CN113310849B - Grouting reinforcement test device and method for simulating shield underground butt joint - Google Patents

Grouting reinforcement test device and method for simulating shield underground butt joint Download PDF

Info

Publication number
CN113310849B
CN113310849B CN202110523376.0A CN202110523376A CN113310849B CN 113310849 B CN113310849 B CN 113310849B CN 202110523376 A CN202110523376 A CN 202110523376A CN 113310849 B CN113310849 B CN 113310849B
Authority
CN
China
Prior art keywords
shield
grouting
shield machine
machine
storage tank
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110523376.0A
Other languages
Chinese (zh)
Other versions
CN113310849A (en
Inventor
陈星欣
何明高
尹清锋
王春河
程跃胜
庄全贵
施烨辉
郭力群
程荷兰
张海荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuzhou Metro Group Co ltd
Nanjing Kentop Civil Engineering Technology Co ltd
Huaqiao University
China Construction Communications Engineering Group Co Ltd
Original Assignee
Fuzhou Metro Group Co ltd
Nanjing Kentop Civil Engineering Technology Co ltd
Huaqiao University
China Construction Communications Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuzhou Metro Group Co ltd, Nanjing Kentop Civil Engineering Technology Co ltd, Huaqiao University, China Construction Communications Engineering Group Co Ltd filed Critical Fuzhou Metro Group Co ltd
Priority to CN202110523376.0A priority Critical patent/CN113310849B/en
Publication of CN113310849A publication Critical patent/CN113310849A/en
Application granted granted Critical
Publication of CN113310849B publication Critical patent/CN113310849B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N13/00Investigating surface or boundary effects, e.g. wetting power; Investigating diffusion effects; Analysing materials by determining surface, boundary, or diffusion effects
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01JMEASUREMENT OF INTENSITY, VELOCITY, SPECTRAL CONTENT, POLARISATION, PHASE OR PULSE CHARACTERISTICS OF INFRARED, VISIBLE OR ULTRAVIOLET LIGHT; COLORIMETRY; RADIATION PYROMETRY
    • G01J5/00Radiation pyrometry, e.g. infrared or optical thermometry
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01JMEASUREMENT OF INTENSITY, VELOCITY, SPECTRAL CONTENT, POLARISATION, PHASE OR PULSE CHARACTERISTICS OF INFRARED, VISIBLE OR ULTRAVIOLET LIGHT; COLORIMETRY; RADIATION PYROMETRY
    • G01J5/00Radiation pyrometry, e.g. infrared or optical thermometry
    • G01J2005/0077Imaging
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N13/00Investigating surface or boundary effects, e.g. wetting power; Investigating diffusion effects; Analysing materials by determining surface, boundary, or diffusion effects
    • G01N2013/003Diffusion; diffusivity between liquids

Abstract

The invention provides a grouting reinforcement test device and a test method for simulating shield underground butt joint, which comprises a first shield machine, a second shield machine, a first grouting system and a second grouting system; the first shield machine and the second shield machine respectively comprise a shield tail, a middle shield, a front shield, an air brake and a cutter head in sequence; the first shield machine and the second shield machine are coaxially arranged, and a cutter head of the first shield machine and a cutter head of the second shield machine are oppositely arranged at intervals; by applying the technical scheme, grouting reinforcement of shield butt joint under the complex seepage condition can be realized, and the effect is remarkable.

Description

Grouting reinforcement test device and method for simulating shield underground butt joint
Technical Field
The invention relates to a grouting reinforcement test device and a grouting reinforcement test method for simulating shield underground butt joint.
Background
The single tunnel is a new development trend by adopting technologies of opposite propulsion, underground butt joint and shell abandoning and disintegration due to the reasons of long line, construction period, river, lake and sea downward crossing, no vertical shaft condition on the ground and the like. At present, the construction method of shield tunneling in opposite directions and butt joint in the international world is divided into two forms, namely direct butt joint and auxiliary butt joint. The direct butt joint utilizes a telescopic cutter head to reduce the diameter of the cutter head and slowly retract the cutter head, and simultaneously, an insert ring stored in a shield shell extends out to enter a reserved receiving groove of another shield, so that the butt joint precision requirement is high. The auxiliary butt joint method comprises a grouting reinforcement method and a freezing reinforcement method, when the stratum is reinforced by the grouting reinforcement method, two shield machines generally enter a preset butt joint area at the same time, then carry out stratum grouting reinforcement respectively, then tunnel to a grouting reinforcement intersection section for butt joint and communication, and finally sequentially remove internal components of the shield shell.
Chinese patent No. CN201310185114.3 discloses a freezing reinforcement simulation test method and apparatus suitable for shield ground docking, which uses a freezing apparatus to freeze and reinforce the soil around two fixed shield shells in a test box, and simulates an auxiliary docking method construction process for reinforcing the ground layer by a freezing method. The shield underground butt joint simulation process is simple, and the stability of the tunnel face in the processes of pressure relief and opening and cutter head dismantling is not researched. On the other hand, the research on the underground docking of the shield by adopting the grouting reinforcement method is rarely reported. In order to directly observe the flowing diffusion range of slurry during grouting and stratum strengthening, the chinese patent with application number CN201710193946.8 adopts transparent soil and laser sheet source for visual simulation, but the transparent soil is usually prepared by mixing amorphous silicon or fused silica sand with corresponding pore fluid, and it is difficult to restore the condition of real stratum (such as clay stratum).
Disclosure of Invention
The invention aims to provide a grouting reinforcement test device and a grouting reinforcement test method for simulating shield underground butt joint, which realize grouting reinforcement of shield butt joint under a complex seepage condition and have obvious effect.
In order to solve the technical problem, the invention provides a grouting reinforcement test device for simulating shield underground butt joint, which comprises a first shield machine, a second shield machine, a first grouting system and a second grouting system; the first shield machine and the second shield machine respectively comprise a shield tail, a middle shield, a front shield, an air brake and a cutter head in sequence; the first shield machine and the second shield machine are coaxially arranged, and a cutter head of the first shield machine is arranged opposite to cutter heads of a plurality of second shield machines at intervals;
the first grouting system comprises a first air compressor, a first pressure delivery pipe, a first pressure gauge, a first storage tank and a first grouting pipe; the second grouting system comprises a second air compressor, a second pressure delivery pipe, a second pressure gauge, a second storage tank and a second grouting pipe; two ends of the first pressure transmission pipe are respectively communicated with the first air compressor and the first storage tank, the first pressure gauge is connected with the first storage tank, and the first storage tank is communicated with the first grouting pipe; two ends of the second pressure transmission pipe are respectively communicated with the second air compressor and a second storage tank, the second pressure gauge is connected with the second storage tank, and the second storage tank is communicated with the second grouting pipe; the first grouting pipe extends from the first shield machine to a position between the first shield machine and a second shield machine, and the second grouting pipe extends from the first shield machine to a position above the second shield machine;
the horizontal seepage simulation device comprises a third air compressor, a third pressure transmission pipe, a third storage tank, a multi-way valve, a hose and a waste liquid collection box; two ends of the third pressure transmission pipe are respectively communicated with a third air compressor and a third storage tank, and the third storage tank is connected with a third pressure gauge; the third storage tank is connected with a plurality of hoses through multi-way valves; the hose is connected with the waste liquid collecting box.
In a preferred embodiment, the device further comprises a monitoring device, wherein the monitoring device comprises a proton thermal imaging detector, an earth pressure sensor, a turbidity meter and a strain gauge.
In a preferred embodiment, the proton thermal imaging detector comprises an electromagnetic wave transmitting and receiving antenna, a data collecting and converting device and an imaging display; the electromagnetic wave transmitting and receiving antenna is connected with a data acquisition and conversion device, and the data acquisition and conversion device is connected with the imaging display.
In a preferred embodiment, a second closing door and a first closing door are sequentially arranged between the cutterhead and the front shield of the first shield tunneling machine and the second shield tunneling machine; soil pressure sensors are respectively arranged at different heights of the first closing door; the first closed door, the cutter head, the front shield, the middle shield and the shield tail form a soil chamber, and the soil pressure sensor is used for detecting soil pressure values at different heights in the soil chamber.
In a preferred embodiment, the turbidity instrument is used for detecting the turbidity degree of the waste liquid, and the turbidity degree of the waste liquid reflects the migration degree of the grouting reinforcement liquid which is wrapped by seepage; the strain gauges are arranged on the inner side faces of the first shield tunneling machine and the second shield tunneling machine and used for monitoring the stress and deformation of the shield shell after the internal components of the first shield tunneling machine and the second shield tunneling machine are removed.
In a preferred embodiment, the cutter head body comprises a plurality of spoke plates and a panel; a center block is arranged in the center of the cutter head; the spoke plates are rotationally and symmetrically distributed by taking the central block as a center; the panels are rotationally and symmetrically distributed by taking the central block as a center; the spoke plates and the panel are arranged at intervals.
In a preferred embodiment, a first grouting liquid mixed by water glass and phosphoric acid solution is arranged in the first storage tank, and a second grouting liquid mixed by water glass and cement paste is arranged in the second storage tank.
In a preferred embodiment, the first shield machine and the second shield machine are spaced by 0.25m;
first slip casting pipe by first shield constructs the machine stretch into to with the position of the blade disc interval 0.1m of first shield structure machine, second slip casting pipe by first shield constructs the machine stretch into to the top of second shield structure machine and with the position of the horizontal distance interval 0.4m of first shield structure machine.
In a preferred embodiment, the device further comprises a model box; the first shield tunneling machine and the second shield tunneling machine are placed in the model box; the periphery of the model box is composed of organic glass plates and metal frames; the organic glass plates are connected through a metal frame; and a plurality of horizontal seepage simulation holes are formed in the organic glass plates on the periphery of the model box.
The invention provides a test method of a grouting reinforcement test device for simulating shield underground butt joint, which adopts the grouting reinforcement test device for simulating shield underground butt joint and comprises the following steps:
step one, installing a shield butt joint simulation device; laying soil at the bottom of the model box, wherein the height of the soil is 0.62m, and the top surface of the soil is tangent to the bottom edges of the horizontal seepage simulation holes of the organic glass plates on the two sides; then, a first shield machine and a second shield machine are installed, all components inside the first shield machine and the second shield machine are connected in a welding mode, the spacing distance between the middle parts of the first shield machine and the second shield machine is set to be 0.25m, and the horizontal deviation and the vertical deviation of butt joint are set to be 20mm;
step two, applying an initial ground stress field and a seepage field: continuously laying soil in the model box to simulate the self-weight stress applied to the first shield machine and the second shield machine, and then injecting water and pressurizing on the top surface of the soil to simulate a vertical seepage field generated by seawater; meanwhile, water is injected into the horizontal seepage simulation hole of the organic glass plate on the left side for pressurization so as to simulate horizontal seepage along the flowing direction of grouting reinforcement slurry; a plurality of waste liquid collecting boxes are arranged on the right side of the model box, waste liquid in the waste liquid collecting boxes is regularly collected every 2min, and the turbidity degree of the waste liquid is analyzed by a turbidity liquid instrument to judge the loss amount of the slurry;
step three, grouting reinforcement: during grouting, iron powder is doped into the slurry, the first grouting liquid is injected from the middle shield to 0.1m in front of the cutter head, and the second grouting liquid is injected from 0.1m to 0.4m in front of the cutter head; the grouting is mainly controlled by pressure and assisted by grouting amount control, namely, when the grouting pressure reaches a set value, the grouting can be stopped; meanwhile, a test bed is arranged at a position 1m away from a glass plate in front of the model box, and a proton thermal imager arranged on the test bed can carry out real-time 3D imaging on the diffusion range of the grouting reinforcement liquid;
fourthly, dismantling internal components of the shield tunneling machine: firstly, pressure relief and bin opening are carried out, and then a second closing plate, a first closing plate and a cutter head are sequentially dismounted; when the panel and the spokes are dismantled, the spokes are cut off in different areas according to the principle of symmetrical dismantling.
Compared with the prior art, the technical scheme of the invention has the following beneficial effects:
1. the testing device can perform 3D imaging on the diffusion range of the iron powder-doped grouting liquid through the proton thermal imaging detector, and can visually research the diffusion rule of the slurry and determine the reinforcement range.
2. The testing device can simulate the butt joint construction conditions under different conditions of transverse through errors and vertical through errors by adjusting the relative position of the underground butt joint shield tunneling machine.
3. According to the test device, through the strain gauge arranged on the inner side of the shield shell, stress and deformation caused by integral rigidity reduction of a shield machine after the inner component of the shield machine is removed can be researched, so that the strength requirement of the secondary lining is determined.
4. The testing device provided by the invention can be used for researching the self-supporting stability of the soil body after the shield machine opens the cabin under different middle partition distances by adjusting the middle partition soil body distance of the underground butt joint shield machine, and avoiding the unfavorable forms such as tensile damage and the like of the reinforced soil body.
5. The testing device provided by the invention can simulate the underground real seepage field condition by injecting water and pressurizing through the horizontal seepage holes of the organic glass plates on the periphery of the model box and the top of the model box.
6. The test device provided by the invention can simulate the construction process of tunnel face water-soil pressure balance and pressure relief and opening of the shield machine under the initial condition by adjusting the pressure in the air brake through the air compressor.
Drawings
FIG. 1 is an isometric view of a mold box testing apparatus of a grouting reinforcement testing apparatus for simulating shield underground docking in a preferred embodiment of the invention;
FIG. 2 is a grouting and pressurized piping diagram of a first shield tunneling machine in a preferred embodiment of the present invention;
FIG. 3 is a diagram of the internal components of a first shield tunneling machine in a preferred embodiment of the present invention;
FIG. 4 is a block diagram of a first grout tube in a preferred embodiment of the present invention;
FIG. 5 is a schematic illustration of the docking of a first shield machine and a second shield machine in a preferred embodiment of the present invention;
FIG. 6 is a schematic view of the cutter head structure in the preferred embodiment of the present invention;
fig. 7 is a diagram of the grouting reinforcement range in the preferred embodiment of the invention.
Detailed Description
The invention is further described with reference to the following figures and detailed description.
A test method of a grouting reinforcement test device for simulating shield underground butt joint adopts a grouting reinforcement test device for simulating shield underground butt joint, and referring to figures 1 to 6, the grouting reinforcement test device for simulating shield underground butt joint comprises a first shield machine 25, a second shield machine 30, a first grouting system and a second grouting system; the first shield machine 25 and the second shield machine 30 respectively comprise a shield tail 36, a middle shield 35, a front shield 34, an air brake and a cutter head 26 in sequence; the first shield tunneling machine 25 and the second shield tunneling machine 30 are coaxially arranged, and the cutterhead 26 of the first shield tunneling machine 25 is arranged opposite to the cutterheads 26 of the plurality of second shield tunneling machines 30 at intervals; the first grouting system comprises a first air compressor 1, a first pressure delivery pipe 2, a first pressure gauge 9, a first storage tank 3 and a first grouting pipe 4; the second grouting system comprises a second air compressor 5, a second pressure delivery pipe 6, a second pressure gauge 10, a second storage tank 7 and a second grouting pipe 8; two ends of the first pressure transmission pipe 2 are respectively communicated with the first air compressor 1 and the first storage tank 3, the first pressure gauge 9 is connected with the first storage tank 3, and the first storage tank 3 is communicated with the first grouting pipe 4; the first grouting pipe 4 is changed from a path to two paths by a three-way valve 37; two ends of the second pressure transmission pipe 6 are respectively communicated with the second air compressor 5 and a second storage tank 7, the second pressure gauge 10 is connected with the second storage tank 7, and the second storage tank 7 is communicated with the second grouting pipe 8; the first grouting pipe 4 extends from the first shield tunneling machine 25 to a position between the first shield tunneling machine 25 and the second shield tunneling machine 30, and the second grouting pipe 8 extends from the first shield tunneling machine 25 to a position above the second shield tunneling machine 30; the device also comprises a horizontal seepage simulation device, wherein the horizontal seepage simulation device comprises a third air compressor 19, a third pressure delivery pipe 20, a third storage tank 21, a multi-way valve 23, a hose 24 and a waste liquid collection box 18; two ends of the third pressure transmission pipe 20 are respectively communicated with a third air compressor 19 and a third storage tank 21, and the third storage tank 21 is connected with a third pressure gauge 22; the third storage tank 21 is connected with a plurality of hoses 24 through a multi-way valve 23; the hose 24 is connected to the waste collection tank 18.
Specifically, the device further comprises a monitoring device, wherein the monitoring device comprises a proton thermal imaging detector, an earth pressure sensor, a turbid liquid instrument 17 and a strain gauge. The testing device can perform 3D imaging on the diffusion range of the iron powder-doped grouting liquid through the proton thermal imaging detector, and can visually research the diffusion rule of the slurry and determine the reinforcement range.
The proton thermal imaging detector comprises an electromagnetic wave transmitting and receiving antenna 15, a data acquisition and conversion device 16 and an imaging display; the electromagnetic wave transmitting and receiving antenna 15 is connected with a data acquisition and conversion device 16, and the data acquisition and conversion device 16 is connected with the imaging display.
A second closing door 28 and a first closing door 27 are further sequentially arranged between the cutterhead 26 and the front shield 34 of the first shield tunneling machine 25 and the second shield tunneling machine 30; soil pressure sensors are respectively arranged at different heights of the first closing door 27; the first closing door 27, the cutter head 26, the front shield 34, the middle shield 35 and the shield tail 36 form a soil chamber, and the soil pressure sensor is used for detecting soil pressure values at different heights in the soil chamber. The second closing door 28, the first closing door 27 and the shield 29 together form an air lock, and the pressure in the air lock is adjusted by an air compressor on the outer side to balance the water and soil pressure on the tunnel face.
The turbid liquid instrument 17 is used for detecting the turbidity degree of the waste liquid, and the turbidity degree of the waste liquid reflects the migration degree of the grouting reinforcement liquid wrapped by seepage; the strain gauges are arranged on the inner side surfaces of the first shield tunneling machine 25 and the second shield tunneling machine 30 and used for monitoring the stress and deformation of the shield shell 29 after the internal components of the first shield tunneling machine 25 and the second shield tunneling machine 30 are removed.
The cutter head 26 specifically comprises a plurality of spoke plates 32 and a panel 33; a center block 31 is arranged in the center of the cutter head 26; the spoke plates 32 are distributed along the rotation symmetry by taking the central block 31 as the center; the panels 33 are distributed in a rotationally symmetrical manner around the central block 31; the spoke plates 32 and the face plate 33 are arranged at intervals.
The first storage tank 3 is internally provided with a first grouting liquid mixed by water glass and phosphoric acid solution, and the second storage tank 7 is internally provided with a second grouting liquid mixed by water glass and cement paste. The first grouting liquid has lower strength, but good water stopping effect, and the second grouting liquid has higher strength.
The interval between the first shield tunneling machine 25 and the second shield tunneling machine 30 is 0.25m; the first shield tunneling machine 25 and the second shield tunneling machine 30 are formed by cylindrical steel drums with two unclosed ends, the outer diameter of each cylindrical steel drum is 0.62m, the inner diameter of each cylindrical steel drum is 0.606m, and the thickness of each cylindrical steel drum is 14mm.
First slip casting pipe 4 by first shield constructs quick-witted 25 stretch into with the position of the blade disc 26 interval 0.1m of first shield constructs quick-witted 25, second slip casting pipe 8 by first shield constructs quick-witted 25 stretch into to the top of second shield constructs quick-witted 30 and with the position of the horizontal distance interval 0.4m of first shield constructs quick-witted 25.
Also comprises a model box; the first shield tunneling machine 25 and the second shield tunneling machine 30 are placed in the model box; the periphery of the model box is composed of an organic glass plate 11 and a metal frame 12; the organic glass plates 11 are connected through a metal frame 12; and a plurality of horizontal seepage simulation holes 13 are formed in the organic glass plates 11 on the periphery of the model box. The mold box is a cuboid and has the size of 2.05m multiplied by 2.48m multiplied by 2.66m. The connection part of the organic glass plate 11 and the metal frame 12 is pasted with a water stop adhesive tape to prevent the model box from leaking. The lower positions of the middle parts of the organic glass plates 11 on the left side and the right side are both provided with an opening hole with the diameter of 0.31m, the circle centers of the opening holes are positioned on the same horizontal axis, the opening holes are mainly used for butting a shield shell 29 in a shield machine simulation device, and simultaneously grouting pipelines and soil pressure balance pipelines are convenient to arrange. Horizontal seepage simulation holes 13 are formed in the periphery of the model box, and the size of each horizontal seepage simulation hole is determined according to the soil permeability of the stratum where the shield is in underground butt joint.
A test method of a grouting reinforcement test device for simulating shield underground butt joint comprises the following steps:
step one, installing a shield butt joint simulation device; laying soil at the bottom of the model box, wherein the height of the soil is 0.62m, and the top surface of the soil is tangent to the bottom edges of the horizontal seepage simulation holes 13 of the organic glass plates 11 at the two sides; then, installing a first shield tunneling machine 25 and a second shield tunneling machine 30, connecting the internal components of the first shield tunneling machine 25 and the second shield tunneling machine 30 in a welding mode, setting the spacing distance between the middle of the first shield tunneling machine 25 and the middle of the second shield tunneling machine 30 to be 0.25m, and setting the horizontal deviation and the vertical deviation of the butt joint to be 20mm;
step two, applying an initial ground stress field and a seepage field: continuously laying soil in the model box to simulate the self-weight stress applied to the first shield tunneling machine 25 and the second shield tunneling machine 30, and then injecting water and pressurizing on the top surface of the soil to simulate a vertical seepage field generated by seawater; meanwhile, water is injected into the horizontal seepage simulation hole 13 of the organic glass plate 11 on the left side for pressurization so as to simulate horizontal seepage along the flowing direction of grouting reinforcement slurry; a plurality of waste liquid collecting boxes 18 are arranged on the right side of the model box, waste liquid in the waste liquid collecting boxes is regularly collected every 2min, and the turbidity of the waste liquid is analyzed by a turbid liquid instrument 17 to judge the loss amount of the slurry;
step three, grouting reinforcement: during grouting, iron powder is mixed into the slurry, the first grouting liquid is injected from the middle shield 35 to 0.1m in front of the cutter head 26, and the second grouting liquid is injected from 0.1m to 0.4m in front of the cutter head 26; the grouting is mainly controlled by pressure and assisted by grouting amount control, namely, when the grouting pressure reaches a set value, the grouting can be stopped; meanwhile, a test bed is arranged at a position 1m away from a glass plate in front of the model box, and a proton thermal imager arranged on the test bed can carry out real-time 3D imaging on the diffusion range of the grouting reinforcement liquid;
step four, dismantling the internal components of the shield tunneling machine: firstly, pressure relief and bin opening are carried out, and then the second closing door 28, the first closing door 27 and the cutter head 26 are sequentially removed; when the panel 33 and spokes are removed, the spokes are cut out in different areas according to the principle of symmetrical removal.
The testing device can simulate the butt joint construction conditions under different conditions of transverse through errors and vertical through errors by adjusting the relative position of the underground butt joint shield tunneling machine. Through the strain gauge arranged on the inner side of the shield shell 29, stress and deformation caused by the reduction of the integral rigidity of the shield shell after the inner component of the shield shell is removed can be researched, so that the strength requirement of the secondary lining can be determined. Through adjusting the distance of the soil body in the middle of the underground butt joint shield machine, the self-supporting stability of the soil body after the shield machine is opened at different middle distances can be researched, and unfavorable forms such as tensile damage and the like caused by the reinforced soil body are avoided. The underground real seepage field condition can be simulated by injecting water and pressurizing through the horizontal seepage holes of the organic glass plates 11 on the periphery of the model box and the top of the model box. The pressure in the air brake is adjusted through the air compressor, so that the construction process of tunnel face water-soil pressure balance and pressure relief and bin opening of the shield machine under the initial condition can be simulated.
The above description is only a preferred embodiment of the present invention, but the design concept of the present invention is not limited thereto, and any person skilled in the art can make insubstantial changes in the technical scope of the present invention within the technical scope of the present invention, and the actions infringe the protection scope of the present invention are included in the present invention.

Claims (1)

1. A test method of a grouting reinforcement test device for simulating shield underground butt joint is characterized by comprising a model box, a first shield machine, a second shield machine, a first grouting system and a second grouting system; the first shield machine and the second shield machine respectively comprise a shield tail, a middle shield, a front shield, an air brake and a cutter head in sequence; the first shield machine and the second shield machine are coaxially arranged, and a cutter head of the first shield machine and a cutter head of the second shield machine are oppositely arranged at intervals;
the first grouting system comprises a first air compressor, a first pressure delivery pipe, a first pressure gauge, a first storage tank and a first grouting pipe; the second grouting system comprises a second air compressor, a second pressure delivery pipe, a second pressure gauge, a second storage tank and a second grouting pipe; two ends of the first pressure transmission pipe are respectively communicated with the first air compressor and the first storage tank, the first pressure gauge is connected with the first storage tank, and the first storage tank is communicated with the first grouting pipe; two ends of the second pressure transmission pipe are respectively communicated with the second air compressor and a second storage tank, the second pressure gauge is connected with the second storage tank, and the second storage tank is communicated with the second grouting pipe; the first grouting pipe extends from the first shield machine to a position between the first shield machine and a second shield machine, and the second grouting pipe extends from the first shield machine to a position above the second shield machine;
the horizontal seepage simulation device comprises a third air compressor, a third pressure delivery pipe, a third storage tank, a multi-way valve, a hose and a waste liquid collecting box; two ends of the third pressure transmission pipe are respectively communicated with a third air compressor and a third storage tank, and the third storage tank is connected with a third pressure gauge; the third storage tank is connected with a plurality of hoses through multi-way valves; the hose is connected with a waste liquid collecting box;
the device also comprises a monitoring device, wherein the monitoring device comprises a proton thermal imaging detector, a soil pressure sensor, a turbid liquid instrument and a strain gauge;
the first shield tunneling machine and the second shield tunneling machine are placed in the model box; the periphery of the model box is composed of organic glass plates and metal frames; the organic glass plates are connected through a metal frame; a plurality of horizontal seepage simulation holes are formed in the organic glass plates on the periphery of the model box;
the proton thermal imaging detector comprises an electromagnetic wave transmitting and receiving antenna, a data acquisition and conversion device and an imaging display; the electromagnetic wave transmitting and receiving antenna is connected with a data acquisition and conversion device, and the data acquisition and conversion device is connected with the imaging display;
a second closing door and a first closing door are sequentially arranged between the cutterheads and the front shields of the first shield tunneling machine and the second shield tunneling machine; soil pressure sensors are respectively arranged at different heights of the first closing door; the first closing door, the cutter head, the front shield, the middle shield and the shield tail form a soil chamber, and the soil pressure sensor is used for detecting soil pressure values at different heights in the soil chamber;
the turbid liquid instrument is used for detecting the turbidity degree of the waste liquid, and the turbidity degree of the waste liquid reflects the migration degree of the grouting reinforcement liquid wrapped by seepage; the strain gauges are arranged on the inner side surfaces of the first shield tunneling machine and the second shield tunneling machine and used for monitoring the stress and deformation of the shield shell after the internal components of the first shield tunneling machine and the second shield tunneling machine are removed;
the cutter head specifically comprises a plurality of spoke plates and panels; a center block is arranged in the center of the cutter head; the spoke plates are rotationally and symmetrically distributed by taking the central block as a center; the panels are rotationally and symmetrically distributed by taking the central block as a center; the spoke plates and the panels are arranged at intervals;
a first grouting liquid mixed by water glass and phosphoric acid solution is arranged in the first storage tank, and a second grouting liquid mixed by water glass and cement paste is arranged in the second storage tank;
the interval between the first shield machine and the second shield machine is 0.25m;
the first grouting pipe extends from the first shield machine to a position which is 0.1m away from a cutter head of the first shield machine, and the second grouting pipe extends from the first shield machine to a position which is above the second shield machine and is 0.4m away from the first shield machine horizontally;
step one, installing a shield butt joint simulation device; laying soil at the bottom of the model box, wherein the height of the soil is 0.62m, and the top surface of the soil is tangent to the bottom edges of the horizontal seepage simulation holes of the organic glass plates on the two sides; then, a first shield machine and a second shield machine are installed, internal components of the first shield machine and the second shield machine are connected in a welding mode, the spacing distance between the middle of the first shield machine and the middle of the second shield machine is set to be 0.25m, and the horizontal deviation and the vertical deviation of butt joint are set to be 20mm;
step two, applying an initial ground stress field and a seepage field: continuously laying soil in the model box to simulate the self-weight stress applied to the first shield machine and the second shield machine, and then injecting water and pressurizing on the top surface of the soil to simulate a vertical seepage field generated by seawater; meanwhile, water is injected into the horizontal seepage simulation hole of the organic glass plate on the left side for pressurization so as to simulate horizontal seepage along the flowing direction of grouting reinforcement slurry; a plurality of waste liquid collecting boxes are arranged on the right side of the model box, waste liquid in the waste liquid collecting boxes is regularly collected every 2min, and the turbidity degree of the waste liquid is analyzed by a turbidity liquid instrument to judge the loss amount of the slurry;
step three, grouting reinforcement: during grouting, iron powder is doped into the slurry, the first grouting liquid is injected from the middle shield to 0.1m in front of the cutter head, and the second grouting liquid is injected from 0.1m to 0.4m in front of the cutter head; the grouting is mainly controlled by pressure and assisted by grouting amount control, namely, when the grouting pressure reaches a set value, the grouting can be stopped; meanwhile, a test bed is arranged at a position 1m away from a glass plate in front of the model box, and a proton thermal imager arranged on the test bed can carry out real-time 3D imaging on the diffusion range of the grouting reinforcement liquid;
fourthly, dismantling internal components of the shield tunneling machine: firstly, pressure relief and bin opening are carried out, and then a second closing plate, a first closing plate and a cutter head are sequentially dismounted; when the panel and the spokes are dismantled, the spokes are cut off in different areas according to the principle of symmetrical dismantling.
CN202110523376.0A 2021-05-13 2021-05-13 Grouting reinforcement test device and method for simulating shield underground butt joint Active CN113310849B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110523376.0A CN113310849B (en) 2021-05-13 2021-05-13 Grouting reinforcement test device and method for simulating shield underground butt joint

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110523376.0A CN113310849B (en) 2021-05-13 2021-05-13 Grouting reinforcement test device and method for simulating shield underground butt joint

Publications (2)

Publication Number Publication Date
CN113310849A CN113310849A (en) 2021-08-27
CN113310849B true CN113310849B (en) 2023-03-24

Family

ID=77373186

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110523376.0A Active CN113310849B (en) 2021-05-13 2021-05-13 Grouting reinforcement test device and method for simulating shield underground butt joint

Country Status (1)

Country Link
CN (1) CN113310849B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114017041B (en) * 2021-09-26 2024-01-30 深圳市政集团有限公司 Monitoring method for shield tail pressure balance

Family Cites Families (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103235110B (en) * 2013-05-17 2015-05-20 上海隧道工程股份有限公司 Freezing reinforcement simulation test method and freezing reinforcement simulation test device suitable for shield ground butt joint
JP6411099B2 (en) * 2014-07-07 2018-10-24 日本基礎技術株式会社 Ground injection method
CN205677624U (en) * 2016-06-27 2016-11-09 海南大学 Shield docks semi-circular shape consolidation by freezing structure
CN106907164A (en) * 2017-03-27 2017-06-30 中铁隧道勘测设计院有限公司 A kind of water-bed combination of mine shield tunnel docking structure form and its construction method
CN206862601U (en) * 2017-05-17 2018-01-09 华侨大学 It is a kind of to simulate the experimental rig that water slip casting is moved under a variety of water environments
CN109975177B (en) * 2019-04-30 2023-11-10 中南大学 Simulation test device and method for grouting diffusion form of horizontal grouting port
CN110397443A (en) * 2019-07-18 2019-11-01 重庆大学 A kind of pilot system and method for slurry shield model test
CN110297076A (en) * 2019-08-14 2019-10-01 中山大学 A kind of three-dimensional visible osmotic grouting model test apparatus and method
CN110566233B (en) * 2019-09-20 2021-04-09 成龙建设集团有限公司 Method for duct piece wall post-grouting in shield tunnel construction of full-section hard rock stratum
CN211877918U (en) * 2020-01-17 2020-11-06 中铁四院集团西南勘察设计有限公司 Test device for simulating shield tunnel grouting
CN111257538A (en) * 2020-02-20 2020-06-09 武汉大学 Fractured rock mass grouting simulation visualization test system and method considering stress effect
CN112324447B (en) * 2020-12-05 2022-04-29 中铁工程装备集团有限公司 Shield equipment capable of realizing underground butt joint and butt joint method

Also Published As

Publication number Publication date
CN113310849A (en) 2021-08-27

Similar Documents

Publication Publication Date Title
CN111983197B (en) Fracture rock mass grouting simulation visualization test system and test method considering stress effect
CN103926383B (en) Tunnel gushing water is dashed forward mud and Grouting three-dimensional model pilot system and test method thereof
CN203881738U (en) Three-dimensional model test system for treating water bursting, mud bursting and grouting of tunnel
CN111122337B (en) Segment soil pressure model test device and method considering shield tail wall post-grouting influence
CN106869949A (en) A kind of method that shield machine is received with steel bushing
CN205038028U (en) Seam waterproof performance test device that shield tunnel multichannel line of defence stagnant water is sealed
CN106761785A (en) A kind of subway tunnel shield originates construction technology
CN108548763B (en) Three-dimensional model test system and method for grouting reinforcement stability under erosion and seepage effects
CN108225934B (en) Testing system for external pressure resistance of lining steel pipe of water delivery tunnel
CN105973710A (en) Complicated jointed rock mass hydraulic coupling field tri-axial testing system and method
CN113310849B (en) Grouting reinforcement test device and method for simulating shield underground butt joint
CN107217676A (en) A kind of steel cylinder with seal groove and occlusion structure or steel sheet pile and steel construction diaphragm wall
CN113266376A (en) Model test device for simulating shield approaching underground structure micro-disturbance construction
CN109386293A (en) The sealed reception construction method of large section rectangular top pipe
CN108008118A (en) Seabed tunnel dynamic response experimental rig under tide simulation load action
CN110763183A (en) Model test device and test method for simulating concentrated stacking load in existing tunnel
CN113514232A (en) Segment floating model test device and method for simulating shield tunnel construction process
CN109668747B (en) Mechanical method connection channel heading machine receiving model test platform and test method thereof
CN216110731U (en) Model test device for simulating shield approaching underground structure micro-disturbance construction
CN203881737U (en) Rack device for tunnel excavating and grouting model test
CN105928794B (en) Built-in soil pressure calculation system
CN207923610U (en) A kind of test system of water-conveyance tunnel lined steel pipe critical external compressive resistance performance
CN207703848U (en) A kind of seabed tunnel experimental rig simulated by tidal action
CN210636473U (en) Indoor simulation test system for waterproof performance of underground continuous wall joint
CN202989929U (en) Underwater concrete guide pipe bottom sealing device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant