CN112575952A - End steel plate self-anchoring structure of double-steel-plate-concrete combined structure - Google Patents

End steel plate self-anchoring structure of double-steel-plate-concrete combined structure Download PDF

Info

Publication number
CN112575952A
CN112575952A CN202011368580.1A CN202011368580A CN112575952A CN 112575952 A CN112575952 A CN 112575952A CN 202011368580 A CN202011368580 A CN 202011368580A CN 112575952 A CN112575952 A CN 112575952A
Authority
CN
China
Prior art keywords
steel
steel plate
double
plate
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011368580.1A
Other languages
Chinese (zh)
Inventor
路冰
刘聪
赵宝成
孔璟常
陈鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou University of Science and Technology
Yantai University
Original Assignee
Suzhou University of Science and Technology
Yantai University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou University of Science and Technology, Yantai University filed Critical Suzhou University of Science and Technology
Priority to CN202011368580.1A priority Critical patent/CN112575952A/en
Publication of CN112575952A publication Critical patent/CN112575952A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/02Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials
    • E04C2/26Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials composed of materials covered by two or more of groups E04C2/04, E04C2/08, E04C2/10 or of materials covered by one of these groups with a material not specified in one of the groups
    • E04C2/28Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials composed of materials covered by two or more of groups E04C2/04, E04C2/08, E04C2/10 or of materials covered by one of these groups with a material not specified in one of the groups combinations of materials fully covered by groups E04C2/04 and E04C2/08
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/30Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the shape or structure
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/30Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the shape or structure
    • E04C2/38Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the shape or structure with attached ribs, flanges, or the like, e.g. framed panels
    • E04C2/384Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the shape or structure with attached ribs, flanges, or the like, e.g. framed panels with a metal frame

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a self-anchoring structure of a steel plate at the end part of a double-steel-plate-concrete combined structure, relates to an anchoring structure of a steel plate at the end part in a double-steel-plate-concrete combined structure, and aims to solve the problem that shear fracture is easy to occur under the action of reciprocating load due to the complex stress of a shear connector in the double-steel-plate-concrete combined structure. The self-anchoring structure of the end steel plate of the double-steel-plate-concrete combined structure is characterized in that the steel plate at one side of the end is bent along the thickness direction of the double-steel-plate-concrete combined structure, a rubber pad is arranged on the inner side of the bent part of the steel plate, one end of a tail-end shear connector is connected to the bent part of the steel plate, the other end of the tail-end shear connector extends into the core concrete, and an end shear connector is arranged on the steel plate at the other side of the end of the double-steel-plate-concrete combined structure along the. The self-anchoring mode of the invention can not only improve the cooperative working capacity of the steel plate and the concrete, but also reduce the shearing acting force of the shearing-resistant connecting piece in the interface.

Description

End steel plate self-anchoring structure of double-steel-plate-concrete combined structure
Technical Field
The invention relates to an anchoring structure of an end steel plate in a double-steel-plate-concrete combined structure.
Background
The double-steel-plate-concrete combined structure consists of steel plates on two sides, core concrete and a shear connector. The cooperative work of the steel plate and the concrete in the double steel plate-concrete composite structure is realized by means of a shear connector. In the existing design specification aiming at the double-steel-plate-concrete combined structure, the connecting mode of the double-steel-plate-concrete combined structure and the connecting mode of the double-steel-plate-concrete combined structure and the reinforced concrete combined structure provide the anchoring effect on the steel plates, so that the shearing force of the shear connector is reduced, and the overall mechanical property and the safety margin of the double-steel-concrete combined structure are improved. However, no design of self-anchoring of the end steel plates of the double-steel-concrete composite structure has been proposed.
Disclosure of Invention
The invention aims to solve the problem that shear fracture resistance is easy to occur under the action of reciprocating load due to the complex stress of a shear connector in a double-steel-plate-concrete combined structure, and provides a double-steel-plate-concrete combined structure end steel plate self-anchoring structure.
The invention relates to a self-anchoring structure of end steel plates of a double-steel-plate-concrete combined structure, which comprises two steel plates at two sides, a plurality of internal anti-shearing connectors, core concrete, a rubber pad, a tail-end anti-shearing connector and an end anti-shearing connector, wherein the two steel plates are oppositely arranged, the internal anti-shearing connector is welded between the two steel plates, pouring core concrete between the two steel plates to form a double-steel-plate-concrete combined structure, bending one side (tension) steel plate at the end part of the double-steel-plate-concrete combined structure along the thickness direction of the double-steel-plate-concrete combined structure, the rubber pads with wedge-shaped thickness are arranged on the inner sides of the steel plate bending parts, one end of the tail end shear connector is connected to the steel plate bending parts, the other end of the tail end shear connector extends into the core concrete, and the end shear connector is arranged on the other side (tension) of the end of the double-steel-concrete combined structure along the thickness direction.
The invention discloses a self-anchoring structure of a steel plate at the end part of a double-steel-plate-concrete composite structure, which comprises two steel plates at two sides, a plurality of internal shear connectors, core concrete, rubber pads and tail end shear connectors, wherein the two steel plates are oppositely arranged, the internal shear connectors are welded between the two steel plates, the core concrete is poured between the two steel plates to form the double-steel-plate-concrete composite structure, the two (pulled) steel plates at the end part of the double-steel-concrete composite structure are respectively bent along the thickness direction of the double-steel-concrete composite structure, the inner side of each steel plate bent part is respectively provided with the rubber pads with wedge-shaped thickness, the tail end shear connector is connected to each steel plate bent part, one end of the tail end shear connector is connected to the steel plate bent part, and the other end.
The double-steel-plate-concrete combined structure consists of steel plates on two sides, core concrete and a shear connector. For the double-steel-plate-concrete combined structure adopting the steel plate self-anchoring mode, the steel plates on the two sides of the combined structure still realize partial interface shear force transmission through the shear connectors, the end bending steel plate section and the tail shear connector can effectively restrain the concrete, the anchoring effect of the end steel plates in the concrete is increased, and the steel plates are prevented from slipping. After the steel plates are connected with the shear connectors, concrete is poured by taking the steel plates at two sides as temporary formworks, so that a double-steel-plate-concrete combined structure form with self-anchored end steel plates is formed.
The self-anchoring structure of the end steel plate of the double-steel-plate-concrete combined structure has the beneficial effects that the steel plate self-anchoring mode can improve the cooperative working capacity of the steel plate and the concrete and can reduce the shearing acting force of the shearing-resistant connecting piece in the interface (under the action of reciprocating load), so that the mechanical property and the seismic performance of the double-steel-plate-concrete combined structure are greatly improved. The steel plates are anchored in the traditional splicing design of the double-steel-plate-concrete composite structure and the connection design of the double-steel-plate-concrete composite structure and the reinforced concrete structure. However, at present, no design research is conducted on the self-anchoring of the steel plate in the double-steel-plate-concrete combined structure. The invention makes up for the short slab in the double-steel-concrete combined structure and is suitable for the industrial application of the double-steel-concrete combined structure.
Drawings
FIG. 1 is a schematic structural view of an end bent steel plate in a self-anchoring structure of an end steel plate of a double-steel-concrete composite structure according to the present invention;
FIG. 2 is a schematic end view of a self-anchoring structure of an end steel plate of a double-steel-plate concrete composite structure according to an embodiment;
FIG. 3 is a schematic view of the overall structure of a self-anchoring structure of end steel plates of a double-steel-plate-concrete composite structure according to an embodiment;
FIG. 4 is a schematic view of the overall structure of a self-anchoring structure of a steel plate at the end of a double-steel-plate-concrete composite structure according to a second embodiment;
FIG. 5 is a schematic view of loading of a self-anchoring structure of end steel plates of a double-steel-plate-concrete composite structure in the embodiment;
FIG. 6 is a diagram showing the result of numerical simulation of the self-anchoring structure of the end steel plates of the double steel plate-concrete composite structure in the example;
fig. 7 is a graph showing the relationship between the internal force of the steel plate and the horizontal displacement of the steel plate in the self-anchoring structure of the end steel plate of the double steel plate-concrete composite structure in the embodiment, wherein 1 represents 0D, 2 represents 2.5D, 3 represents 5D, 4 represents 7.5D, 5 represents 10D, 6 represents 12.5D, 7 represents 15D, 8 represents 17.5D, and 9 represents 20D.
Detailed Description
The first embodiment is as follows: the self-anchoring structure of the end steel plate of the double-steel-plate concrete composite structure comprises two side steel plates 1, a plurality of internal shear connectors 2, core concrete 3, a rubber pad 4, a tail end shear connector 5 and an end shear connector 6, wherein the two steel plates 1 are oppositely arranged, the internal shear connectors 2 are welded between the two steel plates 1, pouring core concrete 3 between the two steel plates 1 to form a double-steel-plate-concrete combined structure, bending the steel plate 1 at one side of the end part of the double-steel-plate-concrete combined structure along the thickness direction of the double-steel-plate-concrete combined structure, the rubber pads 4 with wedge-shaped thickness are arranged on the inner sides of the steel plate bending parts, one end of the tail end shear connector 5 is connected to the steel plate bending parts, the other end of the tail end shear connector 5 extends into the core concrete 3, and the end shear connector 6 is arranged on the steel plate 1 on the other side of the end of the double-steel-concrete combined structure along the thickness direction.
The rubber pads with wedge-shaped thickness are arranged on the inner sides of the steel plates, and the tail-end shear connector is arranged on the bent steel plates, so that the steel plate anchoring effect is improved. The wedge-shaped rubber pad is mainly used for delaying the exertion of the anchoring effect of the bent steel plate, ensuring that the shearing resistance of the shearing-resistant connecting piece is exerted preferentially, and exerting the anchoring effect of the shearing-resistant connecting piece and the bent steel plate simultaneously when the load is large.
The self-anchoring structure of the end steel plate of the double-steel-plate concrete composite structure has the effects of reducing the shearing force of the shear connector in the interface, saving the welding construction cost of the shear connector, reducing the welding residual deformation and the residual stress of the steel plate and better improving the anti-seismic performance of the double-steel-plate concrete composite structure. Meanwhile, according to the existing test result aiming at the shearing resistance of the shearing-resistant connecting piece in the double-steel-plate concrete combined structure, under the action of reciprocating load, the shearing resistance of the shearing-resistant connecting piece is obviously reduced, and the ductility is reduced. For the steel plate-concrete combined structure, once the shear connector in the interface is easy to break under the action of reciprocating load, the bearing capacity of the double steel plate-concrete combined structure is completely lost.
The second embodiment is as follows: the self-anchoring structure of the end steel plate of the double-steel-plate concrete composite structure comprises two side steel plates 1, a plurality of internal shear connectors 2, core concrete 3, a rubber pad 4 and a tail end shear connector 5, wherein the two steel plates 1 are oppositely arranged, the internal shear connectors 2 are welded between the two steel plates 1, pouring core concrete 3 between the two steel plates 1 to form a double-steel-plate-concrete combined structure, bending the steel plates 1 at two sides of the end part of the double-steel-plate-concrete combined structure along the thickness direction of the double-steel-plate-concrete combined structure respectively, the rubber pads 4 with wedge-shaped thickness are respectively arranged on the inner sides of the steel plate bending parts, the tail end shear connector 5 is connected to each steel plate bending part, one end of the tail end shear connector 5 is connected to each steel plate bending part, and the other end of the tail end shear connector 5 extends into the core concrete 3.
The third concrete implementation mode: the difference between the first embodiment and the second embodiment is that the thickness of the steel plate 1 is D, and the radius of curvature R of the inner fillet at the bent part of the steel plate is 1.2D-2.8D.
The fourth concrete implementation mode: the difference between the first or second embodiment is that one side steel plate 1 at the end of the double steel plate-concrete composite structure is bent along the thickness direction of the double steel plate-concrete composite structure, and the included angle between the bent part of the steel plate and the non-bent part of the steel plate is 82-88 degrees.
The fifth concrete implementation mode: the fourth difference between the present embodiment and the present embodiment is that one side steel plate 1 at the end of the double steel plate-concrete composite structure is bent along the thickness direction of the double steel plate-concrete composite structure, and the included angle between the bent portion of the steel plate and the non-bent portion of the steel plate is 85 °.
The sixth specific implementation mode: the present embodiment is different from one of the first to fifth embodiments in that the tail end shear connector 5 is disposed perpendicular to the bent portion of the steel plate.
The seventh embodiment: the present embodiment is different from one of the first to fifth embodiments in that the trailing shear connector 5 is horizontally disposed.
The specific implementation mode is eight: the present embodiment differs from the first to seventh embodiments in that the thickness D of the steel sheet 1 is set, and the distance L from the end of the bent portion of the steel sheet to the bending point Q is set to 13D to 17D.
The specific implementation method nine: the difference between the present embodiment and the eighth embodiment is that the thickness of the steel plate 1 is D, and the distance m from the end of the bent portion of the steel plate to the tail end shear connector 5 is 3D to 6D.
The detailed implementation mode is ten: the present embodiment is different from one of the first to ninth embodiments in that the core concrete 3 has a thickness of 300mm to 1000 mm.
Example (b): the self-anchoring structure of the end steel plate of the double-steel-plate-concrete composite structure comprises two steel plates 1 on two sides, a plurality of internal anti-shearing connectors 2, core concrete 3, rubber pads 4, a tail end anti-shearing connector 5 and an end anti-shearing connector 6, wherein the two steel plates 1 are oppositely arranged, the internal anti-shearing connectors 2 are welded between the two steel plates 1, the core concrete 3 is poured between the two steel plates 1 to form the double-steel-concrete composite structure, one steel plate on one side of the end part of the double-steel-concrete composite structure is bent along the thickness direction of the double-steel-concrete composite structure, the rubber pads 4 with wedge-shaped thickness are arranged on the inner sides of steel plate bending parts, one end of the tail end anti-shearing connector 5 is connected onto the steel plate bending parts, the other end of the tail end anti-shearing connector 5 extends, and an end shear connector 6 is arranged on the steel plate on the other side of the end part of the double-steel-plate concrete combined structure along the thickness direction.
This embodiment is buckled the steel sheet through equipment of buckling, connects both sides steel sheet through shear connector, pours the concrete shaping between two steel sheets.
The ABAQUS finite element software is adopted to carry out simulation analysis on the self-anchoring structure of the end part of the double-steel-plate concrete structure in the embodiment, and the influence of the distance between the break point of the steel plate and the tail end of the steel plate on the maximum internal force value of the steel plate is mainly analyzed. In the embodiment, the thickness of the steel plate is 10mm, the width of the steel plate is 500mm, and the yield strength of the steel plate is 400 MPa; the height of the concrete is 500mm, the width of the concrete is 500mm, and the strength grade of the concrete is C40. The curvature radius of the bending point of the steel plate is 25mm, and the distance between the center of the first bending curve and the tail end of the steel plate is different from 0D to 20D. A loading diagram of the test piece is shown in fig. 5. In the figure, concrete at the end A is fixedly restrained, and horizontal displacement is applied to the steel plate at the end B. The contact surface of the steel plate and the concrete defines friction tangentially, the friction coefficient is 0.6, and the normal direction defines hard contact. The tail-end shear connector is simulated by a spring unit.
The simulation results are shown in fig. 6, and it can be seen that the concrete is compressed and inverted under the horizontal tension of the steel plate. The force versus horizontal displacement curve in the steel plate is plotted in fig. 7. It can be seen from the figure that, as the distance between the center of the bending curve and the tail end of the bent steel plate increases, the maximum internal force value of the steel plate gradually increases, and when the distance between the centers reaches 20D, the steel plate drops sharply. From the simulation result, the reason is that when the center distance is too large, the bending section steel plate is warped, and the effect of self-anchoring of the steel plate is influenced. Therefore, the suggested value of the distance between the circle center of the bending curve and the tail end of the steel plate is 13D-17D, and at the moment, the steel plate can reach the yield tensile strength. From the force-displacement curve, a drop occurs when the internal force reaches a peak, which is caused by plastic deformation of the concrete.

Claims (10)

1. The self-anchoring structure of the end steel plate of the double-steel-plate-concrete composite structure is characterized by comprising two side steel plates (1), a plurality of internal anti-shearing connectors (2), core concrete (3), rubber pads (4), tail end anti-shearing connectors (5) and end anti-shearing connectors (6), wherein the two steel plates (1) are oppositely arranged, the internal anti-shearing connectors (2) are welded between the two steel plates (1), the core concrete (3) is poured between the two steel plates (1) to form the double-steel-plate-concrete composite structure, one side steel plate (1) at the end part of the double-steel-concrete composite structure is bent along the thickness direction of the double-steel-concrete composite structure, the rubber pads (4) with wedge-shaped thickness are arranged on the inner sides of bent parts of the steel plates, one end of each tail end anti-shearing connector (5) is connected to the bent part of each steel plate, the other end of the tail-end shear connector (5) extends into the core concrete (3), and an end shear connector (6) is arranged on the steel plate (1) on the other side of the end of the double-steel-plate concrete combined structure along the thickness direction.
2. The self-anchoring structure of the end steel plate of the double-steel-plate-concrete composite structure is characterized by comprising two side steel plates (1), a plurality of internal shear connectors (2), core concrete (3), rubber pads (4) and tail end shear connectors (5), wherein the two steel plates (1) are oppositely arranged, the internal shear connectors (2) are welded between the two steel plates (1), the core concrete (3) is poured between the two steel plates (1) to form the double-steel-plate-concrete composite structure, the two side steel plates (1) at the end part of the double-steel-concrete composite structure are respectively bent along the thickness direction of the double-steel-concrete composite structure, the inner side of each steel plate bent part is respectively provided with the rubber pad (4) with wedge-shaped thickness, and each steel plate bent part is connected with the tail end shear connector (5), one end of the tail-end shear connector (5) is connected to the steel plate bending part, and the other end of the tail-end shear connector (5) extends into the core concrete (3).
3. The self-anchoring structure of the end steel plates of the double steel plate-concrete composite structure according to claim 1 or 2, characterized in that the thickness of the steel plate (1) is D, and the radius of curvature R of the fillet at the bent part of the steel plate is 1.2D-2.8D.
4. The self-anchoring structure of the end steel plates of the double steel plate-concrete composite structure according to claim 1 or 2, wherein one side steel plate (1) of the end of the double steel plate-concrete composite structure is bent along the thickness direction of the double steel plate-concrete composite structure, and the included angle between the bent part of the steel plate and the non-bent part of the steel plate is 82-88 °.
5. The self-anchoring structure of the end steel plates of the double steel plate-concrete composite structure according to claim 4, wherein one side steel plate (1) of the end of the double steel plate-concrete composite structure is bent along the thickness direction of the double steel plate-concrete composite structure, and the included angle between the bent part of the steel plate and the non-bent part of the steel plate is 85 degrees.
6. The self-anchoring structure of end steel plates of a double steel plate-concrete composite structure according to claim 1 or 2, wherein the tail shear connectors (5) are arranged perpendicular to the bent portions of the steel plates.
7. The double steel plate-concrete composite structure end steel plate self-anchoring structure according to claim 1 or 2, wherein the tail-end shear connector (5) is horizontally disposed.
8. The self-anchoring structure of steel plates at the end of a double steel plate-concrete composite structure according to claim 1 or 2, characterized in that the thickness of the steel plate (1) is D, and the distance L from the end of the bent part of the steel plate to the bending point (Q) is 13D-17D.
9. The self-anchoring structure of the end steel plate of the double steel plate-concrete composite structure according to claim 8, wherein the thickness of the steel plate (1) is D, and the distance m from the end of the bent part of the steel plate to the tail end shear connector (5) is 3D-6D.
10. Double steel plate-concrete composite structure end steel plate self-anchoring structure according to claim 1, characterised in that the core concrete (3) has a thickness of 300mm-1000 mm.
CN202011368580.1A 2020-12-02 2020-12-02 End steel plate self-anchoring structure of double-steel-plate-concrete combined structure Pending CN112575952A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011368580.1A CN112575952A (en) 2020-12-02 2020-12-02 End steel plate self-anchoring structure of double-steel-plate-concrete combined structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011368580.1A CN112575952A (en) 2020-12-02 2020-12-02 End steel plate self-anchoring structure of double-steel-plate-concrete combined structure

Publications (1)

Publication Number Publication Date
CN112575952A true CN112575952A (en) 2021-03-30

Family

ID=75126385

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011368580.1A Pending CN112575952A (en) 2020-12-02 2020-12-02 End steel plate self-anchoring structure of double-steel-plate-concrete combined structure

Country Status (1)

Country Link
CN (1) CN112575952A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3147087A1 (en) * 1981-11-27 1983-06-09 Max Dipl.-Ing. Dr.-Ing. 8700 Würzburg Mengeringhausen SUPPORTING COMPOSITE BUILDING BOARD AND METHOD FOR THE PRODUCTION THEREOF
CN101967853A (en) * 2010-09-16 2011-02-09 南京林业大学 Fiber reinforce plastic (FRP)-rubber-steel composite pipe concrete structure
CN110821038A (en) * 2019-10-21 2020-02-21 上海市建筑科学研究院 Double-steel-plate concrete combined energy-consumption connecting beam and construction method
CN211057596U (en) * 2019-09-11 2020-07-21 江苏高速公路工程养护技术有限公司 Corrugated steel pipe reinforced concrete-filled steel tube pier

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3147087A1 (en) * 1981-11-27 1983-06-09 Max Dipl.-Ing. Dr.-Ing. 8700 Würzburg Mengeringhausen SUPPORTING COMPOSITE BUILDING BOARD AND METHOD FOR THE PRODUCTION THEREOF
CN101967853A (en) * 2010-09-16 2011-02-09 南京林业大学 Fiber reinforce plastic (FRP)-rubber-steel composite pipe concrete structure
CN211057596U (en) * 2019-09-11 2020-07-21 江苏高速公路工程养护技术有限公司 Corrugated steel pipe reinforced concrete-filled steel tube pier
CN110821038A (en) * 2019-10-21 2020-02-21 上海市建筑科学研究院 Double-steel-plate concrete combined energy-consumption connecting beam and construction method

Similar Documents

Publication Publication Date Title
CN203603029U (en) Shearing force connecting piece and composite beam with same
CN105239559A (en) Common deformed steel bar tensioning device, prefabricated square pile and process for prefabricated square pile
CN103590322A (en) Shear force connecting part, combination beam comprising same and construction method of combination beam
CN110055893B (en) Corrugated steel-rubber concrete combined bridge deck
CN110886201A (en) Prefabricated assembled concrete-filled steel tube self-resetting pier with earthquake damage replaceable components
CN101487229B (en) Mounting and using method of lead core rubber support component with friction pairs
CN103485287A (en) Prestressed application method in concrete frame box culvert construction
CN112575952A (en) End steel plate self-anchoring structure of double-steel-plate-concrete combined structure
CN204609123U (en) A kind of Steel concrete compound beam structure
CN201649303U (en) Shear connector
CN201649433U (en) Ribbed reinforced concrete prefabricated part plate
CN202031091U (en) Hollow concrete pre-stressing square pile
CN109736200B (en) Steel-UHPC sheet combination structure system for quickly assembling steel plate support-cluster inclined nail
CN202031090U (en) Hollow prestressed concrete square pile
CN205421237U (en) Precast pile
CN109487699B (en) Steel plate support-inclined nail combined type interface connection steel-UHPC thin plate combined structure system
CN110185145B (en) Steel-concrete one-way combined beam column joint
CN210797280U (en) Anti-cracking construction equipment for hogging moment area of continuous composite beam bridge
CN205152800U (en) Unsettled template system of consolidating under complicated stress condition
CN212478276U (en) Self-resetting square concrete filled steel tube column base node with friction type anchoring device
CN211645913U (en) Prefabricated prestressed steel and concrete spliced continuous combination beam
CN210636821U (en) External prestress anti-cracking measure for basement exterior wall
CN109736197B (en) Steel plate support-inclined nail cluster type interface connection steel-UHPC (ultra high performance polycarbonate) thin plate combined structure system
CN202519852U (en) Concrete composite slab
CN111926690A (en) Novel pier is assembled in prefabrication

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination