CN113074002A - Method for connecting batch jacking gapped discrete steel structure pipe joint and tunnel portal - Google Patents

Method for connecting batch jacking gapped discrete steel structure pipe joint and tunnel portal Download PDF

Info

Publication number
CN113074002A
CN113074002A CN202110305600.9A CN202110305600A CN113074002A CN 113074002 A CN113074002 A CN 113074002A CN 202110305600 A CN202110305600 A CN 202110305600A CN 113074002 A CN113074002 A CN 113074002A
Authority
CN
China
Prior art keywords
jacking
steel pipe
grouting
pipe
ring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110305600.9A
Other languages
Chinese (zh)
Inventor
张中杰
吴航
殷文涛
吕培林
刘书
卢恺
王春凯
杨波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Urban Construction Design Research Institute Group Co Ltd
Original Assignee
Shanghai Urban Construction Design Research Institute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Urban Construction Design Research Institute Group Co Ltd filed Critical Shanghai Urban Construction Design Research Institute Group Co Ltd
Priority to CN202110305600.9A priority Critical patent/CN113074002A/en
Publication of CN113074002A publication Critical patent/CN113074002A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a method for connecting a batch jacking gapped discrete steel structure pipe joint with a hole door, which comprises the following steps of firstly, pre-burying an anchor bar and a hole door ring on the side wall of a lining of a hole opening, and fixing the anchor bar and the hole door ring; step two, embedding a grouting pipe in the side wall of the lining; and step three, jacking the steel pipe joints, and after the jacking of the steel pipe joints is finished, grouting into the grouting pipes to plug gaps between the side walls of the lining and the steel pipe joints. According to the invention, the tunnel portal ring and the steel pipe section are connected and sealed by arranging the end sealing plates to form a waterproof barrier, so that water flowing out from a gap between the pipe piece and the working well tunnel portal is effectively blocked, and the safety of the tunnel portal during jacking construction of the jacking pipe is fundamentally ensured; the construction is convenient and quick, the operation is simple, the connection forming effect is good, and the welding quality is ensured; compared with the traditional connecting interface, the post-cast ring beam is not required to be applied, the economic benefit is high, and the operability is strong.

Description

Method for connecting batch jacking gapped discrete steel structure pipe joint and tunnel portal
Technical Field
The invention relates to the technical field of underground structures, in particular to a method for connecting separated steel structure pipe joints and a tunnel portal in batch jacking.
Background
With the rapid development of economy and the increasing population density of China, the ground developable resources are less and less, and the land utilization rate tends to be saturated. Therefore, the development of cities into underground spaces is a necessary trend for the development of the international metropolis.
The underground excavation method in the prior art gradually becomes a preferred method for building an underground structure in a complex environment by virtue of the advantage that the underground excavation method has less interference to the ground environment. The pipe curtain method is used as an underground excavation method, and has the advantages of low noise during construction, small ground surface settlement, low construction space requirement, no need of road reconstruction and pipeline adjustment, suitability for underground construction of various soil bodies and the like.
When the existing pipe curtain method is used, during the connection construction of pipe joints and working well openings, the portal ring beam is usually used after the pipe joints are jacked and run through, the time is long, gaps exist between the pipe joints and the working well structure, the steel pipe joints are jacked in batches, underground water, fine sand and the like easily flow out of the gaps, cement paste in concrete is taken away, the construction quality of the portal ring beam is difficult to guarantee, more leakage points appear after the portal ring beam is sealed, the grouting and leaking stoppage effects are limited in the later period, and even the ground subsides due to the fact that the underground water and soil are lost through the gaps, and great risks are generated.
Therefore, how to effectively improve the operability and reliability of the sealing between the steel pipe joints pushed in batch and the working well door is a technical problem to be solved urgently by technical personnel in the technical field.
Disclosure of Invention
In view of the above-mentioned drawbacks of the prior art, a technical object of the present invention is to solve the technical problems mentioned in the above-mentioned background art.
In order to achieve the technical purpose, the invention provides a method for connecting separated steel structure pipe joints and a tunnel portal in batch jacking, which comprises the following steps:
firstly, embedding anchor bars and a hole portal ring on the side wall of the lining of the hole, and fixing the anchor bars and the hole portal ring;
step two, embedding a grouting pipe in the side wall of the lining;
jacking the steel pipe joints, and after the jacking of the steel pipe joints is finished, grouting into the grouting pipes to plug gaps between the side walls of the lining and the steel pipe joints;
fixing an end sealing plate, the hole door ring and a flange of the steel pipe joint through a fillet weld;
and fifthly, repeating the third step and the fourth step in sequence according to the jacking sequence of the steel pipe sections to complete the connection of all the steel pipe sections and the door ring.
Preferably, in the first step, the anchor bar is welded and fixed with the hole portal ring.
Preferably, in the third step, concrete is used for grouting in the grouting pipe.
Preferably, in the fourth step, the end sealing plate, the aperture door ring and the flange of the steel pipe joint are welded and fixed through the fillet weld.
Preferably, the grouting pipe is a seamless steel pipe with internal threads on both ends.
The invention has the beneficial effects that:
due to the innovation of the construction method, compared with the prior art, the invention has the following advantages:
firstly, the tunnel portal ring and the steel pipe joint are connected and sealed by arranging the end sealing plates to form a water-proof barrier, so that water flowing out from a gap between the pipe piece and the working well tunnel portal is effectively blocked, and the safety of the tunnel portal during jacking construction of the jacking pipe is fundamentally ensured.
Secondly, the post-cast ring beam is not required to be arranged, and the condition that the post-cast ring beam leaks due to the fact that the construction time is long, the construction quality is difficult to guarantee and the like during construction of the post-cast ring beam is avoided.
And moreover, the construction is convenient and quick, the operation is simple, the connection forming effect is good, and the welding quality is ensured.
And compared with the traditional connecting interface, the post-cast ring beam is not required to be applied, so that the economic benefit is high, and the operability is strong.
In conclusion, the invention not only solves the problem of sealing the steel pipe joints pushed in batches with the working well door, but also has simple process and strong operability, promotes the technical progress of industry, and has good economic and social benefits.
Drawings
FIG. 1 is a schematic structural view of a steel pipe joint of the present invention after being connected to a hole;
fig. 2 is a schematic structural view of the aperture door ring part of the present invention.
In the figure: 1 steel pipe section, 2 inside lining lateral walls, 3 anchor bars, 4 slip casting pipes, 5 hole door rings, 6 fillet welds, 7 end closing plates and 8 concrete.
Detailed Description
The conception, the specific structure and the technical effects of the present invention will be further described with reference to the accompanying drawings to fully understand the objects, the features and the effects of the present invention.
Example (b):
as shown in fig. 1-2, a specific embodiment of the method for connecting pipe joints and portals of batch jacking gapped discrete steel structures of the present invention comprises the following steps:
firstly, pre-typesetting the steel pipe joint 1 before jacking the steel pipe joint 1, and preparing for construction;
secondly, embedding anchor bars 3 and a hole door ring 5 on the side wall 2 of the lining in advance, wherein the anchor bars 3 are welded with the hole door ring 5, and the hole door ring 5 is made of a steel plate;
step three, embedding a grouting pipe 4 in the lining side wall 2, wherein the grouting pipe 4 is a seamless steel pipe with internal threads at two ends;
fourthly, jacking the steel pipe joint 1, and after the jacking of the steel pipe joint 1 is finished, plugging a gap between the lining side wall 2 and the steel pipe joint 1 through a grouting pipe 4 by adopting concrete 8;
fifthly, manufacturing the end sealing plate 7, and welding the end sealing plate 7, the hole door ring 5 and the flange of the steel pipe joint 1 through the fillet weld 6 to form a waterproof barrier;
and step six, sequentially repeating the step three and the step four according to the jacking sequence of the steel pipe joints 1 to complete the connection of all the steel pipe joints 1 and the portal ring 5.
The foregoing detailed description of the preferred embodiments of the invention has been presented. It should be understood that numerous modifications and variations could be devised by those skilled in the art in light of the present teachings without departing from the inventive concepts. Therefore, the technical solutions available to those skilled in the art through logic analysis, reasoning and limited experiments based on the prior art according to the concept of the present invention should be within the scope of protection defined by the claims.

Claims (5)

1. A method for connecting a separated steel structure pipe joint with a tunnel portal in a batch jacking mode is characterized by comprising the following steps:
firstly, embedding anchor bars and a hole portal ring on the side wall of the lining of the hole, and fixing the anchor bars and the hole portal ring;
step two, embedding a grouting pipe in the side wall of the lining;
jacking the steel pipe joints, and after the jacking of the steel pipe joints is finished, grouting into the grouting pipes to plug gaps between the side walls of the lining and the steel pipe joints;
fixing an end sealing plate, the hole door ring and a flange of the steel pipe joint through a fillet weld;
and fifthly, repeating the third step and the fourth step in sequence according to the jacking sequence of the steel pipe sections to complete the connection of all the steel pipe sections and the door ring.
2. The method for connecting a pipe section with a gap and a discrete steel structure pushed in batch according to claim 1, wherein the anchor bars are welded and fixed with the portal ring in the first step.
3. The method for connecting a pipe section with a gap and a discrete steel structure pushed in batch according to claim 1, wherein concrete is used for grouting in the grouting pipe in the third step.
4. The method for connecting the discrete steel pipe joints with gaps in batch jacking as claimed in claim 1, wherein the end sealing plates, the hole door rings and the flanges of the steel pipe joints are welded and fixed by the fillet welds in the fourth step.
5. The method for connecting a pipe section with a gap and a discrete steel structure pushed in batch according to claim 1, wherein the grouting pipe is a seamless steel pipe with internal threads at two ends.
CN202110305600.9A 2021-03-23 2021-03-23 Method for connecting batch jacking gapped discrete steel structure pipe joint and tunnel portal Pending CN113074002A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110305600.9A CN113074002A (en) 2021-03-23 2021-03-23 Method for connecting batch jacking gapped discrete steel structure pipe joint and tunnel portal

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110305600.9A CN113074002A (en) 2021-03-23 2021-03-23 Method for connecting batch jacking gapped discrete steel structure pipe joint and tunnel portal

Publications (1)

Publication Number Publication Date
CN113074002A true CN113074002A (en) 2021-07-06

Family

ID=76613252

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110305600.9A Pending CN113074002A (en) 2021-03-23 2021-03-23 Method for connecting batch jacking gapped discrete steel structure pipe joint and tunnel portal

Country Status (1)

Country Link
CN (1) CN113074002A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104343455A (en) * 2013-08-05 2015-02-11 中铁十八局集团第一工程有限公司 Long-distance curved jacking pipe and pipe roof construction technique
CN206053969U (en) * 2016-08-29 2017-03-29 广州市市政工程设计研究总院 A kind of shield tunnel and open cut main body portal ring beam hermetic water-proof structure
CN107989638A (en) * 2017-12-28 2018-05-04 中铁二局集团有限公司 A kind of push pipe receives water-stopping method
CN108343450A (en) * 2018-04-18 2018-07-31 中铁十四局集团有限公司 A kind of new pipe-roof method active well ruggedized construction and reinforcement means
CN111395391A (en) * 2020-04-13 2020-07-10 中国建筑一局(集团)有限公司 Porous rectangular jacking pipe and light and shade cut connecting pipe gallery joint and construction method thereof
CN111577329A (en) * 2020-04-30 2020-08-25 中国五冶集团有限公司 Pipe curtain construction structure and construction method
CN112393027A (en) * 2020-11-16 2021-02-23 上海市城市建设设计研究总院(集团)有限公司 Top pipe hole-entering sealing ring beam structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104343455A (en) * 2013-08-05 2015-02-11 中铁十八局集团第一工程有限公司 Long-distance curved jacking pipe and pipe roof construction technique
CN206053969U (en) * 2016-08-29 2017-03-29 广州市市政工程设计研究总院 A kind of shield tunnel and open cut main body portal ring beam hermetic water-proof structure
CN107989638A (en) * 2017-12-28 2018-05-04 中铁二局集团有限公司 A kind of push pipe receives water-stopping method
CN108343450A (en) * 2018-04-18 2018-07-31 中铁十四局集团有限公司 A kind of new pipe-roof method active well ruggedized construction and reinforcement means
CN111395391A (en) * 2020-04-13 2020-07-10 中国建筑一局(集团)有限公司 Porous rectangular jacking pipe and light and shade cut connecting pipe gallery joint and construction method thereof
CN111577329A (en) * 2020-04-30 2020-08-25 中国五冶集团有限公司 Pipe curtain construction structure and construction method
CN112393027A (en) * 2020-11-16 2021-02-23 上海市城市建设设计研究总院(集团)有限公司 Top pipe hole-entering sealing ring beam structure

Similar Documents

Publication Publication Date Title
CN206053969U (en) A kind of shield tunnel and open cut main body portal ring beam hermetic water-proof structure
CN103061782B (en) Large-section earth pressure balancing rectangular jacking pipe joint of motor vehicle tunnel and method for constructing large-section earth pressure balancing rectangular jacking pipe
CN111395391B (en) Construction method for multi-hole rectangular jacking pipe and light and dark excavation joint pipe gallery joint
CN109707415A (en) A kind of joint construction method and its joint structure of Shield-bored tunnels and station
WO2024139800A1 (en) Construction method for gas partition system of gas outburst tunnel
CN112901207A (en) Treatment method for collapse in tunnel during arch change of secondary lining in sulfate corrosion section of operation tunnel
CN111765295B (en) Construction method of reinforced concrete pipe
CN106812131B (en) A kind of permanent sheet pile underground structure and its construction method
CN216839585U (en) Sealing structure at joint of new concrete and old concrete
CN111424681A (en) Waterproof joint structure under sectional application condition of underground continuous wall and cast-in-place pile and construction method thereof
CN108808594B (en) Grouting-sealed cable wall bushing structure and construction method thereof
CN110985042A (en) Urban comprehensive pipe gallery and underground shallow-buried underground tunnel combined supporting system and process
CN102535518B (en) Plugging method of large seam of underground diaphragm wall
CN203476354U (en) Underground excavation engineering major structure
CN113074002A (en) Method for connecting batch jacking gapped discrete steel structure pipe joint and tunnel portal
CN204199324U (en) Connecting reinforcement cage i iron in construction of diaphragm wall
CN114412473A (en) Underpass high-speed railway base pipe curtain supporting structure and construction process thereof
CN209324383U (en) A kind of joint structure of Shield-bored tunnels and station
CN112112248A (en) Method for repairing defect of channel box
CN219653691U (en) Underground diaphragm wall joint shutoff and sealing device
KR101682014B1 (en) build method of steel pipe in a tunnel for waterways
CN110924954A (en) Device and method for checking grouting condition of annular space of orifice pipe
CN220955627U (en) External portal ring beam seepage prevention structure of back-covered steel plate of deep-buried shield tunnel
CN113339004B (en) Construction method of prestressed steel structure advanced support
CN216342175U (en) Existing electric power tunnel and newly-built electric power tunnel's structure of plugging into

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210706