CN113346409A - Uninterrupted power operation method for load transfer maintenance of 10kV outgoing line interval of transformer substation - Google Patents

Uninterrupted power operation method for load transfer maintenance of 10kV outgoing line interval of transformer substation Download PDF

Info

Publication number
CN113346409A
CN113346409A CN202110792232.5A CN202110792232A CN113346409A CN 113346409 A CN113346409 A CN 113346409A CN 202110792232 A CN202110792232 A CN 202110792232A CN 113346409 A CN113346409 A CN 113346409A
Authority
CN
China
Prior art keywords
line
equipment
maintenance
bypass
power
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110792232.5A
Other languages
Chinese (zh)
Inventor
刘小立
周伟民
刘卫东
匡志旭
张玉民
张小兵
熊亚涛
吕晓东
董明涛
段发强
师亚杰
王军
程新幽
王得道
刘智强
李闯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Pingdingshan Power Supply Co of State Grid Henan Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Pingdingshan Power Supply Co of State Grid Henan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Pingdingshan Power Supply Co of State Grid Henan Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN202110792232.5A priority Critical patent/CN113346409A/en
Publication of CN113346409A publication Critical patent/CN113346409A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/007Arrangements for selectively connecting the load or loads to one or several among a plurality of power lines or power sources
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/04Circuit arrangements for ac mains or ac distribution networks for connecting networks of the same frequency but supplied from different sources
    • H02J3/06Controlling transfer of power between connected networks; Controlling sharing of load between connected networks

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention belongs to the technical field of electric power overhaul, and particularly relates to a non-power-outage operation method for load transfer overhaul at 10kV outgoing line intervals of a transformer substation, which comprises the following steps: s1, surveying and detecting equipment to be overhauled and a line where the equipment is located, and selecting a bypass line access point; s2, detecting and evaluating the adjacent line; s3, connecting a cable of the bypass line to a line connected with the equipment to be overhauled from an adjacent line, and closing a bypass line switch; s4, disconnecting a high-voltage disconnecting link of a circuit connected with the maintenance equipment, and stopping power at intervals when the bus is outgoing by the maintenance personnel of the transformer substation to start power-off maintenance work; and S5, finishing the equipment maintenance work, closing the high-voltage disconnecting link of the line connecting circuit at the line outlet interval, and disconnecting and removing the bypass line connection to recover each connecting circuit after confirming that the maintenance equipment and the line thereof operate normally. The method utilizes the bypass to realize the transfer of the interval load under the condition that the line side implements the whole line user without power failure.

Description

Uninterrupted power operation method for load transfer maintenance of 10kV outgoing line interval of transformer substation
Technical Field
The invention belongs to the technical field of electric power overhaul, and particularly relates to a non-power-off operation method for load transfer overhaul at 10kV outgoing line intervals of a transformer substation.
Background
When the 10kV outgoing line interval traditional power failure maintenance of the transformer substation is carried out, the line carried by the equipment is stopped, the outgoing line interval is powered off, the whole line is stopped, individual 10kV users are stopped, the load loss of the line cannot be estimated, the power supply reliability is reduced, the assessment index is influenced, the power failure influences the life of the users, the economy suffers from loss, resources are wasted, and the social situation of energy conservation, efficiency improvement, energy conservation and emission reduction at present is not met.
The invention patent of publication number CN112132300A discloses a transformer substation maintenance method, device and system, which comprises the steps of constructing a maintenance work flow according to a maintenance task, and sending a maintenance subtask to an operation terminal according to a work node of the maintenance work flow; receiving a maintenance result, sending an approval request and receiving an approval result; judging whether the approval result passes, if so, entering the next working node, and otherwise, sending a refund instruction to the current working node to receive the updated overhaul result; and traversing the maintenance work flow until the approval results of all the work nodes approved are received, storing the corresponding maintenance results into a maintenance work database, and calling and displaying the maintenance results of the related maintenance tasks in the maintenance work database by constructing indexes. Covering the transformer substation maintenance overall process with digital means, overhauing and approving every work node in proper order, controlling each link of maintenance work, mastering every maintainer's operating condition, solving the supervision problem in the current transformer substation maintenance work, the research that the maintenance process that this patent was directed to goes on does not consider the influence that the maintenance process has a power failure and causes.
The invention patent of publication number CN103427367B discloses a power transmission line maintenance method, which comprises the following steps: carrying out state detection on each line unit in the power transmission line, and recording a detection result; calculating a risk value of the power transmission line according to the recorded detection result; multiplying the risk value by a weight coefficient corresponding to the power transmission line, and calculating a comprehensive risk value of the power transmission line; and executing a corresponding maintenance plan for the power transmission line according to the calculated comprehensive risk value. The invention can preset corresponding weight coefficients according to the characteristics and the actual conditions of the power transmission line, multiplies the risk value of the power transmission line by the corresponding weight coefficient of the power transmission line, calculates the comprehensive risk value of the power transmission line, and then executes a corresponding maintenance plan for the power transmission line according to the calculated comprehensive risk value. The invention considers the defects in the maintenance work of the transmission line, carries out research and design aiming at the defects, and does not consider the influence of the maintenance power failure on the maintenance work.
Disclosure of Invention
The invention aims to provide a non-power-off operation method for load transfer and overhaul of a 10kV outgoing line interval of a transformer substation, aiming at solving the problems in the prior art.
The technical scheme of the invention is as follows:
the uninterrupted power operation method for load transfer maintenance of 10kV outgoing line intervals of the transformer substation comprises the following steps:
s1, firstly, carrying out early-stage investigation and detection on equipment to be overhauled and a line where the equipment is located, selecting a bypass line access point, and approaching a normally-running line suitable for supplying power to the line to be overhauled;
s2, detecting and evaluating the adjacent line, detecting whether the adjacent line operates normally or not, wherein the load and current allowed to be borne by the adjacent line meet the requirements, and performing the next step of work when the adjacent line operates normally;
s3, connecting a cable of the bypass system into a line connected with the equipment to be overhauled from an adjacent line, detecting that the connection line where the equipment to be overhauled is located and a bypass line switch are normal in operation, and switching on the bypass line switch to carry out the next step of work;
s4, disconnecting a high-voltage disconnecting link of a circuit connected with the maintenance equipment, and interrupting power supply to the outgoing line of the bus by the maintenance personnel of the transformer substation to start maintenance;
and S5, after the equipment maintenance work is finished, confirming that the operation requirements are met, closing the high-voltage disconnecting link of the adjacent connected line, disconnecting and removing the bypass line connection after the maintenance equipment and the connected line operate normally, and recovering the normal operation of each connecting line.
Specifically, in step S1, the line current detection of the device to be overhauled does not exceed the carrying capacity of the bypass line, and the current range that can be carried does not exceed 200A.
Specifically, the load and current allowed to be carried by the adjacent line in step S2 do not exceed 200A.
Specifically, the current carried by the bypass line is less than 200A.
In the past, the line carried by the equipment is stopped, the load loss of the line is immeasurable, the power supply reliability is reduced, the assessment index is influenced, the power failure affects the life of a user, and the economy suffers from loss. The resources are wasted, and the social situation of energy conservation, efficiency improvement, energy conservation and emission reduction is not met. At present, no one carries out research and countermeasure on the influence caused by power failure, and only the problem and deficiency in the maintenance process are researched and solved, so that the method for maintenance without power failure is omitted.
The principle of the invention is that a 10kV line carried by a bus outgoing interval of a transformer substation is temporarily connected with a bypass of an adjacent distribution line, and after the normal operation, the outgoing interval is disconnected, the line keeps a normal operation state, and the outgoing interval of the transformer substation can be overhauled by power failure.
The invention has the beneficial effects that: the method provided by the invention can keep the line to run in a live way, the maintenance equipment can realize the maintenance without power failure for users, the safety and the reliability are realized, the load loss is less, the power supply reliability is guaranteed, the power failure of the users of the whole line is realized on the side of the line, the comprehensive maintenance range of the transformer substation equipment can be realized, the power supply reliability is greatly improved, and the maintenance mode without power failure at the 10kV outgoing line interval of the transformer substation is more flexible and convenient, and the method develops towards the direction of diversified maintenance.
Detailed Description
The technical solution of the present invention will be described in detail with reference to the specific embodiments.
The invention provides a non-power-off operation method for load transfer maintenance of a 10kV outgoing line interval of a transformer substation, which comprises the following steps of:
s1, firstly, carrying out early investigation and detection on equipment to be overhauled and a line where the equipment is located, selecting a bypass system access point, and approaching a normally-running line suitable for supplying power to the line to be overhauled, wherein the current detection of the line where the equipment to be overhauled is located does not exceed the bearing capacity of the connected bypass line, and the range of the current capable of being borne does not exceed 200A;
s2, detecting and evaluating the adjacent line, detecting whether the adjacent line operates normally or not, wherein the load and current allowed to be borne by the adjacent line meet the requirements, and when the adjacent line operates normally, performing the next step of work, wherein the load and current allowed to be borne by the adjacent line do not exceed 200A;
s3, connecting a cable of the bypass system to a line connected with equipment to be overhauled from an adjacent line, wherein the current carried by the bypass line is less than 200A, the connection line where the equipment to be overhauled is located and a bypass line switch detect normal operation, and the next step of work can be carried out by switching on the bypass line switch;
s4, disconnecting a high-voltage disconnecting link of a circuit connected with the maintenance equipment, and interrupting power supply to the outgoing line of the bus by the maintenance personnel of the transformer substation to start maintenance;
and S5, after the equipment maintenance work is finished, confirming that the operation requirements are met, closing the high-voltage disconnecting link of the adjacent connected line, disconnecting and removing the bypass line connection after the maintenance equipment and the connected line operate normally, and recovering the normal operation of each connecting line.
In the practical operation process, the temporary power supply line has few users, the corresponding load is certainly not large, the current is about 20A-30A, the load of the line to be supplied is not large, the line current is about 30A, the line current and the line current are connected in series to form a total current of 50A-60A, and the load carrying capacity of a bypass system is within 200A.
Finally, it should be noted that the above examples are only used to illustrate the technical solutions of the present invention and not to limit the same; although the present invention has been described in detail with reference to preferred embodiments, those skilled in the art will understand that: modifications to the specific embodiments of the invention or equivalent substitutions for parts of the technical features may be made; without departing from the spirit of the present invention, it is intended to cover all aspects of the invention as defined by the appended claims.

Claims (4)

1. The uninterrupted power operation method for load transfer maintenance of 10kV outgoing line intervals of the transformer substation is characterized by comprising the following steps of:
s1, firstly, carrying out early-stage investigation and detection on equipment to be overhauled and a line where the equipment is located, selecting a bypass line access point, and enabling the access point to be close to a line which runs normally and is suitable for supplying power to a line to be switched;
s2, detecting and evaluating the adjacent line, detecting whether the adjacent line operates normally or not, wherein the load and current allowed to be borne by the adjacent line meet the requirements of a series line, and performing the next step of work when the adjacent line operates normally;
s3, connecting a cable of the bypass line to a line connected with the equipment to be overhauled from an adjacent line, detecting that the line connected with the equipment to be overhauled and the bypass line switch operate normally, and switching on the bypass line switch to carry out the next step of work;
s4, disconnecting a high-voltage disconnecting link of a circuit connected with the maintenance equipment, and interrupting power supply to the outgoing line of the bus by the maintenance personnel of the transformer substation to start maintenance;
and S5, after the equipment maintenance work is finished, confirming that the operation requirements are met, closing the high-voltage disconnecting link of the connected line, disconnecting and removing the bypass line connection after the maintenance equipment and the connected line operate normally, and recovering the normal operation state of each line.
2. The substation 10kV outgoing line interval load transfer maintenance non-power-off operation method according to claim 1, wherein the line current detection of the equipment to be maintained in step S1 does not exceed the carrying capacity of the connected bypass line, and the current value that can be carried does not exceed 200A.
3. The substation 10kV outgoing line interval load transfer maintenance non-power-off operation method according to claim 1, wherein the allowable load and current of the adjacent line in the step S2 are not more than 200A.
4. The substation 10kV outgoing line interval on-load transfer overhaul uninterrupted operation method according to claim 1, characterized in that the current carried by the bypass line is less than 200A.
CN202110792232.5A 2021-07-14 2021-07-14 Uninterrupted power operation method for load transfer maintenance of 10kV outgoing line interval of transformer substation Pending CN113346409A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110792232.5A CN113346409A (en) 2021-07-14 2021-07-14 Uninterrupted power operation method for load transfer maintenance of 10kV outgoing line interval of transformer substation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110792232.5A CN113346409A (en) 2021-07-14 2021-07-14 Uninterrupted power operation method for load transfer maintenance of 10kV outgoing line interval of transformer substation

Publications (1)

Publication Number Publication Date
CN113346409A true CN113346409A (en) 2021-09-03

Family

ID=77479610

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110792232.5A Pending CN113346409A (en) 2021-07-14 2021-07-14 Uninterrupted power operation method for load transfer maintenance of 10kV outgoing line interval of transformer substation

Country Status (1)

Country Link
CN (1) CN113346409A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103812041A (en) * 2014-02-21 2014-05-21 国网湖南省电力公司带电作业中心 Method for overhauling ring main unit of 10kV cable circuit without switching power supply off
CN105406384A (en) * 2015-12-25 2016-03-16 广东电网有限责任公司佛山供电局 Uninterruptible overhaul system for substation equipment and method thereof
CN109787132A (en) * 2018-12-29 2019-05-21 国网山东省电力公司临清市供电公司 A kind of intelligence 10kV septal accessory pathways vehicle and temporary transmission system
CN113054656A (en) * 2021-03-10 2021-06-29 广东电网有限责任公司广州供电局 Distribution transformer overhauling method and device, electronic equipment and storage medium

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103812041A (en) * 2014-02-21 2014-05-21 国网湖南省电力公司带电作业中心 Method for overhauling ring main unit of 10kV cable circuit without switching power supply off
CN105406384A (en) * 2015-12-25 2016-03-16 广东电网有限责任公司佛山供电局 Uninterruptible overhaul system for substation equipment and method thereof
CN109787132A (en) * 2018-12-29 2019-05-21 国网山东省电力公司临清市供电公司 A kind of intelligence 10kV septal accessory pathways vehicle and temporary transmission system
CN113054656A (en) * 2021-03-10 2021-06-29 广东电网有限责任公司广州供电局 Distribution transformer overhauling method and device, electronic equipment and storage medium

Similar Documents

Publication Publication Date Title
WO2019019296A1 (en) On-line checking discharge apparatus and method for storage battery set
CN102611080A (en) Main station type small current grounding control method
CN103138390A (en) Power distribution network fault handling method based on self-recovering control
CN104184151A (en) Dynamic voltage restorer for realizing smooth switching of different operation modes of microgrid
CN111864889B (en) Uninterrupted emergency power supply system and power supply method for open-circuit protection of lead-acid storage battery pack
CN111668940B (en) Power station control system and control method
CN111342534A (en) Storage battery discharge control system and control method thereof
CN110912109A (en) Low-voltage direct-current power supply and distribution equipment and method
CN111865669A (en) Intelligent decision making system and method for power grid fault recovery
CN206712539U (en) A kind of marine low-pressure continuous-current plant based on the autonomous management of multiple batteries
CN106300339B (en) A kind of Fault Isolation based on unit style power distribution network and service restoration method
CN109950822A (en) 110KV one battery one charger scheme direct current system does not have a power failure replacing options
CN107181268A (en) The intelligent phase-change switch and its method of work of anti-phase fault before a kind of energization
CN105322582B (en) The Emergency power supply unit realized using controllable silicon technology
JP3892547B2 (en) Grid-connected distributed power system
CN110441709B (en) Transformer substation direct-current power supply system for monitoring storage battery and charging module and monitoring method
CN109888765B (en) 220KV two-power-supply two-charging direct current system uninterrupted replacement method
CN113346409A (en) Uninterrupted power operation method for load transfer maintenance of 10kV outgoing line interval of transformer substation
CN204885910U (en) Intelligent low tension distribution box
CN117411117A (en) DC power supply module and system, operation and maintenance control method of system and intelligent control platform
CN110783915A (en) Multi-distribution-platform-area power supply method and power supply system
CN215813253U (en) Remote control system for checking capacity of communication power supply storage battery
CN114336980A (en) Intelligent cloud power distribution method and system based on instruction transmission
CN102003373A (en) Joint inspection device of drainage pump and pump station generating set under high-speed rail and in tunnel
CN113820562A (en) Low-voltage direct-current power distribution network fault processing system and method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210903

RJ01 Rejection of invention patent application after publication