CN113863142A - Method for installing large-span river-crossing corridor cantilever - Google Patents

Method for installing large-span river-crossing corridor cantilever Download PDF

Info

Publication number
CN113863142A
CN113863142A CN202111060842.2A CN202111060842A CN113863142A CN 113863142 A CN113863142 A CN 113863142A CN 202111060842 A CN202111060842 A CN 202111060842A CN 113863142 A CN113863142 A CN 113863142A
Authority
CN
China
Prior art keywords
river
section
crossing
cantilever
span
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111060842.2A
Other languages
Chinese (zh)
Inventor
何日天
彭浩
李冲
田龙杰
张体辉
李善文
程淑萍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN202111060842.2A priority Critical patent/CN113863142A/en
Publication of CN113863142A publication Critical patent/CN113863142A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/10Railings; Protectors against smoke or gases, e.g. of locomotives; Maintenance travellers; Fastening of pipes or cables to bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/0046Loggias
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Revetment (AREA)

Abstract

The invention discloses a method for installing a large-span river-crossing corridor cantilever, which is characterized in that a truss girder is erected on a side-crossing structure of a river-crossing corridor and the side-crossing structure is used as a support, so that the fundamental contradiction of site limitation is solved, a support does not need to be arranged in the middle of a river channel, piles are not needed in the river channel, the use amount of large-scale machines such as a drilling machine is greatly reduced, and the construction cost is reduced. The invention solves the problems that the traditional steel structure river-crossing corridor needs to be piled in a river channel for construction, and the construction difficulty is high.

Description

Method for installing large-span river-crossing corridor cantilever
Technical Field
The invention relates to the technical field of building construction, in particular to a method for installing a large-span river-crossing corridor cantilever.
Background
The common steel structure installation mainly comprises a plurality of modes such as support method hoisting, longitudinal pushing, transverse sliding, lifting and the like, and the requirements on the most site conditions are higher if none of the above construction modes are adopted. When the field is limited, the mechanical type selection is increased or the using amount of technical measures is increased, and the construction cost is difficult to control. Especially to the construction of steel construction river-crossing vestibule, the place condition near the river course is relatively poor, sets up the support in the river course moreover and needs the pile, and the construction degree of difficulty is very big, and the cost is higher.
Disclosure of Invention
In order to overcome the defects in the prior art, the method for installing the large-span river-crossing corridor cantilever is provided so as to solve the problems that the traditional steel structure river-crossing corridor construction needs piling in a river channel and the construction difficulty is large.
In order to achieve the above object, there is provided a method for installing a large-span river-crossing corridor cantilever, the river-crossing corridor including a mid-span structure and side-span structures connected to both ends of the mid-span structure, the mid-span structure including a plurality of unit sections spliced together, the method comprising the steps of:
the side span structures are respectively installed on the river banks on the two sides of the river channel, so that the two side span structures are oppositely arranged;
installing a plurality of first supporting columns on the upper part of one side span structure, and installing a second supporting column on the upper part of the other side span structure, so that the plurality of first supporting columns are arranged along the length direction of the river-crossing corridor;
providing a truss girder which comprises an overhanging section and an anchoring section connected to the overhanging section, and movably mounting the anchoring section on the upper parts of the first support columns so that the overhanging section is overhanging to the outer side of one end of the side span structure facing the other side span structure and aligned to a second support column;
pushing the anchoring section towards the direction of the second supporting column, so that the cantilever section extends to the upper part of the second supporting column and is placed at the upper part of the second supporting column;
fixedly mounting the anchoring section to the first support column and fixedly mounting the cantilever section to the second support column;
and installing a crown block on the truss girder, hoisting the plurality of unit sections to the position between the two side span structures through the crown block, and installing the unit sections on the two side span structures to form the river-crossing corridor.
Furthermore, the side span structure is installed on the river bank by a support method.
Further, when a plurality of unit sections are installed on the two side span structures, the unit sections are spliced in opposite directions from the river banks on the two sides to the middle of the river channel to form the mid-span structure.
Furthermore, in the process of installing a plurality of unit sections on two side span structures, after the unit section in the previous section is installed, a total station is adopted to determine the spatial position of the overhanging end of the unit section in the previous section so as to obtain the deformation amount and the deformation direction of the unit section in the previous section, and when the unit section in the next section is positioned and measured, the anti-three-dimensional spatial deformation opposite to the deformation amount and the deformation direction of the unit section in the previous section is carried out on the positioning axis of the unit section in the next section, so that the position deviation of the unit sections is in a reasonable range.
The method for installing the cantilever of the large-span river-crossing corridor has the advantages that the truss girder is erected on the side-crossing structure of the river-crossing corridor, the side-crossing structure is used as a support, the fundamental contradiction that the site is limited is solved, a support does not need to be arranged in the middle of a river channel, pile driving in the river channel is not needed, the use amount of large machines such as drilling rigs is greatly reduced, the construction cost is reduced, the crown block units on the truss girder are transported to the set position, the situations of hoisting radius limitation, lever rod carrying and the like do not exist under the condition that the structural strength of the truss girder is met, the construction area is fully covered, the links of moving vehicles and supporting legs of the traditional crane are avoided, the installation efficiency is high, and the requirement of the large machines is reduced.
Drawings
Other features, objects and advantages of the present application will become more apparent upon reading of the following detailed description of non-limiting embodiments thereof, made with reference to the accompanying drawings in which:
fig. 1 to 7 are schematic diagrams illustrating steps of a method for installing a large-span river-crossing corridor cantilever according to an embodiment of the present invention.
Detailed Description
The present application will be described in further detail with reference to the following drawings and examples. It is to be understood that the specific embodiments described herein are merely illustrative of the relevant invention and not restrictive of the invention. It should be noted that, for convenience of description, only the portions related to the present invention are shown in the drawings.
It should be noted that the embodiments and features of the embodiments in the present application may be combined with each other without conflict. The present application will be described in detail below with reference to the embodiments with reference to the attached drawings.
Referring to fig. 7, the river-crossing corridor includes a midspan structure B including a plurality of unit sections B spliced together, and an edge-crossing structure a connected to both ends of the midspan structure B.
With continued reference to fig. 1 to 7, the present invention provides a method for installing a large-span river-crossing corridor cantilever, comprising the following steps:
s1: as shown in fig. 1, the side span structures a are respectively installed on the banks at both sides of the river channel, so that the side span structures a are oppositely arranged.
In this embodiment, the side span structure a is installed on the river bank by a scaffolding method.
S2: as shown in fig. 2 and 3, a plurality of first support columns 1 are installed on an upper portion of one side span structure a, and a second support column 2 is installed on an upper portion of the other side span structure a, such that the plurality of first support columns 1 are arranged along a length direction of the river crossing corridor.
S3: with continued reference to fig. 2 and 3, a truss beam 3 is provided, the truss beam 3 including a cantilever section and an anchor section. The cantilever section is connected to the anchoring section, and the cantilever section and the anchoring section are coaxially arranged, and the anchoring section is movably installed on the upper parts of the first support columns 1, so that the cantilever section can be cantilever to the outer side of one end of the side span structure A facing to the other side span structure A and can be aligned to the second support column 2.
S4: with continued reference to fig. 3, the anchoring section is pushed toward the second support column 2, so that the overhanging section extends above the second support column 2 and rests on the upper part of the second support column 2.
In this embodiment, two first support columns are installed on the side span structure on the left side of the river bank, and a first support column near the center of the river channel is hereinafter referred to as "center support". When the anchoring section is pushed, downward tensile force is applied to the anchoring section, the first anti-overturning bending moment of the anchoring section behind the middle support is constantly kept larger than the second anti-overturning bending moment of the cantilever section in front of the middle support, and a safety coefficient of more than 1.3 is kept (the first anti-overturning bending moment/the second anti-overturning bending moment is more than 1.3).
S5: as shown in fig. 4, the anchor section is fixedly attached to the first support column 1, and the cantilever section is fixedly attached to the second support column 2.
S6: as shown in fig. 5 to 6, a crown block 4 is installed on the truss girder 3, and a plurality of unit sections b are hoisted between the two side span structures a by the crown block 4 and installed on the two side span structures a to form a river-crossing corridor.
When the plurality of unit sections B are installed on the two-side span structure A, the plurality of unit sections B are oppositely spliced from the river banks on the two sides to the middle of the river channel to form the span structure B. The two side span structures on the river bank are oppositely constructed towards the center of the river channel, and the construction is closed to the middle position of the center of the river channel.
When the unit sections are installed, the crawler crane is matched with the overhead travelling crane to feed beams to the overhead travelling crane, the overhead travelling crane hoists the unit sections to a set position in a sectional mode, and after welding is completed, the overhead travelling crane loosens the hooks.
In the process of installing a plurality of unit sections b in a two-side span structure A, after the previous unit section b is installed, the spatial position of the overhanging end of the previous unit section b is determined by a total station to obtain the deformation amount and the deformation direction of the previous unit section b, and when the next unit section b is positioned and measured, the reverse three-dimensional spatial deformation opposite to the deformation amount and the deformation direction of the previous unit section b is carried out on the positioning axis of the next unit section b, so that the position deviation of the installed multiple unit sections b is in a reasonable range.
According to the installation method of the large-span river-crossing corridor cantilever, the truss girder is erected on the side-crossing structure of the river-crossing corridor, the side-crossing structure is used as a support, the fundamental contradiction that the site is limited is solved, a support is not required to be arranged in the middle of a river channel, pile driving in the river channel is not required, the use amount of large machines such as drilling machines is greatly reduced, the construction cost is reduced, the crown block units on the truss girder are transported to the set position in a saving mode, under the condition that the structural strength of the truss girder is met, the situations of hoisting radius limitation, lever shoring and the like do not exist, the construction area is fully covered, the links of moving vehicles and supporting legs of a traditional crane are avoided, the installation efficiency is high, and the requirement of the large machines is reduced.
The above description is only a preferred embodiment of the application and is illustrative of the principles of the technology employed. It will be appreciated by a person skilled in the art that the scope of the invention as referred to in the present application is not limited to the embodiments with a specific combination of the above-mentioned features, but also covers other embodiments with any combination of the above-mentioned features or their equivalents without departing from the inventive concept. For example, the above features may be replaced with (but not limited to) features having similar functions disclosed in the present application.

Claims (4)

1. A method for installing a large-span river-crossing corridor cantilever is characterized in that the river-crossing corridor comprises a midspan structure and side span structures connected to two ends of the midspan structure, the midspan structure comprises a plurality of unit sections spliced together, and the method for installing the large-span river-crossing corridor cantilever comprises the following steps:
the side span structures are respectively installed on the river banks on the two sides of the river channel, so that the two side span structures are oppositely arranged;
installing a plurality of first supporting columns on the upper part of one side span structure, and installing a second supporting column on the upper part of the other side span structure, so that the plurality of first supporting columns are arranged along the length direction of the river-crossing corridor;
providing a truss girder which comprises an overhanging section and an anchoring section connected to the overhanging section, and movably mounting the anchoring section on the upper parts of the first support columns so that the overhanging section is overhanging to the outer side of one end of the side span structure facing the other side span structure and aligned to a second support column;
pushing the anchoring section towards the direction of the second supporting column, so that the cantilever section extends to the upper part of the second supporting column and is placed at the upper part of the second supporting column;
fixedly mounting the anchoring section to the first support column and fixedly mounting the cantilever section to the second support column;
and installing a crown block on the truss girder, hoisting the plurality of unit sections to the position between the two side span structures through the crown block, and installing the unit sections on the two side span structures to form the river-crossing corridor.
2. The method for installing the large-span river-crossing corridor cantilever according to claim 1, wherein the side-crossing structure is installed on the river bank by a bracket method.
3. The installation method of the large-span river-crossing corridor cantilever as claimed in claim 1, wherein when installing a plurality of said unit sections on both said side-crossing structures, a plurality of said unit sections are spliced in opposite directions from said both banks to the middle of said river channel to form said mid-crossing structure.
4. The installation method of the large-span river-crossing corridor cantilever as claimed in claim 3, wherein during the installation of the plurality of unit sections on the two side-crossing structures, after the previous unit section is installed, a total station is used to determine the spatial position of the overhanging end of the previous unit section so as to obtain the deformation amount and the deformation direction of the previous unit section, and during the positioning measurement and control of the next unit section, the reverse three-dimensional spatial deformation opposite to the deformation amount and the deformation direction of the previous unit section is performed on the positioning axis of the next unit section, so that the positional deviation of the unit sections is within a reasonable range.
CN202111060842.2A 2021-09-10 2021-09-10 Method for installing large-span river-crossing corridor cantilever Pending CN113863142A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111060842.2A CN113863142A (en) 2021-09-10 2021-09-10 Method for installing large-span river-crossing corridor cantilever

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111060842.2A CN113863142A (en) 2021-09-10 2021-09-10 Method for installing large-span river-crossing corridor cantilever

Publications (1)

Publication Number Publication Date
CN113863142A true CN113863142A (en) 2021-12-31

Family

ID=78995268

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111060842.2A Pending CN113863142A (en) 2021-09-10 2021-09-10 Method for installing large-span river-crossing corridor cantilever

Country Status (1)

Country Link
CN (1) CN113863142A (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202899044U (en) * 2012-07-26 2013-04-24 中铁六局集团有限公司 Vierendeel box-shaped double-girder bridge crane
CN105970836A (en) * 2016-03-23 2016-09-28 中铁四局集团钢结构有限公司 Method for erecting large-span lower chord variable truss high continuous steel trussed beam cantilever
JP2018053496A (en) * 2016-09-27 2018-04-05 三井住友建設株式会社 Bridge girder erection method for multiple span continuous bridge
CN108086166A (en) * 2018-01-15 2018-05-29 中铁大桥勘测设计院集团有限公司 Hybrid beam continuous rigid frame bridge steel box-girder installation method
CN109610330A (en) * 2018-12-18 2019-04-12 腾达建设集团股份有限公司 A kind of Bridge Erector passing method
CN109778718A (en) * 2019-03-05 2019-05-21 中铁四局集团有限公司 Construction method for long-span continuous steel box girder main span pure cantilever assembly mid-span closure
CN109797663A (en) * 2019-01-15 2019-05-24 中铁大桥勘测设计院集团有限公司 A kind of construction method that the floating bracket of bridge structure is set
CN111172892A (en) * 2019-12-31 2020-05-19 广西建工集团第一安装有限公司 Bilateral balance traction device and method for steel structure frame bridge
CN112030772A (en) * 2020-09-14 2020-12-04 河南省交通规划设计研究院股份有限公司 Rapid construction method of continuous rigid frame bridge
CN112195780A (en) * 2020-09-09 2021-01-08 广州瀚阳工程咨询有限公司 Numerical control method for erection line shape of segmental precast bridge

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202899044U (en) * 2012-07-26 2013-04-24 中铁六局集团有限公司 Vierendeel box-shaped double-girder bridge crane
CN105970836A (en) * 2016-03-23 2016-09-28 中铁四局集团钢结构有限公司 Method for erecting large-span lower chord variable truss high continuous steel trussed beam cantilever
JP2018053496A (en) * 2016-09-27 2018-04-05 三井住友建設株式会社 Bridge girder erection method for multiple span continuous bridge
CN108086166A (en) * 2018-01-15 2018-05-29 中铁大桥勘测设计院集团有限公司 Hybrid beam continuous rigid frame bridge steel box-girder installation method
CN109610330A (en) * 2018-12-18 2019-04-12 腾达建设集团股份有限公司 A kind of Bridge Erector passing method
CN109797663A (en) * 2019-01-15 2019-05-24 中铁大桥勘测设计院集团有限公司 A kind of construction method that the floating bracket of bridge structure is set
CN109778718A (en) * 2019-03-05 2019-05-21 中铁四局集团有限公司 Construction method for long-span continuous steel box girder main span pure cantilever assembly mid-span closure
CN111172892A (en) * 2019-12-31 2020-05-19 广西建工集团第一安装有限公司 Bilateral balance traction device and method for steel structure frame bridge
CN112195780A (en) * 2020-09-09 2021-01-08 广州瀚阳工程咨询有限公司 Numerical control method for erection line shape of segmental precast bridge
CN112030772A (en) * 2020-09-14 2020-12-04 河南省交通规划设计研究院股份有限公司 Rapid construction method of continuous rigid frame bridge

Similar Documents

Publication Publication Date Title
WO2021078310A1 (en) Method for removal of temporary support system for road bridge pre-fabricated small box girder-type concealed bent cap, and equipment therefor
CN112227206B (en) Process design and construction method for ground anchor to self-anchored beam
CN110700113B (en) Construction method of prestress applying device of non-prestressed beam bridge
CN110847062A (en) Construction method for whole-hole assembly double-width erection in 80-meter-span wide steel box girder factory
KR100896173B1 (en) Beam, structure, parking structure having the beam, method of manufacturing the beam and method of manufacturing structure without column
CN211735002U (en) Steel-concrete combined beam bridge capable of being installed quickly
CN112281916A (en) Large-axillary-angle single-side-wall movable formwork for subway engineering
CN219218724U (en) Main girder hanging and paving integrated machine for combined girder cable-stayed bridge
JP4880374B2 (en) How to build a bridge
CN113863142A (en) Method for installing large-span river-crossing corridor cantilever
CN110863417A (en) Steel-concrete combined beam bridge capable of being installed quickly and construction method thereof
CN216809623U (en) Steel box girder large segment support-free lap joint mounting structure
CN113216013B (en) Self-balancing construction method for post-loading cantilever arm of composite section girder bridge
JP2963879B2 (en) Bridge girder
CN212925808U (en) Vertical and longitudinal connecting device for bridge erecting machine
CN114263114A (en) Construction system and construction method of large-section steel box girder
CN113931068A (en) Bridge deck crane for mounting steel and concrete superposed beams and beam erecting method thereof
CN217652287U (en) Can have enough to meet need core section of thick bamboo well way operation platform
CN213867922U (en) Large-axillary-angle single-side-wall movable formwork for subway engineering
CN218989877U (en) Double-slider pushing construction structure of large-span steel truss bridge
CN216840804U (en) Unloading device for removing building stressed member
CN219862432U (en) Steel tower vertical rotating device
CN114277673B (en) Large-span large-inclination-angle basket type steel girder and arch segment assembling method
CN212611918U (en) Connecting structure of steel plate beam
CN215104733U (en) Steel pipe arch hydraulic lifting support

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20211231

RJ01 Rejection of invention patent application after publication