CN113027333A - Drilling and piling integrated rotary drilling rig and construction method thereof - Google Patents

Drilling and piling integrated rotary drilling rig and construction method thereof Download PDF

Info

Publication number
CN113027333A
CN113027333A CN202110394549.3A CN202110394549A CN113027333A CN 113027333 A CN113027333 A CN 113027333A CN 202110394549 A CN202110394549 A CN 202110394549A CN 113027333 A CN113027333 A CN 113027333A
Authority
CN
China
Prior art keywords
drilling
pile
mounting bracket
piling
drilling rig
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110394549.3A
Other languages
Chinese (zh)
Other versions
CN113027333B (en
Inventor
杨海峰
刘长奎
秦震宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Jingang Geotechnical Engineering Co ltd
Original Assignee
Wuhan Jingang Geotechnical Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Jingang Geotechnical Engineering Co ltd filed Critical Wuhan Jingang Geotechnical Engineering Co ltd
Priority to CN202110394549.3A priority Critical patent/CN113027333B/en
Publication of CN113027333A publication Critical patent/CN113027333A/en
Application granted granted Critical
Publication of CN113027333B publication Critical patent/CN113027333B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/02Drilling rigs characterised by means for land transport with their own drive, e.g. skid mounting or wheel mounting
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B11/00Other drilling tools
    • E21B11/02Boring rams
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B15/00Supports for the drilling machine, e.g. derricks or masts
    • E21B15/003Supports for the drilling machine, e.g. derricks or masts adapted to be moved on their substructure, e.g. with skidding means; adapted to drill a plurality of wells
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B15/00Supports for the drilling machine, e.g. derricks or masts
    • E21B15/04Supports for the drilling machine, e.g. derricks or masts specially adapted for directional drilling, e.g. slant hole rigs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/04Directional drilling
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Mechanical Engineering (AREA)
  • Earth Drilling (AREA)

Abstract

The application relates to a drilling and piling integrated rotary drilling rig and a construction method thereof, relates to the field of engineering machinery and aims to solve the problem that the existing rotary drilling rig needs to replace accessories after drilling holes to pile piles, so that the construction efficiency is low; the drilling mechanism comprises a drill rod, a drilling tool and a power head, the drilling tool and the power head are respectively arranged at two ends of the drill rod, and the power head is used for driving the drill rod to rotate. This application has and installs drilling mechanism and pile mechanism on the mount to can realize the function of drilling and pile through a rotary drilling rig equipment, and need not to change the accessory, improve the effect of efficiency of construction.

Description

Drilling and piling integrated rotary drilling rig and construction method thereof
Technical Field
The application relates to the field of engineering machinery, in particular to a drilling and piling integrated rotary drilling rig and a construction method thereof.
Background
The rotary drilling rig is a construction machine suitable for hole-forming operation in building foundation engineering, is mainly suitable for soil layer construction of sandy soil, cohesive soil, silty soil and the like, and is widely applied to foundation construction of various foundations such as cast-in-place piles, continuous walls, foundation reinforcement and the like. The drilling machine is matched with different drilling tools, is suitable for hole forming operation of dry (short spiral) or wet (rotary bucket) and rock strata (core drill), and can be matched with a long spiral drill, an underground continuous wall grab bucket, a vibrating pile hammer and the like to realize multiple functions.
The construction of the rotary drilling rig is used as a novel construction process, the construction machine is suitable for hole forming operation in building foundation engineering, the application is more and more extensive in the building industry, in actual construction, after the rotary drilling rig is drilled with holes, when piles are required to be driven into the holes, the parts on the rotary drilling rig need to be replaced, then construction is carried out, the construction efficiency is reduced, the parts need to be replaced through manpower, and a large amount of manpower is wasted.
Disclosure of Invention
In order to enable the rotary drilling rig to conveniently pile in a hole after the hole is opened, the application provides the drilling and piling integrated rotary drilling rig and the construction method thereof.
In a first aspect, the application provides a drilling and piling integrated rotary drilling rig, which adopts the following technical scheme:
a drilling and piling integrated rotary drilling rig comprises a rotary drilling rig main body, a tilting bracket fixedly arranged on the rotary drilling rig main body and a mast assembly arranged on the tilting bracket, wherein the tilting bracket and the mast assembly are controlled by a hydraulic system;
the drilling mechanism comprises a drill rod, a drilling tool and a power head, the drilling tool and the power head are respectively arranged at two ends of the drill rod, the power head is used for driving the drill rod to rotate, the drilling tool and the drill rod are detachably connected, and the drill rod is movably connected along the length direction of the mounting rack;
pile driving mechanism is including getting a structure and pile driving subassembly, it includes rotor plate and two sets of anchor clamps that set up on the rotor plate to get a structure, the one end and the mounting bracket swing joint that the rotor plate is close to the drilling tool, pile driving subassembly fixed mounting in on the mounting bracket.
Through adopting above-mentioned technical scheme, dig the inclined support in the rig main part soon and can drive the motion of mast assembly, can be convenient for receive and release the mast assembly, the mast assembly includes the mounting bracket and sets up drilling mechanism and pile mechanism on the mounting bracket, drilling mechanism through the mounting bracket can punch to ground, and releasable connection between drilling tool and the drilling rod, can use different drilling tool trompils according to the needs of ground and construction position, pile and pile are got to pile mechanism on the rethread mounting bracket, need not to dig the rig main part soon and change the accessory, the efficiency of construction is improved, and it is more convenient to use.
Optionally, the cross-section of the mounting bracket is a regular triangle, a cavity is formed in the mounting bracket, the drilling mechanism and the piling mechanism are respectively arranged on two side faces of the mounting bracket, and the inclined bracket is fixedly connected with the other side face of the mounting bracket.
Through adopting above-mentioned technical scheme, drilling mechanism and pile mechanism set up respectively on two sides of mounting bracket to can not cause the influence each other when making drilling mechanism and pile mechanism construct, and the cavity is seted up to the inside of mounting bracket, make the equipment of drive drilling mechanism and pile mechanism install in the inside of mounting bracket, save the exterior space of mounting bracket, avoid equipment to produce the influence to the motion of drilling mechanism and pile mechanism.
Optionally, one side that is close to drilling mechanism on the mounting bracket is provided with the leading truck, the length direction sliding connection of mounting bracket is followed to the leading truck, the leading truck with fixed connection between the unit head, the both ends of leading truck all are provided with the kink, the first spout that sets up along mounting bracket length direction is all seted up to the both sides of keeping away from drilling mechanism on the mounting bracket, the kink is at the inside sliding connection of first spout.
Through adopting above-mentioned technical scheme, through setting up leading truck and unit head fixed connection, it is fixed to guarantee the direction of motion of drilling, and the both sides of leading truck set up the kink, and the kink is at the inside sliding connection of first spout, because the structural constraint of mounting bracket and leading truck makes the leading truck can not follow the mounting bracket and drops, improves the motion stability of leading truck.
Optionally, a limiting frame is fixedly connected to one side, close to the drilling mechanism, of the mounting frame, a wear-resistant ring is fixedly connected to the limiting frame, a circular through hole matched with the drill rod is formed in the middle of the wear-resistant ring, and the drill rod penetrates through the wear-resistant ring at the circular through hole.
Through adopting above-mentioned technical scheme, the drilling rod passes the circular through-hole at wear-resisting circle middle part to can guarantee drilling rod and rotor plate parallel arrangement, improve the stability of drilling rod, avoid the drilling rod to take place to rock when the construction, to run from opposite directions the hole and cause the influence.
Optionally, a second chute which is vertically arranged is formed in one side, close to the piling mechanism, of the mounting frame, a sliding block is connected to the inside of the second chute in a sliding mode, the rotating plate is connected with the side wall of the sliding block in a rotating mode, a lifting piece is arranged inside the cavity, and the lifting piece is fixedly connected with the sliding block.
Through adopting above-mentioned technical scheme, the slider slides in the inside of second spout, can drive the slider through the lifter and remove to can make the rotor plate rotate and can follow the top of pile foundation when the level and press from both sides it and get, be convenient for press from both sides the pile foundation that the clamp diameter is different, and make anchor clamps more stable.
Optionally, the two sets of the fixtures are arranged on one side of the rotating plate, which is far away from the mounting frame, and the two sets of the fixtures are arranged on the same axis, the fixtures and the inclined support are controlled by a hydraulic system, and the inner wall of each fixture is provided with an anti-slip sheet.
Through adopting above-mentioned technical scheme, start anchor clamps through hydraulic system, and be provided with the antiskid ribbed tile on the inner wall of anchor clamps to can be to the fixed fastening more of pile foundation, avoid pressing from both sides to get and cause the pile foundation to drop after the pile foundation and take place danger.
Optionally, a wire releasing structure is arranged inside the cavity and comprises a driving part and a steel wire rope arranged on the driving part, the driving part is fixedly connected to the inner wall of the cavity, and one end, far away from the driving part, of the steel wire rope is fixedly connected to the rotating plate.
Through adopting above-mentioned technical scheme, can drive the wire rope extension through the driving piece, and then make the rotor plate rotate to the level, be convenient for press from both sides through the anchor clamps on the rotor plate and get the pile foundation, perhaps the driving piece makes wire rope shorten, and the pulling rotor plate rotates to suitable position, is convenient for install the pile foundation.
Optionally, the sliding block is fixedly connected with a fixed pulley, and the steel wire rope is wound outside the fixed pulley.
Through adopting above-mentioned technical scheme, through setting up the fixed pulley, fixed pulley fixed connection is on the slider to the fixed pulley can be along with slider synchronous motion, and wire rope winds in the outside of fixed pulley, thereby can guarantee that the fixed pulley is to the angle fixation of the wire rope between the rotor plate, can stably lift the rotor plate.
Optionally, the piling assembly comprises a hydraulic cylinder and a piling hammer, the hydraulic cylinder is fixedly mounted on the mounting frame, and the piling hammer is detachably and fixedly connected to a piston rod of the hydraulic cylinder.
Through adopting above-mentioned technical scheme, promote the pile hammer motion through the pneumatic cylinder to make the top of pile hammer striking pile foundation, thereby in beating the hole with the pile foundation, and the piston rod releasable connection of pile hammer and pneumatic cylinder, be convenient for dismantle the pile hammer, change and maintain the pile hammer.
In a second aspect, the application provides a construction method of a drilling and piling integrated rotary drilling rig, which adopts the following technical scheme:
a construction method of a drilling and piling integrated rotary drilling rig comprises the following steps:
s1, embedding a protection cylinder, placing the rotary drilling rig main body in place, and driving the mounting frame to rotate by the rotary drilling rig main body so as to enable the mounting frame to rotate to the vertical direction;
s2, starting the power head after the drilling tool lightly lands, driving the drilling tool to rotate by the power head to open the drilling tool, lifting the drilling tool out of the hole when the drilling tool is filled with sand, and discharging the sand in the drilling tool;
s3, drilling, cleaning holes and measuring depth;
s4, paying off through a paying-off structure to enable the rotating plate to rotate to the horizontal direction, fixing the pile foundation through a clamp on the rotating plate, and taking up through the paying-off structure to enable the rotating plate and the pile foundation to rotate to the vertical direction;
s5, placing the pile foundation in the hole, and starting a hydraulic cylinder to drive a pile driving hammer to move so as to drive a pile;
and S6, pulling out the pile casing, cleaning the pile head, and filling the gap between the pile foundation and the hole.
In summary, the present application includes at least the following advantageous technical effects:
1. the mast assembly can be driven to move by the rotary drilling rig main body, the angle of the mast assembly is adjusted by the inclined bracket, the mast assembly is convenient to fold and unfold, the mast assembly comprises a mounting frame and a drilling mechanism and a piling mechanism which are arranged on the mounting frame, holes can be drilled on the ground by the drilling mechanism on the mounting frame, and piles are taken and piled by the piling mechanism on the mounting frame, so that parts of the rotary drilling rig main body do not need to be replaced, the construction efficiency is improved, and the rotary drilling rig is more convenient to use;
2. the guide frame is arranged, the bent parts are arranged at the two ends of the guide frame, the bent parts slide in the first sliding groove on the mounting frame, the guide frame cannot fall off from the mounting frame due to structural limitation of the mounting frame and the guide frame, the guide frame is fixedly connected with the power head, the drill rod penetrates through the circular through hole in the middle of the wear-resisting ring, the drill rod can move in the direction parallel to the mounting frame, the movement is more stable, and the drill rod is prevented from shaking during construction and affecting the split hole;
3. through the inside at the second spout sets up the slider, the rotor plate rotates with the lateral wall of slider to be connected, the lift piece can drive the slider motion, thereby can make the rotor plate rotate when to the level, anchor clamps are got to it clamp from the top of pile foundation, be convenient for press from both sides the pile foundation that gets the diameter difference, and make anchor clamps more stable, drive the rotor plate by unwrapping wire structure again and rotate, be convenient for lift the pile foundation and place in the hole, thereby drive the pile hammer motion through the pneumatic cylinder and beat the pile foundation into the hole, the efficiency of construction is improved.
Drawings
Fig. 1 is a schematic overall structure diagram of an embodiment of the present application.
Fig. 2 is a schematic front view of the structure of the embodiment of the present application.
Fig. 3 is a schematic rear view cross-sectional structure of an embodiment of the present application.
Reference numerals: 1. a main body of the rotary drilling rig; 2. a tilting bracket; 3. a mast assembly; 31. a mounting frame; 32. a drilling mechanism; 321. a drill stem; 322. drilling tools; 323. a power head; 33. a pile driving mechanism; 331. taking a pile structure; 3311. a rotating plate; 3312. a clamp; 332. a pile driving assembly; 3321. a hydraulic cylinder; 3322. a pile hammer; 4. a cavity; 5. a guide frame; 6. a bending section; 7. a first chute; 8. a limiting frame; 9. wear-resistant rings; 10. a second chute; 11. a slider; 12. a lifting member; 13. anti-slip sheets; 14. a paying-off structure; 141. a drive member; 142. a wire rope; 15. and a fixed pulley.
Detailed Description
The present application is described in further detail below with reference to figures 1-3.
The embodiment of the application discloses drilling and piling integrated rotary drilling rig.
Referring to fig. 1, the drilling and piling integrated rotary drilling rig comprises a rotary drilling rig main body 1, one end of the rotary drilling rig main body 1, which is close to a control room, is fixedly provided with an inclined bracket 2 through a bolt, a mast assembly 3 is fixedly provided on the inclined bracket 2 through a bolt, the inclined bracket 2 and the mast assembly 3 are controlled through a hydraulic system, the mast assembly 3 comprises a mounting frame 31, the mounting frame 31 can be rotated to a transverse state and a vertical state through the inclined bracket 2, so that the rotary drilling rig main body 1 drives the mounting frame 31 to move, the cross section of the mounting frame 31 is a regular triangle, the inclined bracket 2 is fixedly connected with one outer wall of the mounting frame 31 through a bolt, the other two side surfaces of the mounting frame 31 are respectively provided with a drilling mechanism 32 and a piling mechanism 33, the drilling mechanism 32 and the piling mechanism 33 cannot mutually influence during construction, make the equipment installation in the inside of mounting bracket 31 of drive drilling mechanism 32 and pile mechanism 33, save the exterior space of mounting bracket 31, avoid equipment to produce the influence to drilling mechanism 32 and pile mechanism 33's motion, for improving drilling mechanism 32 accuracy of changeing the hole position, bottom at mounting bracket 31 is provided with infrared laser emission device (not drawn in the picture), and be swing joint between infrared laser emission device and the mounting bracket 31, there is fixed box bottom of mounting bracket 31 through screw fixed mounting, circular cavity has been seted up to the bottom of fixed box, and be connected with the rolling ball in the internal rotation of circular cavity, infrared laser emission device sets up on the rolling ball, thereby can adjust infrared laser emission device through the rolling ball and take place infrared position.
Referring to fig. 1, the drilling mechanism 32 includes a drill rod 321, a drilling tool 322 and a power head 323, the power head 323 is welded at one end of the drill rod 321, the drill rod 321 is driven to rotate by the power head 323, the drilling tool 322 is disposed at the other end of the drill rod 321, the drilling tool 322 is detachably connected to the drill rod 321, and can be changed according to the construction requirements and different soil qualities, thereby facilitating the replacement of different drilling tools 322, drilling the ground, one side of the mounting frame 31 close to the drilling mechanism 32 is movably connected with a guide frame 5, the guide frame 5 is slidably connected along the length direction of the mounting frame 31, the power head 323 is fixedly mounted on the guide frame 5 through bolts, thereby enabling the power head 323, the drill rod 321, the drilling tool 322 to move along the length direction of the mounting frame 31, bent portions 6 are welded at two ends of the guide frame 5, an included angle between the guide frame 5 and the bent portions 6 is 60 degrees, first chutes 7 arranged, the bending part 6 is connected in a sliding way inside the first sliding chute 7, and the guide frame 5 can stably move along the surface of the mounting frame 31.
Referring to fig. 1, for guaranteeing the stability of drilling rod 321 motion, one side welding that is close to drilling mechanism 32 on mounting bracket 31 has spacing 8, the welding has wear-resisting circle 9 on spacing 8, the circular through-hole with drilling rod 321 looks adaptation is seted up at the middle part of wear-resisting circle 9, drilling rod 321 runs through wear-resisting circle 9 in circular through-hole department, thereby guarantee that drilling rod 321 moves along the direction that is on a parallel with mounting bracket 31 when moving, improve the stability of drilling rod 321, avoid drilling rod 321 to take place to rock when the construction, drilling rod 321 rocks and causes the influence to the trompil.
Referring to fig. 2, the pile driving mechanism 33 includes a pile taking structure 331, the pile taking structure 331 includes a rotating plate 3311 and two sets of clamps 3312 disposed on the rotating plate 3311, the two sets of clamps 3312 are disposed on the same axis, the two sets of clamps 3312 are controlled by a hydraulic system with respect to the inclined bracket 2, the pile foundation can be clamped by the clamps 3312, and an anti-slip sheet 13 is bonded to an inner wall of the clamps 3312, so as to increase friction between the clamps 3312 and the pile foundation, so that the pile foundation can be fixed more stably, one end of the rotating plate 3311 near the drill 322 is movably connected to the mounting frame 31, one side of the mounting frame 31 near the pile driving mechanism 33 is provided with a second sliding groove 10 disposed along a length direction of the mounting frame 31, the inside of the second sliding groove 10 is slidably connected with a sliding block 11, the rotating rod is hinged to a side of the sliding block 11, a lifting member 12 is disposed at a, the cylinder passes through bolt fixed mounting in cavity 4, and the welding can promote the motion of slider 11 through the cylinder between the piston rod of its slider 11 and cylinder, makes slider 11 slide in the inside of second spout 10, when the diameter of pile foundation is great, then need raise the height of rotor plate 3311, is convenient for get the stake.
Referring to fig. 2 and 3, in order to facilitate the rotation of the rotating plate 3311, a wire releasing structure 14 is disposed inside the cavity 4, the wire releasing structure 14 includes a driving member 141 and a wire rope 142 disposed on the driving member 141, in this embodiment, the driving member 141 is a motor, the motor is mounted on the inner wall of the cavity 4 through a bolt, a fixing sleeve is welded on an output shaft of the motor, the wire rope 142 is wound outside the fixing sleeve, one end of the wire rope 142 away from the driving member 141 is fixedly connected to the rotating plate 3311, a connecting ring is welded on the rotating plate 3311, the wire rope 142 is fixedly connected to the connecting ring, the wire rope 142 is driven by the motor to move to realize the rotation of the rotating plate 3311, in order to ensure the angle of the wire rope 142 between the fixed pulley 15 and the rotating plate 3311 to be fixed, the rotating plate 3311 can be stably lifted, the fixed pulley 15, and the wire rope 142 is wound around the outside of the fixed sheave 15.
Referring to fig. 2, the pile driving mechanism 33 further includes a pile driving assembly 332, the pile driving assembly 332 includes a hydraulic cylinder 3321 and a pile hammer 3322, the mounting bracket 31 is welded with a mounting plate, the hydraulic cylinder 3321 is fixedly mounted at the bottom of the mounting plate through a bolt, the hydraulic cylinder 3321 is vertically arranged, the pile hammer 3322 is detachably and fixedly connected to a piston rod of the hydraulic cylinder 3321, the hydraulic cylinder 3321 pushes the pile hammer 3322 to move, so that the pile hammer 3322 impacts the top of the pile foundation, so that the pile foundation is driven into the hole, and the pile hammer 3322 is detachably connected to the piston rod of the hydraulic cylinder 3321, so that the pile hammer 3322 is conveniently detached, and the pile hammer 3322 is replaced and maintained.
The embodiment of the application also discloses a construction method of the drilling and piling integrated rotary drilling rig, which comprises the following steps:
s1, burying a pile casing, preferably checking pile position deviation by using a stay wire method, taking the rotary drilling rig main body 1 in place to enable the rotary drilling rig main body 1 to stop at a proper position when the construction specification requirement is met, opening a support frame to fix the rotary drilling rig main body 1, driving the mounting frame 31 to rotate by the rotary drilling rig main body 1 to enable the mounting frame to rotate to the vertical direction, and enabling the drilling tool 322 to be located at a position needing to be drilled;
s2, starting the power head 323 after the drilling tool 322 lightly lands, wherein the power head 323 drives the drilling tool 322 to rotate to drill, selecting different rotating speeds and feed rates to control according to different levels of soil structures, and lifting the drilling tool 322 out of the hole when the drilling tool 322 is filled with sand to discharge the sand in the drilling tool 322;
s3, drilling, cleaning holes and measuring depth;
s4, starting the cylinder, lifting the slide block 11 to a proper height according to the diameter of the pile foundation, paying off by the paying-off structure 14 to rotate the rotating plate 3311 to the horizontal direction, controlling the clamp 3312 on the rotating plate 3311 to clamp and fix the pile foundation, and taking up by the paying-off structure 14 to rotate the rotating plate 3311 and the pile foundation to the vertical direction;
s5, adjusting the position of the mounting frame 31, placing the pile foundation in a prefabricated hole, starting a hydraulic cylinder 3321 to drive a pile driving hammer 3322 to move in the vertical direction, and enabling the pile driving hammer 3322 to impact the top end of the pile foundation for driving the pile;
and S6, enabling the pile foundation to enter the hole, pulling out the pile casing, cleaning the pile head, filling the gap between the pile foundation and the hole, and fixing the pile foundation.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (10)

1. The utility model provides a drilling pile integral type rotary drilling rig, includes that rotary drilling rig main part (1), fixed mounting incline support (2) on rotary drilling rig main part (1) and mast assembly (3) that set up on incline support (2), through hydraulic system control, its characterized in that between incline support (2) and mast assembly (3): the mast assembly (3) comprises a mounting frame (31) and a drilling mechanism (32) and a piling mechanism (33) which are arranged on the mounting frame (31), and the mounting frame (31) is fixedly connected to the inclined bracket (2);
the drilling mechanism (32) comprises a drill rod (321), a drilling tool (322) and a power head (323), the drilling tool (322) and the power head (323) are respectively arranged at two ends of the drill rod (321), the power head (323) is used for driving the drill rod (321) to rotate, the drilling tool (322) is detachably connected with the drill rod (321), and the drill rod (321) is movably connected along the length direction of the mounting frame (31);
pile mechanism (33) are including getting a structure (331) and pile subassembly (332), get a structure (331) and set up anchor clamps (3312) on rotating plate (3311) including rotating plate (3311) and two sets of, rotating plate (3311) is close to one end and mounting bracket (31) swing joint of drilling tool (322), pile subassembly (332) fixed mounting in on mounting bracket (31).
2. The drilling and piling integrated rotary drilling rig according to claim 1, characterized in that: the cross-section of mounting bracket (31) is regular triangle, cavity (4) have been seted up to the inside of mounting bracket (31), drilling mechanism (32) and pile driving mechanism (33) set up respectively on two sides of mounting bracket (31), fixed connection between another side on slope support (2) and mounting bracket (31).
3. The drilling and piling integrated rotary drilling rig according to claim 1, characterized in that: one side that is close to drilling mechanism (32) on mounting bracket (31) is provided with leading truck (5), the length direction sliding connection of mounting bracket (31) is followed in leading truck (5), leading truck (5) with fixed connection between unit head (323), the both ends of leading truck (5) all are provided with kink (6), first spout (7) that set up along mounting bracket (31) length direction are all seted up to the both sides of keeping away from drilling mechanism (32) on mounting bracket (31), kink (6) are at the inside sliding connection of first spout (7).
4. The drilling and piling integrated rotary drilling rig according to claim 1, characterized in that: one side fixedly connected with spacing (8) that is close to drilling mechanism (32) on mounting bracket (31), fixedly connected with wear-resisting circle (9) on spacing (8), the middle part of wear-resisting circle (9) seted up with the circular through-hole of drilling rod (321) looks adaptation, drilling rod (321) run through in circular through-hole department wear-resisting circle (9).
5. The drilling and piling integrated rotary drilling rig according to claim 2, characterized in that: the utility model discloses a pile driver, including mounting bracket (31), swivel plate (3311), slider (11), mounting bracket (31) is last to be close to one side of pile driver structure (33) and seted up second spout (10) of vertical setting, the inside sliding connection of second spout (10) has slider (11), swivel plate (3311) with the lateral wall of slider (11) rotates to be connected, the inside of cavity (4) is provided with lift piece (12), lift piece (12) with slider (11) fixed connection.
6. The drilling and piling integrated rotary drilling rig according to claim 1, characterized in that: two sets of anchor clamps (3312) all set up in rotor plate (3311) keep away from one side of mounting bracket (31), and two sets of anchor clamps (3312) set up on same axis, through hydraulic system control between anchor clamps (3312) and slope support (2), the inner wall of anchor clamps (3312) all is provided with antiskid ribbed tile (13).
7. The drilling and piling integrated rotary drilling rig according to claim 5, characterized in that: the inside of cavity (4) is provided with unwrapping wire structure (14), unwrapping wire structure (14) include driving piece (141) and set up wire rope (142) on driving piece (141), driving piece (141) fixed connection in on the inner wall of cavity (4), wire rope (142) keep away from one end fixed connection of driving piece (141) on rotor plate (3311).
8. The drilling and piling integrated rotary drilling rig according to claim 7, characterized in that: the sliding block (11) is fixedly connected with a fixed pulley (15), and the steel wire rope (142) is wound outside the fixed pulley (15).
9. The drilling and piling integrated rotary drilling rig according to claim 1, characterized in that: the piling assembly (332) comprises a hydraulic cylinder (3321) and a piling hammer (3322), the hydraulic cylinder (3321) is fixedly installed on the installation frame (31), and the piling hammer (3322) is detachably and fixedly connected to a piston rod of the hydraulic cylinder (3321).
10. The construction method of the drilling and piling integrated rotary drilling rig according to any one of claims 1-9, wherein: the method comprises the following steps:
s1, embedding a protection cylinder, placing the rotary drilling rig main body (1) in place, and driving the mounting frame (31) to rotate by the rotary drilling rig main body (1) to enable the mounting frame to rotate to the vertical direction;
s2, starting the power head (323) after the drilling tool (322) lightly touches the ground, driving the drilling tool (322) to rotate by the power head (323) to drill, lifting the drilling tool (322) out of the hole when the drilling tool (322) is filled with sand, and discharging the sand in the drilling tool (322);
s3, drilling, cleaning holes and measuring depth;
s4, paying off through a paying-off structure (14) to enable a rotating plate (3311) to rotate to the horizontal direction, fixing a pile foundation through a clamp (3312) on the rotating plate (3311), and taking up through the paying-off structure (14) to enable the rotating plate (3311) and the pile foundation to rotate to the vertical direction;
s5, placing the pile foundation in the hole, and starting a hydraulic cylinder (3321) to drive a pile driving hammer (3322) to move so as to drive a pile;
and S6, pulling out the pile casing, cleaning the pile head, and filling the gap between the pile foundation and the hole.
CN202110394549.3A 2021-04-13 2021-04-13 Drilling and piling integrated rotary drilling rig and construction method thereof Active CN113027333B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110394549.3A CN113027333B (en) 2021-04-13 2021-04-13 Drilling and piling integrated rotary drilling rig and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110394549.3A CN113027333B (en) 2021-04-13 2021-04-13 Drilling and piling integrated rotary drilling rig and construction method thereof

Publications (2)

Publication Number Publication Date
CN113027333A true CN113027333A (en) 2021-06-25
CN113027333B CN113027333B (en) 2023-03-28

Family

ID=76456457

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110394549.3A Active CN113027333B (en) 2021-04-13 2021-04-13 Drilling and piling integrated rotary drilling rig and construction method thereof

Country Status (1)

Country Link
CN (1) CN113027333B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113622817A (en) * 2021-09-24 2021-11-09 邯郸市钻岩工程机械有限公司 Low-clearance rotary drilling rig
CN114575339A (en) * 2022-03-04 2022-06-03 沧州水务发展集团有限责任公司 Seat gate cast-in-place pile construction device and construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2428636A1 (en) * 2010-09-13 2012-03-14 CASAGRANDE SpA Articulated support for a hydraulic drill, hydraulic drill and method to actuate said articulated support of said hydraulic drill
JP2017128909A (en) * 2016-01-20 2017-07-27 日本基礎技術株式会社 Hole drilling device
CN210288383U (en) * 2019-06-28 2020-04-10 江苏巨威机械有限公司 Rotary drilling and piling integrated machine
CN210684687U (en) * 2019-08-19 2020-06-05 南阳理工学院 Pile driver for bridge construction
CN212077929U (en) * 2019-09-06 2020-12-04 郑州鑫美高能打桩机有限责任公司 Intelligent pile frame

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2428636A1 (en) * 2010-09-13 2012-03-14 CASAGRANDE SpA Articulated support for a hydraulic drill, hydraulic drill and method to actuate said articulated support of said hydraulic drill
JP2017128909A (en) * 2016-01-20 2017-07-27 日本基礎技術株式会社 Hole drilling device
CN210288383U (en) * 2019-06-28 2020-04-10 江苏巨威机械有限公司 Rotary drilling and piling integrated machine
CN210684687U (en) * 2019-08-19 2020-06-05 南阳理工学院 Pile driver for bridge construction
CN212077929U (en) * 2019-09-06 2020-12-04 郑州鑫美高能打桩机有限责任公司 Intelligent pile frame

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113622817A (en) * 2021-09-24 2021-11-09 邯郸市钻岩工程机械有限公司 Low-clearance rotary drilling rig
CN113622817B (en) * 2021-09-24 2023-06-20 邯郸市钻岩工程机械有限公司 Low-clearance rotary drilling rig
CN114575339A (en) * 2022-03-04 2022-06-03 沧州水务发展集团有限责任公司 Seat gate cast-in-place pile construction device and construction method

Also Published As

Publication number Publication date
CN113027333B (en) 2023-03-28

Similar Documents

Publication Publication Date Title
US4202416A (en) Method and apparatus for sinking a cased borehole for producing cased pile foundations
CN113027333B (en) Drilling and piling integrated rotary drilling rig and construction method thereof
CN102852457B (en) Follow-up drilling machine for down-hole hammer casing pipe
KR20070016292A (en) Pile construction apparatus capable of drilling and piling at a time
CN102425372B (en) Vibrato-drilling type punching drilling rig
JP6081100B2 (en) Existing pile pulling device
CN214145354U (en) Drilling device for complex high and steep slope
CN202788610U (en) Down-hole hammer sleeve follow-up drilling machine
CN211395670U (en) Piling device for building construction
CN202417302U (en) Vibrating drilling type impact digging drilling machine
CN116335532A (en) Powerful multifunctional drilling machine for SWSD
JP5290463B1 (en) Hammer grabs and low-head drilling rigs
KR100474184B1 (en) Hitting machine to drive sheet pile deeply using auger
CN111305753A (en) Geotechnical engineering on-site piling device
JP7359344B2 (en) Drilling vehicle and drilling method
CN210289617U (en) Ultra-large aperture pore-forming working device suitable for complex geological conditions
CN108952568B (en) Drilling machine
JP3012900B2 (en) Auger excavation control method
JP3167247B2 (en) Hydraulic excavator equipped with ground hardness measurement device
JPH10205263A (en) Earth-removing device for excavator
SU747974A1 (en) Vibration earth-drilling unit
CN217439973U (en) Equipment for complex geological pile foundation pore-forming construction
CN218971122U (en) Grouting drilling machine and grouting system
JP2916598B2 (en) Excavator
JPH0235912Y2 (en)

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant