CN113323691A - Foundation pit outer tunnel deformation control method based on liquid grout blocking wall - Google Patents

Foundation pit outer tunnel deformation control method based on liquid grout blocking wall Download PDF

Info

Publication number
CN113323691A
CN113323691A CN202110625899.6A CN202110625899A CN113323691A CN 113323691 A CN113323691 A CN 113323691A CN 202110625899 A CN202110625899 A CN 202110625899A CN 113323691 A CN113323691 A CN 113323691A
Authority
CN
China
Prior art keywords
wall
slurry
liquid
foundation pit
deformation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110625899.6A
Other languages
Chinese (zh)
Other versions
CN113323691B (en
Inventor
杜一鸣
刁钰
张立明
谢光耀
何金明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin University
Original Assignee
Tianjin University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin University filed Critical Tianjin University
Priority to CN202110625899.6A priority Critical patent/CN113323691B/en
Publication of CN113323691A publication Critical patent/CN113323691A/en
Application granted granted Critical
Publication of CN113323691B publication Critical patent/CN113323691B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/18Making embankments, e.g. dikes, dams
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention discloses a method for controlling deformation of a tunnel outside a foundation pit based on a liquid-state slurry blocking wall, which adopts the liquid-state slurry blocking wall to replace a traditional rigid blocking system, effectively controls the 'traction effect' of an active area outside the pit, and releases the deformation energy of a displacement field of the active area outside the pit through the shearing deformation of liquid so as to achieve the effect of effectively controlling the deformation of the tunnel outside the foundation pit; and after the foundation pit construction is finished, the liquid blocking slurry wall is subjected to landfill treatment, so that the site is restored to the original state. The novel liquid-state blocking slurry wall provided by the method divides the soil body of the active area outside the pit into 'traction effect' influence areas according to the characteristics of the soil body of the field,a section of liquid-state separation slurry wall taking slurry as a main body is arranged in the slurry wall, and the main stress sigma in the horizontal direction is effectively separated3When the field is spread, the deformation energy of the field is released by adopting liquid shearing deformation, and the horizontal deformation spreading is effectively blocked. Through setting up reasonable design parameter, effectively improve liquid separation thick liquid wall deformation control effect, can effectively reduce engineering cost simultaneously.

Description

Foundation pit outer tunnel deformation control method based on liquid grout blocking wall
Technical Field
The invention belongs to the field of basic engineering and tunnel engineering, and particularly relates to an engineering method for protecting an existing subway tunnel of a city and controlling the deformation development of the existing subway tunnel.
Background
The construction of urban rail transit effectively drives the development and utilization of various peripheral underground spaces, and a large number of deep and large foundation pit engineering projects are continuously emerging. Meanwhile, the foundation pit engineering around the urban rail transit is developing towards the direction of large-depth excavation. When the deep and large foundation pit engineering construction is carried out on the adjacent existing subway tunnel, the tunnel deformation caused by the foundation pit construction is controlled, and the method is a great problem in the foundation pit engineering in weak soil.
In the process of excavation of the foundation pit, the enclosure structure can generate horizontal displacement towards the inner direction of the pit under the combined action of water pressure and soil pressure inside and outside the pit, and simultaneously cause uplift deformation of the bottom of the foundation pit, and influence is generated on the surrounding environment to a certain extent, the influence is firstly expressed as settlement and horizontal displacement of the surface outside the pit, and further coordinated deformation of the existing subway tunnel in the field can be caused. The urban subway tunnel usually adopts shield construction, and the section of jurisdiction of assembling is highly sensitive to the deformation, if design construction is improper, causes too big tunnel deformation, will seriously threaten its operation safety.
In engineering practice, the following two methods are often used for tunnel deformation control: (1) increasing the design rigidity of a foundation pit supporting structure to control the deformation of the foundation pit and further control the deformation of the tunnel; (2) and (4) driving an isolation pile between the foundation pit and the tunnel to carry out the deformation propagation control of the soil body in the active area, thereby achieving the purpose of controlling the deformation of the tunnel. However, the traditional method often has the following problems in the practical process: (1) the traditional method has unclear stress mechanism and is difficult to carry out quantitative design analysis; (2) passive control measures are adopted, the control effect is poor, and the fine control of the whole process of tunnel deformation is difficult; (3) the construction measures are high in manufacturing cost and are mostly permanent measures, and the foundation pit is considered to be a temporary engineering structure, so that the engineering economy is poor.
The traditional design method of the barrier system is usually based on engineering experience, the stress mechanism is unclear, professional quantitative design analysis is difficult to perform, and then the deformation control effect is optimized. Meanwhile, the traditional separation measures mostly adopt a through-long rigid structure design (such as a row pile or an underground continuous wall), the construction cost is high, and the permanent underground structure in the field can not be recycled after the use, so that the economical efficiency is poor. Based on the research results completed by the applicant, the traditional rigid barrier system has a blocking effect on the shallow soil mass of the active region outside the pit and a pulling effect on the deep soil mass of the active region, and the pulling effect of the rigid section has an opposite effect on the horizontal deformation control of the deep tunnel outside the pit.
Disclosure of Invention
In order to solve the problems in the prior art, the invention provides a method for controlling the deformation of a tunnel outside a foundation pit based on a liquid grout blocking wall, which aims to solve the problem of poor tunnel deformation control effect caused by unloading of foundation pit excavation by traditional engineering measures in the background art.
In order to achieve the purpose, the invention provides the following technical scheme:
a deformation control method for a tunnel outside a foundation pit based on a liquid-state slurry blocking wall is characterized in that the liquid-state slurry blocking wall is adopted to replace a traditional rigid blocking system, the 'traction effect' of an active area outside the pit is effectively controlled, and the deformation energy of a displacement field of the active area outside the pit is released through the shearing deformation of liquid; and after the foundation pit construction is finished, the liquid blocking slurry wall is subjected to landfill treatment, so that the site is restored to the original state.
The method specifically comprises the following steps:
(1) determining design parameters of the barrier slurry wall by combining site engineering conditions and site soil conditions; the design parameters comprise the design depth L of the liquid slurry wall, the design width w of the liquid slurry wall, the distance D from the foundation pit support structure, the excavation depth H of the foundation pit, the clear distance D between the tunnel and the foundation pit support structure, the center burial depth S of the tunnel and the internal friction angle of the soil body in the active area of the field
Figure BDA0003102107740000023
Comprehensively determining the design parameters of the barrier slurry wall;
(2) constructing the barrier slurry wall based on the determined design parameters; excavating a separation slurry wall by adopting underground continuous wall excavation grooving equipment, and preparing slurry while excavating; after the construction of the blocking slurry wall is finished, preparing slurry in the blocking slurry wall, and sealing the top of the blocking slurry wall by using a steel plate;
(3) and excavating the foundation pit, and after the excavation of the foundation pit is finished and the tunnel is deformed stably, carrying out backfill construction on the separation slurry wall.
Determining a position parameter D of the blocking slurry wall according to the clear distance D between the tunnel and the foundation pit support structure, wherein when the D is 0.6-0.8D, the deformation control effect of the blocking slurry wall is obvious; secondly, determining the design depth L of the barrier slurry wall, and working according to the stress diffusion angle of the soil body in the field
Figure BDA0003102107740000021
When the control effect is optimal, the blocking paste wall reaches the optimal control effect if the control effect is optimal
Figure BDA0003102107740000022
At this time, the value L is equal to S; and finally, determining the design width w of the barrier slurry wall according to the excavation depth H of the foundation pit, and taking w as (0.1-0.12). H, so that the deformation control effect of the barrier slurry wall can be maximized.
And (2) preparing the slurry by adopting water, cement and bentonite, wherein the bentonite comprises the following components in volume ratio: cement: water 1: 1.52: 3.13, and the specific gravity of the slurry is controlled to be 1.12-1.34.
And (3) backfilling the groove by using fine sand, and discharging the prepared slurry, wherein the backfilling is preferably performed by using the fine sand with the average particle size of 0.3-0.6 mm, and the backfilling pore ratio is controlled within the range of 0.67-0.95.
And (3) the steel cover plate and the peripheral soil body are in free lap joint in the step (2).
Compared with the prior art, the invention has the beneficial effects that:
1. the design concept of the liquid barrier slurry wall adopting the prepared slurry as the main body is provided. The invention adopts the prepared slurry as the barrier in the designThe system body replaces a rigid structure in a traditional barrier system and effectively blocks the principal stress sigma in the horizontal direction3When the tunnel is spread in a field, the deformation energy of the displacement field of the active region outside the pit is released through the shear deformation of the liquid, the 'traction effect' of the active region outside the pit is reduced, and the horizontal deformation of the tunnel outside the pit caused by the unloading of the foundation pit is further controlled.
2. The traditional design method of the barrier system is usually based on engineering experience, the engineering stress mechanism is unclear, and quantitative design analysis is difficult to carry out. Based on research results of the applicant, the method can be used for excavating the foundation pit according to the excavation depth H of the foundation pit, the clear distance D between the tunnel and the enclosure structure, the center burial depth S of the tunnel and the internal friction angle of the soil body in the ground active region
Figure BDA0003102107740000031
And the engineering characteristics and the physical and mechanical parameters of the soil body are equal, the optimized design parameters of the liquid barrier slurry wall are provided, and the deformation control effect on the tunnel outside the foundation pit is maximized.
3. The invention provides the optimized design parameters of the grout wall and simultaneously gives consideration to construction feasibility and economy. The underground diaphragm wall grooving equipment is used for construction, and the specialized prepared slurry is used as a filling main body. In the construction process, slurry wall grooving construction is carried out firstly, professional slurry preparation is carried out while grooving is carried out, and after the construction is completed, a steel cover plate is adopted for sealing the top of the slurry wall. And after the foundation pit construction is finished and the tunnel is deformed stably, backfilling the groove by adopting fine sand, and discharging the prepared slurry. The invention is easy to construct in actual operation, can effectively reduce the construction cost, and can ensure that the planning and use at the later stage of the site are not influenced after the fine sand is backfilled.
The novel liquid-state blocking slurry wall provided by the method divides the soil body of the active area outside the pit into 'traction effect' influence areas according to the characteristics of the soil body of the field, and a section of liquid-state blocking slurry wall taking slurry as a main body is arranged in the liquid-state blocking slurry wall, so that the main stress sigma in the horizontal direction is effectively blocked3When the field is spread, the deformation energy of the field is released by adopting liquid shearing deformation, and the horizontal deformation spreading is effectively blocked. Through setting reasonable design parameters, the deformation control of the liquid separation slurry wall is effectively improvedThe effect is achieved, and meanwhile, the construction cost can be effectively reduced.
Drawings
FIG. 1 is a sectional view of a liquid insulation grout wall under construction conditions;
FIG. 2 is a cross-sectional layout view of a liquid insulation slurry wall after backfilling;
reference numbers in the drawings and corresponding part names;
1-preparing slurry in a slurry wall, 2-building a foundation pit enclosure structure, 3-digging soil in a pit, 4-an out-of-pit tunnel, 5-a soil body of an 'traction effect' influence area outside the pit, 6-a steel cover plate at the top of the slurry wall, and 7-backfilling fine sand in the slurry wall.
Detailed Description
The technical solution in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention.
The construction and post-backfilling of the liquid barrier slurry wall of the present invention will be further described with reference to the accompanying drawings and the specific embodiments. The following examples are given for the purpose of illustration only and are not intended to be limiting.
As shown in fig. 1 and 2, the invention relates to a liquid barrier grout wall for controlling the deformation of a tunnel caused by unloading. The device disclosed by the invention is a pure liquid barrier system which takes prepared slurry as a main body, and maximizes the control effect on the deformation of the tunnel caused by unloading by utilizing the physical and mechanical characteristics of the prepared slurry. Firstly, determining design parameters of the barrier slurry wall by combining site engineering conditions and site soil conditions, wherein the distance D between the barrier slurry wall and the foundation pit enclosure structure is 0.6-0.8D, and the design depth of the barrier slurry wall
Figure BDA0003102107740000041
When in use
Figure BDA0003102107740000042
At the moment, the value L is equal to S, the design width w of the blocking slurry wall is equal to (0.1-0.12) H (wherein D is the clear distance between the tunnel and the foundation pit enclosure structure, H is the excavation depth of the foundation pit, S is the center buried depth of the existing tunnel,
Figure BDA0003102107740000043
the inner friction angle of the soil body in the active area of the field) is obtained, and the deformation control effect of the grout blocking wall is optimal under the condition of the design parameters. And then, constructing the blocking slurry wall based on the determined design parameters and excavating a foundation pit, as shown in the attached drawing 1. And after the foundation pit is excavated and the tunnel is deformed stably, backfilling construction of the blocking slurry wall is carried out, as shown in the attached figure 2. Firstly, the construction of the foundation pit support structure 2 is completed before the foundation pit is excavated into the soil body 3 in the pit. The main body 1 and 6 of the separation grout wall is constructed before the soil body 3 in the pit is excavated. And (3) adopting underground continuous wall grooving equipment to perform the groove forming construction of the blocking slurry wall between the foundation pit enclosure structure 2 and the existing tunnel 4 outside the pit, and preparing the slurry 1 in the slurry wall while forming the groove on the blocking slurry wall. In the process of forming the groove, slurry circulation is carried out by adopting a slurry circulation method, and the inside of the groove is filled with prepared slurry 1 along with the completion of excavation of the soil body 3 in the groove. In order to optimize the fluidity of slurry 1 in the separation slurry wall, simultaneously ensure that the specific gravity of the slurry meets the requirements and prevent the soil body 5 of the 'traction effect' affected area outside the pit from collapsing, water, cement and bentonite are adopted for preparing the slurry, and the volume ratio of the three components is bentonite: cement: water 1: 1.52: 3.13, the specific gravity of the slurry 1 is controlled to be 1.12-1.34. After the construction of the separation slurry wall is finished, the interior of the separation slurry wall is filled with the prepared slurry 1, and the top of the separation slurry wall is sealed by a steel cover plate 6, so that the steel cover plate 6 is in free lap joint with the peripheral soil body 5 to ensure the deformation control effect. In order to prevent hole collapse caused by overload, the site in the range of 10-15 m around the hole is forbidden to be loaded. So far, this separation thick liquid wall construction is accomplished, can dig the interior earthwork 3 of hole. In the process, the blocking slurry wall can effectively control the horizontal deformation of the existing tunnel 4 outside the pit. And after the whole construction of the foundation pit is finished and the tunnel 4 outside the pit is deformed and stabilized, backfilling the isolation slurry wall, which is shown in the attached figure 2. And removing the steel cover plate 6 at the top of the slurry wall, backfilling the slurry wall in the groove by adopting the fine sand 7, preferably adopting a replacement method for backfilling, and circularly replacing the fine sand 7 and preparing the slurry 1 in the groove. In order to ensure the backfilling quality, the backfilling is preferably made of fine sand with the average grain diameter of 0.3-0.6 mm, and the backfilling pore ratio is controlled within the range of 0.67-0.95. After the prepared slurry 1 in the groove is completely discharged and the fine sand 7 is backfilled to the ground surface, the backfilling construction of the slurry blocking wall is finished, the site is recovered to the original state, and the subsequent site planning is not influenced so that the subsequent site planning is not influencedThe application is as follows.
Although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that various changes in the embodiments and/or modifications of the invention can be made, and equivalents and modifications of some features of the invention can be made without departing from the spirit and scope of the invention.

Claims (6)

1. A deformation control method for a tunnel outside a foundation pit based on a liquid-state slurry blocking wall is characterized in that the liquid-state slurry blocking wall is adopted to replace a traditional rigid blocking system, the 'traction effect' of an active area outside the pit is effectively controlled, and the deformation energy of a displacement field of the active area outside the pit is released through the shearing deformation of liquid; and after the foundation pit construction is finished, the liquid blocking slurry wall is subjected to landfill treatment, so that the site is restored to the original state.
2. The method for controlling the deformation of the tunnel outside the foundation pit based on the liquid grout blocking wall is characterized by comprising the following steps of:
(1) determining design parameters of the barrier slurry wall by combining site engineering conditions and site soil conditions; the design parameters comprise the design depth L of the liquid slurry wall, the design width w of the liquid slurry wall, the distance D from the foundation pit support structure, the excavation depth H of the foundation pit, the clear distance D between the tunnel and the foundation pit support structure, the buried depth S of the center of the tunnel and the internal friction angle of the soil body in the active area of the field
Figure FDA0003102107730000011
Comprehensively determining the design parameters of the barrier slurry wall;
(2) constructing the barrier slurry wall based on the determined design parameters; excavating a separation slurry wall by adopting underground continuous wall excavation grooving equipment, and preparing slurry while excavating; after the construction of the blocking slurry wall is finished, preparing slurry in the blocking slurry wall, and sealing the top of the blocking slurry wall by using a steel plate;
(3) and excavating a foundation pit, after the excavation of the foundation pit is finished and the tunnel is deformed stably, carrying out backfill construction on the separation slurry wall, and removing the steel cover plate.
3. The method for controlling the deformation of the tunnel outside the foundation pit based on the liquid grout blocking wall as claimed in claim 2, wherein the position parameter D of the grout blocking wall is determined according to the clear distance D between the tunnel and the foundation pit enclosure structure in the step (1), and when the D is 0.6-0.8D, the deformation control effect of the grout blocking wall is remarkable; secondly, determining the design depth L of the barrier slurry wall, and working according to the stress diffusion angle of the soil body in the field
Figure FDA0003102107730000021
When the control effect is optimal, the blocking paste wall reaches the optimal control effect if the control effect is optimal
Figure FDA0003102107730000022
At this time, the value L is equal to S; and finally, determining the design width w of the barrier slurry wall according to the excavation depth H of the foundation pit, and taking w as (0.1-0.12). H, so that the deformation control effect of the barrier slurry wall can be maximized.
4. The method for controlling the deformation of the tunnel outside the foundation pit based on the liquid grout blocking wall as claimed in claim 2, wherein the preparation of the slurry in the step (2) is carried out by adopting water, cement and bentonite, and the volume ratio of the three components is bentonite: cement: water 1: 1.52: 3.13, and the specific gravity of the slurry is controlled to be 1.12-1.34.
5. The method for controlling the deformation of the tunnel outside the foundation pit based on the liquid slurry blocking wall as claimed in claim 2, wherein the backfill preferably adopts fine sand with the average grain diameter of 0.3-0.6 mm, and the backfill porosity ratio is controlled within the range of 0.67-0.95.
6. The method for controlling the deformation of the tunnel outside the foundation pit based on the liquid grout blocking wall as claimed in claim 2, wherein the steel cover plate and the surrounding soil body are in free lap joint in the step (2), and the steel cover plate is removed while the grout blocking wall is backfilled in the step (3).
CN202110625899.6A 2021-06-04 2021-06-04 Foundation pit outer tunnel deformation control method based on liquid grout blocking wall Active CN113323691B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110625899.6A CN113323691B (en) 2021-06-04 2021-06-04 Foundation pit outer tunnel deformation control method based on liquid grout blocking wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110625899.6A CN113323691B (en) 2021-06-04 2021-06-04 Foundation pit outer tunnel deformation control method based on liquid grout blocking wall

Publications (2)

Publication Number Publication Date
CN113323691A true CN113323691A (en) 2021-08-31
CN113323691B CN113323691B (en) 2022-08-02

Family

ID=77419740

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110625899.6A Active CN113323691B (en) 2021-06-04 2021-06-04 Foundation pit outer tunnel deformation control method based on liquid grout blocking wall

Country Status (1)

Country Link
CN (1) CN113323691B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117592172A (en) * 2024-01-18 2024-02-23 华东交通大学 Reverse design method and system for deformation control of foundation pit support structure

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0959984A (en) * 1995-08-28 1997-03-04 Kajima Corp Simple subsurface construction structure
CN1361333A (en) * 2000-12-28 2002-07-31 同济大学 Tracing compensation and grouting process to control formation displacement
CN102433884A (en) * 2011-10-17 2012-05-02 同济大学建筑设计研究院(集团)有限公司 System and design method applying tree-root piles and pile side compacted grouting
CN107190752A (en) * 2017-05-31 2017-09-22 郑州安源工程技术有限公司 A kind of design and construction method of the recyclable square-section Row Piles Supporting Structure of flexible compound antiseepage assembled
CN109403348A (en) * 2018-12-10 2019-03-01 中建局集团建设发展有限公司 It is a kind of it is upper just under soft system of deep foundation pit support and its construction method
CN112854242A (en) * 2021-01-15 2021-05-28 浙江省建筑设计研究院 Concrete supporting system capable of actively controlling lateral deformation of foundation pit enclosure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0959984A (en) * 1995-08-28 1997-03-04 Kajima Corp Simple subsurface construction structure
CN1361333A (en) * 2000-12-28 2002-07-31 同济大学 Tracing compensation and grouting process to control formation displacement
CN102433884A (en) * 2011-10-17 2012-05-02 同济大学建筑设计研究院(集团)有限公司 System and design method applying tree-root piles and pile side compacted grouting
CN107190752A (en) * 2017-05-31 2017-09-22 郑州安源工程技术有限公司 A kind of design and construction method of the recyclable square-section Row Piles Supporting Structure of flexible compound antiseepage assembled
CN109403348A (en) * 2018-12-10 2019-03-01 中建局集团建设发展有限公司 It is a kind of it is upper just under soft system of deep foundation pit support and its construction method
CN112854242A (en) * 2021-01-15 2021-05-28 浙江省建筑设计研究院 Concrete supporting system capable of actively controlling lateral deformation of foundation pit enclosure

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
LIU, XY: "《Study on technology and safety measures for supporting structures around deep foundation pit》", 《PROGRESS IN SAFETY SCIENCE AND TECHNOLOGY, VOL III, PTS A AND B》 *
刘涛: "《外滩通道基坑开挖对既有隧道结构影响分析》", 《中国市政工程》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117592172A (en) * 2024-01-18 2024-02-23 华东交通大学 Reverse design method and system for deformation control of foundation pit support structure
CN117592172B (en) * 2024-01-18 2024-04-16 华东交通大学 Reverse design method and system for deformation control of foundation pit support structure

Also Published As

Publication number Publication date
CN113323691B (en) 2022-08-02

Similar Documents

Publication Publication Date Title
WO2021027025A1 (en) High-rise building settling reinforcing and lifting correcting construction method
CN102345300A (en) Construction method of underground structures of seacoasts and artificial islands
CN106884433A (en) Control vibrations pile pulling causes the structure of underground structure depression and control depression method
US11566390B2 (en) Construction method of reclaiming land from the sea based on basement utilization
CN108412503A (en) Bias shallow-buried tunnel portal construction protection structure and construction method thereof
CN108867723B (en) Method for correcting inclination of frame structure building and adding underground layer
CN211500658U (en) Shallow tunnel supporting construction that nearly connects that buries suitable for sand ground
CN113323691B (en) Foundation pit outer tunnel deformation control method based on liquid grout blocking wall
CN209923959U (en) Open caisson structure for dry-process operation of high-groundwater-level soft soil field
CN110093927B (en) Method for controlling deformation of tunnel outside foundation pit
CN105019913A (en) Base rock uplift region shielding tool-changing in-situ reinforcement method
CN100595388C (en) Large-area dredging dredger fill foundation treatment method
CN210530860U (en) Deep-buried blocking barrier for controlling deformation of tunnel outside foundation pit
CN217419736U (en) Compensation type construction structure for underground engineering construction
CN107700434A (en) A kind of dome grating formula armored concrete mud-rock flow blocking dam and its construction process
CN106149624B (en) A kind of gravity type quay and its construction method suitable for roadbed of alluvial silt
CN109083442A (en) The construction method of dynamic load bearing structure when existing building is docked with newly-built basis
CN210459300U (en) Enclosure structure for covering and digging station
JP2604210B2 (en) Construction method of underground large-scale spatial structure
CN213233510U (en) Simple combined steel plate cofferdam structure for preventing and treating quicksand
CN210195752U (en) Underground structure is built to arched cover undercut
CN107859040A (en) A kind of excavation method of foundation ditch large area soft soil horizon
CN114575364A (en) Construction method of soil-filling steel sheet pile cofferdam
CN106013238B (en) A kind of big earthing open trench tunnel subsidence control method of soft stratum
CN217710838U (en) A cover and dig top-down construction equipment for existing pipeline

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant