CN112610221A - Construction method for oversized section and gradual change section of bifurcation part of highway tunnel - Google Patents

Construction method for oversized section and gradual change section of bifurcation part of highway tunnel Download PDF

Info

Publication number
CN112610221A
CN112610221A CN202011481157.2A CN202011481157A CN112610221A CN 112610221 A CN112610221 A CN 112610221A CN 202011481157 A CN202011481157 A CN 202011481157A CN 112610221 A CN112610221 A CN 112610221A
Authority
CN
China
Prior art keywords
section
tunnel
gradual change
right pilot
excavating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202011481157.2A
Other languages
Chinese (zh)
Other versions
CN112610221B (en
Inventor
任松
李永强
宋书一
王乐
郭伟
胡明
何若蘭
全树言
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Juneng Construction Group Co ltd
Chongqing University
Original Assignee
Chongqing Juneng Construction Group Co ltd
Chongqing University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Juneng Construction Group Co ltd, Chongqing University filed Critical Chongqing Juneng Construction Group Co ltd
Priority to CN202011481157.2A priority Critical patent/CN112610221B/en
Publication of CN112610221A publication Critical patent/CN112610221A/en
Application granted granted Critical
Publication of CN112610221B publication Critical patent/CN112610221B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a construction method of an oversized section and a gradual change section of a bifurcation part of a highway tunnel, belonging to the technical field of tunnel engineering and comprising the following steps: 1) excavating from the end part of the right branch road of the tunnel to the direction of the gradual change section, and excavating an upper right pilot pit in the large section; 2) applying temporary support to the upper right pilot tunnel excavated in the step 1); 3) digging a transition section of the tunnel from the upper right pilot tunnel upper step of the large-section forwards horizontally, and forming a right pilot tunnel upper step of the transition section after digging a distance; 4) and (3) performing primary support on the upper right pilot pit dug in the step 3) and simultaneously locking and reinforcing … … and the like. The method adopts the guide pits to penetrate through the super-large section in advance and strengthen the support of the head-tail section of the super-large section, and the special excavation method and the support mode can ensure the safety of the excavation process and avoid the situations of excessive vault settlement, arch wall convergence, unstable arch foot, serious bottom heave and the like caused by the over-large section; compared with the existing excavation method, the method has the advantages that the temporary support is less, and the support is easier to disassemble.

Description

Construction method for oversized section and gradual change section of bifurcation part of highway tunnel
Technical Field
The invention relates to the technical field of tunnel engineering, in particular to a construction method for an oversized section and a gradual change section of a bifurcation part of a hard surrounding rock tunnel.
Background
When the excavation section in underground engineering (including tunnel engineering) is large, the construction is called as a large section, and the large section is unfavorable for excavation stress in the construction engineering. The international tunneling association defines a freeboard area per square meter of greater than 100 as an oversized cross-section.
In the construction process of the ultra-large section hard surrounding rock tunnel, the traditional excavation method is a double-side-wall pit guiding method, a CD method, a CRD method and the like. Aiming at the tunnel with the super large section formed by the intersection of two small-section tunnels and the tunnel with the gradually-reduced section, the double-side-wall pit guiding method and the CRD method have better adaptability; however, the existing excavation method has more temporary supports, difficult support removal and large construction risk, and particularly for the junction formed by 400m2And the tunnel with the ultra-large section has the risks of bias instability of the middle rock pillar at a small clear distance section, the instability of surrounding rocks caused by large span and partial mining disturbance of the ultra-large section, and the risks of rock burst and the like even when the tunnel is deeply buried.
Disclosure of Invention
In view of the above, the invention aims to provide a construction method for an oversized section and a gradual change section of a bifurcation part of a highway tunnel, so as to solve the technical problems of more temporary supports, difficult support removal, larger span, large free surface, large construction risk and the like existing in the prior art for excavating the oversized section and the gradual change section of the bifurcation part of the tunnel.
The invention relates to a construction method of an oversized section and a gradual change section of a bifurcation part of a highway tunnel, which comprises the following steps:
1) excavating from the end part of the right branch of the tunnel to the direction of the gradual change section, and excavating an upper right pilot pit in the large section, wherein the upper right pilot pit extends from the end part of the right branch of the tunnel to the top of an arc at the starting part of the gradual change section in an inclined and upward manner;
2) applying temporary support to the upper right pilot tunnel excavated in the step 1);
3) digging a transition section of the tunnel from the upper right pilot tunnel upper step of the large-section forwards horizontally, and forming a right pilot tunnel upper step of the transition section after digging a distance;
4) applying primary support to the upper right pilot pit dug in the step 3) and simultaneously locking and reinforcing the opening;
5) performing transverse expanding excavation in the gradual change section to form an upper step of the gradual change section, and then performing primary support;
6) implementing reverse top raising on the upper right pilot tunnel of the oversized section, and timely implementing primary support and temporary portal after top raising is completed;
7) excavating from the gradual change section to the direction of a tunnel branch, excavating an upper step with a large section, and constructing primary support and erecting a temporary portal after the upper step with the large section is formed;
8) excavating the middle-lower part of a guide pit on the right side of the large-section from the tunnel bifurcation section to the tunnel transition section, and constructing an inverted arch in time;
9) digging out the middle step at the left side of the large-section, and applying primary support and temporary arch centering in time;
10) digging out a middle step in the middle of the large-section, and applying primary support and temporary arch centering in time;
11) digging out a lower step at the left side of the large-section, and constructing an inverted arch;
12) digging out a lower step in the middle of the large-section, and constructing an inverted arch;
13) and (4) completely excavating the large section and then applying a second lining.
The invention has the beneficial effects that:
the construction method of the super-large sections and the gradual change sections of the bifurcation parts of the highway tunnel adopts the guide pits to penetrate through the super-large section in advance and strengthen the support of the head-tail sections of the super-large sections, and the special excavation method and the support mode can ensure the safety of the excavation process and avoid the situations of excessive vault settlement, arch wall convergence, unstable arch springing, severe bottom bulging and the like caused by the overlarge sections; compared with the existing excavation method, the method has the advantages that the temporary support is less, and the support is easier to disassemble.
Drawings
Fig. 1 is a plan view of the general step sequence of the construction of the oversized cross section of the bifurcation part, wherein arrows represent the excavation direction, and I, II, III, IV and V in the drawing respectively represent the excavation sequence.
FIG. 2 is a schematic diagram of excavating an upper right pilot tunnel in the step 1);
FIG. 3 is a schematic diagram of the right-side upper step of the pilot tunnel that is dug into the transition section to form the transition section in step 3);
FIG. 4 is a schematic view of a locking notch reinforcement;
FIG. 5 is a schematic view of a reverse flip top;
fig. 6 is a schematic view of an upper step with a large cross section dug from the transition section to the branch opening of the tunnel and a temporary gantry applied in step 7);
FIG. 7 is a schematic structural diagram of a temporary portal;
FIG. 8 is a schematic diagram of the excavation sequence of steps 8) -12);
fig. 9 is a top plan schematic view of a tunnel.
Detailed Description
The invention is further described below with reference to the figures and examples.
As shown in the figure, the construction method of the ultra-large section and the gradual change section of the road tunnel bifurcation part of the embodiment comprises the following steps:
1) and excavating from the end part of the right branch of the tunnel to the direction of the transition section, as shown in fig. 2, excavating an upper right pilot pit 1 in the large-section, wherein the upper right pilot pit obliquely extends upwards from the end part of the right branch of the tunnel to the top of the arc at the beginning of the transition section.
2) And (3) applying temporary support to the upper right pilot tunnel dug in the step 1).
3) The transition section of the tunnel is dug horizontally forward from the upper right pit guiding step of the large section, and as shown in fig. 3, the right pit guiding step of the transition section is formed after digging for a certain distance.
4) And (3) applying primary support to the upper right pilot pit dug in the step 3) and simultaneously locking the opening for reinforcement, as shown in figure 4.
5) And performing transverse expanding excavation in the transition section, wherein the excavation direction is the direction indicated by an arrow at the part III in the figure 1, forming an upper step of the transition section, and then performing primary support.
6) And (3) implementing reverse top raising on the upper right pilot tunnel of the oversized section as shown in figure 5, and timely implementing primary support 2 and temporary portal 3 after top raising is completed.
7) Excavating from the gradual change section to the direction of a tunnel branch, excavating an upper step with a large section, wherein the excavating direction is the direction indicated by the arrow of the V part in figure 1, and constructing primary support and erecting a temporary portal frame after the upper step with the large section is formed.
8) And excavating the middle lower part of the guide pit on the right side of the large-section from the tunnel bifurcation section to the tunnel transition section, wherein the excavated part is shown as a serial number I in the figure 8, and an inverted arch is constructed in time.
9) And digging out the middle step at the left side of the large-section, wherein the digging part is shown as a serial number II in the figure 8, and constructing primary support and a temporary arch in time.
10) And digging out the middle step in the middle of the large-section, wherein the digging part is shown as a sequence number III in figure 8, and constructing primary support and temporary arch centering in time.
11) And digging out the lower step at the left side of the large-section, wherein the digging part is shown as a serial number (r) in the figure 8 and is constructed as an inverted arch.
12) Digging out the lower step in the middle of the large section, and constructing an inverted arch at the digging part as shown by the serial number (v) in figure 8.
13) And (4) completely excavating the large section and then applying a second lining.
According to the construction method of the super-large sections and the gradual change sections of the bifurcation parts of the highway tunnel, the guide pits are adopted to penetrate through the super-large section in advance, and the head-to-tail section support of the super-large section is strengthened, so that the safety of an excavation process can be ensured by the special excavation method and the support mode, and the situations of excessive vault settlement, arch wall convergence, unstable arch springing, severe bottom bulging and the like caused by the overlarge sections can be avoided; compared with the existing excavation method, the method has the advantages that the temporary support is less, and the support is easier to disassemble.
Finally, the above embodiments are only for illustrating the technical solutions of the present invention and not for limiting, although the present invention has been described in detail with reference to the preferred embodiments, it should be understood by those skilled in the art that modifications or equivalent substitutions may be made to the technical solutions of the present invention without departing from the spirit and scope of the technical solutions of the present invention, and all of them should be covered in the claims of the present invention.

Claims (1)

1. A construction method for an oversized section and a gradual change section of a bifurcation part of a highway tunnel is characterized by comprising the following steps: the method comprises the following steps:
1) excavating from the end part of the right branch of the tunnel to the direction of the gradual change section, and excavating an upper right pilot pit in the large section, wherein the upper right pilot pit extends from the end part of the right branch of the tunnel to the top of an arc at the starting part of the gradual change section in an inclined and upward manner;
2) applying temporary support to the upper right pilot tunnel excavated in the step 1);
3) digging a transition section of the tunnel from the upper right pilot tunnel upper step of the large-section forwards horizontally, and forming a right pilot tunnel upper step of the transition section after digging a distance;
4) applying primary support to the upper right pilot pit dug in the step 3) and simultaneously locking and reinforcing the opening;
5) performing transverse expanding excavation in the gradual change section to form an upper step of the gradual change section, and then performing primary support;
6) implementing reverse top raising on the upper right pilot tunnel of the oversized section, and timely implementing primary support and temporary portal after top raising is completed;
7) excavating from the gradual change section to the direction of a tunnel branch, excavating an upper step with a large section, and constructing primary support and erecting a temporary portal after the upper step with the large section is formed;
8) excavating the middle-lower part of a guide pit on the right side of the large-section from the tunnel bifurcation section to the tunnel transition section, and constructing an inverted arch in time;
9) digging out the middle step at the left side of the large-section, and applying primary support and temporary arch centering in time;
10) digging out a middle step in the middle of the large-section, and applying primary support and temporary arch centering in time;
11) digging out a lower step at the left side of the large-section, and constructing an inverted arch;
12) digging out a lower step in the middle of the large-section, and constructing an inverted arch;
13) and (4) completely excavating the large section and then applying a second lining.
CN202011481157.2A 2020-12-15 2020-12-15 Construction method for oversized cross section and gradual change section of bifurcation part of highway tunnel Active CN112610221B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011481157.2A CN112610221B (en) 2020-12-15 2020-12-15 Construction method for oversized cross section and gradual change section of bifurcation part of highway tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011481157.2A CN112610221B (en) 2020-12-15 2020-12-15 Construction method for oversized cross section and gradual change section of bifurcation part of highway tunnel

Publications (2)

Publication Number Publication Date
CN112610221A true CN112610221A (en) 2021-04-06
CN112610221B CN112610221B (en) 2022-11-15

Family

ID=75239320

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011481157.2A Active CN112610221B (en) 2020-12-15 2020-12-15 Construction method for oversized cross section and gradual change section of bifurcation part of highway tunnel

Country Status (1)

Country Link
CN (1) CN112610221B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113431588A (en) * 2021-07-30 2021-09-24 中铁十四局集团第三工程有限公司 Construction method for branch tunnel

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060040621A (en) * 2006-04-05 2006-05-10 (주)성풍건설 The construction method excavating underground plaza
CN102996133A (en) * 2012-07-02 2013-03-27 中铁二十三局集团第四工程有限公司 Construction method applicable to intersection between inclined shaft and slant hole of weak surrounding rock tunnel
CN204716248U (en) * 2015-06-17 2015-10-21 大连市市政设计研究院有限责任公司 Tunnel Heng Dong enters main hole and to caunch structure
CN109057807A (en) * 2018-09-28 2018-12-21 北京市市政三建设工程有限责任公司 A kind of gradual change Large span tunnel reversely digs method
CN110259457A (en) * 2019-05-22 2019-09-20 云南建投第四建设有限公司 A kind of fork crosses the construction method of section large section tunnel
CN110306986A (en) * 2019-05-09 2019-10-08 深圳市综合交通设计研究院有限公司 A kind of anti-cut construction method of underground interchange fork node Tunneling by mining method
CN110966009A (en) * 2019-12-31 2020-04-07 中铁第四勘察设计院集团有限公司 Construction method of bifurcated tunnel
CN111043926A (en) * 2020-01-03 2020-04-21 重庆中环建设有限公司 400m is realized based on electron detonator2Blasting excavation method for tunnel with large cross section
CN111188629A (en) * 2020-01-02 2020-05-22 中交第二航务工程局有限公司 Construction method for sudden change of tunnel bifurcation section and expanding excavation
CN111365017A (en) * 2020-03-13 2020-07-03 中铁第四勘察设计院集团有限公司 Construction method of underground intercommunication tunnel
CN111810187A (en) * 2020-07-20 2020-10-23 中国路桥工程有限责任公司 Urban non-center pilot tunnel bifurcation tunnel turning construction method
CN111810163A (en) * 2020-06-02 2020-10-23 中铁十八局集团有限公司 Nine-lane double-arch construction method for underground excavation through underground longitudinal and transverse channels

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060040621A (en) * 2006-04-05 2006-05-10 (주)성풍건설 The construction method excavating underground plaza
CN102996133A (en) * 2012-07-02 2013-03-27 中铁二十三局集团第四工程有限公司 Construction method applicable to intersection between inclined shaft and slant hole of weak surrounding rock tunnel
CN204716248U (en) * 2015-06-17 2015-10-21 大连市市政设计研究院有限责任公司 Tunnel Heng Dong enters main hole and to caunch structure
CN109057807A (en) * 2018-09-28 2018-12-21 北京市市政三建设工程有限责任公司 A kind of gradual change Large span tunnel reversely digs method
CN110306986A (en) * 2019-05-09 2019-10-08 深圳市综合交通设计研究院有限公司 A kind of anti-cut construction method of underground interchange fork node Tunneling by mining method
CN110259457A (en) * 2019-05-22 2019-09-20 云南建投第四建设有限公司 A kind of fork crosses the construction method of section large section tunnel
CN110966009A (en) * 2019-12-31 2020-04-07 中铁第四勘察设计院集团有限公司 Construction method of bifurcated tunnel
CN111188629A (en) * 2020-01-02 2020-05-22 中交第二航务工程局有限公司 Construction method for sudden change of tunnel bifurcation section and expanding excavation
CN111043926A (en) * 2020-01-03 2020-04-21 重庆中环建设有限公司 400m is realized based on electron detonator2Blasting excavation method for tunnel with large cross section
CN111365017A (en) * 2020-03-13 2020-07-03 中铁第四勘察设计院集团有限公司 Construction method of underground intercommunication tunnel
CN111810163A (en) * 2020-06-02 2020-10-23 中铁十八局集团有限公司 Nine-lane double-arch construction method for underground excavation through underground longitudinal and transverse channels
CN111810187A (en) * 2020-07-20 2020-10-23 中国路桥工程有限责任公司 Urban non-center pilot tunnel bifurcation tunnel turning construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
仇在林: "超大断面隧道小导洞先行与台阶反扩挖施工技术研究", 《公路工程》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113431588A (en) * 2021-07-30 2021-09-24 中铁十四局集团第三工程有限公司 Construction method for branch tunnel
CN113431588B (en) * 2021-07-30 2022-07-22 中铁十四局集团第三工程有限公司 Construction method for branch tunnel

Also Published As

Publication number Publication date
CN112610221B (en) 2022-11-15

Similar Documents

Publication Publication Date Title
CN102071947B (en) Construction method for soft surrounding rock section of large-span tunnel portal
CN110219654B (en) Advanced construction method for side pilot tunnel of mud-rock arch tunnel
CN103603679B (en) For arch crown steel frame and the method for tunnel construction of arch, supporting tunnel
CN110242305B (en) Construction process method for constructing main tunnel by inclined shaft entering single side wall pit guiding method
CN104481546B (en) A kind of soft rock tunnel inclined shaft enters the construction method of the double curvature arch in positive hole
CN110439571A (en) Flat pilot tunnel leads to the adit construction method and transverse passage-way of main tunnel
CN110924952B (en) Construction method for three-step seven-step normal medium rock pillar method conversion of super-large section tunnel
CN102400689B (en) Convoluted excavation method for undermined tunnel with extra-large cross section
CN101545376A (en) Execution method for feeding tiny tunnel into ultra heavy section tunnel transversally
CN102865084B (en) Expanding excavation method of underground tunnel from fracture surface of double-track tunnel to ultra-large fracture surface of triple-track tunnel
JPH08170484A (en) Construction method of large cross section tunnel
CN106979013A (en) A kind of excavation construction method for the large section tunnel for biasing Shallow-Buried Soft Rock
CN108643940A (en) Large section Shallow-Buried Soft Rock tunnel groined type double side wall support system and method for tunnel construction
CN108150206A (en) A kind of method by fully-mechanized mining working crossheading caving place
CN112610221B (en) Construction method for oversized cross section and gradual change section of bifurcation part of highway tunnel
CN204457789U (en) A kind of stake arch wall supports the subway station digging large diameter shield tunnel and build
CN109594995A (en) A kind of Support System in Soft Rock Tunnels micro-disturbance machinery branch driving engineering method
CN111677517B (en) Method for entering tunnel into main tunnel by tunnel auxiliary pilot pit
CN214273660U (en) Bias-pressure oblique tunnel hole entering structure of loose accumulation body
CN113481857A (en) Structure for preventing deformation of upper expressway during pushing of frame bridge and construction method
CN114320317A (en) Construction method for weak surrounding rock section of short-step super-large section tunnel
CN210264724U (en) Broken stratum extra-small clear distance urban tunnel supporting structure
CN113622941A (en) Large-span double-arch tunnel excavation method under urban complex environment
CN112502042A (en) Construction method for improving jacking efficiency of large frame bridge
CN108843339B (en) The auxiliary slip casting platform and construction method of large-scale solution cavity are passed through when existing tunnel digs

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant