CN113818482A - New and old pipe gallery connecting method for reducing uneven settlement - Google Patents

New and old pipe gallery connecting method for reducing uneven settlement Download PDF

Info

Publication number
CN113818482A
CN113818482A CN202110876938.XA CN202110876938A CN113818482A CN 113818482 A CN113818482 A CN 113818482A CN 202110876938 A CN202110876938 A CN 202110876938A CN 113818482 A CN113818482 A CN 113818482A
Authority
CN
China
Prior art keywords
pipe gallery
top plate
steel bars
joint
side wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110876938.XA
Other languages
Chinese (zh)
Inventor
张东升
李猛
殷永艺
周锋
刘永旺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Original Assignee
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd, Shanghai Ershiye Construction Co Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN202110876938.XA priority Critical patent/CN113818482A/en
Publication of CN113818482A publication Critical patent/CN113818482A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Hydrology & Water Resources (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention relates to the technical field of underground pipe gallery construction, in particular to a new and old pipe gallery connection method for reducing uneven settlement; the method comprises the following steps of 1, excavating earth below a bottom plate of the constructed pipe gallery; step 2, binding steel bars of the bottom plate; step 3, installing a bottom plate template; step 4, pouring concrete on the bottom plate; step 5, binding side wall steel bars; step 6, installing side wall and top plate templates; step 7, binding steel bars of a top plate; step 8, installing a template at the joint of the top plate; (9) and concrete pouring of the side wall and the top plate. According to the invention, the new and old pipe galleries at the joint are integrated by adopting a hard joint mode at the joint of the new and old pipe galleries, so that the purpose of reducing uneven settlement at the joint of the new and old pipe galleries is achieved. Compared with a simple method of arranging a steel-edge water stop belt at a construction joint, the method has the remarkable advantage of reducing uneven settlement.

Description

New and old pipe gallery connecting method for reducing uneven settlement
Technical Field
The invention relates to the technical field of underground pipe gallery construction, in particular to a new and old pipe gallery connection method for reducing uneven settlement.
Background
With the development of society, more and more cities begin to conduct the construction of utility tunnels. Along with the popularization of the utility tunnel, criss-cross utility tunnel nets can be gradually formed. However, due to the difference of the time of the construction of the pipe gallery, the natural sedimentation of the pipe gallery which is firstly built after one year or more tends to be stable, and the sedimentation amount of the newly-built pipe gallery is difficult to control. How to reduce the uneven settlement of new and old piping lane hookup location becomes the problem that awaits solution urgently. Regarding the connection method of new and old pipe galleries, a method for realizing the connection of pipe galleries by adopting an extensible end well (CN 201710407764.6 a comprehensive pipe gallery extensible end well and a construction method thereof, under the condition that the comprehensive pipe gallery is built in different periods, the problem that the traditional pipe gallery end well cannot be connected with a long-term pipe gallery can be solved. In the aspect of considering the uneven settlement, a fixing structure for preventing the uneven settlement of the pipe gallery joint (CN 202020746908.8 a fixing structure for preventing the uneven settlement of the pipe gallery joint, wherein the fixing structure is arranged at the joint of two pipe gallery sections and comprises a cushion layer and a micro pile, the cushion layer is arranged at the bottom of the joint of the two pipe gallery sections, and the cushion layer limits the lower part of the joint of the two pipe gallery sections to prevent the two pipe gallery sections from settling), and the micro pile is adopted, so that the cost is increased, and the construction is complicated. The cast-in-place pipe gallery is connected through setting up the steel limit waterstop (CN202011355026. X bury formula steel limit waterstop structure and construction method in cast-in-place pipe gallery expansion joint) in the expansion joint department, also does not consider new and old pipe gallery and connects the uneven settlement problem, and does not have reversibility if the waterstop protection is improper, influences water-proof effects.
Disclosure of Invention
The invention aims to overcome the defects and provide a new and old pipe gallery connecting method for reducing uneven settlement.
In order to achieve the above object, the present invention is realized by:
a new and old pipe gallery connecting method for reducing uneven settlement is characterized in that: comprises that
Step 1, excavating earthwork below a bottom plate of a constructed pipe gallery
Adopt machinery to add artificial mode, carry out the earthwork excavation below the piping lane bottom plate of having built. Digging 400mm deep, digging 1000mm inwards from the cross section of the built pipe gallery, digging 1500mm more on two sides of the outer wall of the built pipe gallery to serve as a reserved operation space;
step 2, binding of steel bars of bottom plate
Binding steel bars according to the connecting part of the bottom plates and a reinforcement arrangement diagram of the bottom plate of the newly-built pipe gallery;
step 3, installing a bottom plate template
After the steel bars are bound, installing templates at the connecting part of the bottom plates and the newly-built pipe gallery bottom plate;
step 4, pouring concrete on the bottom plate
After the templates are installed, welding water-stop steel plates at the connecting positions of the bottom plates and the central line positions of the side walls of the bottom plates of the newly-built pipe gallery, then performing concrete pouring, forming the connecting positions of the bottom plates and the bottom plates of the newly-built pipe gallery into a whole, reserving construction joints at the connecting positions of the bottom plates as same as the bottom plates during concrete pouring, and arranging the construction joints 500mm away from the surfaces of the bottom plates;
step 5, binding of side wall steel bars
Binding steel bars according to the side wall joints and the side wall reinforcement map of the newly-built pipe gallery;
step 6, side wall and top plate template installation
After the steel bars are bound, mounting the side wall joints, the side walls and the top plate templates;
step 7, binding of steel bars of top plate
After the top plate template is installed, binding steel bars at the joint of the top plate and the top plate;
step 8, installing the template at the joint of the top plate
After the steel bars at the joint of the top plate are bound, installing a template;
(9) side wall and top plate concrete pouring
After the formwork is installed, concrete is poured on the side walls and the top plate (including the connecting part) at the same time to form a whole.
According to the invention, the new and old pipe galleries at the joint are integrated by adopting a hard joint mode at the joint of the new and old pipe galleries, so that the purpose of reducing uneven settlement at the joint of the new and old pipe galleries is achieved. Compared with a simple method of arranging a steel-edge water stop belt at a construction joint, the method has the remarkable advantage of reducing uneven settlement. The method is simple and convenient to operate, cost-saving and good in effect, has more obvious advantages compared with a method for arranging the micro-piles at the connecting positions, can be suitable for connecting new and old pipe galleries, and the structure for arranging the micro-piles only aims at the connection of a newly-built pipe gallery.
Drawings
Fig. 1 is a schematic view of the joint of the top plate and the bottom plate of the new pipe gallery and the old pipe gallery.
Fig. 2 is a schematic view of the joint of the side walls of the old pipe gallery and the new pipe gallery.
Detailed Description
The invention is further illustrated by the following specific examples.
As shown in fig. 1 and fig. 2, a new and old pipe gallery connection method for reducing uneven settlement is characterized in that: comprises that
Step 1, excavating earthwork below a bottom plate of a constructed pipe gallery
Adopt machinery to add artificial mode, carry out the earthwork excavation below the piping lane bottom plate of having built. Digging 400mm deep, digging 1000mm inwards from the cross section of the built pipe gallery, digging 1500mm more on two sides of the outer wall of the built pipe gallery to serve as a reserved operation space;
step 2, binding of steel bars of bottom plate
Binding steel bars according to the connecting part of the bottom plates and a reinforcement arrangement diagram of the bottom plate of the newly-built pipe gallery;
step 3, installing a bottom plate template
After the steel bars are bound, installing templates at the connecting part of the bottom plates and the newly-built pipe gallery bottom plate;
step 4, pouring concrete on the bottom plate
After the templates are installed, welding water-stop steel plates at the connecting positions of the bottom plates and the central line positions of the side walls of the bottom plates of the newly-built pipe gallery, then performing concrete pouring, forming the connecting positions of the bottom plates and the bottom plates of the newly-built pipe gallery into a whole, reserving construction joints at the connecting positions of the bottom plates as same as the bottom plates during concrete pouring, and arranging the construction joints 500mm away from the surfaces of the bottom plates;
step 5, binding of side wall steel bars
Binding steel bars according to the side wall joints and the side wall reinforcement map of the newly-built pipe gallery;
step 6, side wall and top plate template installation
After the steel bars are bound, mounting the side wall joints, the side walls and the top plate templates;
step 7, binding of steel bars of top plate
After the top plate template is installed, binding steel bars at the joint of the top plate and the top plate;
step 8, installing the template at the joint of the top plate
After the steel bars at the joint of the top plate are bound, installing a template;
(9) side wall and top plate concrete pouring
After the formwork is installed, concrete is poured on the side walls and the top plate (including the connecting part) at the same time to form a whole.
According to the invention, the new and old pipe galleries at the joint are integrated by adopting a hard joint mode at the joint of the new and old pipe galleries, so that the purpose of reducing uneven settlement at the joint of the new and old pipe galleries is achieved. Compared with a simple method of arranging a steel-edge water stop belt at a construction joint, the method has the remarkable advantage of reducing uneven settlement. The method is simple and convenient to operate, cost-saving and good in effect, has more obvious advantages compared with a method for arranging the micro-piles at the connecting positions, can be suitable for connecting new and old pipe galleries, and the structure for arranging the micro-piles only aims at the connection of a newly-built pipe gallery.

Claims (1)

1. A new and old pipe gallery connecting method for reducing uneven settlement is characterized in that: comprises that
Step 1, excavating earthwork below a bottom plate of a constructed pipe gallery
Adopting a mechanical and manual mode to perform earth excavation below the bottom plate of the built pipe gallery;
digging 400mm deep, digging 1000mm inwards from the cross section of the built pipe gallery, digging 1500mm more on two sides of the outer wall of the built pipe gallery to serve as a reserved operation space;
step 2, binding of steel bars of bottom plate
Binding steel bars according to the connecting part of the bottom plates and a reinforcement arrangement diagram of the bottom plate of the newly-built pipe gallery;
step 3, installing a bottom plate template
After the steel bars are bound, installing templates at the connecting part of the bottom plates and the newly-built pipe gallery bottom plate;
step 4, pouring concrete on the bottom plate
After the templates are installed, welding water-stop steel plates at the connecting positions of the bottom plates and the central line positions of the side walls of the bottom plates of the newly-built pipe gallery, then performing concrete pouring, forming the connecting positions of the bottom plates and the bottom plates of the newly-built pipe gallery into a whole, reserving construction joints at the connecting positions of the bottom plates as same as the bottom plates during concrete pouring, and arranging the construction joints 500mm away from the surfaces of the bottom plates;
step 5, binding of side wall steel bars
Binding steel bars according to the side wall joints and the side wall reinforcement map of the newly-built pipe gallery;
step 6, side wall and top plate template installation
After the steel bars are bound, mounting the side wall joints, the side walls and the top plate templates;
step 7, binding of steel bars of top plate
After the top plate template is installed, binding steel bars at the joint of the top plate and the top plate;
step 8, installing the template at the joint of the top plate
After the steel bars at the joint of the top plate are bound, installing a template;
(9) side wall and top plate concrete pouring
After the formwork is installed, concrete is poured on the side walls and the top plate (including the connecting part) at the same time to form a whole.
CN202110876938.XA 2021-07-31 2021-07-31 New and old pipe gallery connecting method for reducing uneven settlement Pending CN113818482A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110876938.XA CN113818482A (en) 2021-07-31 2021-07-31 New and old pipe gallery connecting method for reducing uneven settlement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110876938.XA CN113818482A (en) 2021-07-31 2021-07-31 New and old pipe gallery connecting method for reducing uneven settlement

Publications (1)

Publication Number Publication Date
CN113818482A true CN113818482A (en) 2021-12-21

Family

ID=78924098

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110876938.XA Pending CN113818482A (en) 2021-07-31 2021-07-31 New and old pipe gallery connecting method for reducing uneven settlement

Country Status (1)

Country Link
CN (1) CN113818482A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114960742A (en) * 2022-03-28 2022-08-30 中建五局土木工程有限公司 New and old pipe gallery connection construction method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102345297A (en) * 2011-07-20 2012-02-08 同济大学 Prefabricated and assembled comprehensive pipe gallery with semi-rigid joints
CN203007992U (en) * 2012-11-21 2013-06-19 中国核电工程有限公司 Structure of controlling relative sedimentation at joint of gutter channel and underground structure
CN105908777A (en) * 2016-05-04 2016-08-31 东北大学 Comprehensive pipe gallery sliding mold and application method thereof
CN106894451A (en) * 2017-01-25 2017-06-27 上海建工五建集团有限公司 Suitable for overlapping layers waterproof construction and its construction method at Foundation strengthened
CN107687178A (en) * 2017-09-04 2018-02-13 滨州学院 A kind of precast assembly comprehensive pipe gallery structure of anti-uneven settlement of foundation
CN107700533A (en) * 2017-10-12 2018-02-16 海门市帕源路桥建设有限公司 A kind of box quick assembly and disassembly mould piping lane construction technology
CN111764429A (en) * 2020-06-10 2020-10-13 北京万兴建筑集团有限公司 Steel-edged rubber water stop for trapezoid-shaped socket of underground pipe gallery and construction method of steel-edged rubber water stop
CN112726663A (en) * 2020-12-25 2021-04-30 中国建筑第八工程局有限公司 Connecting construction method for cast-in-situ sections of prefabricated comprehensive pipe gallery

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102345297A (en) * 2011-07-20 2012-02-08 同济大学 Prefabricated and assembled comprehensive pipe gallery with semi-rigid joints
CN203007992U (en) * 2012-11-21 2013-06-19 中国核电工程有限公司 Structure of controlling relative sedimentation at joint of gutter channel and underground structure
CN105908777A (en) * 2016-05-04 2016-08-31 东北大学 Comprehensive pipe gallery sliding mold and application method thereof
CN106894451A (en) * 2017-01-25 2017-06-27 上海建工五建集团有限公司 Suitable for overlapping layers waterproof construction and its construction method at Foundation strengthened
CN107687178A (en) * 2017-09-04 2018-02-13 滨州学院 A kind of precast assembly comprehensive pipe gallery structure of anti-uneven settlement of foundation
CN107700533A (en) * 2017-10-12 2018-02-16 海门市帕源路桥建设有限公司 A kind of box quick assembly and disassembly mould piping lane construction technology
CN111764429A (en) * 2020-06-10 2020-10-13 北京万兴建筑集团有限公司 Steel-edged rubber water stop for trapezoid-shaped socket of underground pipe gallery and construction method of steel-edged rubber water stop
CN112726663A (en) * 2020-12-25 2021-04-30 中国建筑第八工程局有限公司 Connecting construction method for cast-in-situ sections of prefabricated comprehensive pipe gallery

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114960742A (en) * 2022-03-28 2022-08-30 中建五局土木工程有限公司 New and old pipe gallery connection construction method
CN114960742B (en) * 2022-03-28 2024-05-14 中建五局土木工程有限公司 New and old pipe gallery connection construction method

Similar Documents

Publication Publication Date Title
CN107542108B (en) A kind of reverse construction method of building basement structure
CN108842819B (en) Urban rail transit cable line tunnel construction method
CN103741714A (en) Construction method for full cover-excavation reverse method of underground engineering
CN102322064A (en) Construction method for underground diaphragm wall of deep foundation pit for subway station in collapsible loess areas
CN207512745U (en) A kind of caisson device and its foundation pit structure
CN202194148U (en) Waterproof curtain
CN110939303B (en) Semi-reverse construction method of cyclone pool
CN104727302A (en) Cast-in-place construction process for inter-pile board wall between slide-resistant piles
CN112064751A (en) Deep groove construction method for drainage pipeline
CN105484277A (en) Component for tubular well precipitation construction in elevator foundation pit or sump and construction method
CN101538832B (en) Construction method for controlling two-dimension jacking of large-scale case
CN110055973B (en) Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method
CN108035379A (en) A kind of pipe gallery and its construction method
CN103215958A (en) Construction method of dewatering and retaining and protecting of deep foundation pit in expansive-soil area
CN205205844U (en) Member is used in construction of tubular well precipitation in elevator foundation ditch or sump pit
CN114575208A (en) Abrupt slope roadbed structure convenient to prefabricated installation
CN109898556A (en) A kind of underground pipe gallery structure and sunk type construction method
CN113818482A (en) New and old pipe gallery connecting method for reducing uneven settlement
CN109457705A (en) A kind of Open Cut Method construction method
CN110117959B (en) Construction method for foundation pit support near river
CN209760299U (en) light and shade of avoiding house to tear open and move is dug and is combined subway station structure
CN104846837B (en) The construction method of ultra-deep well in a kind of bright draining foundation ditch
CN210122735U (en) Underground structure anti-floating system based on outward-protruding wing foot plate
CN204551521U (en) The cast-in-place construction structure of board wall between a kind of antislide pile stake
CN210315908U (en) Immersed tube type inspection well

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20211221

RJ01 Rejection of invention patent application after publication