CN113685187B - 小净距多孔洞暗挖隧道施工工艺 - Google Patents
小净距多孔洞暗挖隧道施工工艺 Download PDFInfo
- Publication number
- CN113685187B CN113685187B CN202110935342.2A CN202110935342A CN113685187B CN 113685187 B CN113685187 B CN 113685187B CN 202110935342 A CN202110935342 A CN 202110935342A CN 113685187 B CN113685187 B CN 113685187B
- Authority
- CN
- China
- Prior art keywords
- support
- hole
- tube
- side wall
- support pipes
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims abstract description 25
- 238000000034 method Methods 0.000 title claims abstract description 21
- 239000011150 reinforced concrete Substances 0.000 claims abstract description 16
- 239000004567 concrete Substances 0.000 claims abstract description 13
- 229910001294 Reinforcing steel Inorganic materials 0.000 claims abstract description 10
- 239000002689 soil Substances 0.000 claims description 13
- 238000003466 welding Methods 0.000 claims description 8
- 230000000149 penetrating effect Effects 0.000 claims description 4
- 230000015572 biosynthetic process Effects 0.000 claims description 3
- 230000000694 effects Effects 0.000 abstract description 2
- 238000009434 installation Methods 0.000 description 4
- 230000002787 reinforcement Effects 0.000 description 4
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- 238000004026 adhesive bonding Methods 0.000 description 2
- 238000009412 basement excavation Methods 0.000 description 2
- 238000001125 extrusion Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000977 initiatory effect Effects 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- 238000003825 pressing Methods 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 230000005641 tunneling Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/006—Lining anchored in the rock
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Civil Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Lining And Supports For Tunnels (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
本申请涉及小净距多孔洞暗挖隧道施工工艺,涉及隧道施工技术领域,为了解决施工人员的工作量较大的问题,其包括以下步骤:1、在隧道长度方向两端开挖工作井,两个所述工作井包括始发井和接收井;2、从始发井开始沿隧道长度方向朝接收井阶段性地开设若干连接洞,若干所述连接洞围成环状;3、连接洞每开设完成一个阶段,将一个支撑管顶入连接洞内;4、将相邻支撑管相连通,并在支撑管内进行钢筋捆扎;5、向全部支撑管内灌注混凝土,形成钢筋砼;6、开挖钢筋砼内的土方形成隧道。本申请具有减少施工人员的工作量的效果。
Description
技术领域
本申请涉及隧道施工技术领域,尤其是涉及小净距多孔洞暗挖隧道施工工艺。
背景技术
暗挖隧道施工工艺是指在不开挖地面的情况下,在地下进行的一种隧道挖施工工艺。
公开号为CN113027466A的相关专利提供了一种极小净距隧道暗挖施工工艺,其步骤包括:S1、勘测选择具有一定自立性和稳定性的地层土质;S2、在规划隧道的长度方向两端开挖工作井,并将工作井连通形成隧道;S3、隧道土方开挖;S4、初期支护结构安装、防水层和二次衬砌施工;S5、间岩墙支护结构安装。
针对上述中的相关专利,发明人认为步骤S4中的初期支护结构安装、防水层和二次衬砌施工,工程繁琐,导致施工人员的工作量较大。
发明内容
为了减少施工人员的工作量,本申请提供小净距多孔洞暗挖隧道施工工艺。
本申请提供的小净距多孔洞暗挖隧道施工工艺采用如下的技术方案:
小净距多孔洞暗挖隧道施工工艺,包括以下步骤:
S1、开挖工作井:在隧道长度方向两端开挖工作井,两个所述工作井包括始发井和接收井。
S2、开挖连接洞:从始发井开始沿隧道长度方向朝接收井阶段性地开设若干连接洞,若干所述连接洞围成环状。
S3、顶入支撑管:连接洞每开设完成一个阶段,将一个支撑管顶入连接洞内。
S4、支撑管连通:将相邻支撑管相连通,并在支撑管内进行钢筋捆扎。
S5、灌注混凝土:向全部支撑管内灌注混凝土,形成钢筋砼。
S6、开挖土方:开挖钢筋砼内的土方形成隧道。
通过采用上述技术方案,开设一个阶段的连接洞后,将支撑管顶入连接洞内,支撑管可对连接洞内侧壁进行支撑;通过支撑管的使用,减少了施工人员需进行初期支护结构安装、防水层和二次衬砌施工等操作的情况,减少了施工人员的工作量。钢筋砼的形成,提高了支撑管对外侧壁土层支撑的稳定性,提高施工人员开挖土方时的安全性。
可选的,所述步骤S3中,两个轴向相邻的所述支撑管之间设置有连接结构,两个所述支撑管通过连接结构相连。
通过采用上述技术方案,连接架构可对轴向相邻的两个支撑管进行限位,提高轴向相邻支撑管之间的位置稳定性,减少轴向相邻支撑管之间发生错位的情况。
可选的,所述步骤S4中,径向相邻支撑管之间通过顶板和底板进行连通封闭,所述顶板和底板之间设置有支撑柱。
通过采用上述技术方案,支撑柱可对顶板进行支撑,减少压在顶板上方的土层令顶板与支撑管连接处断裂的情况。
可选的,所述始发井的宽度大于二倍支撑管的长度。
通过采用上述技术方案,可在始发井内放置两个支撑管,以便于施工人员在连接洞外部对两个支撑管进行连接,提高了支撑管之间连接操作的便捷性。
可选的,所述连接结构包括连接环板和安装环,所述安装环与连接环板同轴且与连接环板侧壁垂直;所述连接环板侧壁与支撑管端壁相贴,所述安装环插设在支撑管内并与支撑管内侧壁相连。
通过采用上述技术方案,对轴向相邻支撑管进行连接时,将连接环板一侧的安装环***其中一个支撑管内,并将安装环外侧壁与支撑管内侧壁相连,再移动另一个支撑管令连接环板另一侧的安装环***支撑管内,再将安装环外侧壁与支撑管内侧壁相连,即完成连接结构对两个支撑管的连接。
可选的,所述安装环与支撑管内侧壁间隙配合;所述安装环壁开设有条形连接孔,所述条形连接孔内贯穿插设有螺栓,螺栓一端与支撑管内侧壁螺纹连接,所述螺栓侧壁与条形连接孔内侧壁间隙配合。
通过采用上述技术方案,当规划隧道有弧度时,可转动支撑管,支撑管带动螺栓沿条形连接孔长度方向移动,以实现对支撑管延伸方向的调节,同时减少对安装环与支撑管之间连接的影响。
可选的,所述安装环外侧壁设置有弹性条,所述弹性条与支撑管内侧壁相抵。
支撑管转动后,会与连接环板侧壁之间产生缝隙,易发生支撑管外侧壁土层沿着缝隙渗漏到支撑管内的情况;通过采用上述技术方案,弹性条与支撑管内侧壁相抵,以实现对支撑管和连接环板侧壁之间的缝隙进行封堵,减少支撑管外侧壁土层渗漏到支撑管内的情况。
可选的,所述弹性条嵌设在安装环外侧壁上。
一般情况下,弹性条通过胶粘固定连接在安装环外侧壁上,支撑管相对安装环发生移动时,支撑管内侧壁易带动弹性条的位置发生偏移;通过采用上述技术方案,弹性条嵌设在安装环外侧壁,可实现对弹性条在安装环外侧壁上的限位,减少支撑管内侧壁带动弹性条发生位置偏移的情况。
可选的,所述连接环板侧壁设置有缓冲垫。
通过采用上述技术方案,顶入支撑管时,缓冲垫可对支撑管端壁进行缓冲,减少支撑管端壁与连接环板侧壁之间的刚性接触,减少支撑管端壁发生挤压损坏的情况。
综上所述,本申请包括以下至少一种有益技术效果:
1.通过支撑管的使用,减少了施工人员需进行初期支护结构安装、防水层和二次衬砌施工等操作的情况,减少了施工人员的工作量。
2.连接架构可对轴向相邻的两个支撑管进行限位,提高轴向相邻支撑管之间的位置稳定性。
3.施工人员可在连接洞外侧对两个支撑管进行连接,提高了支撑管之间连接操作的便捷性。
附图说明
图1是本申请实施例中小净距多孔洞暗挖隧道施工工艺的流程图。
图2是本申请实施例中用于体现始发井和接收井位置关系的剖面示意图。
图3是图2中A部分的放大示意图。
图4是本申请实施例中用于体现底板、顶板和支撑柱位置关系的结构示意图。
附图标记说明:1、工作井;11、始发井;12、接收井;13、连接洞;2、支撑管;21、洞口;22、顶板;23、底板;24、支撑柱;3、连接结构;31、连接环板;311、缓冲垫;32、安装环;321、条形连接孔;322、螺栓;323、弹性条;4、千斤顶。
具体实施方式
以下结合附图1-4对本申请作进一步详细说明。
本申请实施例公开小净距多孔洞暗挖隧道施工工艺,参照图1和图2,包括如下步骤:
S1、开挖工作井1:利用挖掘机在隧道规划的长度方向两端的地面开挖工作井1,工作井1包括始发井11和接收井12,利用混凝土在始发井11和接收井12的内侧壁和底壁浇筑成型底板和侧板,以便于后期施工。
S2、开挖连接洞13:利用盾构机从始发井11开始沿隧道长度方向朝接收井12开设若干连接洞13,以实现始发井11和接收井12的连通;若干连接洞13的截面围成环形。
S3、顶入支撑管2:连接洞13阶段性向前开设,连接洞13每开通至一定长度,向洞内顶入一个支撑管2;始发井11远离连接洞13一侧内侧壁设置有千斤顶4,千斤顶4可将支撑管2顶入连接洞13内。
S4、支撑管2连通:安装完支撑管2后,在径向相邻的两个支撑管2的侧壁沿支撑管2长度方向开设洞口21,并挖去径向相邻的两个支撑管2之间的土层,令径向相邻的两个支撑管2连通;在支撑管2靠近两个相邻洞口21处的侧壁焊接固定连接顶板22和底板23,以实现对相邻支撑管2的连接;在支撑管2内通过洞口21进行钢筋捆扎,并沿支撑管2长度方向焊接固定连接钢筋条,钢筋条与绕过洞口21的钢筋相连。
S5、灌注混凝土:向全部支撑管2内灌注混凝土,待混凝土冷却成型后,与支撑管2共同形成一个稳定的钢筋砼,钢筋砼的形成可对支撑管2外侧壁的土层进行支撑。
S6、开挖土方:挖去钢筋砼内的土方,钢筋砼内部空间形成隧道,最后再隧道内施工安装附属结构,即可投入使用。
参照图2和图3,两个轴向相邻的支撑管2之间通过连接结构3相连,连接结构3包括连接环板31和两个安装环32,两个安装环32焊接固定连接在连接环板31两侧侧壁上;移动连接结构3令连接环板31一侧的安装环32***至一个支撑管2内,再令连接环板31另一侧的安装环32***另一个支撑管2内,安装环32侧壁贯穿开设有条形连接孔321,条形连接孔321内贯穿插设有螺栓322,螺栓322靠近支撑管2内侧壁一端与支撑管2内侧壁螺纹连接,即完成对两个支撑管2的连接。安装环32与支撑管2内侧壁间隙配合,螺栓322侧壁与条形连接孔321内侧壁间隙配合,当规划隧道有弧度时,可转动支撑管2,支撑管2带动螺栓322沿条形连接孔321长度方向移动,以实现对支撑管2延伸方向的调节,同时减少对安装环32与支撑管2之间连接的影响。
参照图3,安装环32外侧壁嵌设有弹性条323,弹性条323为弹性橡胶材质,弹性条323与与支撑管2内侧壁相抵;支撑管2转动后,会与连接环板31侧壁之间产生缝隙,支撑管2外侧壁土层会沿着缝隙渗漏到支撑管2内;弹性条323可对支撑管2内部进行封堵,减少支撑管2外侧壁土层渗漏到支撑管2内的情况。
参照图3,连接环板31侧壁通过胶粘固定连接有缓冲垫311,缓冲垫311为弹性橡胶材质,缓冲垫311可对支撑管2端壁进行缓冲,减少支撑管2被顶入连接洞13时支撑管2端壁与连接环板31侧壁之间的刚性接触,减少支撑管2端壁发生挤压损坏的情况。
参照图2和图3,工作井1的宽度大于二倍支撑管2的长度,令施工人员可在连接洞13外部对两个支撑管2进行连接,减少了连接洞13对两个支撑管2连接时的影响,提高了支撑管2之间连接操作的便捷性。
参照图4,顶板22和底板23之间通过焊接固定连接有支撑柱24,支撑柱24为铁柱;支撑柱24的数量在本实施例中为四个,支撑柱24可对顶板22进行支撑,减少压在顶板22上方的土层令顶板22与支撑管2连接处断裂的情况。
本申请实施例小净距多孔洞暗挖隧道施工工艺的实施原理为:
利用挖掘机在隧道规划的长度方向两端的地面开挖始发井11和接收井12,利用混凝土在始发井11和接收井12的内侧壁和底壁浇筑成型底板23和侧板;利用盾构机从始发井11开始沿隧道长度方向朝接收井12阶段性地开设若干连接洞13,连接洞13每开通至一定长度,向洞内顶入一个支撑管2,每顶入一个支撑管2,向始发井11内添加新的支撑管2,并与上一个支撑管2相连。
安装完支撑管2后,在径向相邻的两个支撑管2的侧壁沿支撑杆长度方向开设洞口21,并挖去径向相邻的两个支撑管2之间的土层,令径向相邻的两个支撑管2连通;在支撑管2靠近两个相邻洞口21处的侧壁焊接固定连接顶板22和底板23,对洞口21进行封堵,将支撑柱24焊接固定连接在顶板22和底板23之间,在支撑管2内通过洞口21进行钢筋捆扎,并沿支撑管2长度方向焊接固定连接钢筋条,钢筋条与绕过洞口21的钢筋相连;向全部支撑管2内灌注混凝土,以形成一个稳定的钢筋砼,挖去钢筋砼内的土方,钢筋砼内部空间形成隧道,最后再隧道内施工安装附属结构,即可投入使用。
以上均为本申请的较佳实施例,并非依此限制本申请的保护范围,故:凡依本申请的结构、形状、原理所做的等效变化,均应涵盖于本申请的保护范围之内。
Claims (6)
1.小净距多孔洞暗挖隧道施工工艺,其特征在于:包括以下步骤:
S1、开挖工作井(1):在隧道长度方向两端开挖工作井(1),两个所述工作井(1)包括始发井(11)和接收井(12);
S2、开挖连接洞(13):从始发井(11)开始沿隧道长度方向朝接收井(12)阶段性地开设若干连接洞(13),若干所述连接洞(13)围成环状;
S3、顶入支撑管(2):连接洞(13)每开设完成一个阶段,将一个支撑管(2)顶入连接洞(13)内;两个轴向相邻的所述支撑管(2)之间设置有连接结构(3),两个所述支撑管(2)通过连接结构(3)相连;所述连接结构(3)包括连接环板(31)和两个安装环(32),两个所述安装环(32)位于连接环板(31)两侧,并与连接环板(31)侧壁垂直设置,两个安装环32焊接固定连接在连接环板31两侧侧壁上;所述连接环板(31)侧壁与支撑管(2)端壁相贴,所述安装环(32)插设在支撑管(2)内并与支撑管(2)内侧壁相连;
所述安装环(32)与支撑管(2)内侧壁间隙配合;所述安装环(32)板壁开设有条形连接孔(321),所述条形连接孔(321)内贯穿插设有螺栓(322),螺栓(322)一端与支撑管(2)内侧壁螺纹连接,所述螺栓(322)侧壁与条形连接孔(321)内侧壁间隙配合;当规划隧道有弧度时,可转动支撑管(2),支撑管(2)带动螺栓(322)沿条形连接孔(321)长度方向移动,以实现对支撑管(2)延伸方向的调节,同时减少对安装环(32)与支撑管(2)之间连接的影响;
S4、支撑管(2)连通:将径向相邻的支撑管(2)进行连通,并在支撑管(2)内进行钢筋捆扎;安装完支撑管(2)后,在径向相邻的两个支撑管2的侧壁沿支撑管(2)长度方向开设洞口(21),并挖去径向相邻的两个支撑管(2)之间的土层,令径向相邻的两个支撑管(2)连通;在支撑管(2)靠近两个相邻洞口(21)处的侧壁焊接固定连接顶板(22)和底板(23),以实现对相邻支撑管(2)的连接;在支撑管(2)内通过洞口(21)进行钢筋捆扎,并沿支撑管(2)长度方向焊接固定连接钢筋条,钢筋条与绕过洞口(21)的钢筋相连;
S5、灌注混凝土:向全部支撑管(2)内灌注混凝土,形成钢筋砼;向全部支撑管(2)内灌注混凝土,待混凝土冷却成型后,与支撑管(2)共同形成一个稳定的钢筋砼,钢筋砼的形成可对支撑管(2)外侧壁的土层进行支撑;
S6、开挖土方:开挖钢筋砼内的土方形成隧道。
2.根据权利要求1所述的小净距多孔洞暗挖隧道施工工艺,其特征在于:所述步骤S4中,径向相邻支撑管(2)之间通过顶板(22)和底板(23)对连通处进行封闭,所述顶板(22)和底板(23)之间设置有支撑柱(24)。
3.根据权利要求1所述的小净距多孔洞暗挖隧道施工工艺,其特征在于:所述工作井(1)的宽度大于二倍支撑管(2)的长度。
4.根据权利要求1所述的小净距多孔洞暗挖隧道施工工艺,其特征在于:所述安装环(32)外侧壁设置有弹性条(323),所述弹性条(323)与支撑管(2)内侧壁相抵。
5.根据权利要求4所述的小净距多孔洞暗挖隧道施工工艺,其特征在于:所述弹性条(323)嵌设在安装环(32)外侧壁上。
6.根据权利要求1所述的小净距多孔洞暗挖隧道施工工艺,其特征在于:所述连接环板(31)侧壁设置有缓冲垫(311)。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110935342.2A CN113685187B (zh) | 2021-08-16 | 2021-08-16 | 小净距多孔洞暗挖隧道施工工艺 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110935342.2A CN113685187B (zh) | 2021-08-16 | 2021-08-16 | 小净距多孔洞暗挖隧道施工工艺 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN113685187A CN113685187A (zh) | 2021-11-23 |
CN113685187B true CN113685187B (zh) | 2023-12-01 |
Family
ID=78579970
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110935342.2A Active CN113685187B (zh) | 2021-08-16 | 2021-08-16 | 小净距多孔洞暗挖隧道施工工艺 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113685187B (zh) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114382496A (zh) * | 2022-02-22 | 2022-04-22 | 山西开源益通矿业设备制造有限公司 | 矿用坑道深孔微型盾构设备 |
Citations (47)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR890010389A (ko) * | 1987-12-07 | 1989-08-08 | 스즈끼 유끼오 | 추진력 전달 장치 |
CA1314242C (en) * | 1989-09-29 | 1993-03-09 | Ricky D. Austin | Corrosion protection system for a pipeline crossing |
JPH0718975A (ja) * | 1993-06-23 | 1995-01-20 | Kubota Corp | 推進工法用管の推進力伝達部材およびその取外し治具 |
JPH0941877A (ja) * | 1995-08-01 | 1997-02-10 | Kido Kensetsu Kogyo Kk | 曲線推進用凾渠 |
JPH09119287A (ja) * | 1995-10-25 | 1997-05-06 | Fukudagumi:Kk | 横孔穿設工法に使用する管体及び管部材 |
JPH10331577A (ja) * | 1997-05-28 | 1998-12-15 | Taiyo Tekko Kk | 管路形成用推進管 |
JPH1122883A (ja) * | 1997-07-04 | 1999-01-26 | Toyo Tire & Rubber Co Ltd | 推進管の撓み継手 |
JPH1137344A (ja) * | 1997-07-24 | 1999-02-12 | Awaji Sangyo Kk | パイプの高強度接続方法及び接続装置 |
JP2000035169A (ja) * | 1998-05-15 | 2000-02-02 | Kurimoto Concrete Kogyo Kk | 可撓性推進管 |
KR20000031350A (ko) * | 1998-11-05 | 2000-06-05 | 이계철 | 곡선터널 굴착용 추진관의 하중분산 장치 |
JP2001246613A (ja) * | 2000-03-06 | 2001-09-11 | Tokyo Electric Power Co Inc:The | さや管向け推進管の製造方法、さや管向け推進管製造型枠およびさや管向け推進管 |
JP2002155911A (ja) * | 2000-11-17 | 2002-05-31 | Kao Corp | パイプの連結構造 |
JP2002327591A (ja) * | 2001-04-27 | 2002-11-15 | Yachiyo Engineering Co Ltd | 推進工法及びその工法に用いる推進管 |
KR20030038237A (ko) * | 2001-11-10 | 2003-05-16 | 김정윤 | 지하터널 형성용 구조물 설치방법 및 그 구조 |
JP2004324185A (ja) * | 2003-04-24 | 2004-11-18 | Data Tou:Kk | パイプルーフ |
JP2005009674A (ja) * | 2003-05-22 | 2005-01-13 | Kitakyushu Foundation For The Advancement Of Industry Science & Technology | 可撓管用櫛歯型継手及びそれを用いたヒューム管の連結構造並びにその施工方法 |
JP2005048886A (ja) * | 2003-07-29 | 2005-02-24 | Aso Shoji Kk | 管用可撓性継手 |
JP2005090154A (ja) * | 2003-09-19 | 2005-04-07 | Victaulic Co Of Japan Ltd | 推進工法用管路および推進工法用推進管の伸縮可撓継手 |
JP2005240509A (ja) * | 2004-02-27 | 2005-09-08 | Kurimoto Concrete Industries Ltd | 可撓性小口径推進管およびその推進工法 |
JP3711414B1 (ja) * | 2004-03-31 | 2005-11-02 | 財団法人北九州産業学術推進機構 | 可撓管 |
KR20070075067A (ko) * | 2006-01-12 | 2007-07-18 | 이병택 | 터널의 축조 공법 및 그 시공장치 |
TW200844356A (en) * | 2007-04-27 | 2008-11-16 | Disco Corp | Pipe joint |
KR20090032664A (ko) * | 2007-09-28 | 2009-04-01 | 이인덕 | 비닐하우스용 파이프 연결구 |
KR200447760Y1 (ko) * | 2009-02-26 | 2010-02-16 | 윤용수 | 지반 변위 계측용 파이프의 이음구 |
JP2010095915A (ja) * | 2008-10-16 | 2010-04-30 | Mcl Corporation:Kk | 低耐荷力方式の長距離推進工法 |
WO2013155172A1 (en) * | 2012-04-10 | 2013-10-17 | Tor Persson | Bending restrictor assembly for use with a pipeline section |
CN104653188A (zh) * | 2015-02-04 | 2015-05-27 | 北京市政建设集团有限责任公司 | 一种在暗挖风道内设置大直径盾构接收和始发井的方法 |
CN205097137U (zh) * | 2015-10-16 | 2016-03-23 | 天津鑫恒源科技发展有限公司 | 一种用于更换密封件的工具 |
CN105863683A (zh) * | 2016-05-31 | 2016-08-17 | 中铁第四勘察设计院集团有限公司 | 大断面隧道纵环梁预支护结构 |
CN106014460A (zh) * | 2016-06-14 | 2016-10-12 | 中铁隧道勘测设计院有限公司 | 一种顶推式地下空间群构建方法及应用 |
CN106351670A (zh) * | 2016-10-25 | 2017-01-25 | 中铁第四勘察设计院集团有限公司 | 一种封闭的预支护隧道结构 |
CN106437781A (zh) * | 2016-10-25 | 2017-02-22 | 中铁第四勘察设计院集团有限公司 | 一种上软下硬地层隧道支护结构及其施工方法 |
CN107620600A (zh) * | 2017-07-27 | 2018-01-23 | 广州市市政工程设计研究总院 | 一种mjs工法和管幕法联合支护大断面小净距暗挖工法 |
CN206972245U (zh) * | 2017-06-27 | 2018-02-06 | 中铁工程装备集团有限公司 | 矩形曲线管幕掘进机 |
CN108386608A (zh) * | 2018-05-02 | 2018-08-10 | 广东中科华冉智网科技有限公司 | 小管径塑料排水管顶管机具及塑料排水管顶管施工方法 |
CN108930544A (zh) * | 2018-07-27 | 2018-12-04 | 中铁十四局集团有限公司 | 一种松软地层地下大空间建造方法 |
CN109084105A (zh) * | 2018-10-26 | 2018-12-25 | 江苏格睿特管网工程有限公司 | 钢筋混凝土推进管环槽型接头连接结构 |
CN109488314A (zh) * | 2018-12-30 | 2019-03-19 | 中铁十四局集团有限公司 | 管幕施工方法 |
CN109538248A (zh) * | 2018-12-30 | 2019-03-29 | 中铁十四局集团有限公司 | 管幕结构 |
CN109630162A (zh) * | 2018-12-24 | 2019-04-16 | 中铁十八局集团有限公司 | 一种基于超前支护的重型钢与管幕快速连接的方法 |
CN109723443A (zh) * | 2018-12-30 | 2019-05-07 | 中铁十四局集团有限公司 | 隧道施工方法 |
CN210509213U (zh) * | 2019-06-17 | 2020-05-12 | 中铁七局集团有限公司 | 一种小净距隧道中岩柱加固*** |
KR20200109663A (ko) * | 2019-03-14 | 2020-09-23 | 곽현수 | 덕트 일체형 방화 슬리브 |
CN111911168A (zh) * | 2020-09-04 | 2020-11-10 | 石家庄铁道大学 | 浅埋暗挖大跨度隧道的施工方法及永久支护体系 |
CN112593946A (zh) * | 2020-12-16 | 2021-04-02 | 北京市政建设集团有限责任公司 | 一种小净距多孔洞暗挖隧道近接施工方法 |
CN112879660A (zh) * | 2021-01-28 | 2021-06-01 | 安徽唐兴机械装备有限公司 | 一种适用于顶管的中继间 |
CN113027466A (zh) * | 2021-03-30 | 2021-06-25 | 中交一公局集团有限公司 | 极小净距隧道暗挖施工工艺 |
-
2021
- 2021-08-16 CN CN202110935342.2A patent/CN113685187B/zh active Active
Patent Citations (47)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR890010389A (ko) * | 1987-12-07 | 1989-08-08 | 스즈끼 유끼오 | 추진력 전달 장치 |
CA1314242C (en) * | 1989-09-29 | 1993-03-09 | Ricky D. Austin | Corrosion protection system for a pipeline crossing |
JPH0718975A (ja) * | 1993-06-23 | 1995-01-20 | Kubota Corp | 推進工法用管の推進力伝達部材およびその取外し治具 |
JPH0941877A (ja) * | 1995-08-01 | 1997-02-10 | Kido Kensetsu Kogyo Kk | 曲線推進用凾渠 |
JPH09119287A (ja) * | 1995-10-25 | 1997-05-06 | Fukudagumi:Kk | 横孔穿設工法に使用する管体及び管部材 |
JPH10331577A (ja) * | 1997-05-28 | 1998-12-15 | Taiyo Tekko Kk | 管路形成用推進管 |
JPH1122883A (ja) * | 1997-07-04 | 1999-01-26 | Toyo Tire & Rubber Co Ltd | 推進管の撓み継手 |
JPH1137344A (ja) * | 1997-07-24 | 1999-02-12 | Awaji Sangyo Kk | パイプの高強度接続方法及び接続装置 |
JP2000035169A (ja) * | 1998-05-15 | 2000-02-02 | Kurimoto Concrete Kogyo Kk | 可撓性推進管 |
KR20000031350A (ko) * | 1998-11-05 | 2000-06-05 | 이계철 | 곡선터널 굴착용 추진관의 하중분산 장치 |
JP2001246613A (ja) * | 2000-03-06 | 2001-09-11 | Tokyo Electric Power Co Inc:The | さや管向け推進管の製造方法、さや管向け推進管製造型枠およびさや管向け推進管 |
JP2002155911A (ja) * | 2000-11-17 | 2002-05-31 | Kao Corp | パイプの連結構造 |
JP2002327591A (ja) * | 2001-04-27 | 2002-11-15 | Yachiyo Engineering Co Ltd | 推進工法及びその工法に用いる推進管 |
KR20030038237A (ko) * | 2001-11-10 | 2003-05-16 | 김정윤 | 지하터널 형성용 구조물 설치방법 및 그 구조 |
JP2004324185A (ja) * | 2003-04-24 | 2004-11-18 | Data Tou:Kk | パイプルーフ |
JP2005009674A (ja) * | 2003-05-22 | 2005-01-13 | Kitakyushu Foundation For The Advancement Of Industry Science & Technology | 可撓管用櫛歯型継手及びそれを用いたヒューム管の連結構造並びにその施工方法 |
JP2005048886A (ja) * | 2003-07-29 | 2005-02-24 | Aso Shoji Kk | 管用可撓性継手 |
JP2005090154A (ja) * | 2003-09-19 | 2005-04-07 | Victaulic Co Of Japan Ltd | 推進工法用管路および推進工法用推進管の伸縮可撓継手 |
JP2005240509A (ja) * | 2004-02-27 | 2005-09-08 | Kurimoto Concrete Industries Ltd | 可撓性小口径推進管およびその推進工法 |
JP3711414B1 (ja) * | 2004-03-31 | 2005-11-02 | 財団法人北九州産業学術推進機構 | 可撓管 |
KR20070075067A (ko) * | 2006-01-12 | 2007-07-18 | 이병택 | 터널의 축조 공법 및 그 시공장치 |
TW200844356A (en) * | 2007-04-27 | 2008-11-16 | Disco Corp | Pipe joint |
KR20090032664A (ko) * | 2007-09-28 | 2009-04-01 | 이인덕 | 비닐하우스용 파이프 연결구 |
JP2010095915A (ja) * | 2008-10-16 | 2010-04-30 | Mcl Corporation:Kk | 低耐荷力方式の長距離推進工法 |
KR200447760Y1 (ko) * | 2009-02-26 | 2010-02-16 | 윤용수 | 지반 변위 계측용 파이프의 이음구 |
WO2013155172A1 (en) * | 2012-04-10 | 2013-10-17 | Tor Persson | Bending restrictor assembly for use with a pipeline section |
CN104653188A (zh) * | 2015-02-04 | 2015-05-27 | 北京市政建设集团有限责任公司 | 一种在暗挖风道内设置大直径盾构接收和始发井的方法 |
CN205097137U (zh) * | 2015-10-16 | 2016-03-23 | 天津鑫恒源科技发展有限公司 | 一种用于更换密封件的工具 |
CN105863683A (zh) * | 2016-05-31 | 2016-08-17 | 中铁第四勘察设计院集团有限公司 | 大断面隧道纵环梁预支护结构 |
CN106014460A (zh) * | 2016-06-14 | 2016-10-12 | 中铁隧道勘测设计院有限公司 | 一种顶推式地下空间群构建方法及应用 |
CN106351670A (zh) * | 2016-10-25 | 2017-01-25 | 中铁第四勘察设计院集团有限公司 | 一种封闭的预支护隧道结构 |
CN106437781A (zh) * | 2016-10-25 | 2017-02-22 | 中铁第四勘察设计院集团有限公司 | 一种上软下硬地层隧道支护结构及其施工方法 |
CN206972245U (zh) * | 2017-06-27 | 2018-02-06 | 中铁工程装备集团有限公司 | 矩形曲线管幕掘进机 |
CN107620600A (zh) * | 2017-07-27 | 2018-01-23 | 广州市市政工程设计研究总院 | 一种mjs工法和管幕法联合支护大断面小净距暗挖工法 |
CN108386608A (zh) * | 2018-05-02 | 2018-08-10 | 广东中科华冉智网科技有限公司 | 小管径塑料排水管顶管机具及塑料排水管顶管施工方法 |
CN108930544A (zh) * | 2018-07-27 | 2018-12-04 | 中铁十四局集团有限公司 | 一种松软地层地下大空间建造方法 |
CN109084105A (zh) * | 2018-10-26 | 2018-12-25 | 江苏格睿特管网工程有限公司 | 钢筋混凝土推进管环槽型接头连接结构 |
CN109630162A (zh) * | 2018-12-24 | 2019-04-16 | 中铁十八局集团有限公司 | 一种基于超前支护的重型钢与管幕快速连接的方法 |
CN109488314A (zh) * | 2018-12-30 | 2019-03-19 | 中铁十四局集团有限公司 | 管幕施工方法 |
CN109538248A (zh) * | 2018-12-30 | 2019-03-29 | 中铁十四局集团有限公司 | 管幕结构 |
CN109723443A (zh) * | 2018-12-30 | 2019-05-07 | 中铁十四局集团有限公司 | 隧道施工方法 |
KR20200109663A (ko) * | 2019-03-14 | 2020-09-23 | 곽현수 | 덕트 일체형 방화 슬리브 |
CN210509213U (zh) * | 2019-06-17 | 2020-05-12 | 中铁七局集团有限公司 | 一种小净距隧道中岩柱加固*** |
CN111911168A (zh) * | 2020-09-04 | 2020-11-10 | 石家庄铁道大学 | 浅埋暗挖大跨度隧道的施工方法及永久支护体系 |
CN112593946A (zh) * | 2020-12-16 | 2021-04-02 | 北京市政建设集团有限责任公司 | 一种小净距多孔洞暗挖隧道近接施工方法 |
CN112879660A (zh) * | 2021-01-28 | 2021-06-01 | 安徽唐兴机械装备有限公司 | 一种适用于顶管的中继间 |
CN113027466A (zh) * | 2021-03-30 | 2021-06-25 | 中交一公局集团有限公司 | 极小净距隧道暗挖施工工艺 |
Non-Patent Citations (2)
Title |
---|
日本顶管所用钢筋混凝土管的标准及试验;市政技术(第03期);全文 * |
盾构隧道60°斜穿地裂缝的变形破坏机制试验研究;胡志平;彭建兵;王启耀;朱启东;赵振荣;;岩石力学与工程学报(第01期);全文 * |
Also Published As
Publication number | Publication date |
---|---|
CN113685187A (zh) | 2021-11-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2020173100A1 (zh) | 加固装置及富水砂砾地层中深基坑局部冷冻加固施工方法 | |
KR101069705B1 (ko) | 강관압입식 지하터널 구조물 형성공법에 있어서의 강관연결용 방수철판의 설치방법 | |
CN109404012B (zh) | Ⅳ~ⅵ级围岩超挖隧道初期支护方法 | |
CN212835416U (zh) | 一种基坑用装配式围护结构 | |
CN113685187B (zh) | 小净距多孔洞暗挖隧道施工工艺 | |
KR101479267B1 (ko) | 터널 벽체를 선시공한 후 터널 내부를 굴착하는 비개착 터널 시공방법 | |
JP4132442B2 (ja) | トンネル施工法 | |
KR20170102397A (ko) | 사각관을 이용한 비개착식 터널굴착공법 | |
KR100989946B1 (ko) | 확폭된 플랜지부를 구비한 티형 가이드부가 형성된 강관을 이용한 비개착식 지중구조물 시공방법 | |
CN112855181B (zh) | 一种先顶管后盾构上下平行叠交隧道构造及其施工方法 | |
CN113513322A (zh) | 一种富水浅埋大断面矩形顶管土压平衡顶进施工方法 | |
CN114635716B (zh) | 一种内置型钢的管棚超前支护方法及其应用 | |
KR20200133548A (ko) | 케이싱 및 파일의 연속연결을 이용한 지중연속벽체 및 그 시공방법 | |
CN110671114B (zh) | 一种回收式圆形竖井支护装置及方法 | |
KR20110019673A (ko) | 터널 비개착 시공방법 및 그 터널구조물 | |
JP7357517B2 (ja) | 推進工法を用いた管路構築工法 | |
JP6019690B2 (ja) | トンネル拡幅工法 | |
CN114352289A (zh) | 一种破除盾构隧道管片矿山法施工区间风井风道及方法 | |
KR100601399B1 (ko) | 분할 메서플레이트를 이용한 메서실드 굴착장치 및 이를이용한 지중터널굴착공법 | |
JPH07331998A (ja) | 地下空洞の構築工法 | |
KR100362810B1 (ko) | 비개착식 터널 구조물 시공장치 및 그에 따른 시공방법 | |
CN212508352U (zh) | 一种基于中立柱与仰拱的盾构隧道扩挖体系 | |
JP6019689B2 (ja) | トンネル拡幅工法 | |
CN218969976U (zh) | 一种适用于顶推法施工连续墙的顶推结构 | |
CN219754531U (zh) | 一种坚硬地质条件下的小断面隧道的开挖支护施工结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |