CN112796710B - Processing system and method for mining area gas extraction judgment - Google Patents

Processing system and method for mining area gas extraction judgment Download PDF

Info

Publication number
CN112796710B
CN112796710B CN202011609627.9A CN202011609627A CN112796710B CN 112796710 B CN112796710 B CN 112796710B CN 202011609627 A CN202011609627 A CN 202011609627A CN 112796710 B CN112796710 B CN 112796710B
Authority
CN
China
Prior art keywords
data
module
gas
processing unit
database
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202011609627.9A
Other languages
Chinese (zh)
Other versions
CN112796710A (en
Inventor
朱世奎
徐瑞
王新琨
刘振
王庆永
苗二矿
李志�
车路
肖富刚
刘超
程浩
李健
梁峰
袁冬冬
陈瑶
路思远
吴克介
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huaibei Mining Co Ltd
Original Assignee
Huaibei Mining Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huaibei Mining Co Ltd filed Critical Huaibei Mining Co Ltd
Priority to CN202011609627.9A priority Critical patent/CN112796710B/en
Publication of CN112796710A publication Critical patent/CN112796710A/en
Application granted granted Critical
Publication of CN112796710B publication Critical patent/CN112796710B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/006Production of coal-bed methane
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • E21B47/02Determining slope or direction
    • E21B47/022Determining slope or direction of the borehole, e.g. using geomagnetism
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/02Agriculture; Fishing; Forestry; Mining
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Physics & Mathematics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Business, Economics & Management (AREA)
  • Geophysics (AREA)
  • Agronomy & Crop Science (AREA)
  • General Health & Medical Sciences (AREA)
  • General Chemical & Material Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Animal Husbandry (AREA)
  • Marine Sciences & Fisheries (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Health & Medical Sciences (AREA)
  • Economics (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a processing system for mine gas extraction judgment, which comprises a database, a data processing unit, a control module, a PC (personal computer) end browsing module and a monitoring system module, wherein the data processing unit comprises a data access interface and a logic analysis and statistics module, the database is connected with the logic analysis and statistics module through the data access interface, the logic analysis module is connected with the PC end browsing module through the control module, the database receives drilling track data derived by a drilling track measuring instrument and transmits the drilling track data to the data processing module, and the database is also provided with a signal input end connected with the monitoring system module.

Description

Processing system and method for mining area gas extraction judgment
Technical Field
The invention belongs to the field of coal mining, and particularly relates to a processing system and a processing method for judging gas extraction in a mining area.
Background
Gas extraction is a key means for preventing coal and gas outburst accidents, and the 'extraction before extraction' is a consensus of the industry. The mining effect of each mine of Huaibei mining industry group is judged in a manual mode, and the problems of complex judgment process, error-prone judgment result, disordered data management and the like exist. Therefore, a set of coal mine gas extraction standard-reaching judgment system software is urgently needed to realize extraction online monitoring, extraction digital management and online process judgment, and aiming at the problems that the manual extraction judgment process is complex, the judgment result is easy to make mistakes and the like, in the prior art, an informatization and intelligent means is adopted, the industrial standard is taken as the basis, and the expert experience and the field condition are combined, so that extraction standard-reaching online judgment is difficult to realize.
Disclosure of Invention
The invention aims to solve the technical problem of providing a processing system and a method for judging gas extraction in a mining area.
In order to achieve the purpose, the invention adopts the technical scheme that:
the utility model provides a processing system for mining area gas drainage judges, including the database, the data processing unit, a control module, PC end browsing module and monitored control system module, wherein, the package contains data access interface and logic analysis statistics module in the data processing unit, the database links to each other with logic analysis statistics module through data access interface, logic analysis module is connected with PC end browsing module through control module, with the data after receiving the processing browse the module in PC end and show, the database receives the drilling track data that drilling track measuring apparatu derived and transmits in data processing module, the database still is provided with the signal input part who links to each other with monitored control system module.
The invention discloses a processing system for mining area gas extraction judgment, wherein a data processing unit comprises a processing unit module, a coordinate conversion module, a blue light GIS platform and a receiving module, drilling track data in a database are transmitted to the processing unit module, the processing unit module is connected to a signal input end of the blue light GIS platform through the coordinate conversion module so as to transmit the processed drilling track data, and a signal output end of the blue light GIS platform is connected to the other signal input end of the processing unit module through the receiving module so as to output a mine image to the processing unit module.
The invention discloses a processing system for judging gas extraction in a mining area, wherein data transmitted to a database by a monitoring system module comprises gas extraction data and analytic data, and the gas extraction data and the analytic data are transmitted to a data processing unit by the database.
The invention discloses a processing method for judging gas extraction in a mining area, which comprises the following steps of:
s1, the system initially judges the type of the gas emission quantity, and firstly judges whether data need to be transmitted to a data processing unit;
s2, the system initially judges whether the gas emission amount belongs to a mining layer or a tunneling layer, if the gas emission amount belongs to the mining layer, data are output to a data processing module, and then the concentration and the residual gas pressure of the gas emission amount are judged;
if the gas emission quantity belongs to a tunneling layer, judging whether the gas concentration in the wind speed and the return air flow reaches the standard or not;
and S3, recording the initially judged gas data serving as final data into a database.
The invention discloses a processing method for judging gas extraction in a mining area, wherein in the step S2, if the gushed gas quantity is judged to belong to a rock stratum adjacent to a mining layer, the same steps are adopted to judge the concentration and the residual gas pressure.
The invention discloses a processing method for judging gas extraction in a mining area, wherein in the step S2, the residual gas in a tunneling layer is judged to reach the standard under the conditions that the pressure is less than 0.74MPa and the content of the residual gas is less than 8 cubic meters per ton.
The invention discloses a processing method for judging gas extraction in a mining area, which is characterized in that in the step S2, the residual gas in a mining layer or a layer adjacent to the mining layer is judged to reach the standard under the conditions that the pressure is less than 0.74MPa and the content of the residual gas is less than 8 cubic meters per ton.
By adopting the technical scheme, the system of the scheme is adopted to pre-judge the rock stratum and the quantity of the underground residual gas quantity, so that the functions of mine gas monitoring information display, gas extraction basic data management, extraction standard-reaching online process judgment, extraction pipeline visual display and the like are realized, real-time monitoring of all levels of gas extraction quantities of an extraction pipeline, a working face, an evaluation unit, a metering point and a drill hole is provided for a coal mine user, the occurrence of coal mine safety accidents is effectively prevented and controlled, the underground gas condition is known more accurately, and the normal operation of the mine safety production order and the life and property safety of people are guaranteed.
The invention will be described in more detail below with reference to the drawings and examples.
Drawings
The following brief description of the drawings and reference numerals in the drawings forms a part of this specification:
FIG. 1 is a schematic signal transmission diagram of a processing system according to the present invention;
FIG. 2 is a block diagram of the processing system of the present invention;
FIG. 3 is a logic flow diagram of a processing method of the present invention;
fig. 4 is a schematic diagram of the information of the measuring points set in the present invention.
Detailed Description
The following description of the embodiments of the present invention, with reference to the accompanying drawings, will make the embodiments of the present invention, such as the shapes and configurations of the components, the mutual positions and connection relationships between the components, the functions and operating principles of the components, the manufacturing process and the operation method, etc., more detailed description so as to help those skilled in the art to more completely, accurately and deeply understand the inventive concept and technical solution of the present invention.
FIG. 1 is a schematic diagram of signal transmission of a processing system of the invention, FIG. 2 is a schematic diagram of module signal connection of the processing system of the invention, and the processing system for gas extraction judgment in a mining area shown in FIGS. 1 and 2 comprises a database, a data processing unit, a control module, a PC-side browsing module and a monitoring system module, wherein the data processing unit comprises a data access interface and a logic analysis and statistics module, the database is connected with the logic analysis and statistics module through the data access interface, the logic analysis module is connected with the PC-side browsing module through the control module to receive processed data to be displayed on the PC-side browsing module, the database receives drilling track data derived by a drilling track measuring instrument and transmits the drilling track data to the data processing module, the data processing unit comprises a processing unit module, a coordinate conversion module, a blue light GIS platform and a receiving module, drilling track data in the database are transmitted to the processing unit module, the processing unit module is connected to the signal input end of the blue light GIS platform through the coordinate conversion module to transmit the processed drilling track data, the signal output end of the blue light GIS platform is connected to the other signal input end of the processing unit module through the receiving module to output a mine drawing to the processing unit module, the data transmitted to the database by the monitoring system module comprises gas extraction data and analytic data, and the database transmits the gas extraction data and the analytic data to the data processing unit.
The system is based on monitoring data of a safety monitoring system, simultaneously carries out digital management on basic information of extraction related working faces, evaluation units and the like, takes 'temporary standard reaching regulations of coal mine gas extraction' as a theoretical basis on the basis, and is assisted by expert experience and field conditions, so that the online judgment of the coal mine gas extraction effect is realized.
Fig. 3 is a logic flow chart of the processing method in the present invention, and the processing method for judging gas extraction in a mining area shown in fig. 3 includes the following steps:
s1, the system initially judges the type of the gas emission quantity, and firstly judges whether data need to be transmitted to a data processing unit;
s2, the system initially judges whether the gas emission amount belongs to a mining layer or a tunneling layer, if the gas emission amount belongs to the mining layer, data are output to a data processing module, and then the concentration and the residual gas pressure of the gas emission amount are judged;
if the gas emission quantity belongs to the tunneling layer, judging whether the gas concentration in the wind speed and the return air flow reaches the standard or not;
and S3, recording the initially judged gas data serving as final data into a database.
And in the step S2, if the gushing gas amount is judged to belong to the rock stratum adjacent to the mining layer, the concentration and the residual gas pressure are judged by adopting the same step.
And judging that the residual gas in the tunneling layer reaches the standard under the conditions that the pressure is less than 0.74MPa and the residual gas content is less than 8 cubic meters per ton in the step S2, and judging that the residual gas in the mining layer or the layer close to the mining layer reaches the standard under the conditions that the pressure is less than 0.74MPa and the residual gas content is less than 8 cubic meters per ton in the step S2.
Fig. 4 is a schematic view of information of a measurement point set in the invention, and the gas extraction standard-reaching judgment software comprises two sub-modules of gas extraction and standard-reaching judgment. The gas extraction comprises a GIS map, extraction utilization amount configuration, gas utilization rate statistics, pipeline extraction amount statistics, gas extraction two statistics, extraction metering point definition, extraction pipeline monitoring parameter definition, real-time data monitoring and a historical curve;
the extraction control and the extraction effect judgment are divided into extraction digital management and online process judgment. The information to be managed by the extraction digital management comprises working face information, coal seam information, evaluation unit information, drill site information, extraction pipeline information, artificial measuring point information, artificial measuring data information, field actual measurement parameter information and the like, and the standard reaching judgment comprises working face management, evaluation unit management, coal seam basic parameter management, artificial measuring point data management, artificial measuring point configuration, evaluation unit splitting, basic condition judgment, pre-judgment, final judgment data entry and final judgment.
The system is divided into a sensing layer, a persistent layer, a service layer and an application layer from bottom to top.
The perception layer comprises a gas flow metering device, a portable gas flow meter, a KJ90X safety monitoring system and a KJ73X safety monitoring system, and all the devices are the keys for collecting gas measurement data at the bottom layer and provide data sources for the persistence layer.
The persistent layer comprises gas extraction monitoring data transmitted by the sensing layer, extraction standard data generated by system judgment, basic data of normal operation of the system and other data.
The service layer comprises a working face absolute gas emission quantity prediction model, a gas utilization quantity, utilization rate calculation model, an extraction effect pre-evaluation model and a prediction residual time prediction model, and corresponding results are calculated by the models according to data provided by the persistent layer and are sent to the application layer.
The application layer comprises the functions of GIS (geographic information System) map drawing, gas monitoring statistical analysis, gas extraction management, extraction lower effect judgment, judgment report derivation and the like.
The unified collection of the gas extraction data comprises a drilling track data access program and a Meiansen data analysis program of the Western's institute, a gas extraction data uploading protocol is agreed through communication, the data analysis program is researched and developed, a data file generated by the Meiansen data uploading program under a server appointed directory is automatically read every day, the data file is analyzed into structured data according to the protocol, and the structured data is stored in an extraction judgment database.
The monitored drilling track data has the function of exporting Excel track data files, so that the Excel track data exported by the drilling track measuring instrument is converted into a coordinate format which can be identified by a blue light GIS platform in a coordinate conversion mode, and the drilling track is visually displayed on the GIS platform.
By adopting the technical scheme, the system of the scheme is adopted to pre-judge the rock stratum and the quantity of the underground residual gas quantity, so that the functions of mine gas monitoring information display, gas extraction basic data management, extraction standard-reaching online process judgment, extraction pipeline visual display and the like are realized, real-time monitoring of all levels of gas extraction quantities of an extraction pipeline, a working face, an evaluation unit, a metering point and a drill hole is provided for a coal mine user, the occurrence of coal mine safety accidents is effectively prevented and controlled, the underground gas condition is known more accurately, and the normal operation of the mine safety production order and the life and property safety of people are guaranteed.
The invention has been described above with reference to the accompanying drawings, it is obvious that the invention is not limited to the specific implementation in the above-described manner, and it is within the scope of the invention to apply the inventive concept and solution to other applications without substantial modification.

Claims (1)

1. A processing method of a processing system for judging gas extraction in a mining area is characterized by comprising the following steps: the system comprises a database, a data processing unit, a control module, a PC (personal computer) end browsing module and a monitoring system module, wherein the data processing unit comprises a data access interface and a logic analysis and statistics module, the database is connected with the logic analysis and statistics module through the data access interface, the logic analysis module is connected with the PC end browsing module through the control module so as to receive processed data and display the processed data on the PC end browsing module, the database receives drilling track data led out by a drilling track measuring instrument and transmits the drilling track data to the data processing module, and the database is also provided with a signal input end connected with the monitoring system module; the data processing unit comprises a processing unit module, a coordinate conversion module, a blue light GIS platform and a receiving module, drilling track data in the database are transmitted to the processing unit module, the processing unit module is connected to a signal input end of the blue light GIS platform through the coordinate conversion module to transmit the processed drilling track data, and a signal output end of the blue light GIS platform is connected to the other signal input end of the processing unit module through the receiving module to output a mine image to the processing unit module; the data transmitted by the monitoring system module in the database comprise gas extraction data and analytic data, and the database transmits the gas extraction data and the analytic data to the data processing unit;
the processing method using the mining area gas extraction judgment processing system comprises the following steps:
s1, the system initially judges the type of the gas emission quantity, and firstly judges whether data need to be transmitted to a data processing unit;
s2, the system initially judges whether the gas emission quantity belongs to a mining layer or a tunneling layer, if the gas emission quantity belongs to the mining layer, data are output to a data processing module, the concentration and the residual gas pressure of the data are judged, if the gas emission quantity belongs to a rock stratum adjacent to the mining layer, the same steps are adopted for judging the concentration and the residual gas pressure, and the residual gas in the tunneling layer is judged to reach the standard under the conditions that the pressure is less than 0.74MPa and the residual gas content is less than 8 cubic meters per ton; judging that the residual gas in the mining layer or the adjacent layer reaches the standard under the conditions that the pressure is less than 0.74MPa and the content of the residual gas is less than 8 cubic meters per ton;
if the gas emission quantity belongs to a tunneling layer, judging whether the gas concentration in the wind speed and the return air flow reaches the standard or not;
and S3, recording the initially judged gas data serving as final data into a database.
CN202011609627.9A 2020-12-30 2020-12-30 Processing system and method for mining area gas extraction judgment Active CN112796710B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011609627.9A CN112796710B (en) 2020-12-30 2020-12-30 Processing system and method for mining area gas extraction judgment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011609627.9A CN112796710B (en) 2020-12-30 2020-12-30 Processing system and method for mining area gas extraction judgment

Publications (2)

Publication Number Publication Date
CN112796710A CN112796710A (en) 2021-05-14
CN112796710B true CN112796710B (en) 2023-04-07

Family

ID=75804579

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011609627.9A Active CN112796710B (en) 2020-12-30 2020-12-30 Processing system and method for mining area gas extraction judgment

Country Status (1)

Country Link
CN (1) CN112796710B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113153258B (en) * 2021-05-21 2022-09-23 上海亦又新能源科技有限公司 Digital monitoring management system and management method for gas extraction directional drilling machine
CN113513361B (en) * 2021-08-10 2022-04-29 北京大学 Method and system for regulating and controlling gas concentration of stope face of high-gas coal mine
CN114320440A (en) * 2021-11-29 2022-04-12 淮北矿业股份有限公司 Up-down combined extraction method for well

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB0324726D0 (en) * 2003-10-22 2003-11-26 Leica Geosystems Ag Method and apparatus for managing information exchanges between communicating entities, E.G. apparatus on a worksite
CN106777528A (en) * 2016-11-25 2017-05-31 山东蓝光软件有限公司 The holographic forecast method of mine air-required volume

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104612635B (en) * 2014-12-10 2017-12-15 中煤科工集团重庆研究院有限公司 Coal seam group gas combined extraction standard reaching pre-evaluation method
CN104881500A (en) * 2015-06-19 2015-09-02 贵州省矿山安全科学研究院 Local area network system for dynamic prediction of coal mine gas geology and gas emission
CN108119142B (en) * 2017-11-09 2019-05-17 中国矿业大学 - three-two subregion water-protection coal-mining methods of band of five figures
CN110017169A (en) * 2019-03-25 2019-07-16 淮北矿业股份有限公司 A kind of monitoring system of ore faces roof pressure and gas drainage

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB0324726D0 (en) * 2003-10-22 2003-11-26 Leica Geosystems Ag Method and apparatus for managing information exchanges between communicating entities, E.G. apparatus on a worksite
CN106777528A (en) * 2016-11-25 2017-05-31 山东蓝光软件有限公司 The holographic forecast method of mine air-required volume

Also Published As

Publication number Publication date
CN112796710A (en) 2021-05-14

Similar Documents

Publication Publication Date Title
CN112796710B (en) Processing system and method for mining area gas extraction judgment
US20230115586A1 (en) Construction method of digital twin for structure performance of intelligent excavator
CN103527194B (en) A kind of electrical haulage shearer health degree is monitored and intelligent evaluation system and method thereof in real time
CN107909300A (en) Intelligent plant management platform and method
CN105761010A (en) Method and system for real-time monitoring of group enterprise audit based on real-time data acquisition
CN109507924B (en) Remote monitoring system for oil field operation equipment
CN201606065U (en) Oil well working condition analyser
CN111681401A (en) BIM information flow-based high-formwork lora transmission safety monitoring device and method
CN109491341B (en) Monitoring and data analysis system for oil field operation equipment
CN104167084A (en) Engineering-risk wireless-sensing early-warning visualization system and method
CN103334794A (en) Hydrologic monitoring system for coal mine
CN105155599A (en) Remote information monitoring and analyzing device and method for cement soil mixing pile
CN111182052A (en) Mine engineering visual linkage data early warning system based on BIM and Internet of things
CN203430499U (en) Well fracturing parameter intelligent monitoring system
CN104948173A (en) Fracturing field data long-distance real-time monitoring method and system
CN110008274B (en) BIM-based visual automatic monitoring system for internal force of pile foundation
CN110689450A (en) Wisdom water utilities operation system based on three-dimensional visual mode
CN112798316A (en) Comprehensive performance test system of development machine
CN202352045U (en) Portable real-time image monitoring data acquirer for high-pressure water injection
CN113137221B (en) Three-level gas leakage evaluation system and evaluation method for gas extraction full system
CN106677762A (en) Wireless integral indicator
CN101847312A (en) System for implementing data acquisition and early warning in slip forming
CN205680257U (en) Tamping car operation early warning system
CN102748006A (en) Remote monitoring system of downhole operation
CN105116851A (en) Hidden danger investigation CPS (hdiCPS)

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant