- CN112743789A CN112743789A CN202110095577.5A CN202110095577A CN112743789A CN 112743789 A CN112743789 A CN 112743789A CN 202110095577 A CN202110095577 A CN 202110095577A CN 112743789 A CN112743789 A CN 112743789A
- Authority
- CN
- China
- Prior art keywords
- bathroom
- control unit
- central control
- bathroom hanging
- toilet
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B29—WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
- B29C—SHAPING OR JOINING OF PLASTICS; SHAPING OF MATERIAL IN A PLASTIC STATE, NOT OTHERWISE PROVIDED FOR; AFTER-TREATMENT OF THE SHAPED PRODUCTS, e.g. REPAIRING
- B29C45/00—Injection moulding, i.e. forcing the required volume of moulding material through a nozzle into a closed mould; Apparatus therefor
- B29C45/17—Component parts, details or accessories; Auxiliary operations
- B29C45/76—Measuring, controlling or regulating
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B29—WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
- B29C—SHAPING OR JOINING OF PLASTICS; SHAPING OF MATERIAL IN A PLASTIC STATE, NOT OTHERWISE PROVIDED FOR; AFTER-TREATMENT OF THE SHAPED PRODUCTS, e.g. REPAIRING
- B29C45/00—Injection moulding, i.e. forcing the required volume of moulding material through a nozzle into a closed mould; Apparatus therefor
- B29C45/17—Component parts, details or accessories; Auxiliary operations
- B29C45/72—Heating or cooling
- B29C45/73—Heating or cooling of the mould
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B29—WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
- B29C—SHAPING OR JOINING OF PLASTICS; SHAPING OF MATERIAL IN A PLASTIC STATE, NOT OTHERWISE PROVIDED FOR; AFTER-TREATMENT OF THE SHAPED PRODUCTS, e.g. REPAIRING
- B29C2945/00—Indexing scheme relating to injection moulding, i.e. forcing the required volume of moulding material through a nozzle into a closed mould
- B29C2945/76—Measuring, controlling or regulating
- B29C2945/76494—Controlled parameter
- B29C2945/76531—Temperature
Landscapes
- Engineering & Computer Science (AREA)
- Manufacturing & Machinery (AREA)
- Mechanical Engineering (AREA)
- Moulds For Moulding Plastics Or The Like (AREA)
Abstract
The invention relates to a self-learning production system for bathroom hangers, which comprises: the cooling device comprises a machine body, a fixed die frame, a screw rod frame, a movable die power frame, a screw rod, a movable die frame, a storage bin, a cooling device and a central control unit, wherein the central control unit is respectively connected with other parts; the surface of the central control unit is provided with a display screen and a keyboard for inputting the parameters of the mould and the working state of each part; and a PLC control panel is arranged in the central control unit and used for adjusting the working state of each part. When the bathroom hanging parts have defects, the central control unit adjusts the production system, continues to produce the bathroom hanging parts after the adjustment is finished, and detects and adjusts the bathroom hanging parts again until the bathroom hanging parts do not have the defects.
Description
Technical Field
The invention relates to the technical field of injection molding, in particular to a self-learning production system for a bathroom hanging part.
Background
The bathroom hanging parts are mainly used in bathrooms or bathrooms and generally comprise mounting seats and functional parts, and according to different functions, the bathroom hanging parts are generally towel racks, towel rings, cup racks, soap dish racks, hooks, paper towel racks and the like.
The bathroom hangers produced by the traditional production process are mostly metal hangers with surface coatings, wherein copper-chromium products, stainless steel chromium-plated products, aluminum alloy chromium-plated products and iron chromium-plated products are common metal types. The frame surface coating of the bathroom hanging parts is mostly treated by polishing copper except for a few of plating plastics, and more is treated by chrome plating. In the chromium plating product, the plating layer of the common product is 20 microns thick, the time is long, and the material inside is easy to oxidize and corrode.
With the progress of science and technology, in addition to the prevention of corrosion of metal bathroom accessories, more and more people choose plastic bathroom accessories to replace the metal accessories. In order to increase the processing speed of plastic hanging parts, bathroom hanging part manufacturers mostly adopt injection molding, however, bathroom hanging parts are mostly small plastic products and have different shapes, and when the plastic hanging parts are injected, quality defects such as cracks and bubbles often occur.
Disclosure of Invention
Therefore, the invention provides a self-learning production system of a bathroom hanging part, which is used for overcoming the problem of uneven quality of small and medium-sized plastic bathroom hanging parts in the prior art.
In order to achieve the above object, the present invention provides a self-learning production system for bathroom accessories, comprising:
a body;
the fixed die frame is fixed on the machine body and used for installing a fixed die in the bathroom hanger die, the fixed die frame is provided with a plastic channel and an exhaust channel, and the diameter of the exhaust channel is adjustable;
the screw rod frame is fixed on the machine body, a bearing is arranged in the screw rod frame, and flanges are arranged at two ends of the bearing;
the movable die power frame is fixed on the machine body, and a motor is arranged above the movable die power frame;
the screw rod is arranged on the machine body through the screw rod frame and the movable die power frame and is connected with the motor;
the movable die frame is arranged on the lead screw and used for installing a movable die in the bathroom hanger die;
the stock bin is arranged on the machine body and is connected with the fixed die frame; a bin switch is arranged at the lower end of the bin, and a heating device is arranged on the outer wall of the bin; the storage bin is used for containing heated liquid plastic;
the two sets of cooling devices are respectively arranged on the movable mould frame and the fixed mould frame and are used for accelerating the cooling of the pouring of the bathroom hanging parts;
the central control unit is arranged on the machine body and is respectively connected with the bin switch, the motor, the exhaust channel and the heating device; the surface of the central control unit is provided with a display screen and a keyboard for inputting the parameters of the mould and the working state of each part; and a PLC control panel is arranged in the central control unit and used for adjusting the working state of each part.
Further, a bathroom hanging piece mold matrix A0 and a bathroom hanging piece volume matrix B0 are arranged in the central control unit;
for the bathroom hanging piece mold matrix a0, a0(a1, a2, A3, a4), wherein a1 is a first preset bathroom hanging piece mold, a2 is a second preset bathroom hanging piece mold, A3 is a third preset bathroom hanging piece mold, and a4 is a fourth preset bathroom hanging piece mold;
for the bathroom hanger volume matrix B0, B0(B1, B2, B3, B4), wherein B1 is a first preset bathroom hanger volume, B2 is a second preset bathroom hanger volume, B3 is a third preset bathroom hanger volume, and B4 is a fourth preset bathroom hanger volume;
before adopting production system production bathroom hanging parts, select and wait to produce bathroom hanging parts mould A, well accuse unit compares A and bathroom hanging parts mould matrix A0 internal parameter:
when A is a first preset bathroom hanging piece mold A1, the central control unit selects B1 from a bathroom hanging piece volume matrix B0 as a bathroom hanging piece volume;
when A is a second preset bathroom hanging piece mold A2, the central control unit selects B2 from a bathroom hanging piece volume matrix B0 as a bathroom hanging piece volume;
when A is a third preset bathroom hanging piece mold A3, the central control unit selects B3 from a bathroom hanging piece volume matrix B0 as a bathroom hanging piece volume;
when a is the fourth preset bathroom hanging piece mold a4, the central control unit selects B4 from the bathroom hanging piece volume matrix B0 as the bathroom hanging piece volume.
Further, when the central control unit selects Bi as the volume of the bathroom accessory, i is 1,2,3,4, the central control unit calculates the preset opening time T1 of the bin switch, T1 is Bi/tb, and tb is a compensation parameter of the preset opening time of the bin switch by the volume of the bathroom accessory.
Further, when the production system is adopted for producing the bathroom accessories, a fixed die of the bathroom accessory die A to be produced is installed on the fixed die frame, and a movable die of the bathroom accessory die A to be produced is installed on the movable die frame; the central control unit controls the motor to rotate forwardly and start, and the motor drives the screw rod to start until the fixed die and the movable die are closed.
Further, an initial cooling time period T2 is also set in the central control unit;
when the fixed die and the movable die are closed, the central control unit controls the storage bin to be opened for a time period of T1, the central control unit controls the cooling device to be opened, when the time period of cooling is T2, the central control unit controls the motor to be reversely started, the motor drives the lead screw to be started until the fixed die and the movable die are separated, the bathroom hanging parts are taken out to be detected, and the production system performs self-adjustment according to the detection result.
Further, when the bathroom hanging parts are not formed, the central control unit judges that the cooling of the bathroom hanging parts is insufficient, the central control unit controls the cooling device to enhance the refrigerating capacity, and the cooling time length is adjusted to T2', T2 ═ T2 × (1-E) × T2, wherein E is the forming degree of the current product, and T2 is a compensation parameter of the forming degree of the bathroom hanging parts to the cooling time length.
Further, when bubbles and defects exist in the bathroom hanging parts, the central control unit judges that the injection amount of the plastic is insufficient, and adjusts the opening time of the bin switch to T1 ', and T1' is T1 Xf multiplied by T3, wherein f is the plastic defect amount, and T3 is a compensation parameter of the plastic defect amount to the opening time of the bin switch.
Further, when the bathroom hanging parts have cracks, the central control unit judges that the cooling force is too large, and the central control unit enables the refrigerating capacity of the cooling device to be half of the preset level.
Further, when the bathroom hanging parts do not have defects, the central control unit judges that the current settings of all the parts of the production system meet production requirements, and the central control unit does not adjust all the parts.
Further, when the bathroom hanging parts have defects, the central control unit adjusts the production system, continues to produce the bathroom hanging parts after adjustment is completed, and carries out detection and adjustment again until the bathroom hanging parts do not have defects.
Compared with the prior art, the bathroom hanging piece has the beneficial effects that the working state of each part is intelligently adjusted by arranging the central control unit, the defects in the production process are reduced, and the production quality of the bathroom hanging piece is improved.
Drawings
Fig. 1 is a schematic structural view of the self-learning production system for the bathroom hanging parts of the present invention.
Detailed Description
In order that the objects and advantages of the invention will be more clearly understood, the invention is further described below with reference to examples; it should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
Preferred embodiments of the present invention are described below with reference to the accompanying drawings. It should be understood by those skilled in the art that these embodiments are only for explaining the technical principle of the present invention, and do not limit the scope of the present invention.
It should be noted that in the description of the present invention, the terms of direction or positional relationship indicated by the terms "upper", "lower", "left", "right", "inner", "outer", etc. are based on the directions or positional relationships shown in the drawings, which are only for convenience of description, and do not indicate or imply that the device or element must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention.
Furthermore, it should be noted that, in the description of the present invention, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood by those skilled in the art according to specific situations.
Referring to fig. 1, which is a schematic structural diagram of a self-learning production system for a bathroom hanging part according to the present invention, the present invention provides a self-learning production system for a bathroom hanging part, comprising: organism 1, cover half frame 2, lead screw frame 3, movable mould power frame 4, lead screw 5, movable mould frame 6, feed bin 7, cooling device 8, well accuse unit 9, wherein:
the fixed die frame is fixed on the machine body and used for mounting a fixed die in the bathroom hanger die, a plastic channel and an exhaust channel are arranged on the fixed die frame, and the diameter of the exhaust channel is adjustable;
the screw rod frame is fixed on the machine body, a bearing is arranged in the screw rod frame, and flange plates are arranged at two ends of the bearing;
the movable die power frame is fixed on the machine body, and a motor is arranged above the movable die power frame;
the lead screw is arranged on the machine body through the lead screw frame and the movable die power frame and is connected with the motor;
the movable die frame is arranged on the lead screw and used for installing a movable die in the bathroom hanger die;
the stock bin is arranged on the machine body and is connected with the fixed die frame; a bin switch is arranged at the lower end of the bin, and a heating device is arranged on the outer wall of the bin; the storage bin is used for containing heated liquid plastic;
the cooling devices are arranged in two sets and are respectively arranged on the movable mould frame and the fixed mould frame so as to accelerate the cooling of the pouring of the bathroom hanging parts;
the central control unit is arranged on the machine body and is respectively connected with the bin switch, the motor, the exhaust channel and the heating device; the surface of the central control unit is provided with a display screen and a keyboard for inputting the parameters of the mould and the working state of each part; and a PLC control panel is arranged in the central control unit and used for adjusting the working state of each part.
Specifically, a bathroom hanging piece mold matrix A0 and a bathroom hanging piece volume matrix B0 are arranged in the central control unit;
for the bathroom hanging piece mold matrix a0, a0(a1, a2, A3, a4), wherein a1 is a first preset bathroom hanging piece mold, a2 is a second preset bathroom hanging piece mold, A3 is a third preset bathroom hanging piece mold, and a4 is a fourth preset bathroom hanging piece mold;
for the bathroom hanger volume matrix B0, B0(B1, B2, B3, B4), wherein B1 is a first preset bathroom hanger volume, B2 is a second preset bathroom hanger volume, B3 is a third preset bathroom hanger volume, and B4 is a fourth preset bathroom hanger volume;
before adopting production system production bathroom hanging parts, select and wait to produce bathroom hanging parts mould A, well accuse unit compares A and bathroom hanging parts mould matrix A0 internal parameter:
when A is a first preset bathroom hanging piece mold A1, the central control unit selects B1 from a bathroom hanging piece volume matrix B0 as a bathroom hanging piece volume;
when A is a second preset bathroom hanging piece mold A2, the central control unit selects B2 from a bathroom hanging piece volume matrix B0 as a bathroom hanging piece volume;
when A is a third preset bathroom hanging piece mold A3, the central control unit selects B3 from a bathroom hanging piece volume matrix B0 as a bathroom hanging piece volume;
when a is the fourth preset bathroom hanging piece mold a4, the central control unit selects B4 from the bathroom hanging piece volume matrix B0 as the bathroom hanging piece volume.
Specifically, when the central control unit selects Bi as the volume of the bathroom accessory, i is 1,2,3,4, the central control unit calculates the preset opening time T1 of the bin switch, T1 is Bi/tb, and tb is a compensation parameter of the preset opening time of the bin switch by the volume of the bathroom accessory.
Specifically, when the production system is adopted to produce the bathroom accessories, a fixed die of a bathroom accessory die A to be produced is installed on the fixed die frame, and a movable die of the bathroom accessory die A to be produced is installed on the movable die frame; the central control unit controls the motor to rotate forwardly and start, and the motor drives the screw rod to start until the fixed die and the movable die are closed.
Specifically, an initial cooling time period T2 is also set in the central control unit;
when the fixed die and the movable die are closed, the central control unit controls the storage bin to be opened for a time period of T1, the central control unit controls the cooling device to be opened, when the time period of cooling is T2, the central control unit controls the motor to be reversely started, the motor drives the lead screw to be started until the fixed die and the movable die are separated, the bathroom hanging parts are taken out to be detected, and the production system performs self-adjustment according to the detection result.
Specifically, when the bathroom hanging parts are not formed, the central control unit judges that the cooling of the bathroom hanging parts is insufficient, the central control unit controls the cooling device to enhance the refrigerating capacity, and adjusts the cooling time length to T2', T2 ═ T2 × (1-E) × T2, wherein E is the forming degree of the current product, and T2 is a compensation parameter of the forming degree of the bathroom hanging parts to the cooling time length.
Specifically, when bubbles and defects exist in the bathroom hanging parts, the central control unit judges that the injection amount of the plastic is insufficient, and adjusts the opening time of the bin switch to T1 ', and T1' is T1 × f × T3, wherein f is the plastic defect amount, and T3 is a compensation parameter of the plastic defect amount to the opening time of the bin switch.
Specifically, when the bathroom hanging parts have cracks, the central control unit judges that the cooling force is too large, and the central control unit enables the refrigerating capacity of the cooling device to be half of the preset level.
Specifically, when the bathroom hanging parts have no defects, the central control unit judges that the current settings of all the parts of the production system meet the production requirements, and the central control unit does not adjust all the parts.
Specifically, when the bathroom hanging parts have defects, the central control unit adjusts the production system, continues to produce the bathroom hanging parts after adjustment is completed, and carries out detection and adjustment again until the bathroom hanging parts do not have defects.
So far, the technical solutions of the present invention have been described in connection with the preferred embodiments shown in the drawings, but it is easily understood by those skilled in the art that the scope of the present invention is obviously not limited to these specific embodiments. Equivalent changes or substitutions of related technical features can be made by those skilled in the art without departing from the principle of the invention, and the technical scheme after the changes or substitutions can fall into the protection scope of the invention.
The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention; various modifications and alterations to this invention will become apparent to those skilled in the art. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims (10)
1. The utility model provides a bathroom hanging parts is from learning production system which characterized in that includes:
a body;
the fixed die frame is fixed on the machine body and used for installing a fixed die in the bathroom hanger die, the fixed die frame is provided with a plastic channel and an exhaust channel, and the diameter of the exhaust channel is adjustable;
the screw rod frame is fixed on the machine body, a bearing is arranged in the screw rod frame, and flanges are arranged at two ends of the bearing;
the movable die power frame is fixed on the machine body, and a motor is arranged above the movable die power frame;
the screw rod is arranged on the machine body through the screw rod frame and the movable die power frame and is connected with the motor;
the movable die frame is arranged on the lead screw and used for installing a movable die in the bathroom hanger die;
the stock bin is arranged on the machine body and is connected with the fixed die frame; a bin switch is arranged at the lower end of the bin, and a heating device is arranged on the outer wall of the bin; the storage bin is used for containing heated liquid plastic;
the two sets of cooling devices are respectively arranged on the movable mould frame and the fixed mould frame and are used for accelerating the cooling of the pouring of the bathroom hanging parts;
the central control unit is arranged on the machine body and is respectively connected with the bin switch, the motor, the exhaust channel and the heating device; the surface of the central control unit is provided with a display screen and a keyboard for inputting the parameters of the mould and the working state of each part; and a PLC control panel is arranged in the central control unit and used for adjusting the working state of each part.
2. The self-learning production system of toilet and bathroom hangers of claim 1, wherein a toilet and bathroom hanger mold matrix A0 and a toilet and bathroom hanger volume matrix B0 are arranged in the central control unit;
for the bathroom hanging piece mold matrix a0, a0(a1, a2, A3, a4), wherein a1 is a first preset bathroom hanging piece mold, a2 is a second preset bathroom hanging piece mold, A3 is a third preset bathroom hanging piece mold, and a4 is a fourth preset bathroom hanging piece mold;
for the bathroom hanger volume matrix B0, B0(B1, B2, B3, B4), wherein B1 is a first preset bathroom hanger volume, B2 is a second preset bathroom hanger volume, B3 is a third preset bathroom hanger volume, and B4 is a fourth preset bathroom hanger volume;
before adopting production system production bathroom hanging parts, select and wait to produce bathroom hanging parts mould A, well accuse unit compares A and bathroom hanging parts mould matrix A0 internal parameter:
when A is a first preset bathroom hanging piece mold A1, the central control unit selects B1 from a bathroom hanging piece volume matrix B0 as a bathroom hanging piece volume;
when A is a second preset bathroom hanging piece mold A2, the central control unit selects B2 from a bathroom hanging piece volume matrix B0 as a bathroom hanging piece volume;
when A is a third preset bathroom hanging piece mold A3, the central control unit selects B3 from a bathroom hanging piece volume matrix B0 as a bathroom hanging piece volume;
when a is the fourth preset bathroom hanging piece mold a4, the central control unit selects B4 from the bathroom hanging piece volume matrix B0 as the bathroom hanging piece volume.
3. The toilet and bathroom hanger self-learning production system of claim 2, wherein when Bi is selected as the toilet and bathroom hanger volume by the central control unit, i is 1,2,3,4, the central control unit calculates the preset on-time T1 of the bin switch, T1 is Bi/tb, wherein tb is a compensation parameter of the toilet and bathroom hanger volume to the preset on-time of the bin switch.
4. The self-learning production system for the bathroom hanging parts as claimed in claim 3, wherein when the production system is adopted to produce the bathroom hanging parts, a fixed mold of the bathroom hanging part mold A to be produced is installed on the fixed mold frame, and a movable mold of the bathroom hanging part mold A to be produced is installed on the movable mold frame; the central control unit controls the motor to rotate forwardly and start, and the motor drives the screw rod to start until the fixed die and the movable die are closed.
5. The self-learning production system for toilet and bathroom hangers of claim 4, wherein an initial cooling time period T2 is further set in the central control unit;
when the fixed die and the movable die are closed, the central control unit controls the storage bin to be opened for a time period of T1, the central control unit controls the cooling device to be opened, when the time period of cooling is T2, the central control unit controls the motor to be reversely started, the motor drives the lead screw to be started until the fixed die and the movable die are separated, the bathroom hanging parts are taken out to be detected, and the production system performs self-adjustment according to the detection result.
6. The self-learning production system of the toilet and bathroom hanger of claim 5, wherein when the toilet and bathroom hanger is not formed, the central control unit determines that the cooling of the toilet and bathroom hanger is insufficient, the central control unit controls the cooling device to enhance the cooling capability, and adjusts the cooling time to T2', T2 ═ T2 × (1-E) × T2, wherein E is the forming degree of the current product, and T2 is the forming degree of the toilet and bathroom hanger versus the cooling time compensation parameter.
7. The self-learning production system of the toilet and bathroom hanging parts as claimed in claim 6, wherein when there is air bubble and defect in the toilet and bathroom hanging parts, the central control unit determines that the injection amount of plastic is insufficient, and the central control unit adjusts the opening time of the bunker switch to T1 ', T1' T1 xf T3, wherein f is the plastic defect amount, and T3 is the compensation parameter of the plastic defect amount to the opening time of the bunker switch.
8. The self-learning production system of the toilet and bathroom hanging part of claim 7, wherein when the toilet and bathroom hanging part has cracks, the central control unit determines that the cooling force is too large, and the central control unit reduces the cooling capacity of the cooling device to half of a preset level.
9. The bathroom hanging part self-learning production system according to claim 8, wherein when the bathroom hanging part is not defective, the central control unit judges that the current settings of the components of the production system meet production requirements, and the central control unit does not adjust the components.
10. The self-learning production system of the toilet and bathroom hanging parts as claimed in claim 9, wherein when the toilet and bathroom hanging parts are defective, the central control unit adjusts the production system, continues to produce the toilet and bathroom hanging parts after the adjustment is completed, and performs the detection and adjustment again until the toilet and bathroom hanging parts are not defective.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110095577.5A CN112743789A (en) | 2021-01-25 | 2021-01-25 | Bathroom hanging parts self-learning production system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110095577.5A CN112743789A (en) | 2021-01-25 | 2021-01-25 | Bathroom hanging parts self-learning production system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN112743789A true CN112743789A (en) | 2021-05-04 |
Family
ID=75653051
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110095577.5A Withdrawn CN112743789A (en) | 2021-01-25 | 2021-01-25 | Bathroom hanging parts self-learning production system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112743789A (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101544043A (en) * | 2008-03-26 | 2009-09-30 | 宝理塑料株式会社 | Injection molding process analysis method |
CN101659108A (en) * | 2008-08-29 | 2010-03-03 | 住友重机械工业株式会社 | Forming condition setting device, method and picture |
CN104441526A (en) * | 2014-09-24 | 2015-03-25 | 上海智觉光电科技有限公司 | Online mold monitoring and protecting system and method based on contour matching |
CN209830230U (en) * | 2019-04-27 | 2019-12-24 | 漳州阿尔巴金属制品有限公司 | A mould for bathroom hanging parts production |
CN111873303A (en) * | 2020-08-12 | 2020-11-03 | 衢州丰帆科技有限公司 | Injection mold and injection molding method thereof |
CN112024332A (en) * | 2020-09-15 | 2020-12-04 | 东莞市瑞年塑胶科技有限公司 | Mirror surface magic color film preparation process based on raw material adjustment |
CN212331751U (en) * | 2019-09-02 | 2021-01-12 | 深圳市圣丰模具塑胶有限公司 | Injection molding machine mould based on machine vision |
-
2021
- 2021-01-25 CN CN202110095577.5A patent/CN112743789A/en not_active Withdrawn
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101544043A (en) * | 2008-03-26 | 2009-09-30 | 宝理塑料株式会社 | Injection molding process analysis method |
CN101659108A (en) * | 2008-08-29 | 2010-03-03 | 住友重机械工业株式会社 | Forming condition setting device, method and picture |
CN104441526A (en) * | 2014-09-24 | 2015-03-25 | 上海智觉光电科技有限公司 | Online mold monitoring and protecting system and method based on contour matching |
CN209830230U (en) * | 2019-04-27 | 2019-12-24 | 漳州阿尔巴金属制品有限公司 | A mould for bathroom hanging parts production |
CN212331751U (en) * | 2019-09-02 | 2021-01-12 | 深圳市圣丰模具塑胶有限公司 | Injection molding machine mould based on machine vision |
CN111873303A (en) * | 2020-08-12 | 2020-11-03 | 衢州丰帆科技有限公司 | Injection mold and injection molding method thereof |
CN112024332A (en) * | 2020-09-15 | 2020-12-04 | 东莞市瑞年塑胶科技有限公司 | Mirror surface magic color film preparation process based on raw material adjustment |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205185277U (en) | PVB manages extruder | |
NZ199630A (en) | Controlling molten metal level in a plurality of inductive casting units | |
CN205310640U (en) | Casting die utensil water -cooled cooling device | |
CN112743789A (en) | Bathroom hanging parts self-learning production system | |
CN209338685U (en) | A kind of controlling type suspension electroplating device | |
JPH10100216A (en) | Method for obtaining injection molded product of thermoplastic resin having high quality appearance | |
CN213137622U (en) | Shaping die for splash-proof mask | |
CN217622045U (en) | Accurate controlling means of mould temperature | |
CN207431180U (en) | A kind of scalable mould rack of molding machine for evaporative mold | |
CN108115892A (en) | A kind of list pressure head thin-walled plastic mold | |
CN213856509U (en) | Plastic mold dysmorphism bending device | |
CN216999991U (en) | Multifunctional counter basin | |
CN210011229U (en) | Height-adjustable die | |
CN211031108U (en) | Heating device of bakelite injection mold | |
CN220638709U (en) | Novel injection polyurethane foaming mould | |
CN215396446U (en) | Novel foam box body forming device | |
CN108943594A (en) | A kind of controllable injection mold of cavity temperature | |
CN214354022U (en) | Extrusion device for self-adhesive sheets | |
CN214239127U (en) | A device of moulding plastics for ppr water pipe production | |
CN218535577U (en) | Plastic extrusion die facilitating discharging | |
CN213382659U (en) | PVC pipe injection molding equipment is prevented blockking up in feeding | |
CN218227699U (en) | Children's drinking cup mould for injection molding | |
CN219171742U (en) | Heating die for glass fiber reinforced plastic fiber profile production | |
CN215242385U (en) | Water jacket structure of foaming mold | |
CN212097220U (en) | Efficient macromolecular material's device of moulding plastics |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WW01 | Invention patent application withdrawn after publication | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20210504 |