CN113685191A - 一种隧道开挖时碳质板岩遇水塌方的处理方法 - Google Patents

一种隧道开挖时碳质板岩遇水塌方的处理方法 Download PDF

Info

Publication number
CN113685191A
CN113685191A CN202111053562.9A CN202111053562A CN113685191A CN 113685191 A CN113685191 A CN 113685191A CN 202111053562 A CN202111053562 A CN 202111053562A CN 113685191 A CN113685191 A CN 113685191A
Authority
CN
China
Prior art keywords
grouting
collapse
construction
monitoring
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111053562.9A
Other languages
English (en)
Inventor
王海涛
马文贤
于曼丽
刘飞
旦正杰
卢世鸿
韩常智
苏伟
张世安
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Engineering Bureau 4 Co Ltd
Original Assignee
Sinohydro Engineering Bureau 4 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Engineering Bureau 4 Co Ltd filed Critical Sinohydro Engineering Bureau 4 Co Ltd
Priority to CN202111053562.9A priority Critical patent/CN113685191A/zh
Publication of CN113685191A publication Critical patent/CN113685191A/zh
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/003Arrangement of measuring or indicating devices for use during driving of tunnels, e.g. for guiding machines

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Soil Sciences (AREA)
  • Civil Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明涉及隧道开挖技术领域,具体涉及一种隧道开挖时碳质板岩遇水塌方的处理方法。具体施工方法为:反压回填、管棚施工、渗水处理、注浆花管打设并注浆、断面变形监测及开挖。本发明高原碳质板岩遇水段塌方处理方法,施工过程安全可靠、节约成本、施工效率高且对工程施工质量有保证,为后续混凝土浇筑施工奠定了良好的基础。其中,管棚施工对塌方段拱顶进行支撑,避免落石对塌方施工造成安全危害;注浆管棚及注浆导管稳固周边围岩,使塌方处理更安全;预留拱顶注浆孔保证拱顶注浆充实,使拱顶围岩更加稳固。

Description

一种隧道开挖时碳质板岩遇水塌方的处理方法
技术领域
本发明涉及隧道开挖技术领域,具体涉及一种隧道开挖时碳质板岩遇水塌方的处理方法。
背景技术
高寒地区隧道在开挖过程中,局部地区出现渗水情况,高原板岩在渗水段遇水后软化、变质形成炭质板岩,该类岩石密度较大,渗水储存在上下板岩之间不易流出,对两层板岩的接触起了润滑作用,极易造成塌方。针对隧道塌方后的快速处理,结合本工程施工特性,采用了对塌方段进行反压回填及洞内管棚施工的施工方法,保证在安全、质量各方面满足的条件下加快施工进度。
发明内容
基于上述技术问题,本发明针对隧道塌方后的快速处理,结合高原地区工程施工特性,采用了对塌方段进行反压回填及洞内管棚施工的施工方法,保证在安全、质量各方面满足的条件下加快施工进度。目的是提供一种隧道开挖时碳质板岩遇水塌方的处理方法。
本发明保护一种隧道开挖时碳质板岩遇水塌方的处理方法,具体步骤包括如下:
步骤1,反压回填:用机械设备利用隧道洞库开挖时的弃渣,对塌方段进行反压回填,并反复压实回填处,避免塌方段二次塌方段对现场施工造成安全隐患;
步骤2,管棚施工:采用Φ108热轧无缝钢管,长度为12m,外插角按1°~5°,环向间距30cm进行超前管棚注浆加固,隧洞纵向同一横断面内的接头数不大于50%,相邻钢管的接头错开1m,管棚采用钻孔法施工;钻孔时严格控制钻杆轴向,脚手架应搭设可靠,钻机应固定牢固,钻进过程中采用测斜仪器量测钻进偏斜度,若偏斜度超过设计要求时及时进行纠偏;管棚接长时,接头采用钢管箍,上满丝扣,丝扣长度不小于150mm,接头在横断面上错开;
步骤3,渗水处理:采用Φ108热轧无缝钢管,长度20m,在其周边打孔,然后从渗水点***岩体内,将岩体内部积水引排至洞内积水坑内,用污泥泵抽排至洞外污水处理***;
步骤4,注浆花管打设并注浆:在塌方段拱部打设Φ42注浆花管,长度6.0m,间距1m×1m,梅花形布置,进行围岩固结灌浆;注浆花管的管壁上钻设出浆孔,孔径为8mm,纵向间距150mm,梅花形布置;注浆时采用双液浆,使浆液充分渗透到围岩裂隙中;
步骤5,断面变形监测及开挖:对掌子面附近初期支护变形监测频率,监测分为沉降及收敛监测,采用蓝卡TS60全站仪进行监测,监测标埋设间距为2m/排,每排7点,监测频次为3h/次;根据监测数据进行隧洞变形分析,若在注浆过程中注浆压力过大,会增加该部位岩体自重,导致该部位发生变形、造成塌方,对塌方段在进行加固处理;加固完成后根据岩石情况采用上下台阶、预留核心土法进行开挖施工。
进一步的,所述步骤2中,管棚注浆加固时,注浆压力为1.0~2.0MPa,浆液配比中水灰比为0.8:1~1:1。
进一步的,所述步骤5中,蓝卡TS60全站仪进行监测时,精度为0.5秒。
相比于现有的技术,本发明具有如下有益效果:
本发明高原碳质板岩遇水段塌方处理方法,施工过程安全可靠、节约成本、施工效率高且对工程施工质量有保证,为后续混凝土浇筑施工奠定了良好的基础。其中,管棚施工对塌方段拱顶进行支撑,避免落石对塌方施工造成安全危害;注浆管棚及注浆导管稳固周边围岩,使塌方处理更安全;预留拱顶注浆孔保证拱顶注浆充实,使拱顶围岩更加稳固。
附图说明
图1为本发明施工方法流程图。
具体实施方式
下面将结合实施例对本发明的技术方案进行清楚、完整地描述,显然,所描述的实施例仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。
实施例1
一种隧道开挖时碳质板岩遇水塌方的处理方法,具体步骤包括如下:
步骤1,反压回填:用机械设备利用隧道洞库开挖时的弃渣,对塌方段进行反压回填,并反复压实回填处,避免塌方段二次塌方段对现场施工造成安全隐患;
步骤2,管棚施工:采用Φ108热轧无缝钢管,长度为12m,外插角按1°,环向间距30cm进行超前管棚注浆加固,隧洞纵向同一横断面内的接头数不大于50%,相邻钢管的接头错开1m,管棚采用钻孔法施工;钻孔时严格控制钻杆轴向,脚手架应搭设可靠,钻机应固定牢固,钻进过程中采用测斜仪器量测钻进偏斜度,若偏斜度超过设计要求时及时进行纠偏;管棚接长时,接头采用钢管箍,上满丝扣,丝扣长度不小于150mm,接头在横断面上错开;管棚注浆加固时,注浆压力为1.0MPa,浆液配比中水灰比为0.8:1。
步骤3,渗水处理:采用Φ108热轧无缝钢管,长度20m,在其周边打孔,然后从渗水点***岩体内,将岩体内部积水引排至洞内积水坑内,用污泥泵抽排至洞外污水处理***;
步骤4,注浆花管打设并注浆:在塌方段拱部打设Φ42注浆花管,长度6.0m,间距1m×1m,梅花形布置,进行围岩固结灌浆;注浆花管的管壁上钻设出浆孔,孔径为8mm,纵向间距150mm,梅花形布置;注浆时采用双液浆,使浆液充分渗透到围岩裂隙中;
步骤5,断面变形监测及开挖:对掌子面附近初期支护变形监测频率,监测分为沉降及收敛监测,采用蓝卡TS60全站仪进行监测(精度为0.5秒),监测标埋设间距为2m/排,每排7点,监测频次为3h/次;根据监测数据进行隧洞变形分析,若在注浆过程中注浆压力过大,会增加该部位岩体自重,导致该部位发生变形、造成塌方,对塌方段在进行加固处理;加固完成后根据岩石情况采用上下台阶、预留核心土法进行开挖施工。
实施例2
一种隧道开挖时碳质板岩遇水塌方的处理方法,具体步骤包括如下:
步骤1,反压回填:用机械设备利用隧道洞库开挖时的弃渣,对塌方段进行反压回填,并反复压实回填处,避免塌方段二次塌方段对现场施工造成安全隐患;
步骤2,管棚施工:采用Φ108热轧无缝钢管,长度为12m,外插角按5°,环向间距30cm进行超前管棚注浆加固,隧洞纵向同一横断面内的接头数不大于50%,相邻钢管的接头错开1m,管棚采用钻孔法施工;钻孔时严格控制钻杆轴向,脚手架应搭设可靠,钻机应固定牢固,钻进过程中采用测斜仪器量测钻进偏斜度,若偏斜度超过设计要求时及时进行纠偏;管棚接长时,接头采用钢管箍,上满丝扣,丝扣长度不小于150mm,接头在横断面上错开;管棚注浆加固时,注浆压力为2.0MPa,浆液配比中水灰比为1:1;
步骤3,渗水处理:采用Φ108热轧无缝钢管,长度20m,在其周边打孔,然后从渗水点***岩体内,将岩体内部积水引排至洞内积水坑内,用污泥泵抽排至洞外污水处理***;
步骤4,注浆花管打设并注浆:在塌方段拱部打设Φ42注浆花管,长度6.0m,间距1m×1m,梅花形布置,进行围岩固结灌浆;注浆花管的管壁上钻设出浆孔,孔径为8mm,纵向间距150mm,梅花形布置;注浆时采用双液浆,使浆液充分渗透到围岩裂隙中;
步骤5,断面变形监测及开挖:对掌子面附近初期支护变形监测频率,监测分为沉降及收敛监测,采用蓝卡TS60全站仪进行监测(精度为0.5秒),监测标埋设间距为2m/排,每排7点,监测频次为3h/次;根据监测数据进行隧洞变形分析,若在注浆过程中注浆压力过大,会增加该部位岩体自重,导致该部位发生变形、造成塌方,对塌方段在进行加固处理;加固完成后根据岩石情况采用上下台阶、预留核心土法进行开挖施工。
实施例3
“碳质板岩遇水段塌方”施工能够有效的降低隧洞初支的塌方引起的返工费用,碳质板岩遇水段塌方施工效益分析如下:
(1)对正常塌方处理与碳质板岩遇水塌方处理两种工艺进行对比分析如下:
反铲:1台,装载机:1台,手风钻:6个,开挖6人,注浆8人,管棚、逐渐花管打设8人。根据现场施工实况,正常塌方处理;计划工期为35天,所用材料、机械、人工计算如下:
反压回填:2d;
人工:6人/d;共=6*2*300=3600;
机械:反铲=2*480=960、装载机=2*450=900;
材料费:C25喷射混凝土=368*1582.68=582426.24、渣土回填=482*17=8194
机械费:反铲=35*450*8=126000;装载机=35*450=12600;地质探测仪=50000
手风钻:6*35*220=46200;
材料费:水泥浆264t,双液浆135。264*1100=290400;双液浆=135*1230=166050;Φ108热轧无缝钢管=324*170=55080;Φ42注浆花管=402*32.7=13145.4;I18工字钢=0.578*5*4780=13814.2
人工费:35*300*20=210000;;
正常塌方处理所需费用=1502809.84元;
(2)碳质板岩遇水塌方段施工:反铲:1台,装载机:1台,手风钻:6个,开挖6人,立架8人,喷锚6人。根据现场施工实况,一个扩挖断面;实际工期为15天。
反压回填:2d;
人工:6人/d;共=6*2*300=3600;
机械:反铲=2*480=960、装载机=2*450=900;
材料费:C25喷射混凝土=268*1582.68=424158.24、渣土回填=482*17=8194
机械费:反铲=15*450=6750;装载机=15*450=6750;
手风钻:6*15*220=19800;
材料费:水泥浆264t,双液浆135。264*1100=290400;双液浆=135*1230=166050;Φ108热轧无缝钢管=324*170=55080;Φ42注浆花管=402*32.7=13145.4;I18工字钢=0.578*5*4780=13814.2
人工费:15*300*20=90000;
采用碳质板岩遇水处塌方理所需费用=10914078.84元;
对比塌方段正常处理,高原碳质板岩遇水段塌方处理费用=1502809.84-10914078.8=411402元,并保证了施工安全及施工质量,为后续混凝土浇筑施工奠定了良好的基础。
尽管已经示出和描述了本发明的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本发明的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本发明的范围由所附权利要求及其等同物限定。

Claims (3)

1.一种隧道开挖时碳质板岩遇水塌方的处理方法,其特征在于,具体步骤包括如下:
步骤1,反压回填:用机械设备利用隧道洞库开挖时的弃渣,对塌方段进行反压回填,并反复压实回填处;
步骤2,管棚施工:采用Φ108热轧无缝钢管,长度为12m,外插角按1°~5°,环向间距30cm进行超前管棚注浆加固,隧洞纵向同一横断面内的接头数不大于50%,相邻钢管的接头错开1m,管棚采用钻孔法施工;钻孔时严格控制钻杆轴向,脚手架应搭设可靠,钻机应固定牢固,钻进过程中采用测斜仪器量测钻进偏斜度,若偏斜度超过设计要求时及时进行纠偏;管棚接长时,接头采用钢管箍,上满丝扣,丝扣长度不小于150mm,接头在横断面上错开;
步骤3,渗水处理:采用Φ108热轧无缝钢管,长度20m,在其周边打孔,然后从渗水点***岩体内,将岩体内部积水引排至洞内积水坑内,用污泥泵抽排至洞外污水处理***;
步骤4,注浆花管打设并注浆:在塌方段拱部打设Φ42注浆花管,长度6.0m,间距1m×1m,梅花形布置,进行围岩固结灌浆;注浆花管的管壁上钻设出浆孔,孔径为8mm,纵向间距150mm,梅花形布置;注浆时采用双液浆,使浆液充分渗透到围岩裂隙中;
步骤5,断面变形监测及开挖:对掌子面附近初期支护变形监测频率,监测分为沉降及收敛监测,采用蓝卡TS60全站仪进行监测,监测标埋设间距为2m/排,每排7点,监测频次为3h/次;根据监测数据进行隧洞变形分析,若在注浆过程中注浆压力过大,会增加该部位岩体自重,导致该部位发生变形、造成塌方,对塌方段在进行加固处理;加固完成后根据岩石情况采用上下台阶、预留核心土法进行开挖施工。
2.根据权利要求1所述的一种隧道开挖时碳质板岩遇水塌方的处理方法,其特征在于,所述步骤2中,管棚注浆加固时,注浆压力为1.0~2.0MPa,浆液配比中水灰比为0.8:1~1:1。
3.根据权利要求1所述的一种隧道开挖时碳质板岩遇水塌方的处理方法,其特征在于,所述步骤5中,蓝卡TS60全站仪进行监测时,精度为0.5秒。
CN202111053562.9A 2021-09-09 2021-09-09 一种隧道开挖时碳质板岩遇水塌方的处理方法 Pending CN113685191A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111053562.9A CN113685191A (zh) 2021-09-09 2021-09-09 一种隧道开挖时碳质板岩遇水塌方的处理方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111053562.9A CN113685191A (zh) 2021-09-09 2021-09-09 一种隧道开挖时碳质板岩遇水塌方的处理方法

Publications (1)

Publication Number Publication Date
CN113685191A true CN113685191A (zh) 2021-11-23

Family

ID=78586165

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111053562.9A Pending CN113685191A (zh) 2021-09-09 2021-09-09 一种隧道开挖时碳质板岩遇水塌方的处理方法

Country Status (1)

Country Link
CN (1) CN113685191A (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117365376A (zh) * 2023-12-06 2024-01-09 中国电建集团西北勘测设计研究院有限公司 在管棚钻孔施工中防止塌孔及卡钻的方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2005882C1 (ru) * 1990-11-11 1994-01-15 Штумпф Генрих Георгиевич Способ восстановления и крепления горных выработок вблизи земной поверхности при завале вмещающими породами
CN108678776A (zh) * 2018-03-29 2018-10-19 中交路桥北方工程有限公司 砂质黏土地质隧道冒顶处理方法
CN108979644A (zh) * 2018-08-07 2018-12-11 中电建路桥集团有限公司 一种富水隧道溶洞坍塌处理及隧道开挖施工方法
CN109854255A (zh) * 2018-11-30 2019-06-07 中国电建集团成都勘测设计研究院有限公司 隧道不收敛型塌方的处理方法
CN110821513A (zh) * 2019-10-24 2020-02-21 中铁十八局集团有限公司 一种对隧道局部塌方进行超前注浆并进行支撑的施工方法
CN113006825A (zh) * 2021-04-09 2021-06-22 中铁六局集团太原铁路建设有限公司 隧道塌方处的换拱施工方法
CN113187512A (zh) * 2021-04-27 2021-07-30 中铁建云南交通建设管理有限公司 一种用于岩溶隧道大规模涌水突泥的注浆和排水施工方法
CN113236259A (zh) * 2021-06-02 2021-08-10 崔旭雄 一种团结隧道开挖及支护专项施工工艺

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2005882C1 (ru) * 1990-11-11 1994-01-15 Штумпф Генрих Георгиевич Способ восстановления и крепления горных выработок вблизи земной поверхности при завале вмещающими породами
CN108678776A (zh) * 2018-03-29 2018-10-19 中交路桥北方工程有限公司 砂质黏土地质隧道冒顶处理方法
CN108979644A (zh) * 2018-08-07 2018-12-11 中电建路桥集团有限公司 一种富水隧道溶洞坍塌处理及隧道开挖施工方法
CN109854255A (zh) * 2018-11-30 2019-06-07 中国电建集团成都勘测设计研究院有限公司 隧道不收敛型塌方的处理方法
CN110821513A (zh) * 2019-10-24 2020-02-21 中铁十八局集团有限公司 一种对隧道局部塌方进行超前注浆并进行支撑的施工方法
CN113006825A (zh) * 2021-04-09 2021-06-22 中铁六局集团太原铁路建设有限公司 隧道塌方处的换拱施工方法
CN113187512A (zh) * 2021-04-27 2021-07-30 中铁建云南交通建设管理有限公司 一种用于岩溶隧道大规模涌水突泥的注浆和排水施工方法
CN113236259A (zh) * 2021-06-02 2021-08-10 崔旭雄 一种团结隧道开挖及支护专项施工工艺

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117365376A (zh) * 2023-12-06 2024-01-09 中国电建集团西北勘测设计研究院有限公司 在管棚钻孔施工中防止塌孔及卡钻的方法

Similar Documents

Publication Publication Date Title
CN101614125B (zh) V级围岩隧道施工方法
CN110056369B (zh) 一种隧道进出口洞口的施工方法
JP7257086B2 (ja) トンネルの低土被り区間の総合的な工法
CN113153308B (zh) 双联拱隧道塌方段施工方法
CN111997624A (zh) 一种浅埋大断面暗挖矩形隧道施工方法
CN111502696A (zh) 暗挖隧道的密网式超前支护***及施工方法
CN112228082A (zh) 一种管棚与超前小导管组合注浆的隧道塌方处理方法
CN108842819A (zh) 一种城市轨道交通电缆线路隧道施工方法
CN105442605A (zh) 拔出phc桩再利用于深基坑支护施工方法
CN111734425A (zh) 一种下穿机场航站楼的暗挖隧道的施工方法
CN112761166A (zh) Smw工法桩结合前置注浆钢管组合支护浅基坑施工方法
CN206721870U (zh) 一种长螺旋钻孔压灌桩用钢筋笼
CN115539048A (zh) 一种用于浅埋偏压隧道洞口施工方法
CN110777775A (zh) 一种基坑结构及其施工方法
CN112855225B (zh) 一种安全性高的软岩隧道支护施工方法
CN113685191A (zh) 一种隧道开挖时碳质板岩遇水塌方的处理方法
CN113216215A (zh) 一种复杂环境下深沟槽支护逆作施工方法
CN117489367A (zh) 水电站不良地质条件下隧洞坍塌处理加固结构及加固方法
CN113431097A (zh) 一种紧邻深基坑工程浅基础建筑保护结构及施工方法
CN111779004A (zh) 强卸荷破碎岩质高边坡快速支护施工工艺
CN112922635A (zh) 一种水工隧洞开挖支护结构及施工方法
CN111456021A (zh) 利用rjp桩逆做围护结构的施工方法
CN114541408B (zh) 地下车站端头井前上部含风井结构及其下穿施工方法
CN115306428A (zh) 一种适用于双侧壁导坑法隧道二衬安全快速施工方法
CN215057408U (zh) 一种公路隧道斜井与正洞交叉口的加强装置

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20211123

RJ01 Rejection of invention patent application after publication