CN113602155B - Contact net hardware fitting installation and pillar assembling synchronous construction method - Google Patents

Contact net hardware fitting installation and pillar assembling synchronous construction method Download PDF

Info

Publication number
CN113602155B
CN113602155B CN202110746571.XA CN202110746571A CN113602155B CN 113602155 B CN113602155 B CN 113602155B CN 202110746571 A CN202110746571 A CN 202110746571A CN 113602155 B CN113602155 B CN 113602155B
Authority
CN
China
Prior art keywords
installation
construction
support column
hardware
elevation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110746571.XA
Other languages
Chinese (zh)
Other versions
CN113602155A (en
Inventor
张其星
马勇军
张�杰
刘金录
李自力
赵颖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Co Ltd
China Railway 12th Bureau Group Electrification Engineering Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
China Railway 12th Bureau Group Electrification Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, China Railway 12th Bureau Group Electrification Engineering Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN202110746571.XA priority Critical patent/CN113602155B/en
Publication of CN113602155A publication Critical patent/CN113602155A/en
Application granted granted Critical
Publication of CN113602155B publication Critical patent/CN113602155B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B60VEHICLES IN GENERAL
    • B60MPOWER SUPPLY LINES, AND DEVICES ALONG RAILS, FOR ELECTRICALLY- PROPELLED VEHICLES
    • B60M1/00Power supply lines for contact with collector on vehicle
    • B60M1/12Trolley lines; Accessories therefor
    • B60M1/28Manufacturing or repairing trolley lines

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention belongs to the technical field of railway contact network construction, and particularly relates to a synchronous construction method for installation of contact network hardware and erection of a strut, which comprises the following steps: s1, preparing construction; s2, compiling a pillar assembling construction table and a hardware fitting installation construction table; compiling technical and technological intersections according to design requirements, and ensuring that construction technicians master intersections; s3, carrying out foundation pit excavation and foundation pouring construction; s4, measuring parameters; s5, the support column is placed upside down, one end of the support column is lifted through a supporting structure (11), and hardware fitting installation is carried out; s6, assembling and correcting the support column according to the support column assembling construction table, carefully checking the direction of the compression surface of the concrete support column, and adjusting the slope of the support column according to the stress direction; s7, detecting and rechecking. The overhead working capacity of the overhead contact system hardware fitting installation is greatly reduced. The invention has the advantages of simple implementation, small potential safety hazard, high practicability and obvious economic effect.

