CN112711500B - Substation equipment defect management and control method based on mobile phone APP - Google Patents

Substation equipment defect management and control method based on mobile phone APP Download PDF

Info

Publication number
CN112711500B
CN112711500B CN202110157290.0A CN202110157290A CN112711500B CN 112711500 B CN112711500 B CN 112711500B CN 202110157290 A CN202110157290 A CN 202110157290A CN 112711500 B CN112711500 B CN 112711500B
Authority
CN
China
Prior art keywords
defect
substation equipment
mobile phone
storage units
phone app
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110157290.0A
Other languages
Chinese (zh)
Other versions
CN112711500A (en
Inventor
杨海威
吴凯
赵崇娟
李凡
詹锐烽
王瑶
归宇
戴则维
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUZHOU ELECTRIC POWER DESIGN INSTITUTE CO LTD
Huzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
HUZHOU ELECTRIC POWER DESIGN INSTITUTE CO LTD
Huzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUZHOU ELECTRIC POWER DESIGN INSTITUTE CO LTD, Huzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical HUZHOU ELECTRIC POWER DESIGN INSTITUTE CO LTD
Priority to CN202110157290.0A priority Critical patent/CN112711500B/en
Publication of CN112711500A publication Critical patent/CN112711500A/en
Application granted granted Critical
Publication of CN112711500B publication Critical patent/CN112711500B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F11/00Error detection; Error correction; Monitoring
    • G06F11/07Responding to the occurrence of a fault, e.g. fault tolerance
    • G06F11/14Error detection or correction of the data by redundancy in operation
    • G06F11/1402Saving, restoring, recovering or retrying
    • G06F11/1446Point-in-time backing up or restoration of persistent data
    • G06F11/1458Management of the backup or restore process
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/20Administration of product repair or maintenance
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00006Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment
    • H02J13/00022Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment using wireless data transmission
    • H02J13/00024Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment using wireless data transmission by means of mobile telephony
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B90/00Enabling technologies or technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02B90/20Smart grids as enabling technology in buildings sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S40/00Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them
    • Y04S40/12Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment
    • Y04S40/126Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment using wireless data transmission

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Physics & Mathematics (AREA)
  • Economics (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Health & Medical Sciences (AREA)
  • Quality & Reliability (AREA)
  • General Business, Economics & Management (AREA)
  • Strategic Management (AREA)
  • Operations Research (AREA)
  • General Engineering & Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Power Engineering (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The invention relates to the technical field of computers, in particular to a defect management and control method for substation equipment based on mobile phone APP, which comprises the following steps: a) The on-site inspection personnel conduct daily inspection on the power equipment; b) Logging in a mobile phone APP by on-site inspection personnel, and uploading images and/or voice and/or video of defects of substation equipment; c) Corresponding staff in the work area preliminarily reviews the defects and further reports the defects to the company; d) The company is full-time to audit the defect and make a defect elimination plan, and the defect elimination plan is sent to a defect elimination responsible person; e) The defect eliminating responsible person is in charge of preparing defect eliminating tools and spare parts; f) The defect eliminating responsible person organizes the defect eliminating shortage of staff person to eliminate the defect on site and uploads the image and/or video of the power equipment after the defect elimination; g) The work ticket licensor carries out on-site acceptance; h) And archiving and storing the defect eliminating flow data of the transformer substation equipment. The invention has the following substantial effects: the defect eliminating efficiency of the transformer substation equipment is improved.

Description

Substation equipment defect management and control method based on mobile phone APP
Technical Field
The invention relates to the technical field of computers, in particular to a defect management and control method for substation equipment based on mobile phone APP.
Background
Defect management is an important component of operation and maintenance management of substation equipment, and is also a powerful guarantee of reliable operation of the substation equipment. The company sets strict and detailed defect grading standards and defect eliminating requirements according to the severity of defects. Because of being limited by network security, corporate defect management flows circulate in the PMS system of the intranet. Defect management is taken as a module in a PMS system and is limited by factors such as response speed of a server, and the like, and the full flow of filling, auditing, eliminating defects and archiving of defects is mainly adopted at the present stage in a word description mode. The following problems are found in the use of a defect module, namely, the text description can not fully reflect all the conditions of defects, and a certain proportion of false filling conditions exist; secondly, due to various fault devices, the purchasing of spare parts is not influenced by the real image data, and the situation that the purchased spare parts cannot be used often occurs; thirdly, the intranet system has the conditions of partial personnel business trip and the like in the flow, so that the intranet system cannot flow in time, and the defect elimination efficiency is affected; fourthly, the application proficiency of operation, maintenance and repair staff on the computer is different, and part of old ideas are not proficient on the PMS system defect flow module, so that defect filling is affected.
For example, in chinese patent CN111008774a, on day 2020, 4 and 14, a relay protection mobile operation management and control system, where the master station end and the intelligent mobile end implement information intercommunication with each other through a power wireless virtual power network; the master station side adopts a Web access mode to access service data, and the front end adopts intelligent mobile terminal equipment to acquire the service data; the transmission channel of the service data acquires the power wireless virtual private network system to realize the data intercommunication between the master station end and the intelligent mobile end. The intelligent operation and maintenance management platform is used as a core, the mobile terminal is used as a carrier, the relay protection real-time monitoring data and the whole process service data are intelligently analyzed, and the real-time and online monitoring, defect fault alarming and the whole process control of the core operation and maintenance service of the relay protection equipment are realized. But it can only collect and manage business data and cannot manage the deletion process.
Disclosure of Invention
The invention aims to solve the technical problems that: the technical problem of low efficiency of defect elimination and control at present. The defect management and control method for the substation equipment based on the mobile phone APP can realize overall process management and control and reminding, and improves the defect elimination efficiency of the substation equipment.
In order to solve the technical problems, the invention adopts the following technical scheme: a defect management and control method for substation equipment based on mobile phone APP comprises the following steps: a) The on-site inspection personnel performs daily inspection on the power equipment, if the defect of the power equipment is found, the step B) is carried out, otherwise, the step is repeated according to an inspection plan; b) Logging in a mobile phone APP by a field inspection person, uploading images and/or voice and/or video of defects of substation equipment, filling in defect information, and reporting the defects to a server through the mobile phone APP; c) Corresponding staff in the work area preliminarily reviews the defects and further reports the defects to the company; d) The company is full-time to audit the defect and make a defect elimination plan, and the defect elimination plan is sent to a defect elimination responsible person; e) The defect elimination responsible person prepares defect elimination tools and spare parts according to images and/or voices and/or videos of defects of substation equipment uploaded by on-site inspection personnel and filled defect information; f) The defect eliminating responsible person organizes the defect eliminating shortage of staff person to eliminate the defect on site and uploads the image and/or video of the power equipment after the defect elimination; g) The work ticket licensor carries out on-site acceptance, and uploads the image and/or video of the electric power equipment after the acceptance; h) And archiving and storing the defect eliminating flow data of the transformer substation equipment. By controlling each flow, the defect eliminating flow of the transformer substation equipment is standardized, the work of personnel in each link is facilitated, and the defect eliminating efficiency of the transformer substation equipment is improved.
Preferably, in the step B), after the mobile phone APP reports the defect to the server, the server sends the defect information to the mobile phone APP of the professional staff in the corresponding work area, and sends a prompt; in the step C), after the staff in the work area reports the defect to the company for full time, the server sends the defect information to the company for full time and sends a prompt; in the step D), when the server sends the defect elimination plan to the mobile phone APP of the defect elimination responsible person, the mobile phone APP sends a prompt. The working efficiency of related personnel is further improved through the preset template and prompt.
Preferably, a server stores prompt information of a plurality of preset defects of substation equipment, and the prompt information comprises: one or more of field defect review guidelines, typical defect image location and angle, typical defect video, and pre-set defect information filling templates. And provides reference for the field inspection personnel to comprehensively detect information.
Preferably, in step D), the mobile phone APP dedicated to the company displays a preset defect elimination plan and a preset list of spare parts for common use according to the defect types checked by the dedicated staff in the corresponding work area in step C).
Preferably, in step H), when the defect eliminating flow data of the transformer substation equipment is archived and stored, a unique identification code is encoded for the defect eliminating flow data, a hash value of the defect eliminating flow data is extracted, the identification code and the hash value of the defect eliminating flow data are associated and then synchronized to all mobile phone APP for storage, and the mobile phone APP performs read-only protection on the received identification code and hash value. The received identification code and hash value are read-only protected through the mobile phone APP, so that the mobile phone APP can find out in time when the archived defect-eliminating flow data is tampered, and the authenticity of the archived data is ensured.
Preferably, the server is further connected with an array storage device, the array storage device comprises a read-write bus and a plurality of storage units, the storage units comprise a timer, an electronic switch, a data read-write circuit and a storage medium, the timer is connected with a control end of the electronic switch, the data read-write circuit is connected with the read-write bus through the electronic switch, the data read-write circuit is connected with the storage medium, the timer outputs high and low levels in turn according to a period Ti, i is [1, n ], n is the number of the storage units, ti of the timers of the n storage units are unequal to each other, and in the step H), the method for archiving and storing the defect elimination flow data of the transformer station device by the server comprises the following steps: h1 The server inquires the number of the memory units which can be communicated through a read-write bus and marks m; h2 The method comprises the steps that) the server splits defect elimination flow data of the transformer substation equipment into k data segments, k is an integer, and after the data segments are associated with time stamps and identification codes of the elimination flow data, the data segments are sequentially distributed to m storage units capable of being communicated for storage, and the server does not record information of the m storage units capable of being communicated; h3 When the defect eliminating flow data of the transformer substation equipment is required to be verified or restored, all storage units in the array storage equipment are removed, levels which enable the electronic switches to be conducted are additionally added, all the storage units are communicated with the server, the server inquires data segments which are stored in all the storage units and are associated with identification codes of the defect eliminating flow data of the transformer substation equipment to be verified or restored, the data segments are spliced according to time stamps, the defect eliminating flow data of the transformer substation equipment can be restored, the restored defect eliminating flow data of the transformer substation equipment is used for being compared with the defect eliminating flow data of the transformer substation equipment which is directly stored by the server, and whether the defect eliminating flow data of the transformer substation equipment which is directly stored by the server is tampered or not is verified. When the defect eliminating flow data of the transformer substation equipment is tampered or deleted, the data can be retrieved through the array storage equipment. The electronic switches of the storage units in the array storage device have different specific conduction periods, so that the storage units in the conduction state are uncertain in the same period, the same storage units are difficult to be in the conduction available state again in the right time, a password in a substantial sense is formed, and the defect eliminating flow data of the substation equipment can be modified without leaving traces only when the same password is generated. Therefore, the defect eliminating flow data of the substation equipment which is archived to the array storage equipment is almost impossible to change without leaving trace, so that the tampering of the defect eliminating flow data of the substation equipment is almost impossible, and the safety of the defect eliminating flow data of the substation equipment is ensured. The method for archiving the defect eliminating flow data of the transformer substation equipment for multiple times can form backup of the defect eliminating flow data of the transformer substation equipment.
In order to ensure that when the server distributes data segments to m storage units, an electronic switch of the storage unit is kept on, whether the storage unit can still be communicated is queried before the server distributes the data segments to the storage units each time, whether the storage units can be communicated is queried again after the data segments are distributed, if the storage units cannot be communicated is queried, the data segments originally distributed to the storage units are distributed to other storage units which can be communicated in m storage units communicated in the step H1) at will, and if the m storage units communicated in the step H1) cannot be communicated any more before the distribution of the fault elimination flow data of the transformer substation equipment is completed, the data are executed again from the step H1), and the archiving and the preservation of the fault elimination flow data of the transformer substation equipment are carried out again.
The invention has the following substantial effects: the defect eliminating flow of the transformer substation equipment is standardized, the defect false filling probability is reduced, the purchasing accuracy of spare parts is improved, and the defect eliminating efficiency of the transformer substation equipment is improved; the defect elimination management and control work is carried out by adopting the mobile phone terminal, so that the full-flow mobile office of defect elimination management and control is realized, and the circulation efficiency of defect management is improved.
Drawings
Fig. 1 is a flow chart of a defect management and control method of transformer substation equipment according to an embodiment.
Detailed Description
The following description of the embodiments of the present invention will be made with reference to the accompanying drawings.
Embodiment one:
a defect management and control method for substation equipment based on mobile phone APP is shown in fig. 1, and comprises the following steps:
A) And (3) carrying out daily inspection on the power equipment by the on-site inspection personnel, if the defect of the power equipment is found, entering the step B), otherwise, repeating the step according to an inspection plan. The server stores prompt information of a plurality of preset defects of substation equipment, and the prompt information comprises: one or more of field defect review guidelines, typical defect image location and angle, typical defect video, and pre-set defect information filling templates. And provides reference for the field inspection personnel to comprehensively detect information. After logging in the mobile phone APP, the on-site patrol personnel can check the prompt information of the defects of the preset substation equipment.
B) The on-site inspection personnel logs in the mobile phone APP, uploads images and/or voice and/or video of the defects of the substation equipment, fills in defect information, and reports the defects to the server through the mobile phone APP.
C) Corresponding staff in the work area preliminarily reviews the defects and further reports the defects to the company.
D) The company is full-time to audit the defect and make a defect elimination plan, and the defect elimination plan is sent to a defect elimination responsible person. And C), displaying a preset defect elimination plan and a preset common spare part list according to the defect types checked by the professional staff in the work area in the step C) by the mobile phone APP of the company professional.
E) The defect eliminating responsible person prepares defect eliminating tools and spare parts according to images and/or voices and/or videos of defects of substation equipment uploaded by on-site inspection personnel and filled defect information.
F) The defect eliminating responsible person organizes the defect eliminating shortage of staff person to eliminate the defect on site and uploads the image and/or video of the power equipment after the defect elimination.
G) And the work ticket licensor carries out on-site acceptance, and uploads the image and/or video of the accepted power equipment.
H) And archiving and storing the defect eliminating flow data of the transformer substation equipment. By controlling each flow, the defect eliminating flow of the transformer substation equipment is standardized, the work of personnel in each link is facilitated, and the defect eliminating efficiency of the transformer substation equipment is improved. When the defect eliminating flow data of the transformer substation equipment is archived and stored, a unique identification code is encoded for the defect eliminating flow data, the hash value of the defect eliminating flow data is extracted, the identification code of the defect eliminating flow data is associated with the hash value, the defect eliminating flow data is synchronized to all mobile phone APP for storage, and the mobile phone APP performs read-only protection on the received identification code and the hash value. The received identification code and hash value are read-only protected through the mobile phone APP, so that the mobile phone APP can find out in time when the archived defect-eliminating flow data is tampered, and the authenticity of the archived data is ensured.
In the step B), after the mobile phone APP reports the defects to the server, the server sends the defect information to the mobile phone APP of the professional staff in the corresponding work area and sends out a prompt; in the step C), after the staff in the work area reports the defect to the company for full time, the server sends the defect information to the company for full time and sends a prompt; in the step D), when the server sends the defect elimination plan to the mobile phone APP of the defect elimination responsible person, the mobile phone APP sends a prompt. The working efficiency of related personnel is further improved through the preset template and prompt.
The essential effects of this embodiment are: the mobile phone end is adopted to perform defect elimination management and control, so that the whole-flow mobile office of defect elimination and management and control is realized, the probability of defect misfilling is reduced, the purchasing accuracy of spare parts is improved, and the defect elimination efficiency of substation equipment is improved.
Embodiment two:
A defect management and control method for substation equipment based on a mobile phone APP is provided, and the implementation method of a server is further improved on the basis of the first embodiment. In this embodiment, the server is further connected to an array storage device, where the array storage device includes a read-write bus and a plurality of storage units, the storage units include a timer, an electronic switch, a data read-write circuit and a storage medium, the timer is connected to a control end of the electronic switch, the data read-write circuit is connected to the read-write bus through the electronic switch, the data read-write circuit is connected to the storage medium, the timer outputs high and low levels in turn according to a period Ti, i e [1, n ], n is the number of storage units, and Ti of the timers of the n storage units are unequal to each other, and in step H), the method for archiving and storing the fault elimination flow data of the transformer substation equipment by the server includes: h1 The server inquires the number of the memory units which can be communicated through a read-write bus and marks m; h2 The method comprises the steps that) the server splits defect elimination flow data of the transformer substation equipment into k data segments, k is an integer, and after the data segments are associated with time stamps and identification codes of the elimination flow data, the data segments are sequentially distributed to m storage units capable of being communicated for storage, and the server does not record information of the m storage units capable of being communicated; h3 When the defect eliminating flow data of the transformer substation equipment is required to be verified or restored, all storage units in the array storage equipment are removed, levels which enable the electronic switches to be conducted are additionally added, all the storage units are communicated with the server, the server inquires data segments which are stored in all the storage units and are associated with identification codes of the defect eliminating flow data of the transformer substation equipment to be verified or restored, the data segments are spliced according to time stamps, the defect eliminating flow data of the transformer substation equipment can be restored, the restored defect eliminating flow data of the transformer substation equipment is used for being compared with the defect eliminating flow data of the transformer substation equipment which is directly stored by the server, and whether the defect eliminating flow data of the transformer substation equipment which is directly stored by the server is tampered or not is verified. When the defect eliminating flow data of the transformer substation equipment is tampered or deleted, the data can be retrieved through the array storage equipment. The electronic switches of the storage units in the array storage device have different specific conduction periods, so that the storage units in the conduction state are uncertain in the same period, the same storage units are difficult to be in the conduction available state again in the right time, a password in a substantial sense is formed, and the defect eliminating flow data of the substation equipment can be modified without leaving traces only when the same password is generated. Therefore, the defect eliminating flow data of the substation equipment which is archived to the array storage equipment is almost impossible to change without leaving trace, so that the tampering of the defect eliminating flow data of the substation equipment is almost impossible, and the safety of the defect eliminating flow data of the substation equipment is ensured. The method for archiving the defect eliminating flow data of the transformer substation equipment for multiple times can form backup of the defect eliminating flow data of the transformer substation equipment.
In order to ensure that when the server distributes data segments to m storage units, an electronic switch of the storage unit is kept on, before the server distributes the data segments to the storage units, whether the storage units still can be communicated is queried, after the data segments are distributed, whether the storage units can be communicated is queried again, if the storage units which cannot be communicated are queried, the data segments of the storage units which are distributed originally are distributed to other storage units which can be communicated in m storage units communicated in the step H1) are distributed randomly, and if the m storage units communicated in the step H1) cannot be communicated any more before the distribution of the defect eliminating flow data of the transformer substation equipment is completed, the data are executed again from the step H1), and archiving and saving of the defect eliminating flow data of the transformer substation equipment are carried out again.
The above embodiment is only a preferred embodiment of the present invention, and is not limited in any way, and other variations and modifications may be made without departing from the technical aspects set forth in the claims.

Claims (5)

1. A defect management and control method for transformer substation equipment based on mobile phone APP is characterized in that,
The method comprises the following steps:
A) The on-site inspection personnel performs daily inspection on the power equipment, if the defect of the power equipment is found, the step B) is carried out, otherwise, the step is repeated according to an inspection plan;
B) Logging in a mobile phone APP by a field inspection person, uploading images and/or voice and/or video of defects of substation equipment, filling in defect information, and reporting the defects to a server through the mobile phone APP;
the server is also connected with an array storage device, and the array storage device comprises a plurality of storage units, wherein the storage units comprise electronic switches with different conduction periods;
c) Corresponding staff in the work area preliminarily reviews the defects and further reports the defects to the company;
d) The company is full-time to audit the defect and make a defect elimination plan, and the defect elimination plan is sent to a defect elimination responsible person;
E) The defect elimination responsible person prepares defect elimination tools and spare parts according to images and/or voices and/or videos of defects of substation equipment uploaded by on-site inspection personnel and filled defect information;
f) The defect eliminating responsible person organizes the defect eliminating shortage of staff person to eliminate the defect on site and uploads the image and/or video of the power equipment after the defect elimination;
g) The work ticket licensor carries out on-site acceptance, and uploads the image and/or video of the electric power equipment after the acceptance;
H) Archiving and storing the defect eliminating flow data of the transformer substation equipment;
The server is also connected with an array storage device, the array storage device comprises a read-write bus and a plurality of storage units, the storage units comprise a timer, an electronic switch, a data read-write circuit and a storage medium,
The timer is connected with the control end of the electronic switch, the data read-write circuit is connected with the read-write bus through the electronic switch, the data read-write circuit is connected with the storage medium, the timer outputs high and low levels in turn according to a period Ti, i E [1, n ], n are the number of storage units, ti of the timers of the n storage units are not equal to each other, and in the step H), the method for archiving and storing the defect elimination flow data of the transformer substation equipment by the server comprises the following steps:
H1 The server inquires the number of the memory units which can be communicated through a read-write bus and marks m;
h2 The method comprises the steps that) the server splits defect elimination flow data of the transformer substation equipment into k data segments, k is an integer, and after the data segments are associated with time stamps and identification codes of the elimination flow data, the data segments are sequentially distributed to m storage units capable of being communicated for storage, and the server does not record information of the m storage units capable of being communicated;
H3 When the defect eliminating flow data of the transformer substation equipment is required to be verified or restored, removing all storage units in the array storage equipment, adding levels which enable the electronic switches to be conducted additionally, enabling all storage units to be communicated with a server, inquiring data segments which are stored in all storage units and are associated with identification codes of the defect eliminating flow data of the transformer substation equipment to be verified or restored, splicing the data segments according to time stamps to restore the defect eliminating flow data of the transformer substation equipment, wherein the restored defect eliminating flow data of the transformer substation equipment is used for comparing with the defect eliminating flow data of the transformer substation equipment directly stored by the server, and verifying whether the defect eliminating flow data of the transformer substation equipment directly stored by the server is tampered or not;
And (3) before each server distributes the data segments to the storage units, inquiring whether the storage units still can be communicated, after distributing the data segments, inquiring whether the storage units can be communicated again, and if the storage units which cannot be communicated are inquired, randomly distributing the data segments of the storage units which are distributed originally to other storage units which can be communicated in the m storage units communicated in the step H1).
2. The substation equipment defect management and control method based on the mobile phone APP according to claim 1 is characterized in that in the step B), after the mobile phone APP reports the defect to a server, the server sends the defect information to the mobile phone APP of the professional staff in the corresponding work area and gives a prompt;
In the step C), after the staff in the work area reports the defect to the company for full time, the server sends the defect information to the company for full time and sends a prompt;
In the step D), when the server sends the defect elimination plan to the mobile phone APP of the defect elimination responsible person, the mobile phone APP sends a prompt.
3. The substation equipment defect management and control method based on the mobile phone APP according to claim 1 is characterized in that a server stores prompt information of a plurality of preset substation equipment defects, and the prompt information comprises: one or more of field defect review guidelines, typical defect image location and angle, typical defect video, and pre-set defect information filling templates.
4. The method for managing and controlling defects of substation equipment based on mobile phone APP according to claim 1, wherein in step D), the mobile phone APP dedicated to the company displays a preset defect elimination plan and a preset list of spare parts commonly used according to the defect types checked by the staff dedicated to the work area in step C).
5. The substation equipment defect management and control method based on the mobile phone APP according to claim 1, wherein in the step H), when the defect eliminating flow data of the substation equipment defect is archived and stored, a unique identification code is encoded for the defect eliminating flow data, a hash value of the defect eliminating flow data is extracted, the identification code and the hash value of the defect eliminating flow data are associated and then are synchronized to all mobile phone APP for storage, and the mobile phone APP performs read-only protection on the received identification code and the hash value.
CN202110157290.0A 2021-02-05 2021-02-05 Substation equipment defect management and control method based on mobile phone APP Active CN112711500B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110157290.0A CN112711500B (en) 2021-02-05 2021-02-05 Substation equipment defect management and control method based on mobile phone APP

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110157290.0A CN112711500B (en) 2021-02-05 2021-02-05 Substation equipment defect management and control method based on mobile phone APP

Publications (2)

Publication Number Publication Date
CN112711500A CN112711500A (en) 2021-04-27
CN112711500B true CN112711500B (en) 2024-06-11

Family

ID=75550004

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110157290.0A Active CN112711500B (en) 2021-02-05 2021-02-05 Substation equipment defect management and control method based on mobile phone APP

Country Status (1)

Country Link
CN (1) CN112711500B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107977714A (en) * 2017-11-08 2018-05-01 天津市普迅电力信息技术有限公司 A kind of intelligent control platform of power transformation fortune inspection
CN109840711A (en) * 2019-02-14 2019-06-04 国网山东省电力公司菏泽供电公司 A kind of attached ancillary equipment defect analysis of substation and closed loop management system
CN109918519A (en) * 2019-02-26 2019-06-21 重庆善功科技有限公司 A kind of method and system stored towards magnanimity time-lapse photography embryo's image with inquiry
CN111309978A (en) * 2020-02-24 2020-06-19 广西电网有限责任公司防城港供电局 Transformer substation system safety protection method and device, computer equipment and storage medium

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5430484B2 (en) * 2010-04-15 2014-02-26 ルネサスエレクトロニクス株式会社 Semiconductor memory device and control method thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107977714A (en) * 2017-11-08 2018-05-01 天津市普迅电力信息技术有限公司 A kind of intelligent control platform of power transformation fortune inspection
CN109840711A (en) * 2019-02-14 2019-06-04 国网山东省电力公司菏泽供电公司 A kind of attached ancillary equipment defect analysis of substation and closed loop management system
CN109918519A (en) * 2019-02-26 2019-06-21 重庆善功科技有限公司 A kind of method and system stored towards magnanimity time-lapse photography embryo's image with inquiry
CN111309978A (en) * 2020-02-24 2020-06-19 广西电网有限责任公司防城港供电局 Transformer substation system safety protection method and device, computer equipment and storage medium

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
基于大数据架构的变电站设备智能化巡检***设计;褚大可;楼杏丹;包迅格;谢若承;张景明;;制造业自动化;20180825(第08期);全文 *

Also Published As

Publication number Publication date
CN112711500A (en) 2021-04-27

Similar Documents

Publication Publication Date Title
CN105184442A (en) Power distribution network dispatching management statistical analysis system
KR20070121238A (en) Digital substation based on iec61850 measuring partial discharge
CN101826757A (en) Method and device for managing earth wire
CN112150596B (en) Holographic reconstruction method and system for substation equipment fault
CN107093017B (en) The business datum acquisition methods and its device and system of power-off event
CN104076767A (en) Railway signal equipment overhauling control system and method
CN112270422A (en) Knowledge service-based electricity maintenance auxiliary system and method
CN1972287B (en) Communication protocol record analysis apparatus and its analysis method
CN110994801A (en) Distribution network automation-based distribution first-aid repair method and system
CN114971588A (en) Work order automatic auditing and transmitting method and related device
CN112711500B (en) Substation equipment defect management and control method based on mobile phone APP
CN109087006B (en) Method and device for processing power equipment monitoring information
CN111444991A (en) Power equipment management system and method based on physical ID
CN108920305B (en) USB device access risk detection method and device based on distributed accounting
CN111709597A (en) Power grid production domain operation monitoring system
CN110879867A (en) Information publishing method and system based on LED advertisement function power distribution cabinet
CN114173216B (en) Electric energy meter reading method and device, field meter reading terminal, storage medium and system
CN108875977A (en) Multimachine structure Maintenance Management System based on block chain
CN201004645Y (en) Recording and analysis device for communication regulation breach
CN113691390A (en) Cloud-end-coordinated edge node alarm system and method
CN112446619A (en) Power distribution network emergency repair processing method and device
Hamdan et al. Digitalization of protection relay management
CN112581305A (en) System and method for checking and accepting section of transformer substation maintenance site based on block chain
CN117709780B (en) High tension switchgear construction qualification's audit management system based on artificial intelligence
RU2589400C2 (en) Automated system recording, collection, processing, storage and viewing by emergency power system operator of oscillographic information obtained from different controlled power engineering facilities in power system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant