CN113239108A CN202110466313.6A CN202110466313A CN113239108A CN 113239108 A CN113239108 A CN 113239108A CN 202110466313 A CN202110466313 A CN 202110466313A CN 113239108 A CN113239108 A CN 113239108A
Authority
CN
China
Prior art keywords
information
data
forms
updating
logic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110466313.6A
Other languages
Chinese (zh)
Inventor
李前
孙瑞娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202110466313.6A priority Critical patent/CN113239108A/en
Publication of CN113239108A publication Critical patent/CN113239108A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/26Visual data mining; Browsing structured data
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/23Updating
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/04Manufacturing
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Databases & Information Systems (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • General Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Data Mining & Analysis (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • General Health & Medical Sciences (AREA)
  • Economics (AREA)
  • Health & Medical Sciences (AREA)
  • Manufacturing & Machinery (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a manufacturing industry information management system, a method, equipment and a storage medium, wherein the information management system comprises: the information input module: the system comprises a database, a data pool and a database, wherein the database is used for recording data information of each department into each form, setting the incidence relation among the forms and generating the data pool based on the incidence relation among the forms and the forms; a logic writing module: the system comprises a data processing system, a data processing system and a data processing system, wherein the data processing system is used for setting a flow relation among forms and compiling calculation logic among form data based on the flow relation; an information updating module: the data information in the data pool is extracted, and the related data information is automatically updated according to the computing logic; a chart generation module: and the chart is used for forming a chart required by a decision layer according to the data information in the data pool and updating the chart in real time according to the update of the data information. The data is real-time and accurate, the system interface is friendly, and the use is practical and scientific.

Description

Manufacturing information management system, method, device and storage medium
Technical Field
The invention relates to the technical field of information management in the metal plate production and processing and electrical assembly industries, in particular to a manufacturing industry information management system, method, equipment and storage medium.
Background
The existing commercial enterprise management information system mainly has the following problems: (1) because the system can only record the process data, real-time and accurate decision information cannot be flexibly provided according to the requirements of enterprises; (2) because the system customization and development difficulty is high and the threshold is high, any individual requirements of an enterprise need to be continuously invested into a software company to form a bottomless hole; (3) because the customization development period of the system is long, the flexible and changeable iteration requirements of an enterprise cannot be met; (4) because the basic logic formulation of the system is formed, the enterprise can only execute according to the established method, and therefore, the management method accumulated by the enterprise at present is difficult to be merged.
Disclosure of Invention
An object of the present invention is to provide a manufacturing information management system, method, apparatus, and storage medium, which aim to solve the above problems.
The invention provides a manufacturing information management system, comprising:
the information input module: the system comprises a database, a data pool and a database, wherein the database is used for recording data information of each department into each form, setting the incidence relation among the forms and generating the data pool based on the incidence relation among the forms and the forms;
a logic writing module: the system comprises a data processing system, a data processing system and a data processing system, wherein the data processing system is used for setting a flow relation among forms and compiling calculation logic among form data based on the flow relation;
an information updating module: the data information in the data pool is extracted, and the related data information is automatically updated according to the computing logic;
a chart generation module: and the chart is used for forming a chart required by a decision layer according to the data information in the data pool and updating the chart in real time according to the update of the data information.
The invention provides an information management method, which comprises the following steps:
recording data information of each department into each form, setting an incidence relation among the forms, and generating a data pool based on the incidence relation among the forms and the forms;
setting a flow relation among forms, and compiling calculation logic among form data based on the flow relation;
extracting the data information in the data pool, and automatically updating the related data information according to the calculation logic;
and forming a chart required by a decision layer according to the data information in the data pool, and updating the chart in real time according to the updating of the data information.
An embodiment of the present invention further provides an information management apparatus, including: a memory, a processor and a computer program stored on the memory and executable on the processor, the computer program, when executed by the processor, implementing the steps of the above-described information management method.
The embodiment of the invention also provides a computer readable storage medium, wherein an implementation program for information transmission is stored on the computer readable storage medium, and the implementation program realizes the steps of the information management method when being executed by a processor.
By adopting the embodiment of the invention, all layers of an enterprise can obtain required real-time and accurate decision data; because the system adopts a Chinese table programming method, enterprises can completely cultivate the existing managers to engage in the iterative development work of the system without additional investment; the simplicity of system logic determines that an enterprise can flexibly realize system updating iteration within minutes to hours; although the system has an existing management method, the friendly bottom logic of the system can contain most management modes and methods, and the actual needs of all levels of enterprises are highly combined with the application products of the existing scientific management method, so that the system is scientific and practical.
The foregoing description is only an overview of the technical solutions of the present invention, and the embodiments of the present invention are described below in order to make the technical means of the present invention more clearly understood and to make the above and other objects, features, and advantages of the present invention more clearly understandable.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, and it is obvious that the drawings in the following description are some embodiments of the present invention, and other drawings can be obtained by those skilled in the art without creative efforts.
FIG. 1 is a flow chart of an information management method of an embodiment of the present invention;
FIG. 2 is a flow diagram of an information management system data platform according to an embodiment of the invention;
FIG. 3 is a schematic diagram of an information management system according to an embodiment of the present invention;
FIG. 4 is a schematic diagram of an information management apparatus of an embodiment of the present invention;
FIG. 5 is a diagram illustrating the completion and load hours status of each team in an embodiment of the present invention;
FIG. 6 is a block diagram illustrating the direction of production commissioning and delaying of part count in an embodiment of the present invention;
FIG. 7 is a distribution of production man-hours in an embodiment of the present invention.
Detailed Description
The technical solutions of the present invention will be described clearly and completely with reference to the following embodiments, and it should be understood that the described embodiments are some, but not all, embodiments of the present invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", and the like, indicate orientations and positional relationships based on those shown in the drawings, and are used only for convenience of description and simplicity of description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be considered as limiting the present invention.
Furthermore, the terms "first", "second" and "first" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, features defined as "first", "second", may explicitly or implicitly include one or more of the described features. In the description of the present invention, "a plurality" means two or more unless specifically defined otherwise. Furthermore, the terms "mounted," "connected," and "connected" are to be construed broadly and may, for example, be fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Method embodiment
According to an embodiment of the present invention, an information management method is provided, fig. 1 is a flowchart of the information management method according to the embodiment of the present invention, and as shown in fig. 1, the information management method according to the embodiment of the present invention specifically includes:
s1, recording data information of each department into each form, setting an incidence relation among the forms, and generating a data pool based on the forms and the incidence relation among the forms.
Specifically, the data information of each department includes: the special process processing information records different process routes of the parts to the special process links such as welding and coating, and the colors of bar code paper for marking the different routes, so that color separation printing of the part identification bar codes is realized.
And S2, setting a flow relation among the forms, and compiling calculation logic among the form data based on the flow relation.
Specifically, compiling a calculation logic for automatically calculating the total quantity of the same parts and outsourcing parts of each part of the whole computer according to the hierarchical relationship in an Excel table; compiling a calculation logic for automatically calculating the upper and lower process relations of the process of each figure number according to the process route; and compiling calculation logic for generating the purchase suggested quantity by extracting data of the past 1 month and 3 months and comparing the data with the existing consumption.
And S3, extracting the data information in the data pool, and automatically updating the related data information according to the calculation logic.
Specifically, there are two cases of data update: firstly, manually changing data in the form according to each department, simultaneously updating the data in the data pool, and acquiring the updated data updating form from the data pool by using other forms using the data; and after the data which can be manually input or can be directly acquired from the data pool is updated, other data in the form, which have a logical operation relation with the data, is updated according to the calculation result of the corresponding calculation logic and is updated into the data pool, so that the data in other related forms can be updated conveniently.
And S4, forming a chart required by a decision layer according to the data information in the data pool, and updating the chart in real time according to the updating of the data information.
By adopting the embodiment of the invention, all layers of an enterprise can obtain required real-time and accurate decision data; because the system adopts a Chinese table programming method, enterprises can completely cultivate the existing managers to engage in the iterative development work of the system without additional investment; the simplicity of system logic determines that an enterprise can flexibly realize system updating iteration within minutes to hours; although the system has an existing management method, the friendly bottom logic of the system can contain most management modes and methods, and the actual needs of all levels of enterprises are highly combined with the application products of the existing scientific management method, so that the system is scientific and practical.
System embodiment
According to an embodiment of the present invention, a manufacturing information management system is provided, fig. 3 is a schematic diagram of an information management system according to an embodiment of the present invention, and as shown in fig. 3, the manufacturing information management system according to an embodiment of the present invention specifically includes:
the information entry module 30: the data pool is used for recording the data information of each department into each form, setting the incidence relation among the forms and generating the data pool based on the incidence relation among the forms and the forms.
The information entry module 30 is specifically configured to: acquiring required information of each department which is respectively input into the production process through a form, wherein the required information comprises the following steps: order information, production material information, special process information, assembly information and purchase quantity information; and associating all the forms according to the relation among the form fields to generate a data pool.
The logic writing module 32: the method is used for setting the flow relation among the forms and compiling the calculation logic among the form data based on the flow relation.
The logic writing module 32 is specifically configured to write a data calculation method in a form, and includes:
automatically calculating the total number of the same parts and purchased parts of each part of the whole computer according to the hierarchical relationship;
automatically calculating the upper and lower process relations of the technological process of each figure number according to the technological route;
and generating the recommended quantity of purchase by extracting the data of the past 1 month and 3 months and comparing the data with the current consumption.
The information updating module 34: the data information in the data pool is extracted, and the related data information is automatically updated according to the computing logic.
The information updating module 34 is specifically configured to: updating the information of each form according to the input of new data or the calculation result of the calculation logic in the form; and updating the related information in other forms according to the incidence relation among the forms.
The chart generation module 36: and the chart is used for forming a chart required by a decision layer according to the data information in the data pool and updating the chart in real time according to the update of the data information.
Fig. 2 is a flowchart of a data platform of an information management system according to an embodiment of the present invention, and as shown in fig. 2, the data platform of the information management system according to the embodiment of the present invention includes four parts, namely, order processing, self-made product production, outsourced supply, and material supply.
The order processing section includes: customer information: the basic information and the product category of the client are maintained, and later-stage contract classification statistics and classification tracking are facilitated; material table (finished product): a simple and unique identification number is corresponding to the product; detail of the sales contract: the system is used for issuing production requirements, counting contract amount and tracking orders; selling invoices: the data is from the sales contract, and the finished product is used for reconciling with the customer and making an invoice after being completely delivered, so that an order closed loop is formed.
The self-made part production part comprises: after the contract is issued, the plan is combined with the customer requirements and the product processes, the final reply delivery time and the final technical arrangement production time are given, the process sequence can be directly calculated for old materials without BOM, the process flow card can be filled after the delivery is confirmed, the process operation is carried out, the production plan is scheduled, the start date is respectively arranged for all processes of the product, two flow directions of the self-made parts and the outside cooperation parts are arranged after the link, the self-made parts flow to the dispatching lists of all production processes to guide all teams to produce, and the team leader allocates tasks to the team after balancing the task. In the production process, the raw material part required to be used is filled in a material receiving list by production personnel so as to facilitate the timely and accurate material preparation of a raw material warehouse. After the product is finished, the reporting work of the procedure is carried out, namely, the operation sheet is carried out. And after the final procedure is reported, checking to confirm whether the finished product is qualified. If the contract is qualified, continuing to transfer to a finished product inspection task list downwards until finished products are put in storage and taken out of the storage, wherein the result of the out-of-storage influences contract invoicing information; if the work piece is unqualified, an unqualified product examination order is opened by inspection, an examination result is given by an examination group, the work piece is repaired or reworked, a rework repair order is filled, and after the work piece is rearranged by a plan, the repaired work piece is returned to the process dispatching order by the identity of the reworked work piece.
The external cooperation supply part: the difference between the flow of the production plan to the outside cooperation parts after production scheduling and the flow of the production plan to the outside cooperation parts and the self-made parts is that the outside cooperation parts need to be commissioned for processing, and the outside cooperation parts fill in the outside cooperation work order. If the outsourced materials have prices, the outsourced materials are transferred to an outsourced order and the outsourced order is sent to the customer supplier; if no price exists, the three price comparisons are needed to fill out the external cooperation inquiry order, the leader confirms the winning bid supplier and the price on the external cooperation price confirmation table and then refers to the external cooperation order, the external cooperation supplier finishes processing according to the requirement and needs to fill out the external cooperation delivery order according to the requirement, and after the receiving quantity and the qualified quantity are confirmed by the other party, the other party can check the account and fill out the external cooperation check order. The invoicing information informs the outsource factory of paying after invoicing, and finally the closed loop of the outsource is realized.
A material supply part: the other link of the delivery period confirmation table is material supply, and after the delivery period confirmation table gives a technical plan date, technical responsible persons need to fill in a drawing task dispatching list and issue tasks to designers according to the characteristics of the tasks. The material table is an important basic data support and an important process for classifying, coding and maintaining information of each material. The design BOM is an important form filled by a designer and determines the lower-layer parts and material details of the product. The lower-layer part needs to provide PDF drawings or electronic drawings, and the accessory is hung on the platform for subsequent picture checking. The material specification of the outsourcing part can be combined with a specific task order number, a BOM operation task sheet is filled in by purchasing, batch material information is calculated, whether purchasing needs to be implemented or not is discriminated by a purchaser after operation, a purchasing distribution sheet is filled in, and available inventory is calculated by combining the current inventory with occupied, in-transit and safety inventory, so that whether order placing or order closing processing needs to be carried out on a supplier or not is determined, the purchasing order needs to be issued, if the price exists, the purchasing order is directly filled in, and the price, the delivery period and the like are confirmed by the supplier; if no price exists, the outsourcing enquiry list needs to be filled, three price comparisons are carried out, the outsourcing price examination and approval table is filled, the leader determines the winning manufacturer and the price, and the confirmed price information is brought into the purchase order. After the supplier sends the goods according to the requirement, the raw material storehouse receives the materials, fills in the raw material warehousing list, maintains the actual receiving quantity to form the inventory so as to fill in the raw material delivery list when the production receives the materials and to carry out the material delivery. After the order is put in storage, the purchase can inform the supplier to make an invoice and maintain the purchase invoice according to the actual receiving condition, so that the closed loop of the purchase flow is realized.
Fig. 5, 6, and 7 are partial graphs generated by embodiments of the present invention.
Apparatus embodiment one
An embodiment of the present invention provides an information management apparatus, as shown in fig. 4, including: a memory 40, a processor 42 and a computer program stored on the memory 40 and executable on the processor 42, which computer program, when executed by the processor 42, carries out the following method steps:
s1, recording data information of each department into each form, setting an incidence relation among the forms, and generating a data pool based on the forms and the incidence relation among the forms.
Specifically, the data information of each department includes: the special process processing information records different process routes of the parts to the special process links such as welding and coating, and the colors of bar code paper for marking the different routes, so that color separation printing of the part identification bar codes is realized.
And S2, setting a flow relation among the forms, and compiling calculation logic among the form data based on the flow relation.
Specifically, compiling a calculation logic for automatically calculating the total quantity of the same parts and outsourcing parts of each part of the whole computer according to the hierarchical relationship in an Excel table; compiling a calculation logic for automatically calculating the upper and lower process relations of the process of each figure number according to the process route; and compiling calculation logic for generating the purchase suggested quantity by extracting data of the past 1 month and 3 months and comparing the data with the existing consumption.
And S3, extracting the data information in the data pool, and automatically updating the related data information according to the calculation logic.
Specifically, there are two cases of data update: firstly, manually changing data in the form according to each department, simultaneously updating the data in the data pool, and acquiring the updated data updating form from the data pool by using other forms using the data; and after the data which can be manually input or can be directly acquired from the data pool is updated, other data in the form, which have a logical operation relation with the data, is updated according to the calculation result of the corresponding calculation logic and is updated into the data pool, so that the data in other related forms can be updated conveniently.
And S4, forming a chart required by a decision layer according to the data information in the data pool, and updating the chart in real time according to the updating of the data information.
Device embodiment II
The embodiment of the present invention provides a computer-readable storage medium, on which an implementation program for information transmission is stored, and when being executed by the processor 52, the implementation program implements the following method steps:
s1, recording data information of each department into each form, setting an incidence relation among the forms, and generating a data pool based on the forms and the incidence relation among the forms.
Specifically, the data information of each department includes: the special process processing information records different process routes of the parts to the special process links such as welding and coating, and the colors of bar code paper for marking the different routes, so that color separation printing of the part identification bar codes is realized.
And S2, setting a flow relation among the forms, and compiling calculation logic among the form data based on the flow relation.
Specifically, compiling a calculation logic for automatically calculating the total quantity of the same parts and outsourcing parts of each part of the whole computer according to the hierarchical relationship in an Excel table; compiling a calculation logic for automatically calculating the upper and lower process relations of the process of each figure number according to the process route; and compiling calculation logic for generating the purchase suggested quantity by extracting data of the past 1 month and 3 months and comparing the data with the existing consumption.
And S3, extracting the data information in the data pool, and automatically updating the related data information according to the calculation logic.
Specifically, there are two cases of data update: firstly, manually changing data in the form according to each department, simultaneously updating the data in the data pool, and acquiring the updated data updating form from the data pool by using other forms using the data; and after the data which can be manually input or can be directly acquired from the data pool is updated, other data in the form, which have a logical operation relation with the data, is updated according to the calculation result of the corresponding calculation logic and is updated into the data pool, so that the data in other related forms can be updated conveniently.
And S4, forming a chart required by a decision layer according to the data information in the data pool, and updating the chart in real time according to the updating of the data information.
The computer-readable storage medium of this embodiment includes, but is not limited to: ROM, RAM, magnetic or optical disks, and the like.
It will be apparent to those skilled in the art that the modules or steps of the present invention described above may be implemented by a general purpose computing device, they may be centralized on a single computing device or distributed across a network of multiple computing devices, and alternatively, they may be implemented by program code executable by a computing device, such that they may be stored in a storage device and executed by a computing device, and in some cases, the steps shown or described may be performed in an order different than that described herein, or they may be separately fabricated into individual integrated circuit modules, or multiple ones of them may be fabricated into a single integrated circuit module. Thus, the present invention is not limited to any specific combination of hardware and software.
Finally, it should be noted that: the above embodiments are only used to illustrate the technical solution of the present invention, and not to limit the same; while the invention has been described in detail and with reference to the foregoing embodiments, it will be understood by those skilled in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some or all of the technical features may be equivalently replaced; and the modifications or the substitutions do not make the essence of the corresponding technical solutions depart from the scope of the technical solutions of the embodiments of the present invention.

Claims (10)

1. A manufacturing information management system, comprising:
the information input module: the system comprises a database, a data pool and a database, wherein the database is used for recording data information of each department into each form, setting the incidence relation among the forms and generating the data pool based on the incidence relation among the forms and the forms;
a logic writing module: the system comprises a data processing system, a data processing system and a data processing system, wherein the data processing system is used for setting a flow relation among forms and compiling calculation logic among form data based on the flow relation;
an information updating module: the data information in the data pool is extracted, and the related data information is automatically updated according to the computing logic;
a chart generation module: and the chart is used for forming a chart required by a decision layer according to the data information in the data pool and updating the chart in real time according to the update of the data information.
2. The manufacturing industry information management system of claim 1, wherein the information entry module is configured to: acquiring required information of each department which is respectively input into the production process through a form, wherein the required information comprises the following steps: order information, production material information, special process information, assembly information and purchase quantity information; and associating all the forms according to the relation among the form fields to generate a data pool.
3. The manufacturing information management system of claim 1, wherein the logic writing module is specifically configured to write a data calculation method in a form, and comprises:
automatically calculating the total number of the same parts and purchased parts of each part of the whole computer according to the hierarchical relationship;
automatically calculating the upper and lower process relations of the technological process of each figure number according to the technological route;
and generating the recommended quantity of purchase by extracting the data of the past 1 month and 3 months and comparing the data with the current consumption.
4. The manufacturing information management system of claim 1, wherein the information update module is configured to: updating the information of each form according to the input of new data or the calculation result of the calculation logic in the form; and updating the related information in other forms according to the incidence relation among the forms.
5. An information management method, characterized in that the method comprises:
recording data information of each department into each form, setting an incidence relation among the forms, and generating a data pool based on the incidence relation among the forms and the forms;
setting a flow relation among forms, and compiling calculation logic among form data based on the flow relation;
extracting the data information in the data pool, and automatically updating the related data information according to the calculation logic;
and forming a chart required by a decision layer according to the data information in the data pool, and updating the chart in real time according to the updating of the data information.
6. The information management method according to claim 5, wherein the data information of each department specifically includes: order information, production material information, special process information, assembly information and purchase quantity information.
7. The information management method according to claim 5, wherein the writing of the calculation logic between the form data based on the flow relation specifically includes:
compiling a calculation logic for automatically calculating the total quantity of the same parts and purchased parts of each part of the whole computer according to the hierarchical relationship;
compiling a calculation logic for automatically calculating the upper and lower process relations of the process of each figure number according to the process route;
and compiling calculation logic for generating purchase suggested quantity by extracting data of the past 1 month and 3 months and comparing the data with the existing consumption.
8. The information management method according to claim 5, wherein the automatically updating the related data information according to the computation logic specifically comprises: updating the information of each form according to the input of new data or the calculation result of the calculation logic in the form; and updating the related information in other forms according to the incidence relation among the forms.
9. An information management apparatus characterized by comprising: memory, processor and computer program stored on the memory and executable on the processor, which computer program, when executed by the processor, carries out the steps of the information management method according to any one of claims 5 to 8.
10. A computer-readable storage medium, characterized in that the computer-readable storage medium has stored thereon an implementation program of information transfer, which when executed by a processor implements the steps of the information management method according to any one of claims 5 to 8.
CN202110466313.6A 2021-04-28 2021-04-28 Manufacturing information management system, method, device and storage medium Pending CN113239108A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110466313.6A CN113239108A (en) 2021-04-28 2021-04-28 Manufacturing information management system, method, device and storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110466313.6A CN113239108A (en) 2021-04-28 2021-04-28 Manufacturing information management system, method, device and storage medium

Publications (1)

Publication Number Publication Date
CN113239108A true CN113239108A (en) 2021-08-10

Family

ID=77129705

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110466313.6A Pending CN113239108A (en) 2021-04-28 2021-04-28 Manufacturing information management system, method, device and storage medium

Country Status (1)

Country Link
CN (1) CN113239108A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103745311A (en) * 2013-12-25 2014-04-23 天通精电新科技有限公司 Production data management information system
CN104599015A (en) * 2013-11-01 2015-05-06 正将自动化设备(江苏)有限公司 Management method of daily workflow and funds of mechanism manufacturing enterprise
CN106296087A (en) * 2016-08-04 2017-01-04 中冶赛迪电气技术有限公司 A kind of Spare Parts Inventory Management System of Facing to Manufacturing industry
CN108132777A (en) * 2016-11-30 2018-06-08 上海驭创信息科技有限公司 Across the table exploitation system and method for one kind
CN108876267A (en) * 2018-09-05 2018-11-23 南通诚品软件科技有限公司 Household building materials shops quick order management system
CN111126748A (en) * 2019-10-30 2020-05-08 江山雷钧智能制造技术有限公司 Dynamic production plan scheduling method for discrete manufacturing industry
CN112330481A (en) * 2020-09-30 2021-02-05 上海民艳信息科技有限公司 Method for intelligently calculating delivery date in manufacturing industry

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104599015A (en) * 2013-11-01 2015-05-06 正将自动化设备(江苏)有限公司 Management method of daily workflow and funds of mechanism manufacturing enterprise
CN103745311A (en) * 2013-12-25 2014-04-23 天通精电新科技有限公司 Production data management information system
CN106296087A (en) * 2016-08-04 2017-01-04 中冶赛迪电气技术有限公司 A kind of Spare Parts Inventory Management System of Facing to Manufacturing industry
CN108132777A (en) * 2016-11-30 2018-06-08 上海驭创信息科技有限公司 Across the table exploitation system and method for one kind
CN108876267A (en) * 2018-09-05 2018-11-23 南通诚品软件科技有限公司 Household building materials shops quick order management system
CN111126748A (en) * 2019-10-30 2020-05-08 江山雷钧智能制造技术有限公司 Dynamic production plan scheduling method for discrete manufacturing industry
CN112330481A (en) * 2020-09-30 2021-02-05 上海民艳信息科技有限公司 Method for intelligently calculating delivery date in manufacturing industry

Similar Documents

Publication Publication Date Title
Munyaka et al. Inventory management concepts and implementations: a systematic review
CN109034728A (en) A kind of purchase, sales and inventory management system
CN102346880B (en) Enterprise Resources Planning computer system and method
Tarhini et al. An integrated single-vendor multi-buyer production inventory model with transshipments between buyers
CN106127426A (en) A kind of the Internet shopping platform kinds of goods management method and system
CN101593302A (en) Supplier inventory management method
CN101593300A (en) Delivery management method of supply chain
Tahami et al. Multilevel Reorder Strategy-based Supply Chain Model
Barman et al. Two-echelon production inventory model with imperfect quality items with ordering cost reduction depending on controllable lead time
Taleizadeh et al. Optimization of price, lot size and backordered level in an EPQ inventory model with rework process
CN107679815A (en) Supplier inventory management system
CN101593301A (en) Delivery management system of supply chain
Singha et al. Computational experiment of methods to determine periodic (R, Q) inventory policy parameters: a case study of information decentralised distribution network
Rawat Today's inventory management systems: A tool in achieving best practices in indian business
US7650297B1 (en) System and method for managing returnable containers
CN113239108A (en) Manufacturing information management system, method, device and storage medium
Cha-ume et al. Meta-prediction model for introducing lateral transshipment policies in a retail supply chain network through regression analysis
JP7438041B2 (en) inventory evaluation device
Rabbani et al. Leagile supply chain network design through a dynamic two-phase optimization in view of order penetration point
Gokaram Narayana Murthy Production ramp-up of a hardware startup: developing inventory management strategies and establishing a framework for vendor selection
Rifai et al. Inventory Control and EOQ Forecasting Tools as Effective Decision-Making Model
Howard Inventory management in practice
SOLÍS et al. Inventory record inaccuracy causes: Case of study electronic industry
Malek et al. Supply chain material management framework in assemble to orders (ATO)
US20230169455A1 (en) Method and system for managing inventory

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210810

RJ01 Rejection of invention patent application after publication