Description

Contact net hardware fitting installation and pillar assembling synchronous construction method
Technical Field
The invention belongs to the technical field of railway contact net construction, and particularly relates to a synchronous construction method for installation of contact net hardware and erection of a strut.
Background
Railway contact net construction mainly takes high altitude construction as the main, at high altitude construction in-process, needs to take effective measure, reduces the potential safety hazard, reduces the construction degree of difficulty, improves the efficiency of construction. At present, the construction process of the contact net is to complete the support column erection firstly and then carry out the high-altitude hardware fitting installation. After the support is adjusted, measurement is firstly carried out, the hardware installation height and size are determined, then overhead hardware installation operation is carried out, however, the overhead operation efficiency is low, the potential safety hazard is large, and at present, efficiency is improved and the potential safety hazard is reduced mainly by wearing safety helmets and safety belts or adopting special professional tools and equipment.
Disclosure of Invention
The invention aims to provide a construction method for synchronously installing contact net hardware and assembling and constructing a support column, which finishes part of overhead work content on the ground, thereby reducing the occurrence of overhead falling accidents and simultaneously improving the construction efficiency and the process quality.
In order to achieve the purpose, the invention adopts the technical scheme that: a synchronous construction method for installation of contact network hardware and erection of a strut comprises the following steps:
s1, familiarizing drawings and design requirements, and preparing installation materials;
s2, compiling a support column assembly construction table and a hardware fitting installation construction table; compiling technical mating and process mating according to design requirements, and ensuring that construction technicians master the mating;
s3, carrying out foundation pit excavation and foundation pouring construction, placing the bottom plate after the concrete strut foundation pit excavation is finished, and pouring the foundation after the steel column foundation or cup foundation pit excavation is finished;
s4, measuring the upper surface elevation of the concrete strut foundation pit base plate, the surface elevation of the steel column foundation and the bottom elevation of the cup foundation pit, comparing the measured upper surface elevation with the designed rail surface elevation, and determining the position of the rail surface elevation on the strut or the steel column so as to determine the installation position of the hardware fitting with the installation height according to the rail surface elevation;
s5, putting the support columns upside down, lifting one end of each support column through a supporting structure, determining the fitting installation position according to a fitting installation construction table, and then carrying out fitting installation according to technical bottom crossing and process bottom crossing requirements, so that the contact net fittings are fastened in place according to the design torque, the fitting installation directions are uniform, and the installation processes are uniform;
s6, after the hardware fitting is installed, carrying out support column assembly and correction according to a support column assembly construction table, carefully checking the direction of a compression surface of the concrete support column, and adjusting the slope of the support column according to the stress direction;
s7, detection and rechecking: and rechecking and checking the compression surface, the slope of the concrete support and the red line position of the rail surface, and simultaneously checking whether the installation of each support and the hardware fitting is consistent with a construction table and whether the installation process is consistent with the design, if the error of the red line position of the rail surface is more than 100mm, adjusting the hardware fitting.
In the step S4, the calculation formulas of the distance h between the rail surface elevation and the column bottom and the distance h' between the rail surface elevation and the steel column bottom are as follows:
h=h1+h2;
h’=Hg-Hj;
wherein h1 represents the height difference between the pit bottom and the ground elevation, h2 represents the height difference between the ground elevation and the rail surface design elevation, hg represents the rail surface design elevation, and Hj represents the foundation surface elevation.
The hardware fitting comprises a wrist arm lower base, a wrist arm insulator, a wire anchor angle steel, a wire jumper shoulder frame, a wrist arm upper base, an anchor bearing angle steel, an additional lead shoulder frame, an additional lead lower anchor angle steel and a large limit frame.
And in the step S3, the elevation parameter is measured by an RTK measuring instrument.
The support structure is a square timber, and the size of the square timber is adjusted according to the size and the installation position of the installed hardware fitting.
Compared with the prior construction method, the invention has the following beneficial effects: the invention provides a synchronous construction method for installation of contact net hardware and erection of a support column, various hardware, such as additional lead shoulder frames, cantilever bases, rod-type composite insulators, large-limit frames, lower anchor angle steel, jumper shoulder frames, soft crossing fixed angle steel and other contact net hardware can be installed on the ground, and the construction method is compared with the traditional construction method according to the field construction completion amount and personnel investment statistics:
1. hardware fitting installation is carried out in traditional overhead operation, and the hardware fitting installation of each support column needs 0.4 overhead workers and 0.2 ground workers;
2. by adopting the construction technology, the hardware fitting installation is carried out before the support column assembly, and only 0.056 overhead personnel and 0.22 ground personnel are needed for completing the installation of each support column hardware fitting;
by comparison it can be seen that: the total use amount of personnel can be saved by about 50%, the labor cost difference of high-altitude personnel and low-altitude personnel is considered, the labor cost can be saved by about 64%, the economic effect and the construction efficiency are obviously improved, high-altitude operation is basically not needed, and the safety risk is greatly reduced. Therefore, the invention greatly reduces the workload of high-altitude operation, thereby improving the construction efficiency, reducing the safety construction such as high-altitude falling and the like.
Drawings
Fig. 1 is a process flow diagram of a method for synchronously constructing installation of contact network hardware and erection of a support column according to an embodiment of the present invention;
FIG. 2 is a schematic diagram illustrating measurement of parameters of a concrete column according to an embodiment of the present invention;
FIG. 3 is a schematic view of the measurement of parameters of steel columns in the embodiment of the present invention;
FIG. 4 is a schematic view of the placement of the support posts according to an embodiment of the present invention;
fig. 5 is a schematic diagram illustrating installation of an overhead contact system hardware on the ground in the embodiment of the present invention;
fig. 6 is a front view of the synchronous installation of a strut and a contact network fitting in the embodiment of the present invention;
fig. 7 is a front side view of the synchronous installation of the strut and the overhead line system hardware in the embodiment of the invention;
in the figure: 1-a pillar; 2-rail surface red line; 3-the bottom of the foundation pit; 4-a lower wrist-arm base; 5-cantilever rod insulator; 6-line anchor angle steel; 7-jumper shoulder frames; 8-upper base of wrist arm; 9-anchor bearing angle steel; 10-additional lead shoulder frame, 11-supporting structure, 12 foundation pit, 13 foundation pit bottom, 14-steel column and 15-foundation bolt.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below, and it is obvious that the described embodiments are some embodiments of the present invention, but not all embodiments; all other embodiments, which can be obtained by a person skilled in the art without making any creative effort based on the embodiments in the present invention, belong to the protection scope of the present invention.
As shown in fig. 1, an embodiment of the present invention provides a method for installing an overhead line system hardware and constructing a strut assembly synchronously, including the following steps:
s1, familiarizing with drawings and design requirements, and preparing a mounting material.
Before construction, preparation work needs to be done, design drawings and requirements need to be familiar at first, design intentions are convenient to know accurately, whether construction and material equipment have special requirements or not is judged by the project, technical background of the transaction, construction schemes and material planning are accurately carried out, and due to the fact that hardware fitting installation and pillar assembly synchronous construction are required to be achieved, contact net pillars and hardware fitting materials need to arrive at goods synchronously, and the situation that synchronous construction cannot be achieved due to the fact that the materials do not arrive at the goods simultaneously is avoided. The material production cycle is long, so the planning of material and the procurement of material bidding need to be carried out as early as possible.
S2, compiling a support column assembly construction table and a hardware fitting installation construction table; then, technical and technological intersections are compiled according to design requirements, and construction technicians are guaranteed to master intersections.
In order to ensure the accuracy of the pillar assembly and the hardware fitting installation and avoid the error of the hardware fitting installation and the pillar assembly, a pillar assembly and hardware fitting installation construction table is accurately compiled before construction, so that constructors can be guided to take and install materials conveniently. The construction of the assembled struts is shown in Table 1.
TABLE 1 construction table for assembling contact net and support
Figure BDA0003143190490000041
The fitting installation construction table is shown in table 2, the contact net fitting suitable for installation mainly comprises a bracket base, a composite rod type insulator for a bracket, an additional wire shoulder frame, a jumper shoulder frame, a soft crossing fixing angle steel, a wire bearing lower anchoring angle steel, a compensation device, a large limit frame, an additional wire lower anchoring angle steel and the like, and after part of fittings are installed, fitting equipment which is not easy to fix or influences the support column assembly construction should be carried out after the support column assembly is completed, such as bracket assembly, soft crossing, an isolating switch, a lightning arrester and the like.
TABLE 2 contact net hardware fitting installation and construction table
Figure BDA0003143190490000042
After the construction of the support assembly construction table and the hardware fitting installation construction table is finished, technical bottom crossing construction is carried out according to design requirements before construction, meanwhile, the construction process is carried out, and then the technical bottom crossing is carried out step by step, so that all constructors and technicians can be ensured to post after bottom crossing, and therefore, after construction according to the construction method, not only can the construction quality be improved, and the phenomenon of high-altitude reworking in the later period is avoided, but also the construction process is greatly improved.
S3, foundation pit excavation and foundation pouring: and (4) carrying out foundation pit excavation and foundation pouring construction, placing the bottom plate after the concrete strut foundation pit excavation is finished, and pouring the foundation after the steel column foundation or cup foundation pit excavation is finished.
Specifically, the technology is finished at the bottom of the building, after construction conditions are met on the site, foundation pit excavation and foundation pouring can be unfolded, construction is finished before track construction as much as possible, later-stage conflict with track construction is avoided, and construction efficiency is reduced. After the foundation pit of the concrete strut is excavated, the bottom plate is placed. After excavation of the steel column foundation or the cup foundation pit is completed, the foundation can be poured, the foundation surface is smooth, and later parameter measurement and pillar assembly are facilitated.
S4, parameter measurement and calculation: and measuring the upper surface elevation of the concrete pillar foundation pit base plate, the surface elevation of the steel column foundation and the bottom elevation of the cup foundation pit, comparing the measured upper surface elevation with the designed rail surface elevation, and determining the position of the rail surface elevation on the pillar or the steel column so as to determine the installation position of the hardware fitting with the installation height according to the rail surface elevation.
The schematic diagram of the parameter measurement of the concrete pillar foundation pit or the cup foundation pit is shown in fig. 2, and the foundation pit 12 in the diagram can be the concrete pillar foundation pit or the cup foundation pit. The ground elevation H is measured through an RTK measuring instrument, then the height difference H1 between the pit bottom and the ground elevation H is measured through a measuring tape, the height difference between the ground elevation H and the designed rail surface elevation Hg is H2, then the distance between the position of the rail surface elevation (a rail surface red line) and the bottom of the support column is H = H1+ H2, the rail surface red line mark can be made on the support column according to the size, and the hardware fitting installation height can be conveniently measured in the later period.
The schematic diagram of the measurement of the basic parameters of the steel column is shown in fig. 3, the elevation of the basic surface of the steel column is measured by an RTK measuring instrument, the distance between the elevation position (rail surface red line) of the rail surface and the bottom of the steel column is h' = Hg-Hj, the rail surface red line mark can be made on the support according to the size, and the hardware fitting installation height can be conveniently measured at the later stage. When the H-shaped steel column is assembled, the thickness of a bolt needs to be adjusted by considering the bottom of the H-shaped steel column, and the red line error of the rail surface is reduced as much as possible.
Specifically, the calculation formula of the distance h between the rail surface elevation and the bottom of the support column and the distance h' between the rail surface elevation and the bottom of the steel column is as follows:
h=h1+h2;(1)
h’=Hg-Hj;(2)
wherein h1 represents the height difference between the pit bottom and the ground elevation, h2 represents the height difference between the ground elevation and the rail surface design elevation, hg represents the rail surface design elevation, and Hj represents the foundation surface elevation.
After the data measurement is finished, arrangement and recording are well carried out, and a parameter recording table is shown in table 3.
Table 3: parameter measuring meter
Figure BDA0003143190490000061
S5, hardware fitting installation: confirm the gold utensil mounted position, then put the pillar down and put to fill up pillar one end through bearing structure 11, confirm the gold utensil mounted position according to gold utensil installation construction table, then hand over the end and carry out the gold utensil installation according to the technique according to the end of handing over and the end requirement is handed over to the technology, ensure that the contact net gold utensil fastens according to design moment and targets in place, the gold utensil installation orientation is unified, and the installation technology is unified.
After the pillar is transported to the scene, put the pillar according to gold utensil mounted position and direction to adopt bearing structure 11 with the pillar to fill up it, the installation of bolt and back angle steel when the gold utensil of being convenient for is installed, the schematic diagram is put to the pillar is shown in figure 4, and bearing structure's position and size should be according to the nimble adjustment of gold utensil size and mounted position, and when two cantilever bases were installed, the space in pillar lower part should satisfy two cantilever sizes. In particular, in this embodiment, the support structure may be a square timber.
After the red line position of the rail surface of the support column is determined according to the table 3, the position and the installation direction of the corresponding hardware on the support column are determined according to the installation and construction table of the contact network hardware in the table 2. After the fitting installation position and direction are determined, fitting installation can be carried out according to the requirements of technical intersection and process intersection, the contact net fitting is ensured to be fastened in place according to the design torque, the fitting installation direction is uniform, the installation process is uniform, and the process quality is ensured.
Specifically, the hardware comprises a wrist arm lower base 4, a wrist arm insulator 5, a wire anchor angle steel 6, a jumper shoulder frame 7, a wrist arm upper base 8, an anchor bearing angle steel 9 and an additional lead shoulder frame 10. Fig. 5 is a schematic view of the metal fitting of this embodiment after the metal fitting is completed.
S6, assembling the support.
After the hardware fitting is installed, the support post is assembled and corrected according to the support post assembly construction table, the direction of the compression surface of the concrete support post is carefully checked, and the slope of the support post is adjusted according to the stress direction. As shown in fig. 6 to 7, the structure of the present embodiment is schematically illustrated after the support is assembled.
S7, detection and rechecking: and after the support column is assembled, rechecking and checking the compression surface, the slope of the support column and the red line position of the rail surface of the concrete support column, simultaneously checking whether the installation of each support column and the hardware fitting is consistent with a construction table or not, and checking whether the installation process is consistent with the design or not, and if the error of the red line position of the rail surface is greater than 100mm, adjusting the hardware fitting.
According to the field construction completion amount and the personnel investment statistics, the construction method of the invention is compared with the traditional construction method:
1. hardware fitting installation is carried out in traditional overhead operation, and the hardware fitting installation of each support column needs 0.4 overhead workers and 0.2 ground workers;
2. by adopting the construction technology, the hardware fitting installation is carried out before the support column assembly, and only 0.056 overhead personnel and 0.22 ground personnel are needed for completing the installation of each support column hardware fitting;
by comparison it can be seen that: the total use amount of personnel can be saved by about 50%, the labor cost can be saved by about 64% by considering the labor cost difference of high-altitude personnel and low-altitude personnel, therefore, the construction method provided by the invention has the advantages that the economic effect and the construction efficiency are obviously improved, high-altitude operation is basically not needed, and the safety risk is greatly reduced.
Finally, it should be noted that: the above embodiments are only used to illustrate the technical solution of the present invention, and not to limit the same; while the invention has been described in detail and with reference to the foregoing embodiments, it will be understood by those skilled in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some or all of the technical features may be equivalently replaced; and the modifications or the substitutions do not make the essence of the corresponding technical solutions depart from the scope of the technical solutions of the embodiments of the present invention.

Claims (5)

1. A contact net hardware fitting installation and pillar assembling synchronous construction method is characterized by comprising the following steps:
s1, familiarizing drawings and design requirements, and preparing installation materials;
s2, compiling a pillar assembling construction table and a hardware fitting installation construction table; compiling technical mating and process mating according to design requirements, and ensuring that construction technicians master the mating;
s3, carrying out foundation pit excavation and foundation pouring construction, placing the bottom plate after the concrete strut foundation pit excavation is finished, and pouring the foundation after the steel column foundation or cup foundation pit excavation is finished;
s4, measuring the upper surface elevation of the concrete strut foundation pit base plate, the surface elevation of the steel column foundation and the bottom elevation of the cup foundation pit, comparing the measured upper surface elevation with the designed rail surface elevation, determining the position of the rail surface elevation on the strut or the steel column, and marking the rail surface elevation as a rail surface red line, so that the installation position of the hardware fitting is determined according to the rail surface elevation;
s5, the support is laid down and placed, one end of the support is lifted through the supporting structure (11), and hardware fitting installation is carried out according to the hardware fitting installation position and direction and the technical cross bottom and process cross bottom requirements, so that the contact net hardware fitting is fastened in place according to the design torque, the hardware fitting installation direction is uniform, and the installation process is uniform;
s6, after the hardware fitting is installed, assembling and correcting the support column according to a support column assembling construction table, carefully checking the direction of a compression surface of the concrete support column, and adjusting the slope of the support column according to the stress direction;
s7, detection and rechecking: and (4) rechecking and checking the compression surface, the slope of the concrete strut and the red line position of the rail surface, checking whether the installation of each strut and the hardware fittings is consistent with a construction table, and checking whether the installation process is consistent with the design, if the position error of the red line of the rail surface is greater than 100mm, adjusting the hardware fittings.
2. The method for synchronously constructing the installation of the overhead line system hardware and the erection of the support column according to claim 1, wherein in the step S4, the calculation formulas of the distance h between the rail surface elevation and the bottom of the support column and the distance h' between the rail surface elevation and the bottom of the steel column are as follows:
h=h1+h2;
h’=Hg-Hj;
wherein h1 represents the height difference between the pit bottom and the ground elevation, h2 represents the height difference between the ground elevation and the rail surface design elevation, hg represents the rail surface design elevation, and Hj represents the foundation surface elevation.
3. The synchronous construction method for installation of the contact net hardware and assembly of the support column according to claim 1, wherein the hardware comprises a lower wrist arm base (4), a wrist arm insulator (5), a wire anchor angle steel (6), a jumper shoulder frame (7), an upper wrist arm base (8), an anchor angle steel (9) and an additional wire shoulder frame (10).
4. The method for synchronously constructing the installation of the overhead line system hardware and the erection of the support column according to claim 1, wherein in the step S4, the high-range parameter is measured by an RTK measuring instrument.
5. The synchronous construction method for installation of the contact net hardware and erection of the support column according to claim 1, wherein the support structure (11) is a square timber, and the size of the square timber is adjusted according to the size and the installation position of the installed hardware.
CN202110746571.XA 2021-07-01 2021-07-01 Contact net hardware fitting installation and pillar assembling synchronous construction method Active CN113602155B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110746571.XA CN113602155B (en) 2021-07-01 2021-07-01 Contact net hardware fitting installation and pillar assembling synchronous construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110746571.XA CN113602155B (en) 2021-07-01 2021-07-01 Contact net hardware fitting installation and pillar assembling synchronous construction method

Publications (2)

Publication Number Publication Date
CN113602155A CN113602155A (en) 2021-11-05
CN113602155B true CN113602155B (en) 2023-02-10

Family

ID=78337159

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110746571.XA Active CN113602155B (en) 2021-07-01 2021-07-01 Contact net hardware fitting installation and pillar assembling synchronous construction method

Country Status (1)

Country Link
CN (1) CN113602155B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2644218Y (en) * 2003-07-16 2004-09-29 石家庄同力铁路供电设备技术有限公司 Combined type overhead contact line equipment pillar for electrified railroad
CN101327748A (en) * 2008-06-18 2008-12-24 中铁十一局集团电务工程有限公司 Method for calculating and installing high-speed rail electrification catenary wrist-arm
CN105275251A (en) * 2014-12-30 2016-01-27 中国铁建电气化局集团第五工程有限公司 Railway existing line overhead line system hard crossbeam erection method
CN107084835A (en) * 2017-05-04 2017-08-22 中铁十二局集团有限公司 A kind of bracket pre-configuration data detection means and its detection method
WO2018086602A1 (en) * 2016-11-11 2018-05-17 成都国佳电气工程有限公司 Insulated and composite overhead-contact-system supporting apparatus

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2644218Y (en) * 2003-07-16 2004-09-29 石家庄同力铁路供电设备技术有限公司 Combined type overhead contact line equipment pillar for electrified railroad
CN101327748A (en) * 2008-06-18 2008-12-24 中铁十一局集团电务工程有限公司 Method for calculating and installing high-speed rail electrification catenary wrist-arm
CN105275251A (en) * 2014-12-30 2016-01-27 中国铁建电气化局集团第五工程有限公司 Railway existing line overhead line system hard crossbeam erection method
WO2018086602A1 (en) * 2016-11-11 2018-05-17 成都国佳电气工程有限公司 Insulated and composite overhead-contact-system supporting apparatus
CN107084835A (en) * 2017-05-04 2017-08-22 中铁十二局集团有限公司 A kind of bracket pre-configuration data detection means and its detection method

Also Published As

Publication number Publication date
CN113602155A (en) 2021-11-05

Similar Documents

Publication Publication Date Title
CN1978801B (en) Super-span steel skew arch construction method
CN111042539A (en) Single-point support installation construction method for large-span steel structure truss
CN106638318B (en) The localization method and cable guide pipe installation method of cable-stayed bridge beam-ends anchor point
CN110219326A (en) The underwater vertical adjustment construction technology of inverse method one-column one-pile
CN107090775A (en) A kind of full framing space beam-ends cable guide pipe construction localization method
CN102828469A (en) Positioning mounting construction method for triangular steel constructed pillar of inclined-leg steel box
CN210441865U (en) Urban road bridge road bed engineering measuring equipment
CN113602155B (en) Contact net hardware fitting installation and pillar assembling synchronous construction method
CN206722425U (en) Adjustable conveniently-detachable parallel chord truss assembling jig frame
CN110241735B (en) Positioning and adjusting device and method for main tower cable guide pipe of cable-stayed bridge
CN210507148U (en) Positioning and adjusting device for main tower cable guide pipe of cable-stayed bridge
CN107620270A (en) Portable positioning die carrier and its application method for guardrail reinforcing bar colligation
CN109137963A (en) Fixing bracket body and its construction method for foundation bolt group positioning
CN116446293A (en) Construction method of concrete beam cable guide pipe of cable-stayed bridge
CN105735228A (en) Construction method and installation accuracy control method of rack systems of high-lift rack climbing type ship lift
CN212477455U (en) Pre-buried positioner of bridge suspension cable anchor cylinder
CN110685306B (en) Positioning and measuring method for Y-shaped steel structural column of subway open-cut station
CN114030394A (en) Subway contact net full-parameter trackless measurement construction method
CN210622423U (en) Welded connection's hard crossbeam of contact net
CN206554273U (en) A kind of pre-assembled Anchor Bolts in Steel Column Bases structure
CN214993151U (en) Accurate quick positioner of short tower cable-stay bridge branch silk pipe cable saddle
CN109826221A (en) A kind of large bridge pile base construction method that pile bearing capacity is high
CN212298225U (en) Measuring instrument fixing support for high-rise frame steel structure
CN202787088U (en) Embedded template structure for cable sleeve of main beam of stayed-cable bridge
CN212742615U (en) Lightning rod basic embedded part positioning and fixing device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant