CN113216218A - Cutting slope anti-slip structure and construction method thereof - Google Patents

Cutting slope anti-slip structure and construction method thereof Download PDF

Info

Publication number
CN113216218A
CN113216218A CN202110330956.8A CN202110330956A CN113216218A CN 113216218 A CN113216218 A CN 113216218A CN 202110330956 A CN202110330956 A CN 202110330956A CN 113216218 A CN113216218 A CN 113216218A
Authority
CN
China
Prior art keywords
pile
reinforcing rib
pile body
hole
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110330956.8A
Other languages
Chinese (zh)
Inventor
周小军
曹毅
王理吉
郝春华
林永胜
汪昭宇
许智威
杨喆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Merchants Chongqing Communications Research and Design Institute Co Ltd
Original Assignee
China Merchants Chongqing Communications Research and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Merchants Chongqing Communications Research and Design Institute Co Ltd filed Critical China Merchants Chongqing Communications Research and Design Institute Co Ltd
Priority to CN202110330956.8A priority Critical patent/CN113216218A/en
Publication of CN113216218A publication Critical patent/CN113216218A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The invention discloses a cut slope anti-slumping structure which comprises a plurality of pile bodies for fixing a soil foundation slumping layer, wherein the pile bodies are arranged in pile holes of a soil foundation; the pile body comprises a reinforcing rib of a plate-fin structure and a pile body pouring material; the reinforcing rib and the axis of the pile hole are coaxially arranged, and the pile body pouring material is located between the pile hole and the reinforcing rib. The construction method comprises the following steps: positioning and processing the pile hole; step two: (1) placing the reinforcing rib in the pile hole; (2) filling filler between the reinforcing rib and the pile hole; (3) the maintenance of the pile body is completed; step three: the exposed frameworks at the upper ends of two adjacent pile bodies are fixedly connected through a pile body connecting beam, and a concrete connecting beam is poured outside the pile body connecting beam. The invention has the advantages of small influence on the surrounding environment in the construction process, high construction speed and good supporting effect.

Description

Cutting slope anti-slip structure and construction method thereof
Technical Field
The invention relates to the technical field of civil engineering supports, in particular to a cutting slope anti-slip structure and a construction method thereof.
Background
China is a world mountain land and a large country, the area of the mountain land occupies about 2/3 of the total land and soil area, the terrain and geology of most mountain areas are complex, the natural environment conditions are fragile, high-grade roads are built in the mountain areas and are comprehensively influenced by climate, geology and construction activities, and the phenomenon that cutting slopes collapse frequently occurs in the road construction and operation processes. At present, a method and a structure for rapidly treating side slope landslide are urgently needed to prevent secondary damage of the side slope so as to ensure the safety and stability of the landslide side slope.
At present, the slope stability problem solved by the engineering world mainly has the following two aspects.
Firstly, unloading and clearing: adopt in the design and slow down the side slope, increase big platform, reduce the load of slope top, reduce gliding force. The method has simple construction process, but has the following problems: the newly increased land occupation is needed for relieving the side slope, and the method is not suitable for being adopted particularly when a structure is arranged on the top of the slope; a large amount of waste is added in the process of relieving the side slope, and outward transportation and stacking need to be considered; when the side slope is relieved, the rain season is avoided, and new landslide is probably caused by unreasonable slope cutting.
Secondly, supporting and blocking protection: in the design, the existing side slope is reinforced by adopting modes such as anti-slide piles, pile foundation joist retaining walls, anchor cables (rods) and the like, and the anti-slide force of a slope body or slope toe is increased. The method has wide application range, but has the following problems: the construction period of the anti-slide pile is long, and the square pile with better anti-slide capability cannot be constructed mechanically; the pile foundation joist retaining wall masonry amount is large, and the construction is complicated due to the fact that the pile foundation joist retaining wall relates to a plurality of structures such as a retaining wall, a joist and a pile foundation; the anchor cable (rod) has a service life as a steel member, and can be loosened with time, so that the anchoring force is reduced and even the anchor cable (rod) fails.
Therefore, in order to solve the above problems, a cutting slope collapse prevention structure is needed, and the cutting slope collapse prevention structure has a structure for treating slope collapse, which has the advantages of small influence on the surrounding environment in the construction process, high construction speed and good supporting effect.
Disclosure of Invention
In view of the above, the invention aims to overcome the defects in the prior art and provide a cutting slope anti-collapse structure and a construction method thereof.
The cut slope anti-slumping structure comprises a plurality of pile bodies for fixing soil foundation slumping layers, wherein the pile bodies are arranged in pile holes of a soil foundation, the pile holes are round holes, and mechanical pore forming can be adopted in construction, for example, small drilling machines are adopted for drilling. The pile body comprises a reinforcing rib of a plate-fin structure and a pile body pouring material, the reinforcing rib is vertically arranged in the pile hole and is coaxial with the axis of the pile hole, and the space between the pile hole and the reinforced rib is filled with the pile body pouring material; the reinforcing rib can be hoisted mechanically, the efficiency is high, and the bearing capacity can be exerted quickly. The end face of the wing plate in the plate-fin structure faces to the predicted slumping direction of the soil foundation slumping layer, and bending moment caused by the soil foundation slumping layer is resisted through the web plate. And because the reinforcing rib adopts a plate-fin structure, the pile body casting material is not easy to separate from the pile body casting material under the action of torque after being filled with the pile body casting material, and the pile body casting material is preferably concrete in the embodiment. In the plate-fin structure, the wing plates can be provided with a plurality of wing plates, and the included angle between the wing plates and the web plate is not limited to a right angle, namely, the included angle between the wing plates and the web plate can also be an acute angle or an obtuse angle.
Furthermore, a connecting beam for fixing the pile bodies is arranged between every two adjacent pile bodies. All the pile bodies are connected into a whole through the connecting beams, so that the bearing capacity of the pile bodies can be exerted, and all the pile bodies can resist the sliding force of the sliding layer.
Furthermore, the reinforcing rib is I-shaped steel, and the wing plate of the reinforcing rib faces to the collapse direction of the soil foundation collapse layer. Because the reinforcing rib adopts I-shaped steel, the diameter of the pile hole is 20 cm-50 cm. The preferred length of the pile hole is 20cm in the embodiment, so that the diameter of the pile hole is not too large, and the influence on the surrounding environment during pile hole machining is reduced. The connecting beam can also adopt a plate-fin structure, and is preferably I-shaped steel. In order to ensure the strength of the pile body, the strength of I-shaped steel used by the reinforcing ribs and the connecting beams is not lower than 14.
Furthermore, a plurality of positioning ribs for positioning the reinforcing ribs are regularly distributed between the reinforcing rib and the inner side wall of the pile hole along the axial direction, the positioning ribs can enable the reinforcing rib to be erected in the pile hole, and meanwhile, the axis of the reinforcing rib is overlapped with the axis of the pile hole. The thickness of the pile body pouring material between the reinforcing rib and the pile hole is ensured to be uniform, so that the pile body provides stable resistance to bear the thrust generated by slope collapse. Preferably, the positioning rib can be formed by bending a steel bar, the middle part of the positioning rib protrudes outwards and abuts against the inner side wall of the pile hole, and two ends of the positioning rib are welded with the reinforcing rib. The positioning ribs can also be formed by bending or welding metal pipes, metal plates and the like.
Further, the upper end of the pile body is connected with the connecting beam, and specifically, the upper end of the reinforcing rib extends out of the port of the pile hole and is connected with the connecting beam. The lower end of the pile body penetrates through the collapse layer and extends into the stable stratum, wherein the length of the pile body extending into the stable stratum is 1/3-1/2 of the total length of the pile body.
Further, the pile bodies are arranged in at least two rows along the collapse direction of the soil foundation collapse layer, and the adjacent two rows of pile bodies can be arranged in an aligned mode or in a staggered mode. The connecting beam comprises a cross beam and a longitudinal beam, and the cross beam can be welded with two adjacent reinforcing ribs in the same row by adopting shorter I-shaped steel; the cross beam can also adopt longer I-shaped steel, and the same row of reinforcing ribs are welded on the same cross beam. The longitudinal beams are positioned between two rows of adjacent reinforcing ribs.
The beam wing plates face the predicted slumping direction of the soil foundation slumping layer and are positioned on the same plane with the reinforcing rib wing plates and are welded and fixed, and the beam web plates are perpendicular to the reinforcing rib web plates. The longitudinal direction of the longitudinal beam is substantially the same as the expected slumping direction of the soil foundation slumping layer. The longitudinal beams can be welded with the reinforcing ribs and also can be welded with the cross beams. The distance between the pile bodies is not less than 3 times of the diameter of the pile hole, preferably 1m to 1.2m, and is 1m in the embodiment.
Furthermore, the connecting beam is coated with a protective layer. Each connecting beam can be independently coated with a protective layer to form a grid structure, and the protective layer can also coat all the connecting beams to form a plate-shaped structure.
A method for constructing a cutting slope anti-slip structure,
the method comprises the following steps: positioning and processing the pile hole;
step two: (1) placing the reinforcing rib in the pile hole; (2) pouring a pile body pouring material between the reinforcing ribs and the pile holes; (3) the maintenance of the pile body is completed;
and repeating the first step and the second step until all the pile bodies are poured and the maintenance is finished.
Step three: the reinforcing ribs exposed at the upper ends of two adjacent pile bodies are fixedly connected through a connecting beam, and a protective layer is coated outside the pile body connecting beam.
Further, in the first step, the pile holes are processed in a jumping mode at intervals; the pile hole spacing is not less than three times the diameter of the pile holes.
Further, the pile body penetrates through the soil foundation collapse layer to a stable stratum below the pile body; the length of the pile body for stabilizing the ground layer is 1/3-1/2 of the total length of the pile body.
The invention has the beneficial effects that: (1) the invention has simple structure, simple and convenient construction and short construction period; (2) the cross section of the pile hole is circular, and the hole can be formed by adopting mechanical methods such as a small-sized drilling machine and the like, so that the construction efficiency is improved; (3) the reinforcing rib is made of high-strength I-shaped steel, can be hoisted mechanically, and has high efficiency and quick bearing capacity; (4) the pile hole diameter is small, additional stress is hardly generated on the soil foundation body when the pile hole is processed, and the disturbance on the slope body of the existing side slope is small in the construction process, so that the construction risk and the construction difficulty are reduced; (5) the slope does not need to be slowed down, and the construction is not affected by rainy seasons.
Drawings
The invention is further described below with reference to the following figures and examples:
FIG. 1 is a perspective view of the cut slope collapse prevention structure of the present invention;
FIG. 2 is a structural diagram of a protective layer in the anti-slumping structure of the cutting slope of the present invention;
FIG. 3 is a floor plan of FIG. 2;
FIG. 4 is a cross-sectional view A-A of FIG. 3;
FIG. 5 is another structural diagram of a protective layer in the anti-slumping structure of the cutting slope of the invention;
FIG. 6 is a schematic view of a cut slope collapse prevention structure with reinforcing ribs placed in pile holes;
FIG. 7 is a cross-sectional view taken along line B-B of FIG. 6;
FIG. 8 is a schematic view of a cut slope collapse prevention structure with retaining wall sleeves arranged in pile holes;
FIG. 9 is a cross-sectional view taken along line D-D of FIG. 8;
FIG. 10 is a structural diagram of the connection of reinforcing ribs with cross beams and longitudinal beams in the cut slope anti-slip structure of the invention;
FIG. 11 is an enlarged view of C in FIG. 10;
FIG. 12 is a schematic view of a cut slope collapse prevention structure in which two adjacent rows of pile holes are staggered and coated with a protective layer;
FIG. 13 is another schematic view of the cut slope collapse prevention structure of the present invention, in which two adjacent rows of pile holes are staggered and covered with the protection layer;
FIG. 14 is a schematic diagram of a plate-fin structure adopted by a reinforcing rib in the cut slope anti-slip structure.
In the figure, 1 is a pile body, 2 is a stable stratum, 3 is a road, 4 is a road cutting slope surface, 5 is a potential slip surface, 6 is a protective wall sleeve, 7 is a slip layer, 11 is a pile hole, 12 is a pile body pouring material, 13 is a reinforcing rib, 13-1 is a reinforcing rib web, 13-2 is a reinforcing rib wing plate, 14 is a protective layer, 15 is a connecting beam, 15-1 is a cross beam, 15-11 is a cross beam web, 15-12 is a cross beam wing plate, 15-2 is a longitudinal beam, 15-21 is a longitudinal beam web, 15-22 is a longitudinal beam wing plate, and 16 is a positioning rib.
Detailed Description
The present invention will be further described with reference to the accompanying fig. 1 to 14 and the embodiments, it should be noted that in the description of the present invention, the terms "upper", "lower", and the like indicate the orientation or positional relationship based on the orientation or positional relationship shown in the drawings, which are only for convenience of describing the present invention and simplifying the description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific manner, and thus, should not be construed as limiting the present invention.
The cut slope anti-collapse structure comprises a plurality of pile bodies 1 for fixing a soil foundation collapse layer 7, wherein the pile bodies 1 are arranged in pile holes 11 of a soil foundation, the pile holes 11 are round holes, and mechanical hole forming can be adopted in construction, for example, small-sized drilling machines are adopted for drilling. If the pile hole 11 is formed, the hole wall is soft, the inner wall of the pile hole 11 can be firstly provided with the retaining wall sleeve 6, and then the pile body 1 is arranged in the retaining wall sleeve 6. The pile body 1 comprises a reinforcing rib 13 of a plate-fin structure and a pile body casting material 12, the reinforcing rib 13 is vertically arranged in the pile hole 11 and is coaxial with the axis of the pile hole 11, and the space between the pile hole 11 and the reinforcing rib 13 is filled with the pile body casting material 12; the reinforcing rib 13 can be hoisted mechanically, so that the efficiency is high and the bearing capacity is quickly developed. The end surfaces of the wing plates in the plate-fin structure face the predicted slumping direction of the soil foundation slumping layer 7, and bending moment caused by the soil foundation slumping layer 7 is resisted through the webs. And because the reinforcing rib 13 adopts a plate-fin structure, the pile body casting material 12 is not easy to separate from the pile body casting material 12 under the torque after being filled, and the pile body casting material 12 is preferably concrete in the embodiment. In the plate-fin structure, there may be a plurality of stiffening rib wing plates 13-2, and the included angle between the stiffening rib wing plate 13-2 and the stiffening rib web 13-1 is not limited to a right angle, i.e. the included angle between the stiffening rib wing plate 13-2 and the stiffening rib web 13-1 may also be an acute angle or an obtuse angle, as shown in fig. 14.
In this embodiment, a connecting beam 15 for fixing the pile body 1 is arranged between two adjacent pile bodies 1. All the pile bodies 1 are connected into a whole through the connecting beams 15, so that the bearing capacity of the pile bodies 1 can be exerted, and all the pile bodies 1 can resist the sliding force of the collapse layer 7.
In this embodiment, the reinforcing rib 13 is an i-steel, and the reinforcing rib wing plate 13-2 faces the collapsing direction of the soil foundation collapsing layer 7, as shown in fig. 10 and 11. Because the reinforcing rib 13 is made of I-shaped steel, the diameter of the pile hole 11 is 20 cm-50 cm. The preferred length of 20cm in this embodiment is to ensure that the diameter of the pile hole 11 is not too large, thereby reducing the influence on the surrounding environment when the pile hole 11 is machined. The connecting beam 15 may also be of a plate-fin structure, preferably an i-steel. In order to ensure the strength of the pile body 1, I-steel used by the reinforcing ribs 13 and the connecting beams 15 has the strength not lower than 14.
In this embodiment, a plurality of positioning ribs 16 for positioning the reinforcing rib 13 are regularly distributed between the reinforcing rib 13 and the inner side wall of the pile hole 11 along the axial direction, and the positioning ribs 16 can enable the reinforcing rib 13 to stand in the pile hole 11, and simultaneously enable the axis of the reinforcing rib 13 to coincide with the axis of the pile hole 11, as shown in fig. 6 and 7. The thickness of the pile body pouring material 12 between the reinforcing ribs 13 and the pile holes 11 is ensured to be uniform, so that the pile body 1 provides stable resistance to bear the thrust generated by slope collapse. Preferably, the positioning rib 16 is formed by bending a steel bar, the middle of the positioning rib 16 protrudes outwards and abuts against the inner side wall of the pile hole 11, and two ends of the positioning rib 16 are welded to the reinforcing rib 13. The positioning ribs 16 may be formed by bending or welding metal pipes or metal plates.
In this embodiment, the upper end of the pile body 1 is connected to the connecting beam 15, and specifically, the upper end of the reinforcing rib 13 extends out of the port of the pile hole 11 and is connected to the connecting beam 15. The lower end of the pile body 1 penetrates through the collapse layer 7 and extends into the stable stratum 2, wherein the length of the pile body 1 extending into the stable stratum 2 is 1/3-1/2 of the total length of the pile body 1.
In this embodiment, at least two rows of pile bodies 1 are arranged along the collapse direction of the soil foundation collapse layer 7, and two adjacent rows of pile bodies 1 can be aligned, as shown in fig. 3 and 4; alternatively, they may be arranged in a staggered arrangement, as shown in fig. 12 and 13. The connecting beam 15 comprises a cross beam 15-1 and a longitudinal beam 15-2, the cross beam 15-1 can be welded with two reinforcing ribs 13 adjacent to each other in the transverse row by adopting short I-steel, the longitudinal beam 15-2 is positioned between two reinforcing ribs 13 adjacent to each other in the longitudinal row, and two ends of the longitudinal beam 15-2 are respectively welded with the two reinforcing ribs 13; the cross beam 15-1 can also be made of longer I-shaped steel, the reinforcing ribs 13 in the same transverse row are welded on the same cross beam 15-1, the longitudinal beam 15-2 is positioned between two adjacent reinforcing ribs 13 in the longitudinal row, and two ends of the longitudinal beam 15-2 are respectively welded with the corresponding cross beam 15-1.
The beam wing plates 15-12 face the predicted slumping direction of the soil foundation slumping layer 7 and are positioned on the same plane with the reinforcing rib wing plates 13-2 and are welded and fixed, and the beam web plates 15-11 are perpendicular to the reinforcing rib web plates 13-1. The longitudinal direction of the longitudinal beam 15-2 is approximately the same as the predicted slumping direction of the soil foundation slumping layer 7, and the longitudinal beam web 15-21 is perpendicular to the reinforcing rib web 13-1. The longitudinal beam 15-2 can be welded with the reinforcing rib 13 and can also be welded with the cross beam 15-1. The distance between the pile bodies 1 is not less than 3 times of the diameter of the pile hole 11, preferably 1m to 1.2m, and 1m in the embodiment.
In this embodiment, the connection beam 15 is coated with a protective layer 14 to reinforce the integrity of the connection beam 15 and the reinforcing rib 13. Each connecting beam 15 can be individually coated with a protective layer 14 to form a grid structure, as shown in fig. 5 and 13; the protective layer 14 may also cover all the connecting beams 15 to form a plate-like structure, as shown in fig. 2, 3 and 12. The protective layer 14 is preferably concrete.
The method is not limited to rapidly treating the landslide of the road cutting slope, and is also suitable for reinforcing foundations such as cohesive soil, silt and sandy soil, artificial filling and the like.
A construction method of a cutting slope anti-slip device,
the method comprises the following steps: positioning and processing the pile hole 11;
(1) and (3) measurement and paying-off: and (3) according to the range and the position of the potential slip crack surface 5, adopting a GPS instrument or a theodolite to measure and sample, determining the working surface of the road cutting slope surface 4 to be treated, and positioning the pile hole 11.
(2) Positioning a drilling machine: and selecting mechanical modes such as a rotary drilling rig or a geological drill and the like.
(3) And (3) processing a group of pile holes 11, and additionally arranging a retaining wall sleeve 6 in a stratum with a weak interlayer in the pile holes 11.
Step two:
(1) welding a positioning rib 16 on the pile body 1 framework, and placing the pile body 1 framework in the pile hole 11 by using a drilling machine to hoist into the hole or a crane to hoist into the hole;
(2) then pouring concrete filler between the pile body 1 framework and the pile hole 11, and pressing slurry at the hole bottom of the slurry pump until the hole opening returns;
(3) the maintenance of the pile body 1 is completed;
and repeating the first step and the second step until all the pile bodies 1 are poured and the maintenance is finished.
Step three: the exposed frameworks of the pile bodies 1 at the upper ends of two adjacent pile bodies 1 are fixedly connected through a connecting beam 15, and a concrete protective layer 14 is poured outside the connecting beam 15 of the pile body 1.
In this embodiment, in the step one (3), the pile holes 11 in each row are processed by jumping at intervals; the pile holes 11 are spaced at intervals not less than three times the diameter of the pile holes 11.
In this embodiment, the pile body 1 penetrates through the soil foundation collapse layer 7 to the stable stratum 2 below; the length of the pile body 1 of the stable stratum 2 is 1/3-1/2 of the total length of the pile body 1.
According to the construction method of the cutting slope anti-slip device, the diameter of the processed pile hole 11 is small, so that the disturbance to the surrounding environment during drilling is small, and the construction difficulty can be further reduced. And the whole construction process can be basically and completely carried out by adopting mechanized construction, the construction efficiency is greatly improved, the construction time is shortened, the phenomenon that the road cutting side slope frequently collapses in the construction and operation processes of the highway 3 can be quickly treated, the secondary damage of the side slope is prevented, and the safety and the stability of the road cutting slope surface 4 are ensured.
Finally, the above embodiments are only for illustrating the technical solutions of the present invention and not for limiting, although the present invention has been described in detail with reference to the preferred embodiments, it should be understood by those skilled in the art that modifications or equivalent substitutions may be made to the technical solutions of the present invention without departing from the spirit and scope of the technical solutions of the present invention, and all of them should be covered in the claims of the present invention.

Claims (10)

1. Cutting side slope antiskid structure that collapses, its characterized in that: the pile body is arranged in a pile hole of the soil foundation; the pile body comprises a reinforcing rib of a plate-fin structure and a pile body pouring material; the reinforcing rib and the axis of the pile hole are coaxially arranged, and the pile body pouring material is located between the pile hole and the reinforcing rib.
2. The cutting slope anti-slip structure according to claim 1, characterized in that: and a connecting beam for fixing the pile body is arranged between every two adjacent pile bodies.
3. The cutting slope anti-slip structure according to claim 1, characterized in that: the reinforcing rib is made of I-shaped steel, and wing plates of the I-shaped steel face the collapsing direction of the soil foundation collapsing layer.
4. The cutting slope anti-slip structure according to claim 3, characterized in that: and a plurality of positioning ribs for positioning the reinforcing rib are regularly distributed between the reinforcing rib and the inner side wall of the pile hole along the axial direction.
5. The cutting slope anti-slip structure according to any one of claims 2 or 3, wherein: the upper ends of the reinforcing ribs extend out of the pile holes to be connected with the connecting beams, and the lower ends of the pile bodies penetrate through the collapse layer and extend into the stable stratum.
6. The cutting slope anti-slip structure according to claim 1, characterized in that: the pile bodies are at least arranged in two rows along the collapse direction of the soil foundation collapse layer.
7. The cutting slope anti-slip structure according to claim 1, characterized in that: the connecting beam is coated with a protective layer.
8. A construction method of the cutting slope anti-collapse structure according to any one of claims 1 to 7, characterized in that:
the method comprises the following steps: positioning and processing the pile hole;
step two: (1) placing the reinforcing rib in the pile hole; (2) pouring a pile body pouring material between the reinforcing rib and the pile hole; (3) the maintenance of the pile body is completed;
step three: the reinforcing ribs exposed at the upper ends of two adjacent pile bodies are fixedly connected through a connecting beam, and the pile body connecting beam is coated with a protective layer.
9. The construction method according to claim 9, wherein: in the first step, the pile holes are processed in a jumping mode at intervals; the pile hole spacing is not less than three times the diameter of the pile holes.
10. The construction method according to claim 9 or 10, wherein: the pile body penetrates through the soil foundation collapse layer to a stable stratum below the soil foundation collapse layer; the length of the pile body for stabilizing the ground layer is 1/3-1/2 of the total length of the pile body.
CN202110330956.8A 2021-03-26 2021-03-26 Cutting slope anti-slip structure and construction method thereof Pending CN113216218A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110330956.8A CN113216218A (en) 2021-03-26 2021-03-26 Cutting slope anti-slip structure and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110330956.8A CN113216218A (en) 2021-03-26 2021-03-26 Cutting slope anti-slip structure and construction method thereof

Publications (1)

Publication Number Publication Date
CN113216218A true CN113216218A (en) 2021-08-06

Family

ID=77084383

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110330956.8A Pending CN113216218A (en) 2021-03-26 2021-03-26 Cutting slope anti-slip structure and construction method thereof

Country Status (1)

Country Link
CN (1) CN113216218A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116005693A (en) * 2023-01-04 2023-04-25 北京住总集团有限责任公司 Rock area combined type hole digging anti-slide pile structure and construction method thereof

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201406687Y (en) * 2009-04-13 2010-02-17 中冶实久建设有限公司 Deep foundation pit supporting structure
KR20110130239A (en) * 2010-05-27 2011-12-05 최승희 Field infused post and constructing method thereof
KR20140001554A (en) * 2012-06-27 2014-01-07 반석기초이앤씨(주) Steel pipe joint structures of rotary pile and pile construction method using the same
CN104389315A (en) * 2014-11-12 2015-03-04 国家电网公司 Consolidation grouting drilled pile wall and construction method thereof
CN106013088A (en) * 2016-06-07 2016-10-12 湖北天利建筑技术有限责任公司 High-bearing-capacity drilling pile planting method
CN206477344U (en) * 2017-01-16 2017-09-08 中国建筑第八工程局有限公司 Foundation pit supporting construction
CN107687167A (en) * 2017-09-18 2018-02-13 中国科学院武汉岩土力学研究所 A kind of I-steel mini pile pile making method
CN110042828A (en) * 2019-05-17 2019-07-23 通号工程局集团有限公司 A kind of positioning device for filling pile reinforcement cage and its application method
CN209585067U (en) * 2019-01-11 2019-11-05 中铁西北科学研究院有限公司 A kind of high-bearing capacity mini pile
CN110700248A (en) * 2019-11-01 2020-01-17 河北工业大学 Miniature steel pipe pile for grouting small and medium-sized span bridge, pile foundation and construction method
CN111719562A (en) * 2020-06-24 2020-09-29 中铁第五勘察设计院集团有限公司 Foundation pit supporting structure
CN211816394U (en) * 2020-01-07 2020-10-30 青岛市勘察测绘研究院 Retaining wall structure without drainage in bedrock area

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201406687Y (en) * 2009-04-13 2010-02-17 中冶实久建设有限公司 Deep foundation pit supporting structure
KR20110130239A (en) * 2010-05-27 2011-12-05 최승희 Field infused post and constructing method thereof
KR20140001554A (en) * 2012-06-27 2014-01-07 반석기초이앤씨(주) Steel pipe joint structures of rotary pile and pile construction method using the same
CN104389315A (en) * 2014-11-12 2015-03-04 国家电网公司 Consolidation grouting drilled pile wall and construction method thereof
CN106013088A (en) * 2016-06-07 2016-10-12 湖北天利建筑技术有限责任公司 High-bearing-capacity drilling pile planting method
CN206477344U (en) * 2017-01-16 2017-09-08 中国建筑第八工程局有限公司 Foundation pit supporting construction
CN107687167A (en) * 2017-09-18 2018-02-13 中国科学院武汉岩土力学研究所 A kind of I-steel mini pile pile making method
CN209585067U (en) * 2019-01-11 2019-11-05 中铁西北科学研究院有限公司 A kind of high-bearing capacity mini pile
CN110042828A (en) * 2019-05-17 2019-07-23 通号工程局集团有限公司 A kind of positioning device for filling pile reinforcement cage and its application method
CN110700248A (en) * 2019-11-01 2020-01-17 河北工业大学 Miniature steel pipe pile for grouting small and medium-sized span bridge, pile foundation and construction method
CN211816394U (en) * 2020-01-07 2020-10-30 青岛市勘察测绘研究院 Retaining wall structure without drainage in bedrock area
CN111719562A (en) * 2020-06-24 2020-09-29 中铁第五勘察设计院集团有限公司 Foundation pit supporting structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116005693A (en) * 2023-01-04 2023-04-25 北京住总集团有限责任公司 Rock area combined type hole digging anti-slide pile structure and construction method thereof
CN116005693B (en) * 2023-01-04 2023-08-25 北京住总集团有限责任公司 Rock area combined type hole digging anti-slide pile structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN111364486B (en) Remediation and reinforcement device and method for emergency rescue of slide-resistant pile side slope
CN102864781A (en) Foundation pit supporting method utilizing inclined piles
CN108914954B (en) Slope supporting method combining pre-supporting and permanent supporting
CN111254966A (en) Mountain abutment and pier column foundation structure and construction method thereof
CN110735436A (en) cutting rock slope reinforced structure
CN110886507B (en) Method for increasing storey and expanding under existing building
CN110042843A (en) A kind of large deep foundation pit construction method of complex condition
CN115012426A (en) Steel pipe pile support and construction method for existing telegraph pole during four-cycle full excavation
CN104264683A (en) Concave ultra-deep foundation pit zoned supporting method for three-side surrounded cultural protection building
CN112195779A (en) Multifunctional trestle construction method suitable for thick pebble layer
CN114278310B (en) Construction method of micro steel pipe pile lattice beam at shallow buried section of tunnel
CN109653101B (en) Method for erecting trestle for bridge construction
CN113417300B (en) Slope support system and construction method thereof
CN108797323B (en) Steel trestle suitable for hard stratum
CN113216218A (en) Cutting slope anti-slip structure and construction method thereof
CN114319435A (en) Underpass underground passage supporting structure with large-section shallow pipe gallery and construction method
CN111719550B (en) Guide drilling construction method for cast-in-situ bored pile in complex geology
CN215759068U (en) Cutting slope anti-slip structure
CN109989346B (en) Bridge large-diameter precast concrete tubular column foundation and construction method thereof
CN115387207A (en) Shallow covering layer steel-concrete composite pile pier structure and construction method
CN111472363A (en) Construction method of foundation pit enclosure structure located in underground space of existing building
CN115198787B (en) Steel tube column type tower crane foundation and construction method thereof, and cover-excavation reverse construction method
CN115506375B (en) Excavation supporting system for U-shaped groove foundation pit close to bridge pile foundation and construction method
CN216891934U (en) Steel trestle bridge anchoring pile for hard stratum of sea area tidal zone
CN219491038U (en) Advanced reinforcing structure for slope toe of abandoned mine slope

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210806

RJ01 Rejection of invention patent application after publication