CN113323668B - Method and device system for reverse well expansion and excavation of oversized-section underground reservoir chamber - Google Patents

Method and device system for reverse well expansion and excavation of oversized-section underground reservoir chamber Download PDF

Info

Publication number
CN113323668B
CN113323668B CN202110609548.6A CN202110609548A CN113323668B CN 113323668 B CN113323668 B CN 113323668B CN 202110609548 A CN202110609548 A CN 202110609548A CN 113323668 B CN113323668 B CN 113323668B
Authority
CN
China
Prior art keywords
underground
well
reverse
excavation
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110609548.6A
Other languages
Chinese (zh)
Other versions
CN113323668A (en
Inventor
彭振华
朱荣强
丁浩
李玉忠
程亮
郭春雷
王金昌
王敬奎
胡学兵
于永东
朱仁景
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Offshore Oil Corp CNOOC
CNOOC Petrochemical Engineering Co Ltd
CNOOC Oil and Petrochemicals Co Ltd
Original Assignee
China National Offshore Oil Corp CNOOC
CNOOC Petrochemical Engineering Co Ltd
CNOOC Oil and Petrochemicals Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Offshore Oil Corp CNOOC, CNOOC Petrochemical Engineering Co Ltd, CNOOC Oil and Petrochemicals Co Ltd filed Critical China National Offshore Oil Corp CNOOC
Priority to CN202110609548.6A priority Critical patent/CN113323668B/en
Publication of CN113323668A publication Critical patent/CN113323668A/en
Application granted granted Critical
Publication of CN113323668B publication Critical patent/CN113323668B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D1/00Sinking shafts
    • E21D1/03Sinking shafts mechanically, e.g. by loading shovels or loading buckets, scraping devices, conveying screws
    • E21D1/06Sinking shafts mechanically, e.g. by loading shovels or loading buckets, scraping devices, conveying screws with shaft-boring cutters
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D13/00Large underground chambers; Methods or apparatus for making them
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/04Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention provides a method and a device system for reverse well expansion and excavation of an oversized-section underground reservoir chamber, wherein the method comprises the following steps: (1) Forward drilling from the ground into the underground rock mass to form a pilot hole communicated with an underground construction channel; (2) Reversely enlarging and excavating the pilot hole obtained in the step (1) to the ground to form a pipeline well; (3) Performing reverse excavation on the pipeline well obtained in the step (2) for at least 1 time to form a vertical shaft corresponding to the height of the underground reservoir cavity; (4) Performing reverse excavation on the vertical shaft obtained in the step (3) for at least 1 time to form a well wall corresponding to the diameter of the underground reservoir cavity; (5) Excavating the bottom of an underground storage cavern, and reinforcing the bottom, the top and the well wall of the underground storage cavern; (6) And reinforcing the pipeline well between the surface and the top of the underground storage cavern. The excavation method provided by the invention has the advantages of small engineering quantity, safety, high efficiency and small damage to the structural stability of the cavity.

Description

Method and device system for reverse well expansion and excavation of oversized-section underground reservoir chamber
Technical Field
The invention belongs to the technical field of underground cavern engineering construction, relates to a method for expanding and excavating an underground storage cavern, and particularly relates to a method for expanding and excavating an extra-large-section underground storage cavern reverse well and a device system thereof.
Background
Natural gas is an important energy source required for the production activities of the society today, and the demand of natural gas is increasing in all countries of the world. The natural gas supply system is a large country of energy consumption, the demand for natural gas is also higher and higher, and in order to ensure the peak shaving use of natural gas and the national energy supply, the natural gas reserve of the country is continuously expanded all over the world. At present, three modes of ground gas storage tank storage, pipeline storage and underground gas storage are mainly adopted for storing natural gas. Because the ground gas storage tank and the pipeline can provide limited gas storage capacity, the requirement of large-scale natural gas supply cannot be met, and the underground gas storage tank has the advantages of large gas storage capacity, ground resource conservation, safety, reliability, small environmental pollution, no influence of weather and the like, and is an important guarantee for maintaining normal use of natural gas and national energy strategy storage.
The establishment of a large underground natural gas storage group is an important policy for development in China, and a large-section underground cavity is required to be excavated in a stratum with good surrounding rock. Considering the overall construction cost and the technical maturity, the volume of the underground cavity is generally more than 10 ten thousand cubic meters, the cavity structure adopts a cylinder, the cavity diameter is more than 35m, the height reaches about 100m, and the upper part and the lower part respectively adopt a hemispherical shape and an ellipsoidal shape so as to ensure that the gas storage can store natural gas with enough pressure in the operation period. The domestic scholars develop a great deal of researches on the vertical cylindrical underground cavity excavation method, mainly adopts the ground positive well excavation, but the method is only suitable for excavating the underground cavity directly connected with the ground, and the slag sliding well arranged in the vertical cylindrical underground cavity excavation method is easy to be blocked due to small diameter, so that the slag sliding well is difficult to dredge, and the dredging working danger is high. However, for underground caverns buried deeply below the ground, on one hand, an excavation working face is difficult to form at the upper part of the caverns, on the other hand, the forced excavation engineering amount from the ground is large, and the stability of operation of a gas storage structure can be greatly influenced in the later period. In addition, because the whole gas storage is buried in the stratum 100m-200m below the ground, and the cross section of the gas storage cavity is larger, the gas storage cavity is difficult to excavate directly from the ground, namely, the positive well excavation is not suitable for the underground storage cavity with the oversized cross section. Therefore, the development of the excavation method which is small in engineering quantity, safe, efficient and small in damage to the structural stability of the cavern has very important significance.
Disclosure of Invention
The invention aims to provide a method for reverse well expansion and excavation of an oversized-section underground reservoir chamber and a device system thereof, wherein the method has the advantages of small engineering quantity, safety, high efficiency and small damage to the structural stability of the chamber.
In order to achieve the aim of the invention, the invention adopts the following technical scheme:
in a first aspect, the invention provides a method for reverse well expansion and excavation of an oversized-section underground storage cavern, the method comprising the steps of:
(1) Forward drilling from the ground into the underground rock mass to form a pilot hole communicated with an underground construction channel;
(2) Reversely enlarging and excavating the pilot hole obtained in the step (1) to the ground to form a pipeline well;
(3) Performing reverse excavation on the pipeline well obtained in the step (2) for at least 1 time to form a vertical shaft corresponding to the height of the underground reservoir cavity;
(4) Performing reverse excavation on the vertical shaft obtained in the step (3) for at least 1 time to form a well wall corresponding to the diameter of the underground reservoir cavity;
(5) Excavating the bottom of an underground storage cavern, and reinforcing the bottom, the top and the well wall of the underground storage cavern;
(6) And reinforcing the pipeline well between the ground and the top of the underground storage cavern.
In the present invention, the number of times of reverse expansion in the step (3) is at least 1, for example, 1, 2, 3, 4, 5, 6, 7, 8, 9 or 10 times, but not limited to the recited values, and other non-recited values within the range are equally applicable.
In the present invention, the number of times of reverse expansion in the step (4) is at least 1, for example, 1, 2, 3, 4, 5, 6, 7, 8, 9 or 10 times, but not limited to the recited values, and other non-recited values within the range are equally applicable.
The invention only needs one construction shaft and one underground construction channel for slag discharge in the whole excavation process of the underground storage cavern, has small whole excavation engineering quantity, no pipeline well blockage problem, small slag skimming quantity, less potential safety hazard and high construction speed.
Preferably, steps (1) - (3) are performed using a backdrilling machine.
Preferably, steps (4) - (6) are performed using a lifting device and a construction platform.
Preferably, step (4) is performed using a drill-burst method.
The invention relates to a drilling and blasting method, in particular to a construction method for breaking rock mass and opening a cavity by adopting explosive blasting, which comprises the following basic procedures: manual drilling, explosive loading and blasting, ventilation, necessary construction support and slag discharging and cleaning.
According to the invention, through a mode of combining reverse well excavation and drilling, explosion and expanding excavation, on one hand, an excavation working surface is prevented from being formed between the ground and the top of an underground reservoir cavity, and on the other hand, the stability of a reservoir structure in the later use process is improved; the method is particularly suitable for excavating the underground storage cavern with the ultra-large section, is safe and efficient, and has little damage to the structural stability of the cavern.
The drilling direction of the drilling and blasting method is preferably a downward inclination angle of 40 ° -50 °, for example, 40 °, 41 °, 42 °, 43 °, 44 °, 45 °, 46 °, 47 °, 48 °, 49 °, or 50 °, but is not limited to the recited values, and other non-recited values within the range of values are equally applicable.
In the invention, the downward inclination angle is an acute angle below the horizontal plane and clamped with the horizontal plane.
Preferably, the vertical row distance of the drill and burst method is 1-2m, for example, 1m, 1.1m, 1.2m, 1.3m, 1.4m, 1.5m, 1.6m, 1.7m, 1.8m, 1.9m or 2m, but is not limited to the recited values, and other non-recited values within the range of values are equally applicable.
Preferably, the step (4) carries out temporary spraying and mixing treatment on the inner wall of the vertical shaft before each reverse expansion and excavation.
In the invention, the temporary spraying and mixing treatment is specifically to spray the mixture of water, cement, aggregate, additive and the like to the surface of the excavated exposed surrounding rock by adopting compressed air, so that the surface of the excavated exposed surrounding rock is cemented and solidified. The method uses spraying machinery and compressed air to spray the mixed material prepared according to a certain proportion to the sprayed surface at high speed through a pipeline, and the mixed material is coagulated and hardened to form a concrete layer. The method can temporarily form shotcrete support for surrounding rocks and protect the stability of the surrounding rocks of the grotto.
According to the invention, the temporary spraying and mixing treatment is carried out on the well wall before each reverse expansion and excavation so as to ensure the surface strength of the inner wall of the vertical shaft, thereby improving the safety of a grotto and providing support for subsequent drilling, blasting and expansion and excavation.
Preferably, the ratio of the circumferential footage to the vertical footage of each reverse expansion in step (4) is in the range of 1 (2.5-3.5), and may be, for example, 1:2.5, 1:2.7, 1:2.9, 1:3, 1:3.1, 1:3.3, or 1:3.5, but is not limited to the recited values, and other non-recited values within the range of values are equally applicable.
Preferably, the reinforcement treatment of step (5) is specifically the application of steel lined concrete.
Preferably, the steel lining concrete adopts a segmented and layer-by-layer mode when reinforcing the well wall.
Preferably, the single-node height of the sections layer by layer is 18-22m, for example, 18m, 18.5m, 19m, 19.5m, 20m, 20.5m, 21m, 21.5m or 22m, but is not limited to the recited values, and other non-recited values within the range of values are equally applicable.
Preferably, the reinforcement treatment in step (6) is specifically to provide a conduit on the wall surface of the piping well.
As a preferred technical solution of the first aspect of the present invention, the method includes the following steps:
(1) Adopting a reverse well drilling machine to drill forward from the ground into the underground rock mass to form a pilot hole communicated with an underground construction channel;
(2) Performing reverse expansion digging on the pilot hole obtained in the step (1) to the ground by adopting a reverse well drilling machine to form a pipeline well;
(3) Performing reverse expansion digging on the pipeline well obtained in the step (2) for at least 1 time by adopting a reverse well drilling machine to form a vertical shaft corresponding to the height of the underground reservoir cavity;
(4) Adopting a lifting device and a construction platform, and performing reverse excavation on the vertical shaft obtained in the step (3) for at least 1 time by using a drilling and blasting method to form a well wall corresponding to the diameter of a cavity of an underground reservoir; the drilling direction of the drilling and blasting method is a downward inclination angle of 40-50 degrees, and the vertical row spacing is 1-2m; carrying out temporary spraying and mixing treatment on the inner wall of the vertical shaft before each reverse expansion, wherein the ratio of the circumferential footage to the vertical footage of each reverse expansion is 1 (2.5-3.5);
(5) Excavating the bottom of an underground storage cavern by adopting a lifting device and a construction platform, and applying steel lining concrete to the bottom, the top and a well wall of the underground storage cavern; the steel lining concrete adopts a mode of sections and layers when reinforcing the well wall, and the height of a single section is 18-22m;
(6) And a conduit is arranged on the wall surface of the pipeline between the ground and the top of the underground storage chamber.
In a second aspect, the invention provides a device system for performing reverse well expansion and excavation of an oversized-section underground reservoir cavity by using the method in the first aspect, wherein the device system comprises a reverse well drilling machine, a lifting device and a construction platform.
The well reversing drilling machine is arranged at the ground opening of the underground storage chamber and is used for forward drilling from the ground into the underground rock body to form a pilot hole communicated with the underground construction channel, a pipeline well formed by reverse expansion and excavation and a vertical shaft corresponding to the height of the underground storage chamber.
The lifting device is used for replacing the reverse well drilling machine, is arranged at the ground opening of the underground storage chamber, and is connected with a construction platform arranged in the vertical shaft through the pipeline well.
The construction platform serves as a load carrier.
Preferably, the construction platform adopts a detachable steel frame structure.
Preferably, the radial length of the construction platform is adapted to the circumferential footage of each reverse expansion.
In the invention, the specific meaning of the radial length of the construction platform adapting to the circumferential footage of each reverse expansion is as follows: the radial length of the construction platform is lengthened along with the increase of the size of the annular ruler for each reverse expanding excavation, so that the drilling, explosion and expanding excavation of the vertical shaft in the annular ruler process are facilitated.
Preferably, the construction platform has a circumferential rotation function with respect to the shaft.
Compared with the prior art, the invention has the following beneficial effects:
(1) The method provided by the invention only needs one construction shaft and one underground construction channel for deslagging in the excavation process of the whole underground storage cavern, the whole excavation engineering amount is small, the problem of blockage of a pipeline well is avoided, the deslagging amount is small, the potential safety hazard is low, and the construction speed is high;
(2) According to the method provided by the invention, through a mode of combining inverted well excavation and drilling, explosion and expanding excavation, on one hand, an excavation working surface is prevented from being formed between the ground and the top of an underground reservoir cavity, and on the other hand, the stability of a reservoir structure in the later use process is improved; the method is particularly suitable for excavating the underground storage cavern with the ultra-large section, is safe and efficient, and has little damage to the structural stability of the cavern.
Drawings
FIG. 1 is a schematic diagram of a method for reverse well expansion and excavation of an oversized-section underground reservoir chamber provided by the invention;
FIG. 2 is a schematic diagram of the structure of an oversized-section underground storage cavern finally formed by the method provided by the invention.
Wherein: 1-a reverse well drilling machine; 2-pilot holes; 3-piping well; 4-shaft; 5-an underground construction channel; 6-lifting means; 7-a construction platform; 8-an underground storage cavern; 9-catheter.
Detailed Description
The technical scheme of the invention is further described by the following specific embodiments. It will be apparent to those skilled in the art that the examples are merely to aid in understanding the invention and are not to be construed as a specific limitation thereof.
The invention provides a device system for reverse well expansion and excavation of an oversized-section underground reservoir chamber, which is shown in fig. 1 and 2, and comprises a reverse well drilling machine 1, a lifting device 6, a construction platform 7, a small drilling machine, a blasting detonator and the like; the reverse well drilling machine 1 is arranged at the ground opening of the underground storage cavern 8 and is used for drilling forward from the ground into the underground rock body to form a pilot hole 2 communicated with the underground construction channel 5, a pipeline well 3 formed by reverse expansion and excavation and a vertical shaft 4 corresponding to the height of the underground storage cavern 8; the lifting device 6 is used for replacing the reverse well drilling machine 1, is arranged at a ground opening of an underground storage chamber 8, and is connected with a construction platform 7 arranged in the vertical shaft 4 through the pipeline well 3; the construction platform 7 serves as a load carrier.
Example 1
The embodiment provides a method for performing reverse well expansion and excavation of an oversized-section underground reservoir cavity by adopting the device system, as shown in fig. 1 and 2, the method comprises the following steps:
(1) Adopting a reverse well drilling machine 1 to drill forward from the ground into an underground rock mass to form a phi 244mm pilot hole 2 communicated with an underground construction channel 5, enlarging and digging the underground construction channel 5 (width x height: 6.0m x 6.0 m) to the interface position of the pilot hole 2, erecting an intersection portal (not shown in the figure), and continuing to construct to the side wall according to the outline (width x height: 7.5m x 6.0 m) of the underground construction channel 5;
(2) The pilot hole 2 obtained in the step (1) is reversely dug to the ground along the direction from bottom to top by adopting a reverse well drilling machine 1 to form a phi 1500mm pipeline well 3 for the subsequent arrangement of a conduit 9 so as to communicate an underground reservoir cavity 8 with the ground;
(3) 2 times of reverse expansion digging is carried out on the pipeline well 3 obtained in the step (2) along the direction from bottom to top by adopting a reverse well drilling machine 1, so as to form a phi 5000mm vertical shaft 4 corresponding to the height of an underground storage chamber 8, and the circumferential footage of the vertical shaft is as in section a in fig. 1;
(4) Withdrawing the back-well drilling machine 1, arranging a lifting device 6 on the installation position of the original back-well drilling machine 1, and arranging a construction platform 7 connected with the lifting device 6 in the vertical shaft 4 obtained in the step (3) so as to pull the construction platform 7 to do lifting motion in the vertical shaft 4; adopting a lifting device 6 and a construction platform 7 and carrying out temporary spraying and mixing treatment on the inner wall of the vertical shaft 4 manually; the vertical shaft 4 is reversely excavated from bottom to top for 4 times from inside to outside by using a drilling and blasting method, so as to form a well wall corresponding to an underground reservoir cavity 8 with the diameter of 35m, and the circumferential footage of the well wall is as b, c, d, e in fig. 1; carrying out temporary spraying and mixing treatment on the inner wall of the vertical shaft 4 before each reverse expansion, designing the circumferential footage of 3.75m each time, carrying out explosive charging blasting in batches after finishing all blast holes are constructed vertically once, and carrying out vertical footage of 11m each time, wherein the drilling direction of the drilling and blasting method is 45 degrees in a downward inclination angle, and the vertical row spacing is 1.5m;
(5) Excavating the bottom of an underground storage cavern 8 by adopting a lifting device 6 and a construction platform 7, and applying steel lining concrete to the bottom of the underground storage cavern 8; applying steel lining concrete layer by layer along the bottom-up direction to the wall of the underground storage cavern 8, wherein the height of a single section is 20m;
(6) The conduit 9 is arranged on the wall surface of the piping shaft 3 between the ground and the top of the underground storage cavern 8, and the concrete operation is as follows: firstly, the construction platform 7 is lowered, a guide pipe is placed on the construction platform 7, then the construction platform 7 is connected with the lifting device 6, the construction platform 7 is lifted through the lifting device 6, the guide pipe 9 on the construction platform 7 is inserted into the pipeline well 3 and stretches out of the ground, the guide pipe 9 is fixed when steel lining concrete is applied to the top of the underground storage cavern 8, and finally the lifting device 6 and the construction platform 7 are removed, so that an oversized-section underground storage cavern 8 with the diameter of 35m is formed.
Example 2
The embodiment provides a method for performing reverse well expansion and excavation of an oversized-section underground reservoir cavity by adopting the device system, as shown in fig. 1 and 2, the method comprises the following steps:
(1) Adopting a reverse well drilling machine 1 to drill forward from the ground into an underground rock mass to form a phi 250mm pilot hole 2 communicated with an underground construction channel 5, enlarging and digging the underground construction channel 5 (width x height: 6.0m x 6.0 m) to the interface position of the pilot hole 2, erecting an intersection portal (not shown in the figure), and continuing to construct to the side wall according to the outline (width x height: 7.5m x 6.0 m) of the underground construction channel 5;
(2) The pilot hole 2 obtained in the step (1) is reversely dug to the ground along the direction from bottom to top by adopting a reverse well drilling machine 1 to form a phi 2000mm pipeline well 3 for the subsequent arrangement of a conduit 9 so as to communicate an underground reservoir cavity 8 with the ground;
(3) Performing reverse excavation on the pipeline well 3 obtained in the step (2) for 1 time by adopting a reverse well drilling machine 1 along the direction from bottom to top to form a phi 4400mm vertical shaft 4 corresponding to the height of an underground storage chamber 8, wherein the circumferential footage of the vertical shaft is as in section a in fig. 1;
(4) Withdrawing the back-well drilling machine 1, arranging a lifting device 6 on the installation position of the original back-well drilling machine 1, and arranging a construction platform 7 connected with the lifting device 6 in the vertical shaft 4 obtained in the step (3) so as to pull the construction platform 7 to do lifting motion in the vertical shaft 4; adopting a lifting device 6 and a construction platform 7 and carrying out temporary spraying and mixing treatment on the inner wall of the vertical shaft 4 manually; the vertical shaft 4 is reversely excavated from bottom to top for 4 times from inside to outside by using a drilling and blasting method, so as to form a well wall corresponding to an underground reservoir cavity 8 with the diameter of 40m, and the circumferential footage of the well wall is as b, c, d, e in fig. 1; carrying out temporary spraying and mixing treatment on the inner wall of the vertical shaft 4 before each reverse expansion, designing the circumferential footage of 4.45m each time, carrying out charging blasting in a divided manner after finishing all blast hole construction vertically once, and carrying out vertical footage 11m each time, wherein the drilling direction of the drilling and blasting method is a downward inclination angle of 40 degrees, and the vertical row spacing is 2m;
(5) Excavating the bottom of an underground storage cavern 8 by adopting a lifting device 6 and a construction platform 7, and applying steel lining concrete to the bottom of the underground storage cavern 8; applying steel lining concrete layer by layer along the bottom-up direction to the wall of the underground storage cavern 8, wherein the height of a single section is 18m;
(6) The conduit 9 is arranged on the wall surface of the piping shaft 3 between the ground and the top of the underground storage cavern 8, and the concrete operation is as follows: firstly, the construction platform 7 is lowered, a guide pipe is placed on the construction platform 7, then the construction platform 7 is connected with the lifting device 6, the construction platform 7 is lifted through the lifting device 6, the guide pipe 9 on the construction platform 7 is inserted into the pipeline well 3 and stretches out of the ground, the guide pipe 9 is fixed when steel lining concrete is applied to the top of the underground storage cavern 8, and finally the lifting device 6 and the construction platform 7 are removed, so that an oversized-section underground storage cavern 8 with the diameter of 40m is formed.
Example 3
The embodiment provides a method for performing reverse well expansion and excavation of an oversized-section underground reservoir cavity by adopting the device system, as shown in fig. 1 and 2, the method comprises the following steps:
(1) Adopting a reverse well drilling machine 1 to drill forward from the ground into an underground rock mass to form a phi 250mm pilot hole 2 communicated with an underground construction channel 5, enlarging and digging the underground construction channel 5 (width x height: 6.0m x 6.0 m) to the interface position of the pilot hole 2, erecting an intersection portal (not shown in the figure), and continuing to construct to the side wall according to the outline (width x height: 7.5m x 6.0 m) of the underground construction channel 5;
(2) The pilot hole 2 obtained in the step (1) is reversely dug to the ground along the direction from bottom to top by adopting a reverse well drilling machine 1 to form a 2500mm phi pipeline well 3 for the subsequent arrangement of a conduit 9 so as to communicate an underground reservoir cavity 8 with the ground;
(3) 2 times of reverse expansion digging is carried out on the pipeline well 3 obtained in the step (2) along the direction from bottom to top by adopting a reverse well drilling machine 1, so as to form a phi 5000mm vertical shaft 4 corresponding to the height of an underground storage chamber 8, and the circumferential footage of the vertical shaft is as in section a in fig. 1;
(4) Withdrawing the back-well drilling machine 1, arranging a lifting device 6 on the installation position of the original back-well drilling machine 1, and arranging a construction platform 7 connected with the lifting device 6 in the vertical shaft 4 obtained in the step (3) so as to pull the construction platform 7 to do lifting motion in the vertical shaft 4; adopting a lifting device 6 and a construction platform 7 and carrying out temporary spraying and mixing treatment on the inner wall of the vertical shaft 4 manually; the vertical shaft 4 is reversely excavated from bottom to top and from inside to outside by using a drilling and blasting method to form a well wall corresponding to an underground reservoir cavity 8 with the diameter of 45m, and the circumferential footage of the well wall is as b, c, d, e in the section in figure 1; carrying out temporary spraying and mixing treatment on the inner wall of the vertical shaft 4 before each reverse expansion, designing the circumferential footage of 5m each time, carrying out explosive loading blasting in a divided manner after finishing all blast hole construction vertically once, and carrying out vertical footage of 17.5m each time, wherein the drilling direction of the drilling and blasting method is a downward inclination angle of 50 degrees, and the vertical row spacing is 1m;
(5) Excavating the bottom of an underground storage cavern 8 by adopting a lifting device 6 and a construction platform 7, and applying steel lining concrete to the bottom of the underground storage cavern 8; applying steel lining concrete layer by layer along the bottom-up direction to the wall of the underground storage cavern 8, wherein the height of a single section is 22m;
(6) The conduit 9 is arranged on the wall surface of the piping shaft 3 between the ground and the top of the underground storage cavern 8, and the concrete operation is as follows: firstly, the construction platform 7 is lowered, a guide pipe is placed on the construction platform 7, then the construction platform 7 is connected with the lifting device 6, the construction platform 7 is lifted through the lifting device 6, the guide pipe 9 on the construction platform 7 is inserted into the pipeline well 3 and stretches out of the ground, the guide pipe 9 is fixed when steel lining concrete is applied to the top of the underground storage cavern 8, and finally the lifting device 6 and the construction platform 7 are removed, so that an oversized-section underground storage cavern 8 with the diameter of 45m is formed.
In the embodiments 1-3, the ultra-large section underground storage caverns with the diameters of 35-45m are excavated by a reverse well expansion excavation mode, so that the expected targets are completed.
Therefore, the method provided by the invention only needs one construction shaft and one underground construction channel for deslagging in the excavation process of the whole underground storage cavern, the whole excavation engineering amount is small, the problem of blockage of a pipeline well is avoided, the deslagging amount is small, the potential safety hazard is low, and the construction speed is high; in addition, the method provided by the invention avoids forming an excavation working surface between the ground and the top of the underground reservoir cavity by combining the reverse well excavation and the drilling, blasting and expanding excavation, and improves the stability of the reservoir structure in the later use process; the method is particularly suitable for excavating the underground storage cavern with the ultra-large section, is safe and efficient, and has little damage to the structural stability of the cavern.
The applicant declares that the above is only a specific embodiment of the present invention, but the scope of the present invention is not limited thereto, and it should be apparent to those skilled in the art that any changes or substitutions that are easily conceivable within the technical scope of the present invention disclosed by the present invention fall within the scope of the present invention and the disclosure.

Claims (13)

1. A method for reverse well expansion and excavation of an oversized-section underground storage cavern, the method comprising the steps of:
(1) Forward drilling from the ground into the underground rock mass to form a pilot hole communicated with an underground construction channel;
(2) Reversely enlarging and excavating the pilot hole obtained in the step (1) to the ground to form a pipeline well;
(3) Performing reverse excavation on the pipeline well obtained in the step (2) for at least 1 time to form a vertical shaft corresponding to the height of the underground reservoir cavity;
(4) Performing reverse excavation on the vertical shaft obtained in the step (3) for at least 1 time to form a well wall corresponding to the diameter of the underground reservoir cavity;
(5) Excavating the bottom of an underground storage cavern, and reinforcing the bottom, the top and the well wall of the underground storage cavern;
(6) And reinforcing the pipeline well between the ground and the top of the underground storage cavern.
2. The method of claim 1, wherein steps (1) - (3) are performed using a backdrilling machine.
3. The method of claim 1, wherein steps (4) - (6) are performed using a lifting device and a construction platform.
4. The method of claim 1, wherein step (4) is performed using a drill-burst method.
5. The method of claim 4, wherein the direction of drilling by the detonation method is at a downward inclination of 40 ° -50 °.
6. The method of claim 4, wherein the vertical gauge of the drill-burst method is 1-2m.
7. The method of claim 1, wherein the inner wall of the shaft is subjected to a temporary spray-mixing treatment before each reverse reaming in step (4).
8. The method of claim 1, wherein the ratio of the circumferential footage to the vertical footage of each reverse reaming of step (4) ranges from 1 (2.5-3.5).
9. The method according to claim 1, wherein the reinforcement treatment of step (5) is in particular the application of steel lined concrete.
10. The method of claim 9, wherein the steel lined concrete is used in a section-by-section manner when reinforcing the borehole wall.
11. The method of claim 10, wherein the individual section height of the sections layer by layer is 18-22m.
12. The method according to claim 1, wherein the strengthening treatment of step (6) is in particular the placement of a conduit on the wall of the piping well.
13. The method according to any one of claims 1-12, characterized in that the method comprises the steps of:
(1) Adopting a reverse well drilling machine to drill forward from the ground into the underground rock mass to form a pilot hole communicated with an underground construction channel;
(2) Performing reverse expansion digging on the pilot hole obtained in the step (1) to the ground by adopting a reverse well drilling machine to form a pipeline well;
(3) Performing reverse expansion digging on the pipeline well obtained in the step (2) for at least 1 time by adopting a reverse well drilling machine to form a vertical shaft corresponding to the height of the underground reservoir cavity;
(4) Adopting a lifting device and a construction platform, and performing reverse excavation on the vertical shaft obtained in the step (3) for at least 1 time by using a drilling and blasting method to form a well wall corresponding to the diameter of a cavity of an underground reservoir; the drilling direction of the drilling and blasting method is a downward inclination angle of 40-50 degrees, and the vertical row spacing is 1-2m; carrying out temporary spraying and mixing treatment on the inner wall of the vertical shaft before each reverse expansion, wherein the ratio of the circumferential footage to the vertical footage of each reverse expansion is 1 (2.5-3.5);
(5) Excavating the bottom of an underground storage cavern by adopting a lifting device and a construction platform, and applying steel lining concrete to the bottom, the top and a well wall of the underground storage cavern; the steel lining concrete adopts a mode of sections and layers when reinforcing the well wall, and the height of a single section is 18-22m;
(6) And a conduit is arranged on the wall surface of the pipeline between the ground and the top of the underground storage chamber.
CN202110609548.6A 2021-06-01 2021-06-01 Method and device system for reverse well expansion and excavation of oversized-section underground reservoir chamber Active CN113323668B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110609548.6A CN113323668B (en) 2021-06-01 2021-06-01 Method and device system for reverse well expansion and excavation of oversized-section underground reservoir chamber

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110609548.6A CN113323668B (en) 2021-06-01 2021-06-01 Method and device system for reverse well expansion and excavation of oversized-section underground reservoir chamber

Publications (2)

Publication Number Publication Date
CN113323668A CN113323668A (en) 2021-08-31
CN113323668B true CN113323668B (en) 2023-10-20

Family

ID=77423048

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110609548.6A Active CN113323668B (en) 2021-06-01 2021-06-01 Method and device system for reverse well expansion and excavation of oversized-section underground reservoir chamber

Country Status (1)

Country Link
CN (1) CN113323668B (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016204848A (en) * 2015-04-16 2016-12-08 大成建設株式会社 Vertical shaft construction method and underground storage tank construction method

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016204848A (en) * 2015-04-16 2016-12-08 大成建設株式会社 Vertical shaft construction method and underground storage tank construction method

Also Published As

Publication number Publication date
CN113323668A (en) 2021-08-31

Similar Documents

Publication Publication Date Title
CN103470267B (en) The one Rapid Construction of Tunnels technique of growing up
CN102121395B (en) Method for integrated comprehensive management of gas in low-permeability single coal bed
CN109736827B (en) Method for excavating urban subway hard rock stratum communication channel by high-pressure gas expansion fracturing
CN103835723B (en) Pit shaft passes through the comprehensive pre-administering method on stratum, goaf
CN113153308B (en) Construction method for collapse section of double-arch tunnel
CN103835729A (en) Ground pre-grouting strengthening technology for deep long-distance roadway surrounding rock
CN102678126A (en) Method for excavating mountain tunnels in weak surrounding rock-fractured zones or shallow covered slope sections
CN103726858A (en) Underground large-scale cave depot project sphere-cylinder combination excavation method
CN102704936A (en) Caving control method for fully mechanized mining face tip mining road way top plate
CN103510572A (en) Construction method of water getting vertical shaft under complex geological condition
CN102235010B (en) Treatment method for hanging sinking stop due to expansive soil in well sinking
CN105156120A (en) Inclined-shaft reverse excavation construction method for hillside cave depot
CN113154979B (en) Static rock breaking construction method of large-inclination-angle wet drilling expanding agent
CN213233469U (en) Triaxial down-the-hole impact high-pressure jet grouting equipment
CN204099720U (en) The protective housing that under soil stone combination geological condition, artificial pipe jacking construction method is used
CN113323668B (en) Method and device system for reverse well expansion and excavation of oversized-section underground reservoir chamber
CN112943306A (en) Roadway fault zone supporting method and step based on instability deformation research
CN112160767B (en) Tunneling construction method combining mechanical-chemical corrosion-hydraulic cutting of tunnel
CN109555158A (en) A kind of piping lane construction method
CN104315251A (en) Manual pipe jacking construction method for earth and rock combined geological conditions
CN104389609A (en) No-blasting mechanical digging method
CN113587760A (en) Combined rock breaking method for heat expansion rock breaking pipe and hard rock stratum foundation pit
CN112031738A (en) Construction method of vertical shaft slag sliding well raise boring machine with diameter of 4-6 m
CN208039234U (en) Engineering pile in karst cave geology
CN206129306U (en) Portable vapour -pressure type slip casting device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant