difficult to transport due to the fact that wind towers with different calibers cannot be movably adjusted on a shipping assembly and transportation base, so that the invention relates to the vertical installation and transportation integrated tool.
Disclosure of Invention
The invention aims to provide a vertical installation and delivery integrated tool, which aims to solve the problems that in the wind tower installation and delivery process, the tool is required to be used for assembly and delivery, in the process, the angle is required to be continuously adjusted through manual experience, the assembly and delivery are carried out, and in addition, wind towers with different calibers are difficult to be delivered due to the fact that wind towers cannot be movably adjusted on a shipping assembly and delivery base.
In order to achieve the above purpose, the present invention provides the following technical solutions: the utility model provides a perpendicular installation and shipment integral type frock, includes base, fixed tower section of thick bamboo, the base top is provided with the spacing ring, the spacing ring top is provided with fixed tower section of thick bamboo, fixed tower section of thick bamboo top fixed mounting has the annular piece, base upper surface middle part department is provided with the link, spacing ring upper surface demountable installation has the dead lever, second alignment jig openly holds and is provided with first alignment jig, link one side is provided with the second alignment jig.
Preferably, the top of the limiting ring is provided with a fixing hole in a penetrating mode, and the edge of the upper surface of the limiting ring is provided with a limiting groove in a penetrating mode.
Preferably, the movable grooves are formed in the two ends of the front face and the back face of the connecting frame, and the periphery of the connecting frame is provided with a sliding groove in a penetrating mode on one side, close to the second adjusting frame.
Preferably, the top end of the fixing rod is fixedly connected with a conical block, a through hole is formed in the circumferential edge of the bottom surface of the fixing tower in a penetrating manner, and the fixing rod is inserted into the through hole and extends to the top of the fixing tower.
Preferably, the positioning groove is formed in the front face of the second adjusting frame in a penetrating mode, and two ends of the first adjusting frame are connected to the inside of the positioning groove in a sliding mode.
Preferably, the first adjusting frame and the second adjusting frame are both in a concave structure, and two ends of each adjacent first adjusting frame and second adjusting frame are both in a crisscross shape.
Preferably, the connecting frame is of an H-shaped structure, two ends of the first adjusting frame are respectively connected with two ends of the movable groove in a sliding mode to extend to the back of the positioning groove, and two ends of the first adjusting frame are in clearance fit with the movable groove.
Preferably, two ends of the second adjusting frame are respectively inserted into the inside of the sliding groove, and two ends of the second adjusting frame are in clearance fit with the sliding groove.
Preferably, the limiting ring is in a circular ring structure, the limiting groove equally divides the limiting ring into eight sections of arcs with the same size, and each section of arc is respectively and equally connected to the inner angle of the upper surfaces of the first adjusting frame and the second adjusting frame.
Preferably, the shape of the fixed tower cylinder is a circular ring structure, and the base is a regular hexagon structure.
Compared with the prior art, the invention has the beneficial effects that:
according to the invention, the first adjusting frame moves and adjusts to the positioning grooves at the two ends of the second adjusting frame through the first adjusting frame, so that the first adjusting frame slides and adjusts at the positions, deviating from the two ends, of the connecting frame, and the second adjusting frame slides to the positions, deviating from the movable groove, of the connecting frame, so that the tool can expand to the periphery of the base, the limiting ring can expand outwards, the limiting ring can be suitable for fixing fixed tower barrels with different diameter values, the problem that wind towers with different calibers are difficult to transport due to the fact that the wind towers cannot be movably adjusted in the shipment base during shipment assembly is solved, meanwhile, the conical blocks at the top ends of the fixing rods are inserted into the through holes in the bottom surfaces of the fixed tower barrels, the tool can be positioned through the fixing rods when the fixed tower barrels are installed, the tool is convenient to assemble a plurality of fixed tower barrels, and the problem that time and labor are wasted when assembling and shipping are required to be continuously adjusted through manual experience in the installation and shipment process is solved.
Drawings
FIG. 1 is a schematic diagram of the overall structure of the present invention;
FIG. 2 is a schematic view of the bottom structure of the present invention;
FIG. 3 is a schematic view of a fixing rod according to the present invention;
FIG. 4 is a schematic view of the base structure of the present invention;
fig. 5 is a schematic view of a partial enlarged structure at a in fig. 4.
In the figure: 1. a base; 2. a limiting ring; 21. a fixing hole; 22. a limit groove; 3. fixing the tower barrel; 4. an annular block; 5. a connecting frame; 51. a movable groove; 52. a chute; 6. a fixed rod; 61. a conical block; 7. a first adjusting frame; 8. a second adjusting frame; 81. and a positioning groove.
Detailed Description
The following description of the embodiments of the present invention will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present invention, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
Referring to fig. 1-5, the present invention provides a technical solution: the vertical installation and delivery integrated tool comprises a base 1 and a fixed tower drum 3, wherein a limiting ring 2 is arranged at the top of the base 1, the edge of the limiting ring 2 is fixedly connected to the inner corners of the upper surfaces of a first adjusting frame 7 and a second adjusting frame 8 through bolts, the top of the limiting ring 2 is provided with the fixed tower drum 3, a fixed rod 6 is inserted into a through hole in the bottom surface of the fixed tower drum 3, an annular block 4 is fixedly arranged at the top of the fixed tower drum 3 through bolts, a connecting frame 5 is arranged at the middle part of the upper surface of the base 1, a first adjusting frame 7 is slidably connected in a movable groove 51 at two ends of the connecting frame 5, and a second adjusting frame 8 is slidably connected in a sliding groove 52 at two sides of the connecting frame 5, which is close to two ends;
the upper surface of the limiting ring 2 is detachably provided with a fixing rod 6 through threads, the front end of a second adjusting frame 8 is provided with a first adjusting frame 7, the front end of the second adjusting frame 8 is slidably connected with the first adjusting frame 7 through a positioning groove 81, one side of the connecting frame 5 is provided with a second adjusting frame 8, and one side of the connecting frame 5 is slidably connected with the second adjusting frame 8 through a sliding groove 52.
Wherein fixed orifices 21 have been run through to spacing ring 2 top, spacing groove 22 has been run through to spacing ring 2 upper surface edge, movable groove 51 has all been seted up at link 5 front and back both ends, link 5 periphery is close to second alignment jig 8 one side and has been run through and have been seted up spout 52, second alignment jig 8 front has been run through and has been seted up constant head tank 81, first alignment jig 7 both ends all sliding connection is inside constant head tank 81, first alignment jig 7 and second alignment jig 8 are concave structure, and adjacent first alignment jig 7 and second alignment jig 8 both ends all are the cross shape, link 5 is H-shaped structure, first alignment jig 7 both ends sliding connection respectively in movable groove 51 both ends extend to the back department of constant head tank 81, and first alignment jig 7 both ends are clearance fit with movable groove 51, second alignment jig 8 both ends are pegged graft respectively in spout 52 inside, and second alignment jig 8 both ends are clearance fit with spout 52, spacing ring 2 shape is circular-ring structure, spacing groove 22 is equidistant eight sections size the same with spacing ring 2, and every equal spacing section is connected in first alignment jig 7 and the first alignment jig 8 inner angle surface.
Wherein, through the constant head tank 81 position removal regulation at first alignment jig 7 to second alignment jig 8 both ends for first alignment jig 7 deviates from both ends slip regulation at link 5, slide to deviating from movable groove 51 one side department through second alignment jig 8, thereby make this frock can be to the peripheral expansion of base 1, thereby realized that spacing ring 2 can outwards circle expansion, spacing ring 2 can be suitable for fixed tower section of thick bamboo 3 of fixed different diameter values, solved the problem of difficult problem when shipment of wind tower section of thick bamboo is led to in the unable movable regulation of shipment base of shipment equipment to the wind tower of different bore.
Wherein, fixed pole 6 top end fixedly connected with toper piece 61, fixed tower section of thick bamboo 3 bottom surface circumference edge runs through and has seted up the through-hole, and fixed pole 6 is pegged graft in the through-hole and is extended to fixed tower section of thick bamboo 3 top department, and fixed tower section of thick bamboo 3 shape is the ring shape structure, and base 1 is regular hexagon structure.
Wherein, peg graft in fixed tower section of thick bamboo 3 bottom surface through-hole inside through the toper piece 61 on dead lever 6 top, realized this frock when installing fixed tower section of thick bamboo 3, can fix a position through dead lever 6, be convenient for assemble a plurality of fixed tower section of thick bamboo 3, solved the wind tower installation and the delivery in-process need constantly through the manual experience angle adjustment, assemble the problem of wasting time and energy of delivering.
Working principle: when the wind tower fixing device is used, the diameter value of the fixed tower cylinder 3 to be installed is determined, the first adjusting frame 7 is moved and adjusted to the positions of the positioning grooves 81 at two ends of the second adjusting frame 8, the first adjusting frame 7 is slidably adjusted at two ends of the connecting frame 5, the second adjusting frame 8 slides towards one side deviating from the movable groove 51, the tool is expanded towards the periphery of the base 1, the limiting ring 2 can be expanded outwards, the fixed tower cylinder 3 to be installed is fixed to the limiting ring 2, finally, the through holes on the bottom surface of the fixed tower cylinder 3 are fixedly positioned with the fixed rods 6, the fixed tower cylinders 3 are sleeved on the periphery of the fixed rods 6, the problem that labor is wasted when assembling and shipping is required to be continuously adjusted through manual experience in the wind tower installation and shipping process is solved.
It is noted that relational terms such as first and second, and the like are used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Moreover, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. Perpendicular installation and shipment integral type frock, including base (1), fixed tower section of thick bamboo (3), its characterized in that: the utility model discloses a fixing device for a high-speed water heater, which comprises a base (1), wherein a limiting ring (2) is arranged at the top of the base (1), a fixed tower barrel (3) is arranged at the top of the limiting ring (2), an annular block (4) is fixedly arranged at the top of the fixed tower barrel (3), a connecting frame (5) is arranged at the middle part of the upper surface of the base (1), a fixing rod (6) is detachably arranged on the upper surface of the limiting ring (2), a second adjusting frame (8) is arranged on one side of the connecting frame (5), a first adjusting frame (7) is arranged at the front end of the second adjusting frame (8), movable grooves (51) are respectively formed in the front end and the back end of the connecting frame (5), sliding grooves (52) are respectively formed in the periphery of the connecting frame (5) near one side of the second adjusting frame (8), positioning grooves (81) are formed in the front end of the second adjusting frame (8), two ends of the first adjusting frame (7) are respectively connected in a sliding mode in the inner part of the positioning grooves (81), the connecting frame (5) is of an H-shaped structure, two ends of the first adjusting frame (7) are respectively connected in a sliding mode, two ends of the first adjusting frame (7) are respectively connected to the movable grooves (51) respectively, two ends of the first adjusting frame (51) are respectively matched with two ends of the first adjusting frame (51) are respectively, and two ends of the second adjusting frame (8) are in clearance fit with the sliding groove (52).
2. The vertical installation and shipping integrated fixture of claim 1, wherein: the top of the limiting ring (2) is provided with a fixing hole (21) in a penetrating mode, and the edge of the upper surface of the limiting ring (2) is provided with a limiting groove (22) in a penetrating mode.
3. The vertical installation and shipping integrated fixture of claim 1, wherein: the top end of the fixing rod (6) is fixedly connected with a conical block (61), a through hole is formed in the circumferential edge of the bottom surface of the fixing tower (3) in a penetrating mode, and the fixing rod (6) is inserted into the through hole and extends to the top of the fixing tower (3).
4. The vertical installation and shipping integrated fixture of claim 1, wherein: the first adjusting frame (7) and the second adjusting frame (8) are of concave structures, and two ends of the adjacent first adjusting frame (7) and two ends of the adjacent second adjusting frame (8) are in crossed shapes.
5. The vertical installation and shipping integrated fixture of claim 2, wherein: the limiting ring (2) is of a circular ring structure, the limiting groove (22) equally divides the limiting ring (2) into eight sections of arcs with the same size, and each section of arc is respectively connected with the inner angles of the upper surfaces of the first adjusting frame (7) and the second adjusting frame (8) at equal intervals.
6. The integrated vertical mounting and shipping fixture of claim 5, wherein: the fixed tower cylinder (3) is in a circular ring structure, and the base (1) is in a regular hexagon structure.
CN202111127994.XA 2021-09-26 2021-09-26 Vertical installation and delivery integrated tool Active CN113997226B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111127994.XA CN113997226B (en) 2021-09-26 2021-09-26 Vertical installation and delivery integrated tool

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111127994.XA CN113997226B (en) 2021-09-26 2021-09-26 Vertical installation and delivery integrated tool

Publications (2)

Publication Number Publication Date
CN113997226A CN113997226A (en) 2022-02-01
CN113997226B true CN113997226B (en) 2023-04-25

Family

ID=79921646

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111127994.XA Active CN113997226B (en) 2021-09-26 2021-09-26 Vertical installation and delivery integrated tool

Country Status (1)

Country Link
CN (1) CN113997226B (en)

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN208169062U (en) * 2018-04-28 2018-11-30 于勇尧 A kind of transport base of hub of wind power generator
CN108655659A (en) * 2018-06-29 2018-10-16 河南东起机械有限公司 A kind of wind-power tower rolling wheel support
CN209493963U (en) * 2019-01-18 2019-10-15 中国十七冶集团有限公司 A kind of prefabricated wind power generation machine tower base platform
CN209494662U (en) * 2019-03-06 2019-10-15 苏州华达环保设备股份有限公司 A kind of bindiny mechanism of wind-power tower protection support construction
DK3800348T3 (en) * 2019-10-01 2023-11-20 Siemens Gamesa Renewable Energy As MODULAR TOOLS

Also Published As

Publication number Publication date
CN113997226A (en) 2022-02-01

Similar Documents

Publication Publication Date Title
CN204449766U (en) Welding tool setup
CN203726056U (en) Auxiliary support device for sidewise-mounting welding of large structures
CN113997226B (en) Vertical installation and delivery integrated tool
CN207840554U (en) A kind of flange welding positioning tooling
CN104826960B (en) A kind of seal head necking machine
CN109332525A (en) The production technology of nuclear power safety injection tank end socket
CN205838295U (en) A kind of pivoting support production and transport equipment
CN204700103U (en) For bending the bending machine of oil pipe
CN105773130A (en) Embedding tool for bolt of blade root
CN105903908A (en) Method and device for fixing salt core for piston casting
CN206732396U (en) A kind of stainless steel hanger automated production welding equipment
CN210908705U (en) Vertical oil separator extension piece welding frock
CN210731479U (en) Aerogenerator stator support welding frock
CN210524198U (en) Special group of large-scale petrochemical industry reactor net section of thick bamboo internals laser beam machining school circle frock
CN204603126U (en) A kind of seal head necking machine
CN109175017B (en) Steel pipe repairing device
CN206444792U (en) A kind of two-sided spray-painting plant
CN202639993U (en) Support feeding roller of solid tube blank stripping machine
CN107398671B (en) Segment tower cylinder welding system and segment tower cylinder welding method
CN105638291A (en) Detachable flower planting shelf
CN221019407U (en) Positioning tool for welding of spring disc of liquid storage cylinder of shock absorber
CN206301092U (en) A kind of center calibrating installation and laser coupling table apparatus
CN216325651U (en) Pipe thread processing support
CN219383354U (en) Horizontal container class equipment transportation fixing device
CN210211902U (en) Tire mounting die

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant