CN113032872A - BIM technology-based integrated resource management and control method for assembly type building progress plan - Google Patents

BIM technology-based integrated resource management and control method for assembly type building progress plan Download PDF

Info

Publication number
CN113032872A
CN113032872A CN202110271436.4A CN202110271436A CN113032872A CN 113032872 A CN113032872 A CN 113032872A CN 202110271436 A CN202110271436 A CN 202110271436A CN 113032872 A CN113032872 A CN 113032872A
Authority
CN
China
Prior art keywords
construction
plan
progress
collision
project
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110271436.4A
Other languages
Chinese (zh)
Other versions
CN113032872B (en
Inventor
杨震卿
宋萍萍
张强
王仑
王波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING LIUJIAN CONSTRUCTION GROUP CO LTD
Beijing Construction Engineering Group Co Ltd
Original Assignee
BEIJING LIUJIAN CONSTRUCTION GROUP CO LTD
Beijing Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING LIUJIAN CONSTRUCTION GROUP CO LTD, Beijing Construction Engineering Group Co Ltd filed Critical BEIJING LIUJIAN CONSTRUCTION GROUP CO LTD
Priority to CN202110271436.4A priority Critical patent/CN113032872B/en
Publication of CN113032872A publication Critical patent/CN113032872A/en
Application granted granted Critical
Publication of CN113032872B publication Critical patent/CN113032872B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063118Staff planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06395Quality analysis or management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Educational Administration (AREA)
  • General Business, Economics & Management (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Geometry (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Pure & Applied Mathematics (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a BIM technology-based integrated resource management and control method for an assembly type building progress plan, which comprises the following specific steps of: step one, establishing a three-dimensional BIM model; step two, splitting the model; thirdly, simulating in a linear progress plan mode; fourthly, the management platform collects data; step five, generating a curve of the linear progress plan in the BIM software; step six, sequentially adjusting subsequent processes and resources to avoid repetition or interruption in the same time period; and seventhly, guiding the site construction after adjustment. According to the invention, based on the application of information means such as BIM technology and intelligent construction site in the assembly type construction engineering, the production of components and the inventory of limited site components are important factors in the assembly type engineering, and a comprehensive resource management and control standard method taking linear progress division of the components as a unit as a core is researched and innovated by combining the information technology such as BIM technology and intelligent construction site.

Description

BIM technology-based integrated resource management and control method for assembly type building progress plan
Technical Field
The invention belongs to the technical field of assembly type building construction, and particularly relates to a BIM technology-based integrated resource management and control method for an assembly type building progress plan.
Background
With the popularization and vigorous promotion of the prefabricated buildings, the prefabricated buildings such as prefabricated concrete structures, steel structures, modern wood structures and the like are developed according to local conditions, so that the proportion of the prefabricated buildings occupying the area of newly built buildings is increased year by year. However, the assembly type building construction also provides requirements and challenges for construction management and construction technology while solving the problems of the traditional construction mode.
The assembly type building changes the traditional cast-in-place construction mode, the construction field management mode is changed due to the change of the construction mode, particularly, in the aspects of order, production and field management of prefabricated components, the components are produced in a centralized mode frequently, the site cannot meet the requirement of stacking the components, the searching of the installed components is difficult, the periodic production of the component yard is long, the secondary carrying of the components is damaged, and a large amount of manpower and material resources are lost.
Disclosure of Invention
The invention provides a BIM technology-based integrated resource management and control method for an assembly type building progress plan, which is used for solving the technical problems of integrated management and control of construction period, materials, labor service and the like in the construction process based on BIM and field data feedback during the construction of an assembly type building.
In order to achieve the purpose, the invention adopts the following technical scheme:
the integrated resource management and control method for the progress plan of the prefabricated building based on the BIM technology comprises the following specific steps:
step one, according to an assembly type building design drawing, a three-dimensional BIM structure model is established by combining construction organization design to carry out construction simulation;
secondly, splitting the model according to the subsection and the item; the method comprises the following steps that a component crossing a flowing water section is disconnected according to the arrangement of a horizontal flowing water section, and the actual attribute of the component is consistent with the type name of the component when a model component is named;
thirdly, dividing the horizontal and vertical positions of the BIM structural model according to the structural characteristics and the structural type of the project; the floors at the bottoms of the assembled building columns are vertically divided, and the cast-in-place concrete part is divided according to the floors; dividing the horizontal position according to a dividing mode designed by a construction organization and combining the number of the sub-packages; performing work task decomposition according to the granularity of the work task of the analysis project, and compiling a total schedule of the Vico Office; performing team-level construction procedure simulation in a linear progress plan mode;
acquiring data by adopting an intelligent construction site management platform and a digital asset management platform to obtain work efficiency of equipment and various work classes and groups;
step five, adjusting interval values of work efficiency of teams and groups in BIM software, and generating a curve by a linear progress plan;
step six, taking the cell as a unit, and adjusting the crossed curve to be zero crossing; sequentially adjusting subsequent processes and resources to avoid repetition or interruption in the same time period;
and seventhly, automatically deriving a production plan, a resource allocation plan, a personnel allocation plan and a capital cost allocation plan table from the adjusted new linear progress plan, and guiding field construction.
Further, after the model in the step one is built, collision detection is carried out for ensuring the accuracy of the model, the collision detection comprises model collision, construction collision and dynamic collision, wherein a collision detection report which embodies axis positioning, collision components and collision images is obtained in the model collision according to the requirements of collision detection range, type, tolerance and distance; obtaining a collision detection report about the reflected axis positioning, the collision component and the collision image according to the project version of the construction progress plan in the construction collision; the dynamic collision is to obtain a collision detection report about the reflected axis positioning, the collision component and the collision image according to the project version of the construction progress plan, the mechanical running route and the time; the progress planning process needs to correspond to the construction simulation effect representing process.
Furthermore, in the step one, the construction simulation comprises macroscopic construction simulation, progress tracking simulation and construction procedure simulation, the macroscopic construction simulation is carried out by a single layer or a whole structure single body, the information of a water section is not reflected, and achievements are submitted to be a construction simulation video file and a synchro original file; the progress tracking simulation embodies the operation of each water diversion section, and the results are submitted to a construction progress tracking report, a construction simulation video file and a synchronous original file; the construction process simulation embodies the construction process of a complex process, and the results are submitted to a construction simulation video file and a synchronous original file.
Further, for the BIM structural model generated in the step one, which contains PC component design requirements, the PC components are divided according to layers and flow batches, and a PC component requirement schedule is generated before project operation; in the project construction process, if the construction period is advanced or lagged, the project plan is predicted quickly and automatically through software, a new PC component demand schedule is derived according to the prediction, and the project can submit the changed demand to a PC component factory in advance in time so that the component factory can arrange production conveniently and the construction period is not delayed.
Further, for the BIM structure model generated in the first step, which contains concrete design requirements, before project operation, a concrete early-stage planning purchase summary table is generated, which contains engineering quantity and cost, and according to a layer and flowing water batch concrete overall demand schedule, a manual resource plan, a histogram, a cost curve graph, a concrete engineering quantity plan, a histogram and a cost curve graph; in the project construction process, if the construction period is advanced or lagged, the project plan is rapidly and automatically predicted through software, meanwhile, a new concrete overall demand schedule which is batched according to layers is derived according to the prediction, and the project can timely submit the changed demand to a mixing plant in advance, so that the mixing plant can arrange production conveniently, and the construction period cannot be delayed.
Further, in the third step, the main contents of work task decomposition include work task name writing, project amount correlation and work efficiency filling; and decomposing the granularity of the progress analysis corresponding to the labor yield in the later period by the work task.
Further, in the third step, compiling a Vico Office total progress meter into a key task for analyzing a key route, namely restricting the whole construction progress; wherein, the large-scale mechanical equipment fully meets the requirements of site construction and is used as a key line according to the process with the longest time consumption; establishing a logical relationship among the work packages; further determining the number of groups of work shifts, the number of workers and an efficiency factor; and adjusting work groups, number of people and efficiency factors to ensure that the total construction period is consistent with the plan when the total construction period does not meet the plan requirement.
Furthermore, the working procedures in the key line are calibrated and controlled every day, and the working procedures on the non-key line are paid stage attention; wherein individual module processing and output of quantification tables and correction tables are performed for project time, teams, materials and machines in the critical line.
Furthermore, in the fourth step, the team and team efficiency is optimized, the technical route of work efficiency optimization is to adjust the construction and production organization mode, and the progress is deduced by selecting the construction organization modes such as sequential construction, parallel construction, flow construction and the like according to the actual situation on site; adjusting the flow section and the construction layer according to the condition of the sub-package team and the distribution condition of the engineering quantity; and adjusting work efficiency, namely adjusting the work efficiency of each process according to experience and actual on-site progress conditions to ensure the total construction period.
Furthermore, the field guidance in the step seven is that the BIM technology and the Internet of things technology are combined for common management, the assembly type construction quality inspection requirements, specifications and the like are planned in advance through the construction quality requirements, the assembly type construction quality inspection requirements, the specifications and the like are input into the platform in advance through the BIM technology, the two-dimensional code technology is combined, the field quality inspection is facilitated, the real-time retrieval of inspection record information such as component entrance quality inspection, component installation quality inspection and the like is achieved, the quality management, the process monitoring and the data summarization retrieval are facilitated.
The invention has the beneficial effects that:
1) the invention is beneficial to the organization and the resource supply in advance by simulating the linear working procedure of the fabricated building, dividing modules and combining the working procedure and the resource to carry out the plan arrangement of the division;
2) according to the method, the simulation model is favorably checked and optimized through the capture of field data and the feedback of actual construction, so that the process control is realized;
3) the method integrates and analyzes the used procedures through the Vico Office software, defines the logical relationship between the key procedures and each procedure, and is beneficial to ensuring that the actual design requirements are met during later adjustment;
4) the invention interacts with the on-site construction check through the BIM model, which is beneficial to implementing control and adjustment on the process construction and further ensuring the construction quality requirement;
the invention is based on the application of information means such as BIM technology and intelligent construction site in the assembly type construction engineering, the production of components and the inventory of limited site components are important factors in the assembly type engineering, and a comprehensive resource management and control standard method taking linear progress division of the components as a core is researched and innovated by combining the information technology such as BIM technology and intelligent construction site. Additional features and advantages of the invention will be set forth in the description which follows, and in part will be obvious from the description, or may be learned by practice of the invention; the primary objects and other advantages of the invention may be realized and attained by the instrumentalities particularly pointed out in the specification.
Drawings
FIG. 1 is a flow chart of an integrated resource management and control method for an assembly type building progress plan based on BIM technology;
FIG. 2 is an ergonomic optimization flow diagram;
FIG. 3 is a schematic view of a construction simulation workflow;
FIG. 4 is a schematic crash detection workflow;
FIG. 5 is a schematic view of a construction progress tracking workflow;
FIG. 6 is a schematic of a field data check (optimization) workflow;
FIG. 7 is a PC component linear plan view;
FIG. 8 is a graph of PC component linear plan versus actual alignment;
FIG. 9 is a comparison graph of the logistics management time of PC components.
Detailed Description
Taking a certain fabricated passive residential project as an example, the project is a residential project, 3 floors underground and 30 floors above ground. The BIM-based prefabricated assembly component and part order generation and delivery scheduling management technology comprises the following steps: as shown in fig. 1 and fig. 2, by means of the BIM technique, a 4D construction simulation of the project is performed based on the three-dimensional model, the requirements of the project on the time and resources of the component are planned and planned in advance, and the production operation plan and the construction process control of the component are guided. Through the Vico software 4D construction simulation site construction process, the installation sequence is known in advance to provide production and processing requirements, the production component processing plan is arranged according to the construction plan, and the control of the site on components, construction period and resources is realized.
With reference to fig. 1 to 9, a method for integrated resource management and control of an assembly type building schedule plan based on the BIM technology is further described, which specifically comprises the following steps:
step one, according to an assembly type building design drawing, a three-dimensional BIM structure model is established by combining construction organization design to carry out construction simulation.
For step one, BIM software three-dimensional modeling can be implemented by applying REVIT. After the model is built, collision detection is carried out for ensuring the accuracy of the model, the collision detection comprises model collision, construction collision and dynamic collision, wherein a collision detection report which embodies axis positioning, collision components and collision images is obtained according to the requirements of collision detection range, type, tolerance and distance in the model collision; obtaining a collision detection report about the reflected axis positioning, the collision component and the collision image according to the project version of the construction progress plan in the construction collision; the dynamic collision is to obtain a collision detection report about the reflected axis positioning, the collision component and the collision image according to the project version of the construction progress plan, the mechanical running route and the time; the progress planning process needs to correspond to the construction simulation effect representing process.
In the embodiment, the construction simulation comprises macroscopic construction simulation, progress tracking simulation and construction procedure simulation, wherein the macroscopic construction simulation is carried out by using a single layer or a whole structure monomer, does not reflect the information of a water section, and submits results to be a construction simulation video file and a synchro original file; the progress tracking simulation embodies the operation of each water diversion section, and the results are submitted to a construction progress tracking report, a construction simulation video file and a synchronous original file; the construction process simulation embodies the construction process of a complex process, and the results are submitted to a construction simulation video file and a synchronous original file.
In the embodiment, the generated BIM structural model comprises PC component design requirements, the PC components are divided according to layers and flow batches, and a PC component requirement schedule is generated before project operation; in the project construction process, if the construction period is advanced or lagged, the project plan is predicted quickly and automatically through software, a new PC component demand schedule is derived according to the prediction, and the project can submit the changed demand to a PC component factory in advance in time so that the component factory can arrange production conveniently and the construction period is not delayed.
In the embodiment, taking a PC prefabricated part as an example, a generated BIM structure model comprises concrete design requirements, before project operation, a generated concrete early-stage planning purchase summary table comprises engineering quantity and cost, and a concrete overall demand schedule, a manual resource plan, a histogram, a cost curve graph, a concrete engineering quantity plan, a histogram and a cost curve graph according to layer and running water batches are generated; in the project construction process, if the construction period is advanced or lagged, the project plan is rapidly and automatically predicted through software, meanwhile, a new concrete overall demand schedule which is batched according to layers is derived according to the prediction, and the project can timely submit the changed demand to a mixing plant in advance, so that the mixing plant can arrange production conveniently, and the construction period cannot be delayed.
Secondly, splitting the model according to the subsection and the item; and when the model component is named, the actual attribute of the component is consistent with the type name of the component.
Thirdly, dividing the horizontal and vertical positions of the BIM structural model according to the structural characteristics and the structural type of the project; the floors at the bottoms of the assembled building columns are vertically divided, and the cast-in-place concrete part is divided according to the floors; dividing the horizontal position according to a dividing mode designed by a construction organization and combining the number of the sub-packages; performing work task decomposition according to the granularity of the work task of the analysis project, and compiling a total schedule of the Vico Office; and performing team-level construction procedure simulation in a linear progress plan mode.
For the third step, the main contents of work task decomposition comprise work task name writing, project amount correlation and work efficiency filling; and decomposing the granularity of the progress analysis corresponding to the labor yield in the later period by the work task. Compiling a site construction progress plan according to the design requirements of the model; the labor conditions of the site comprise teams, work efficiency and manual information; and (5) making a project amount statistical table.
In the embodiment, a Vico Office total progress meter is compiled into a key task for analyzing a key route, namely restricting the whole construction progress; wherein, the large-scale mechanical equipment fully meets the requirements of site construction and is used as a key line according to the process with the longest time consumption; the hoisting capacity of the tower crane can be used as a key factor temporarily at the stage of large hoisting machinery with large hoisting frequency requirement. Establishing a logical relationship among the work packages, and further determining the number of work shifts, the number of workers and an efficiency factor; and adjusting work groups, number of people and efficiency factors to ensure that the total construction period is consistent with the plan when the total construction period does not meet the plan requirement.
Three basic ways of ergonomics: adjusting an efficiency factor: the reason for adjusting the efficiency factor is mainly that the efficiency factor is applicable to different space environments and different position environments at the same time and the same work and the same construction team. Team consumption (number of work groups): the team consumption adjustment is mainly to adjust the number of working groups, and when the construction period is short, the progress can be guaranteed by increasing the number of groups. The method is applicable to the condition that the working face permission and the labor resource can be guaranteed. Consumption: the consumption is the work efficiency adjustment which is the core of labor productivity, the consumption adjustment can achieve the effect of pulling and moving the whole body, and the consumption adjustment is an effective means for improving or balancing the production efficiency of a construction site; the process of consuming continuous adjustment is also a necessary way for the establishment of the enterprise rating library and the construction rating library. The final goal of work efficiency optimization is to serve construction enterprises to organize production to achieve cost reduction and efficiency improvement effects, and work efficiency optimization is from the site and controls the site.
In the embodiment, the working procedures in the key line are calibrated and controlled every day, and the working procedures on the non-key line are paid stage attention; wherein individual module processing and output of quantification tables and correction tables are performed for project time, teams, materials and machines in the critical line.
And step four, acquiring data by adopting an intelligent construction site management platform and a digital asset management platform to obtain the work efficiency of equipment and various work classes and groups. The intelligent construction site management platform is used for performing integrated platform management on each management data and data generated in the construction process; the digital asset management platform is used for displaying required resources, manpower and the like in a data mode and performing Internet platform management. This way, it is beneficial to control the construction progress and consumption in real time. In the fabricated engineering, the working value of each team on the construction working surface is measured by adopting data collected by front-end equipment of a smart construction site and the frequency of the hanging times of the tower crane.
In the fourth step, the team efficiency is optimized, the technical route of the work efficiency optimization is to adjust the construction and production organization mode, and the progress deduction is carried out by selecting the construction organization modes such as sequential construction, parallel construction, flow construction and the like according to the actual situation on site; adjusting the flow section and the construction layer according to the condition of the sub-package team and the distribution condition of the engineering quantity; and adjusting work efficiency, namely adjusting the work efficiency of each process according to experience and actual on-site progress conditions to ensure the total construction period.
And step five, adjusting the interval value of the work efficiency of the team in BIM software, and generating a curve by the linear progress plan.
As shown in fig. 7, the construction sequence of the PC member is linear, and includes steel bar installation, prefabricated floor installation, formwork installation, cast-in-place concrete wall, beam, column, and floor slab in sequence; the time required for planning each construction process is clarified by dividing different floors and dividing the same floor into A, B construction zones.
Step six, taking the cell as a unit, and adjusting the crossed curve to be zero crossing; and sequentially adjusting subsequent processes and resources without repetition or interruption in the same time period.
As shown in fig. 8, the actual construction time of the construction process is recorded as the process progresses, and the start time of the subsequent process is automatically predicted. In the figure, the scheduled starting time of installing the precast floor slab in the 5-storey A area is 2018.1.21, and the actual time is 2018.1.20 for starting construction, which is 1 day ahead of the scheduled starting time, so that the starting time of future tasks is influenced; due to the increased efficiency of 'installing precast floor slabs', the required time for the PC components is changed when the task starting time is predicted to start 1 day ahead of the original plan in the 6-storey A area.
In the embodiment, when the construction plan changes, the changed new time node is rapidly derived; due to the variability of the linear plan and the effective control of the progress of the construction site, the requirements of the PC components are adjusted in time when the plan changes; predicting the planned demand time of the precast floor slab in the area B of 6 floors as 2018.2.2, changing the demand plan into 2018.2.1 according to the predicted demand plan, and providing the time to the component factory to change the demand plan time of the PC components
As shown in FIG. 9, a comparison table of PC component logistics management time is obtained from the previous schedule adjustment, and the comparison table of the scheduled start time, the actual start time and the predicted start time of the PC component is indicated in the figure. The field personnel input the actual completion condition of the work, and the workload is little and convenient. Meanwhile, the condition can be fed back to a BIM department for recording, and the entering change time of the PC component can be predicted in real time.
And seventhly, automatically deriving a production plan, a resource allocation plan, a personnel allocation plan and a capital cost allocation plan table from the adjusted new linear progress plan, and guiding field construction.
And seventhly, combining the BIM technology and the Internet of things technology for common management, planning out the requirements, specifications and the like of the assembled construction quality inspection in advance through the construction quality requirements, inputting the requirements into the platform in advance through the BIM technology, combining the two-dimensional code technology, facilitating the field quality inspection, achieving real-time retrieval of inspection record information such as component entrance quality inspection, component installation quality inspection and the like, and facilitating quality management, process monitoring and data summarization retrieval.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any changes or substitutions that may be made by those skilled in the art within the technical scope of the present invention will be covered by the scope of the present invention.

Claims (10)

1. The integrated resource management and control method for the progress plan of the fabricated building based on the BIM technology is characterized by comprising the following specific steps of:
step one, according to an assembly type building design drawing, a three-dimensional BIM structure model is established by combining construction organization design to carry out construction simulation;
secondly, splitting the model according to the subsection and the item; the method comprises the following steps that a component crossing a flowing water section is disconnected according to the arrangement of a horizontal flowing water section, and the actual attribute of the component is consistent with the type name of the component when a model component is named;
thirdly, dividing the horizontal and vertical positions of the BIM structural model according to the structural characteristics and the structural type of the project; the floors at the bottoms of the assembled building columns are vertically divided, and the cast-in-place concrete part is divided according to the floors; dividing the horizontal position according to a dividing mode designed by a construction organization and combining the number of the sub-packages; performing work task decomposition according to the granularity of the work task of the analysis project, and compiling a total schedule of the Vico Office; performing team-level construction procedure simulation in a linear progress plan mode;
acquiring data by adopting an intelligent construction site management platform and a digital asset management platform to obtain work efficiency of equipment and various work classes and groups;
step five, adjusting interval values of work efficiency of teams and groups in BIM software, and generating a curve by a linear progress plan;
step six, taking the cell as a unit, and adjusting the crossed curve to be zero crossing; sequentially adjusting subsequent processes and resources to avoid repetition or interruption in the same time period;
and seventhly, automatically deriving a production plan, a resource allocation plan, a personnel allocation plan and a capital cost allocation plan table from the adjusted new linear progress plan, and guiding field construction.
2. The BIM technology-based fabricated building progress planning integrated resource management and control method of claim 1, wherein after the model is built in the step one, collision detection is performed to ensure the accuracy of the model, the collision detection comprises model collision, construction collision and dynamic collision, wherein in the model collision, a collision detection report about the embodiment of axis positioning, collision components and collision images is obtained according to the collision detection range, type, tolerance and spacing requirements; obtaining a collision detection report about the reflected axis positioning, the collision component and the collision image according to the project version of the construction progress plan in the construction collision; the dynamic collision is to obtain a collision detection report about the reflected axis positioning, the collision component and the collision image according to the project version of the construction progress plan, the mechanical running route and the time; the progress planning process needs to correspond to the construction simulation effect representing process.
3. The BIM technology-based prefabricated building progress plan comprehensive resource management and control method as claimed in claim 2, wherein for the step one, the construction simulation comprises a macroscopic construction simulation, a progress tracking simulation and a construction process simulation, the macroscopic construction simulation is carried out by a single layer or a whole structure single body, the information of a water section is not reflected, and results are submitted to be a construction simulation video file and a synchronous original file; the progress tracking simulation embodies the operation of each water diversion section, and the results are submitted to a construction progress tracking report, a construction simulation video file and a synchronous original file; the construction process simulation embodies the construction process of a complex process, and the results are submitted to a construction simulation video file and a synchronous original file.
4. The BIM technology-based integrated resource management and control method for the assembly type building progress plan of the assembly type building as claimed in claim 3, wherein for the BIM structure model generated in the step one, which includes PC component design requirements, the PC components are divided according to layers and running batches, and before the project is started, a PC component requirement plan table is generated; in the project construction process, if the construction period is advanced or lagged, the project plan is predicted quickly and automatically through software, a new PC component demand schedule is derived according to the prediction, and the project can submit the changed demand to a PC component factory in advance in time so that the component factory can arrange production conveniently and the construction period is not delayed.
5. The integrated resource management and control method for the prefabricated building progress plan based on the BIM technology as claimed in claim 3, wherein for the BIM structure model generated in the first step including concrete design requirements, before project operation, a concrete early-stage planning purchase summary table including engineering quantity and cost is generated, and the concrete overall demand plan table, the artificial resource plan-histogram and cost curve chart, the concrete engineering quantity plan-histogram and cost curve chart are generated according to layer and running batch; in the project construction process, if the construction period is advanced or lagged, the project plan is rapidly and automatically predicted through software, meanwhile, a new concrete overall demand schedule which is batched according to layers is derived according to the prediction, and the project can timely submit the changed demand to a mixing plant in advance, so that the mixing plant can arrange production conveniently, and the construction period cannot be delayed.
6. The BIM technology-based assembly type building progress plan comprehensive resource management and control method as claimed in claim 1, wherein for step three, the main contents of work task decomposition comprise work task name writing, project amount correlation and work efficiency filling; and decomposing the granularity of the progress analysis corresponding to the labor yield in the later period by the work task.
7. The BIM technology-based assembly type building progress plan comprehensive resource management and control method of claim 6, wherein in the third step, a Vico Office total progress plan is compiled as a key task for analyzing a key route, namely, restricting the whole construction progress; wherein, the large-scale mechanical equipment fully meets the requirements of site construction and is used as a key line according to the process with the longest time consumption; establishing a logical relationship among the work packages; further determining the number of groups of work shifts, the number of workers and an efficiency factor; and adjusting work groups, number of people and efficiency factors to ensure that the total construction period is consistent with the plan when the total construction period does not meet the plan requirement.
8. The BIM technology-based fabricated building progress plan comprehensive resource management and control method of claim 7, wherein the procedures in the critical line are calibrated and controlled every day, and the procedures on the non-critical line are paid periodical attention; wherein individual module processing and output of quantification tables and correction tables are performed for project time, teams, materials and machines in the critical line.
9. The BIM technology-based prefabricated building progress plan comprehensive resource management and control method as claimed in claim 1, wherein in step four, team efficiency is optimized, a technical route of work efficiency optimization is to adjust a construction production organization mode, and a construction organization mode such as sequential construction, parallel construction, flow line construction and the like is selected according to actual conditions on site to carry out progress deduction; adjusting the flow section and the construction layer according to the condition of the sub-package team and the distribution condition of the engineering quantity; and adjusting work efficiency, namely adjusting the work efficiency of each process according to experience and actual on-site progress conditions to ensure the total construction period.
10. The integrated resource management and control method for the progress plan of the prefabricated building based on the BIM technology as claimed in claim 1, wherein for the field guidance in the seventh step, the BIM technology and the Internet of things technology are combined for common management, the requirements, specifications and the like of the assembled construction quality inspection are planned in advance through the construction quality requirements, the assembled construction quality inspection requirements, the specifications and the like are input into the platform in advance through the BIM technology, the two-dimensional code technology is combined, the field quality inspection is facilitated, the inspection record information such as the component entry quality inspection, the component installation quality inspection and the like is called in real time, and the quality management, the process monitoring and the data collection are facilitated.
CN202110271436.4A 2021-03-12 2021-03-12 BIM technology-based fabricated building progress plan comprehensive resource management and control method Active CN113032872B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110271436.4A CN113032872B (en) 2021-03-12 2021-03-12 BIM technology-based fabricated building progress plan comprehensive resource management and control method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110271436.4A CN113032872B (en) 2021-03-12 2021-03-12 BIM technology-based fabricated building progress plan comprehensive resource management and control method

Publications (2)

Publication Number Publication Date
CN113032872A true CN113032872A (en) 2021-06-25
CN113032872B CN113032872B (en) 2023-12-15

Family

ID=76470485

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110271436.4A Active CN113032872B (en) 2021-03-12 2021-03-12 BIM technology-based fabricated building progress plan comprehensive resource management and control method

Country Status (1)

Country Link
CN (1) CN113032872B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113609550A (en) * 2021-07-05 2021-11-05 江苏徐工工程机械研究院有限公司 BIM-based construction process planning management method and system
CN113626925A (en) * 2021-08-18 2021-11-09 深圳润世华软件和信息技术服务有限公司 Construction plan management method, construction plan management device, computer equipment and storage medium
CN114781027A (en) * 2022-04-14 2022-07-22 浙江大东吴杭萧绿建科技有限公司 BIM-based digital steel structure building construction method and system

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130335413A1 (en) * 2012-06-13 2013-12-19 National Chiao Tung University System and method for estimating construction duration
CN105888248A (en) * 2016-04-27 2016-08-24 河北建筑工程学院 Construction method of guiding informationization prefabricated member based on BIM (Building Information Modeling)) technology
KR20170062632A (en) * 2015-11-27 2017-06-08 이화여자대학교 산학협력단 Method for performing BIM-integrated productivity simulation for generating construction plan
CN107563089A (en) * 2017-09-15 2018-01-09 中建海峡建设发展有限公司 The method and computing device of PC components generation task list based on BIM
CN107958101A (en) * 2017-11-07 2018-04-24 山东住工装配建筑有限公司 A kind of assembled architecture Information Management System and method based on BIM
CN108053141A (en) * 2017-12-29 2018-05-18 青建集团股份公司 A kind of assembled architecture construction data adjustment control system
CN109801038A (en) * 2019-01-25 2019-05-24 中铁三局集团广东建设工程有限公司 A kind of versatility engineering construction method based on BIM technology application
CN110008648A (en) * 2019-05-15 2019-07-12 平煤神马建工集团有限公司 A kind of wisdom building site Integration Data Model method based on BIM model
CN110929328A (en) * 2019-12-04 2020-03-27 中国电建集团江西省水电工程局有限公司 Concrete assembly type building construction method based on BIM
WO2021031336A1 (en) * 2019-08-16 2021-02-25 清华大学 Method for automated construction progress resource optimization employing building information model

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130335413A1 (en) * 2012-06-13 2013-12-19 National Chiao Tung University System and method for estimating construction duration
KR20170062632A (en) * 2015-11-27 2017-06-08 이화여자대학교 산학협력단 Method for performing BIM-integrated productivity simulation for generating construction plan
CN105888248A (en) * 2016-04-27 2016-08-24 河北建筑工程学院 Construction method of guiding informationization prefabricated member based on BIM (Building Information Modeling)) technology
CN107563089A (en) * 2017-09-15 2018-01-09 中建海峡建设发展有限公司 The method and computing device of PC components generation task list based on BIM
CN107958101A (en) * 2017-11-07 2018-04-24 山东住工装配建筑有限公司 A kind of assembled architecture Information Management System and method based on BIM
CN108053141A (en) * 2017-12-29 2018-05-18 青建集团股份公司 A kind of assembled architecture construction data adjustment control system
CN109801038A (en) * 2019-01-25 2019-05-24 中铁三局集团广东建设工程有限公司 A kind of versatility engineering construction method based on BIM technology application
CN110008648A (en) * 2019-05-15 2019-07-12 平煤神马建工集团有限公司 A kind of wisdom building site Integration Data Model method based on BIM model
WO2021031336A1 (en) * 2019-08-16 2021-02-25 清华大学 Method for automated construction progress resource optimization employing building information model
CN110929328A (en) * 2019-12-04 2020-03-27 中国电建集团江西省水电工程局有限公司 Concrete assembly type building construction method based on BIM

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113609550A (en) * 2021-07-05 2021-11-05 江苏徐工工程机械研究院有限公司 BIM-based construction process planning management method and system
CN113626925A (en) * 2021-08-18 2021-11-09 深圳润世华软件和信息技术服务有限公司 Construction plan management method, construction plan management device, computer equipment and storage medium
CN114781027A (en) * 2022-04-14 2022-07-22 浙江大东吴杭萧绿建科技有限公司 BIM-based digital steel structure building construction method and system

Also Published As

Publication number Publication date
CN113032872B (en) 2023-12-15

Similar Documents

Publication Publication Date Title
CN113032872B (en) BIM technology-based fabricated building progress plan comprehensive resource management and control method
Wang et al. Work package-based information modeling for resource-constrained scheduling of construction projects
Mansuri et al. Building information modeling enabled cascading formwork management tool
Shim et al. Three-dimensional information model-based bridge engineering in Korea
Biruk et al. Optimization of vertical formwork layout plans using mixed integer linear programming
CN116561871A (en) Deep construction method for mounting embedded part of bridge bearing platform
Rui et al. Construction project management based on building information modeling (Bim)
Yang et al. A BIM-based approach to automated prefabricated building construction site layout planning
Marx et al. Preparation of constraints for construction simulation
He et al. Scheduling optimization of prefabricated buildings under resource constraints
Lim et al. Dynamic simulation model for estimating in-situ production quantity of PC members
Xu The Construction Site Management of Concrete Prefabricated Buildings by ISM-ANP Network Structure Model and BIM under Big Data Text Mining Analytic Network Process (ANP)
Si et al. A solution to Just-in-Time delivery for off-site construction: a conceptual model
Suarez et al. Using 5D models and Cba for planning the foundations and concrete structure stages of a complex office building
Oktaviani et al. Implementation of 3D concrete printing technology in precast concrete mass production industry
Yang Application of BIM technology in construction cost management of building engineering
Krepp et al. BIMsite-towards a BIM-based generation and evaluation of realization variants comprising construction methods, site layouts and schedules
Ghammad et al. Transforming building renovation: A holistic, strategic approach with construction robot management
Yuan et al. Simulating and optimizing precast wall lifting in prefabricated building construction
Guan et al. CONSTRUCTION SCHEDULE OPTIMIZATION FOR HIGH ARCH DAMS BASED ON REAL-TIME INTERACTIVE SIMULATION.
Shin et al. A Study on Method of Vertical Zoning of Construction Lift for High-rise Building based on Lift Planning & Operation History Database
He Research on the Application of BIM Technology in Prefabricated Building Construction
Liu Study on Fine Management of Construction Engineering Projects Based on BIM Technology: Taking the Construction of Group C Project of Zibo Cultural Center as an Example
Wang et al. PRODUCTION DECISION RESCHEDULING OF PREFABRICATED BUILDING PARTS SUBJECT TO INTERFERENCE FROM THE ARRIVAL OF NEW ORDERS.
Feng Research on Visualization of Prefabricated Building Process Based on BIM Technology

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant